CN109695246A - A kind of mass concrete construction heat dissipating method - Google Patents

A kind of mass concrete construction heat dissipating method Download PDF

Info

Publication number
CN109695246A
CN109695246A CN201811406060.8A CN201811406060A CN109695246A CN 109695246 A CN109695246 A CN 109695246A CN 201811406060 A CN201811406060 A CN 201811406060A CN 109695246 A CN109695246 A CN 109695246A
Authority
CN
China
Prior art keywords
reinforcing bar
concrete
heat dissipating
mass concrete
dissipating method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811406060.8A
Other languages
Chinese (zh)
Inventor
谭启厚
蒋华贵
范东岭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN201811406060.8A priority Critical patent/CN109695246A/en
Publication of CN109695246A publication Critical patent/CN109695246A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Foundations (AREA)

Abstract

The invention discloses a kind of mass concrete construction heat dissipating methods, include the following steps, the anti-Support of Foundation Pit Excavation construction for pushing away basis of mass concrete, surveying setting-out, release distributing bar and supporting frame with steel structure built-in fitting position, it is installed in order, first floor support frame and measure reinforcing bar are installed, pour blinding concrete, support frame and measure reinforcing bar are gradually installed from the bottom up, cracking resistance reinforcing bar is installed and the three-dimensional reinforcing bar that radiates, laminated pouring mass concrete, by increasing anticracking and heat dissipation reinforcing bar system in reinforcing bar system, after concreting, inside concrete heat is transmitted to the reinforcing bar and support frame in the concreting face of stretching by three-dimensional reinforcing bar radiator system, utilize the heating conduction that reinforcing bar and steel are excellent, the heat of hydration of concrete is transmitted to reinforcing bar, by the reinforcing bar heat dissipation for stretching out concrete surface, heat is formed to pass Pathway.

Description

A kind of mass concrete construction heat dissipating method
Technical field
The present invention relates to building engineering fields, more particularly to a kind of mass concrete construction heat dissipating method.
Background technique
With the development of the social economy, architectural image is intended to heteromorphosis development, the application of cable-membrane analysis or arch structure is got over Come more, with the increase of the building scale of construction, the anti-volume for pushing away basis is also increasing, and the anti-basis that pushes away is located underground, and one As using former slot casting concrete method, heat dissipation area is small, and curing time is long, and internal-external temperature difference is difficult to meet related request, It is easy to produce crack, influences duration and quality.To ensure mass concrete quality, shortens curing time, how to improve heat dissipation The radiating mode of the limited concrete of area, is those skilled in the art always in the problem of thinking.
Summary of the invention
It is an object of the invention to: overcome the above-mentioned problems in the prior art, proposes that a kind of mass concrete is applied Work heat dissipating method, by increasing anticracking and heat dissipation reinforcing bar system, after concreting, inside concrete in reinforcing bar system Heat is transmitted to the reinforcing bar and support frame in the concreting face of stretching by three-dimensional reinforcing bar radiator system, excellent using reinforcing bar and steel The heat of hydration of concrete is transmitted to reinforcing bar by different heating conduction, and the reinforcing bar by stretching out concrete surface radiates, and is formed heat and is passed Inside concrete heat is transmitted in air by pathway with this, to realize that the balance of internal temperature and heat dissipation can increase The anti-crack ability of volume of concrete foundation improves the construction quality and efficiency of mass concrete.
The purpose of the present invention is realized by following technical proposals:
A kind of mass concrete construction heat dissipating method, comprising the following steps:
Step 1: the anti-Support of Foundation Pit Excavation construction for pushing away basis of mass concrete;
Step 2: surveying setting-out is released distributing bar and supporting frame with steel structure built-in fitting position, is installed in order;
Step 3: installation first floor support frame and measure reinforcing bar;
Step 4: pouring blinding concrete;
Step 5: support frame and measure reinforcing bar are gradually installed from the bottom up;
Step 6: installation cracking resistance reinforcing bar and the three-dimensional reinforcing bar that radiates;
Step 7: laminated pouring mass concrete.
A kind of mass concrete construction heat dissipating method of the invention is set between support frame and foundation pit walls in the step 5 Connector is set, the installation of the connector should be installed before the measure reinforcement installation more than corresponding position.
A kind of mass concrete construction heat dissipating method of the invention, support frame described in the step 5 is from bottom of foundation ditch It takes root and stretches out blinding concrete surface.
A kind of mass concrete construction heat dissipating method of the invention, the three-dimensional bar frame of cracking resistance heat dissipation includes: perpendicular To reinforcing bar, horizontal reinforcement, bridging reinforcing bar and horizontal oblique reinforcing bar.
A kind of mass concrete construction heat dissipating method of the invention, the vertical reinforcement rely on installed support frame It is installed with measure reinforcing bar, the vertical reinforcement is arranged upwards from foundation pit bottom and stretches out concrete surface.
A kind of mass concrete construction heat dissipating method of the invention, the vertical reinforcement stretch out construction joint and concrete table Face at least 1m.
A kind of mass concrete construction heat dissipating method of the invention, the horizontal reinforcement in the vertical direction from top to bottom between Every arrangement several layers vertical and horizontal reinforcing bar, the vertical and horizontal reinforcing bar is extended to above concreting face.
A kind of mass concrete construction heat dissipating method of the invention, the spacing of the vertical and horizontal reinforcing bar are 1-2m, The vertical and horizontal reinforcing bar extends to 2m above concreting face.
A kind of mass concrete construction heat dissipating method of the invention, the bridging reinforcing bar are installing vertical and horizontal direction When reinforcing bar, be arranged respectively in the plane of steel mesh and facade along foundation pit length and width direction, the horizontal oblique reinforcing bar according to The spacing of vertical 1.5m is arranged in steel bar plane position.
A kind of mass concrete construction heat dissipating method of the invention, vertical bridging reinforcing bar according to 2.4m spacing arrange, The steel mesh heat dissipation system of vertical reinforcement that is entire original and adding, horizontal reinforcement composition is linked to be an entirety.
A kind of mass concrete construction heat dissipating method of the invention, the cracking resistance reinforcing bar apart from concrete surface 5cm and The position 25cm, is respectively arranged single-layer bidirectional setting cracking resistance steel mesh, the cracking resistance reinforcing bar to be mounted on concreting flat to this Behind face, it is placed directly in concrete surface, is fixed by vertical reinforcement, casting concrete.
According to the above technical scheme, the beneficial effects of the present invention are: proposing a kind of mass concrete construction heat dissipating method, By increasing anticracking and heat dissipation reinforcing bar system in reinforcing bar system, after concreting, inside concrete heat passes through vertical Body reinforcing bar heat dissipation system is transmitted to the reinforcing bar and support frame in the concreting face of stretching, utilizes the thermal conductivity that reinforcing bar and steel are excellent Can, the heat of hydration of concrete is transmitted to reinforcing bar, the reinforcing bar by stretching out concrete surface radiates, thermal conduction path is formed, with Inside concrete heat is transmitted in air by this, to realize that the balance of internal temperature and heat dissipation can increase large volume coagulation The anti-crack ability of earth foundation improves the construction quality and efficiency of mass concrete.
Detailed description of the invention
Fig. 1 is a kind of schematic diagram of mass concrete construction heat dissipating method of the present invention;
Fig. 2 is a kind of section of mass concrete construction heat dissipating method of the present invention.
Specific embodiment
The present invention is further illustrated with attached drawing combined with specific embodiments below.
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to the accompanying drawings and embodiments, right The present invention is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, and It is not used in the restriction present invention.
If Fig. 1-2 is a kind of embodiment of mass concrete construction heat dissipating method of the present invention, a kind of mass concrete Construction heat dissipating method, comprising the following steps:
Step 1: the anti-Support of Foundation Pit Excavation construction for pushing away basis of mass concrete;
Step 2: surveying setting-out releases distributing bar and supporting frame with steel structure built-in fitting position, in order into
Row installation;
Step 3: installation first floor support frame and measure reinforcing bar 1;
Step 4: pouring blinding concrete;
Step 5: support frame and measure reinforcing bar 1 are gradually installed from the bottom up;
Step 6: installation cracking resistance reinforcing bar and the three-dimensional reinforcing bar that radiates;
Step 7: laminated pouring mass concrete.
Connector is set between support frame and foundation pit walls in the step 5, and the installation of the connector should be in corresponding position It is installed before above installation of measure reinforcing bar 1.
Support frame described in the step 5 takes root from bottom of foundation ditch and stretches out blinding concrete surface.
The three-dimensional bar frame of cracking resistance heat dissipation includes: that vertical reinforcement 2, horizontal reinforcement 5, bridging reinforcing bar 4 and level are oblique To reinforcing bar 3.
The vertical reinforcement 2 relies on installed support frame and measure reinforcing bar 1 to be installed, the vertical reinforcement 2 from Foundation pit bottom is arranged upwards and stretches out concrete surface.
The vertical reinforcement 2 stretches out construction joint and concrete surface at least 1m.
The horizontal reinforcement 5 arranged for interval several layers vertical and horizontal reinforcing bar from top to bottom in the vertical direction, the longitudinal direction It is extended to below concreting face with transverse steel.
The spacing of the vertical and horizontal reinforcing bar is 1-2m, and the vertical and horizontal reinforcing bar extends under concreting face Square 2m or less.
The bridging reinforcing bar 4 is when installing vertical and horizontal steel bar, along foundation pit length and width direction respectively in steel The plane and facade of muscle net are arranged, and the horizontal oblique reinforcing bar 3 is arranged according to the spacing of vertical 1.5m in steel bar plane position.
Vertical bridging reinforcing bar 4, is arranged according to 2.4m spacing, by vertical reinforcement 2, horizontal reinforcement entire original and add The steel mesh heat dissipation system of 5 compositions is linked to be an entirety.
The cracking resistance reinforcing bar is respectively arranged single-layer bidirectional setting cracking resistance reinforcing bar apart from the position concrete surface 5cm and 25cm Net, the cracking resistance reinforcing bar be mounted on concreting to the plane after, be placed directly in concrete surface, pass through vertical reinforcement 2 is fixed, casting concrete.
Connection between reinforcing bar and between reinforcing bar and built-in fitting must firm welding.When installation, first spot welding is fixed temporarily section Point reinforcing bar, then integral solder are fixed.Welded unit uses 18 reinforcing bar of φ, and length 25cm, symmetric curvature is in 90 °, with each steel bar welding Fixation is connect, fusion length is not less than 10cm.
The connection of vertical reinforcement 2 is using diversified forms such as straight thread, butt welding or overlap weldings, and according to overlap welding, weld seam is long Degree is not less than 10d.
On the reinforcing bar that temperature sensor is laid in corresponding position when installing bar frame, sensor connector draws coagulation Native top surface.Then casting concrete.Wherein, vertical bridging reinforcing bar 4 and horizontal oblique connection reinforcing bar by entire reinforcing bar system with Support frame connects into an entirety, keeps heat dissipation effect more preferable.
After concreting, inside concrete heat is transmitted to stretching concrete by three-dimensional reinforcing bar radiator system and pours The heat of hydration of concrete is transmitted to reinforcing bar using the heating conduction that reinforcing bar and steel are excellent by the reinforcing bar and support frame for building face, is led to The reinforcing bar heat dissipation for stretching out concrete surface is crossed, thermal conduction path is formed, inside concrete heat is transmitted in air with this, from And realize the balance and heat dissipation of internal temperature.
In vertically and horizontally reinforcing bar and crater wall contact position, vertically and horizontally 20 reinforcing bar of φ of the terminally positioned 15cm length of reinforcing bar, with It avoids being subjected to displacement.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Made any modifications, equivalent replacements, and improvements etc., should all be included in the protection scope of the present invention within mind and principle.

Claims (10)

1. a kind of mass concrete construction heat dissipating method, which comprises the following steps:
Step 1: the anti-Support of Foundation Pit Excavation construction for pushing away basis of mass concrete;
Step 2: surveying setting-out is released distributing bar and supporting frame with steel structure built-in fitting position, is installed in order;
Step 3: installation first floor support frame and measure reinforcing bar;
Step 4: pouring blinding concrete;
Step 5: support frame and measure reinforcing bar are gradually installed from the bottom up;
Step 6: installation cracking resistance reinforcing bar and the three-dimensional reinforcing bar that radiates;
Step 7: laminated pouring mass concrete.
2. a kind of mass concrete construction heat dissipating method according to claim 1, it is characterised in that: in the step 5 Connector is set between support frame and foundation pit walls, the installation of the connector should measure reinforcement installation more than corresponding position it Before be installed.
3. a kind of mass concrete construction heat dissipating method according to claim 2, it is characterised in that: in the step 5 Support frame as described above takes root from bottom of foundation ditch and stretches out blinding concrete surface.
4. a kind of mass concrete construction heat dissipating method according to claim 1, it is characterised in that: the cracking resistance heat dissipation Three-dimensional bar frame includes: vertical reinforcement, horizontal reinforcement, bridging reinforcing bar and horizontal oblique reinforcing bar.
5. a kind of mass concrete construction heat dissipating method according to claim 4, it is characterised in that: the vertical reinforcement Installed support frame and measure reinforcing bar is relied on to be installed, the vertical reinforcement is arranged upwards from foundation pit bottom and stretches out coagulation Native surface.
6. a kind of mass concrete construction heat dissipating method according to claim 5, it is characterised in that: the vertical reinforcement Stretch out construction joint and concrete surface at least 1m.
7. a kind of mass concrete construction heat dissipating method according to claim 4, it is characterised in that: the horizontal reinforcement Arranged for interval several layers vertical and horizontal reinforcing bar, the vertical and horizontal reinforcing bar extend to concrete from top to bottom in the vertical direction It pours below face.
8. a kind of mass concrete construction heat dissipating method according to claim 7, it is characterised in that: described longitudinal and horizontal It is 1-2m to the spacing of reinforcing bar, the vertical and horizontal reinforcing bar extends to 2m or less below concreting face.
9. a kind of mass concrete construction heat dissipating method according to claim 4, it is characterised in that: the bridging steel Muscle is arranged in the plane of steel mesh and facade respectively when installing vertical and horizontal steel bar, along foundation pit length and width direction, The horizontal oblique reinforcing bar is arranged according to the spacing of vertical 1.5m in steel bar plane position.
10. a kind of mass concrete construction heat dissipating method according to claim 4, it is characterised in that: the cracking resistance steel Muscle is respectively arranged single-layer bidirectional setting cracking resistance steel mesh, the peace of the cracking resistance reinforcing bar apart from the position concrete surface 5cm and 25cm After concreting to the plane, it is placed directly in concrete surface, is fixed by vertical reinforcement, casting concrete is It can.
CN201811406060.8A 2018-11-23 2018-11-23 A kind of mass concrete construction heat dissipating method Pending CN109695246A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811406060.8A CN109695246A (en) 2018-11-23 2018-11-23 A kind of mass concrete construction heat dissipating method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811406060.8A CN109695246A (en) 2018-11-23 2018-11-23 A kind of mass concrete construction heat dissipating method

Publications (1)

Publication Number Publication Date
CN109695246A true CN109695246A (en) 2019-04-30

Family

ID=66230178

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811406060.8A Pending CN109695246A (en) 2018-11-23 2018-11-23 A kind of mass concrete construction heat dissipating method

Country Status (1)

Country Link
CN (1) CN109695246A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111910641A (en) * 2020-08-14 2020-11-10 河南省出山店水库管理局 Mass concrete anti-cracking method under spring pouring condition of strong base rock strong constraint area
CN111910653A (en) * 2020-08-14 2020-11-10 河南省出山店水库管理局 Anti-cracking method for quickly backfilling large-volume concrete in large deep and long defect groove
CN112261499A (en) * 2020-10-21 2021-01-22 深圳艾灵网络有限公司 Communication base station
CN112609819A (en) * 2020-11-11 2021-04-06 河海大学 Concrete member and temperature control method thereof
CN113187240A (en) * 2021-05-25 2021-07-30 国厦建设有限公司 Concrete pouring method for reducing crack generation

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102704483A (en) * 2012-02-26 2012-10-03 成都市第六建筑工程公司 Method for taking cooling pipe network as building bottom plate multi-layer reinforced support frame
CN203347203U (en) * 2013-05-29 2013-12-18 中建三局第二建设工程有限责任公司 Multi-functional super-thick bulked concrete steel tube support system
CN204875833U (en) * 2015-06-24 2015-12-16 江苏南通三建集团有限公司 Super thick super large concrete foundation resistance to compression board steel bar support
CN106049519A (en) * 2016-07-18 2016-10-26 重庆建工第三建设有限责任公司 Stepped large raft construction technology

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102704483A (en) * 2012-02-26 2012-10-03 成都市第六建筑工程公司 Method for taking cooling pipe network as building bottom plate multi-layer reinforced support frame
CN203347203U (en) * 2013-05-29 2013-12-18 中建三局第二建设工程有限责任公司 Multi-functional super-thick bulked concrete steel tube support system
CN204875833U (en) * 2015-06-24 2015-12-16 江苏南通三建集团有限公司 Super thick super large concrete foundation resistance to compression board steel bar support
CN106049519A (en) * 2016-07-18 2016-10-26 重庆建工第三建设有限责任公司 Stepped large raft construction technology

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111910641A (en) * 2020-08-14 2020-11-10 河南省出山店水库管理局 Mass concrete anti-cracking method under spring pouring condition of strong base rock strong constraint area
CN111910653A (en) * 2020-08-14 2020-11-10 河南省出山店水库管理局 Anti-cracking method for quickly backfilling large-volume concrete in large deep and long defect groove
CN112261499A (en) * 2020-10-21 2021-01-22 深圳艾灵网络有限公司 Communication base station
CN112609819A (en) * 2020-11-11 2021-04-06 河海大学 Concrete member and temperature control method thereof
CN113187240A (en) * 2021-05-25 2021-07-30 国厦建设有限公司 Concrete pouring method for reducing crack generation

Similar Documents

Publication Publication Date Title
CN109695246A (en) A kind of mass concrete construction heat dissipating method
CN104196042B (en) A kind of steel sheet pile cofferdam structure construction method
CN104631666B (en) A kind of super thick built-in wall steel plate waterproof radioprotective construction method
CN103205979B (en) Method for constructing large raft foundation under high temperature
CN101761229B (en) Method for constructing hollow overlapped rib plate support system
CN105951848A (en) Non-intermittent composite transfer structure for super-deep foundation pit support and construction method
CN208151819U (en) Base even spreads formwork system
CN105421476A (en) Construction method for installing tower crane embedded parts on raft foundation and installation structure
CN203729322U (en) Precast concrete pipeline foundation
CN103835303B (en) A kind of cast-type armored concrete shearing resistance method and structure
CN104711996A (en) End steel shell mounting and positioning device and operation method
CN106638612B (en) Simple foundation pit support system and its construction method
CN110080454A (en) LPM light filling body Construction of Cast-in-situ Concrete Hollow
CN206337678U (en) The assembled steel frame wall filled with masonry system of door shape steel disc connection
CN210767353U (en) Assembled shear force wall node connection structure
CN107476451A (en) Assembled foam concrete external wall insulation and its construction and installation method
CN106760061A (en) The assembled steel frame wall filled with masonry system and its construction method of door shape steel disc connection
CN206233405U (en) The attachment structure of shear wall and after-pouring concrete frame beam
CN206571149U (en) A kind of shear wall formwork bottom positions fastener
CN205116182U (en) Simple and easy excavation supporting system
CN204531184U (en) For fixing the locator card of steel plastic compount anti-crack net in reinforced concrete wallboard
CN205530729U (en) Ceiling radiant tube structure based on bury under reinforcing bar
CN210459707U (en) Novel composite floor installation device
CN106400687A (en) Positioning assisting assembly jig for pier column reinforcing rib
CN206368433U (en) A kind of built-in fitting attachment structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190430

RJ01 Rejection of invention patent application after publication