CN109681243B - Comprehensive restoration method for tunnel lining two-lining concrete waterproof board exposure - Google Patents

Comprehensive restoration method for tunnel lining two-lining concrete waterproof board exposure Download PDF

Info

Publication number
CN109681243B
CN109681243B CN201811537104.0A CN201811537104A CN109681243B CN 109681243 B CN109681243 B CN 109681243B CN 201811537104 A CN201811537104 A CN 201811537104A CN 109681243 B CN109681243 B CN 109681243B
Authority
CN
China
Prior art keywords
waterproof board
secondary lining
lining
waterproof
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811537104.0A
Other languages
Chinese (zh)
Other versions
CN109681243A (en
Inventor
寇军
林石泉
陈阵
陈航
唐颖
陈平燕
吴桂栓
陈礼榕
陈金盛
简注清
孙敦江
朱承鸿
苏擎
李其泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Luhai Engineering Technology Co ltd
Original Assignee
Fujian Luhai Engineering Investigation & Design Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Luhai Engineering Investigation & Design Co ltd filed Critical Fujian Luhai Engineering Investigation & Design Co ltd
Publication of CN109681243A publication Critical patent/CN109681243A/en
Application granted granted Critical
Publication of CN109681243B publication Critical patent/CN109681243B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete

Abstract

The invention discloses a comprehensive repair method for the exposure of a tunnel lining two-lining concrete waterproof board, which comprises the following steps: a. detecting whether a multilayer waterproof board exists or not by using a geological radar matched with a corresponding antenna; determining the range of the secondary lining needing chiseling; b. excavating and chiseling reinforced concrete in the secondary lining area; c. cutting off the waterproof board of the actual area to be processed, and spraying concrete to form an initial supporting layer; d. a waterproof board which is larger than the secondary lining digging position is used for patching the waterproof layer at the digging position; e. constructing a layer of sealing paste after the waterproof board is repaired; f. arranging anchor bolts on the inner side surface of the secondary lining at the excavation position for drilling holes; g. waterproof is carried out by comprehensively sealing and pasting; h. laying a reinforcing mesh on the inner side surface of the secondary lining at the excavation position; j. building a mould and rebuilding a secondary lining; k. and (5) dismantling a steel die, cutting and modifying. The invention can quickly process the local tunnel lining secondary lining concrete waterproof board exposure, and can effectively solve the problems of safe structure, water prevention and drainage, beautiful tunnel building and the like.

Description

Comprehensive restoration method for tunnel lining two-lining concrete waterproof board exposure
Technical Field
The invention relates to a comprehensive repair method for the exposure of a tunnel lining two-lining concrete waterproof board.
Background
With the rapid development of traffic in China, the mileage of various roads is continuously increased, the number of various tunnels for new construction and operation is increased year by year, various tunnel defects affect the safety of the tunnels, and particularly the common tunnel lining two-lining concrete waterproof board exposes the defects. The tunnel protection generally comprises three layers, namely an initial support layer, a water-resisting layer and a secondary lining layer from inside to outside, wherein the water-resisting layer is mainly made of waterproof boards. However, for various reasons, after the secondary lining layer of the newly-built tunnel is removed, the waterproof board is exposed outside, so that the use safety, drainage and attractiveness of the tunnel are affected, and therefore, traffic quality governing departments and regulations require repair, and the structural safety and the use durability after repair are evaluated.
The newly-built tunnel lining two-lining concrete waterproof board exposes diseases or defects, the reasons need to be checked, and a corresponding method is adopted for processing. Most of the existing repairs only adopt proper excavation and cutting, the concrete on the surface layer is simply repaired, and the integral structure and the waterproof system of the tunnel are damaged.
The document with the Chinese patent number of CN 104373138 discloses a construction method for remodeling a waterproof layer during repairing a tunnel lining structure, but the method cannot solve the related structural safety problems of insufficient thickness of a secondary lining during the exposure treatment of the waterproof board.
The method is only used for treating the exposure of the local tunnel lining secondary lining concrete waterproof board, and can effectively solve the problems of safe structure, water prevention and drainage, attractive tunnel building and the like; however, for the structural safety problem caused by insufficient thickness of the two liners in large area, additional engineering reinforcement measures are needed.
Disclosure of Invention
The invention aims to overcome the defects in the prior art and provide a comprehensive repair method for the exposed tunnel lining two-lining concrete waterproof board.
The invention is realized by the following modes:
a comprehensive repairing method for the exposed tunnel lining two-lining concrete waterproof board is characterized in that: the method comprises the following steps:
a. detecting whether a multilayer waterproof board exists or not by using a geological radar matched with a corresponding antenna; if the waterproof plate is more than two layers, when the embedding depth of the waterproof plate of the inner layer meets the structural design requirement, only the exposed waterproof plate needs to be treated, the exposed secondary lining is chiseled off, and modified epoxy mortar is adopted for repairing; if the waterproof board is a single-layer waterproof board, determining the range of the secondary lining needing to be chiseled and processed according to the detected thickness of the secondary lining outside the detection and repair area, and making a contour line; the range of processing the secondary lining is not less than 20-40 cm beyond the actual area to be processed;
b. digging and chiseling the reinforced concrete in the secondary lining area without damaging the waterproof board;
c. cutting off the waterproof board of the area to be actually processed, supplementing and excavating the original primary supporting layer and surrounding rocks to the design requirement, and spraying concrete to form the primary supporting layer;
d. patching the waterproof layer at the excavated part by using a waterproof board which is larger than the excavated part of the secondary lining, wherein before patching, the sharp protrusion is treated or is smoothed by adopting mortar to prevent the waterproof board from puncturing a new waterproof layer;
e. after the waterproof board is repaired, a layer of sealing paste is constructed to ensure that the waterproof board does not leak or penetrate water;
f. chiseling the inner side surface of the secondary lining at the excavated position into a rough surface with the concave-convex difference not less than 0.6mm, laying anchor drilling holes with the hole depth of 15-25 cm and the diameter of 25-32 mm, cleaning the holes, injecting a chemical anchoring adhesive, and implanting rust-removing anchors with the diameter of 18-25 mm, wherein the implantation depth is 15cm and the binding force is required to be more than 40 KN;
g. cleaning the waterproof board, and sealing and sticking the waterproof board comprehensively to prevent water and prevent local damage;
h. cleaning the inner side surface of the secondary lining at the excavated part, uniformly coating an interface agent, and laying a reinforcing mesh to ensure that the anchor is firmly welded with the anchor;
j. building a mould and building a secondary lining, namely building the mould and building the secondary lining by adopting C25 self-compaction fine-grain micro-expansive concrete;
k. and (5) dismantling a steel die, cutting and modifying.
Further, the C25 self-compacting fine-particle micro-expansion concrete is formed by mixing 8-12% of grouting agent into the self-compacting fine-particle micro-expansion concrete, wherein the self-compacting fine-particle micro-expansion concrete is formed by mixing cement: sand: crushing stone: the water is mixed according to the mass ratio of 1:1.94:3.16: 0.48.
The invention has the beneficial effects that: the local exposure of the tunnel lining secondary lining concrete waterproof board is quickly processed, so that the problems of safe structure, water prevention and drainage, attractive tunnel building and the like can be effectively solved; the treatment range is defined mainly by test detection; the water seepage prevention after the repair is ensured through the repair and the double-layer waterproof protection; the fine-grained micro-expansion concrete is self-compacted through C25, vibration is not needed, the forming is rapid, and the strength meets the requirement; and the secondary boundary repair makes the tunnel secondary lining attractive in appearance.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings that are required to be used in the embodiments will be briefly described below, it should be understood that the following drawings only illustrate some embodiments of the present invention and therefore should not be considered as limiting the scope, and for those skilled in the art, other related drawings can be obtained according to the drawings without inventive efforts.
FIG. 1 is a schematic structural view of the present invention;
icon: 1-initial branch protective layer; 2-waterproof board; and 3-secondary lining.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention more apparent, the technical solutions of the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings of the embodiments of the present invention, and it is obvious that the described embodiments are some, but not all embodiments of the present invention. All other embodiments, which can be obtained by a person skilled in the art without any inventive step based on the embodiments of the present invention, are within the scope of the present invention. Thus, the following detailed description of the embodiments of the present invention, presented in the figures, is not intended to limit the scope of the invention, as claimed, but is merely representative of selected embodiments of the invention. All other embodiments, which can be obtained by a person skilled in the art without any inventive step based on the embodiments of the present invention, are within the scope of the present invention.
Example 1:
a comprehensive repairing method for the exposed tunnel lining two-lining concrete waterproof board comprises the following steps as shown in figure 1:
a. matching a geological radar with a corresponding antenna, wherein the type of the geological radar is TSP203 or TSP 203A; detecting whether the multilayer waterproof board 2 exists or not; if the waterproof plate 2 is more than two layers, when the embedding depth of the waterproof plate 2 of the inner layer meets the structural design requirement, only the exposed waterproof plate 2 needs to be processed, the exposed secondary lining 3 is chiseled off, and modified epoxy mortar is adopted for repairing; if the waterproof plate is a single-layer waterproof plate 2, determining the range of the secondary lining 3 to be chiseled according to the detected thickness of the secondary lining outside the detection repair area, and making a contour line; the range of processing the secondary lining 3 is not less than 20-40 cm beyond the actual area to be processed;
b. digging and chiseling the reinforced concrete in the secondary lining 3 area without damaging the waterproof board 2;
c. cutting off the waterproof board 2 of the area to be actually processed, supplementing and excavating the original primary supporting layer and surrounding rocks to the design requirement, and spraying concrete to form the primary supporting layer 1;
d. patching the waterproof layer at the excavated part by using a waterproof board which is larger than the excavated part of the secondary lining 3, wherein before patching, the sharp protrusion is treated or is smoothed by adopting mortar to prevent the waterproof board from puncturing a new waterproof layer;
e. after the waterproof board 2 is repaired, a layer of sealing paste is constructed to ensure that the leakage or the water seepage is not leaked or punctured;
f. chiseling the inner side surface of a secondary lining 3 at an excavated position into a rough surface with the concave-convex difference not less than 0.6mm, laying anchor drilling holes with the hole depth of 15-25 cm and the diameter of 25-32 mm, cleaning the holes, injecting a chemical anchoring adhesive, wherein the chemical anchoring adhesive is mainly used for chemical method bar planting, namely building engineering chemical method bar planting adhesive bar planting, called bar planting and bar planting, is a connecting technology for post-anchoring of a steel bar on the building structure earthquake-resistant reinforcement engineering by utilizing the holding force effect of a structural adhesive locking key, and is the optimal choice for the application of structural bar planting reinforcement and heavy load fastening; implanting derusted anchor nails with the diameter of 18-25 mm, wherein the implantation depth is 15cm, and the binding force is required to be more than 40 KN;
g. cleaning the waterproof board, and sealing and sticking the waterproof board comprehensively to prevent water and prevent local damage;
h. cleaning the inner side surface of the secondary lining 3 at the excavated part, uniformly coating an interface agent, and laying a reinforcing mesh to ensure that the anchor is firmly welded with the anchor;
j. building a mold and building a secondary lining 3, and building the mold and the secondary lining 3 by adopting C25 self-compacting fine-grain micro-expansive concrete;
k. and (5) dismantling a steel die, cutting and modifying.
The C25 self-compacting fine-grain micro-expansion concrete of the invention:
c25 self-compacting fine-grained micro-expansive concrete: the material adopts XHD-D prestressed pipe grouting agent, and has the advantages that: the vibration is not needed, the self-sealing is realized, the strength is high, and the water bleeding and the delamination are avoided; the durability is good, the inorganic grouting material does not age, does not rust the reinforcing steel bar, and is durable and firm; the plump drought is strong, the slight expansion is realized, and the disease restoration is facilitated; firmly bonding with the original concrete on the side surface; the self-compacting fine-particle micro-expansion concrete C25 is convenient to use, 8-12% of grouting agent is doped into the self-compacting fine-particle micro-expansion concrete, and the self-compacting fine-particle micro-expansion concrete is prepared from cement: sand: crushing stone: the water is mixed according to the mass ratio of 1:1.94:3.16: 0.48. The micro-expansion concrete can be used after being mixed, and the recommended mixing amount is based on experiments.
In this embodiment, attention is paid to restore the appearance decoration after the repair process; in the second lining construction of the tunnel during the repair construction, the slab staggering phenomenon exists in the new interface and the old interface due to the uneven splicing of the templates, so that the slab staggering phenomenon exists in the second lining concrete; under the condition that the reinforcing steel bar protective layer is not influenced, a polisher is adopted to polish the two lining staggered platforms within a certain effective range in time, and the appearance is guaranteed to meet the requirements.
The invention quickly processes the local tunnel lining secondary lining concrete waterproof board exposure, and can effectively solve the problems of safe structure, water prevention and drainage, beautiful tunnel building and the like; the treatment range is defined mainly by test detection; the water seepage prevention after the repair is ensured through the repair and the double-layer waterproof protection; the fine-grained micro-expansion concrete is self-compacted through C25, vibration is not needed, the forming is rapid, and the strength meets the requirement; and the secondary boundary repair makes the tunnel secondary lining attractive in appearance.
The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention, and various modifications and changes may be made by those skilled in the art. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (1)

1. A comprehensive repairing method for the exposed tunnel lining two-lining concrete waterproof board is characterized in that: the method comprises the following steps:
a. detecting whether a multilayer waterproof board (2) exists or not by matching a geological radar with a corresponding antenna; if the waterproof plate (2) is more than two layers, when the embedding depth of the waterproof plate (2) of the inner layer meets the structural design requirement, only the exposed waterproof plate (2) needs to be treated, the exposed secondary lining (3) is chiseled off, and modified epoxy mortar is adopted for repairing; if the waterproof board is a single-layer waterproof board (2), determining the range of the secondary lining (3) to be chiseled according to the detected thickness of the secondary lining outside the detection repair area, and making a contour line; the range of the secondary lining (3) to be processed is not less than 20-40 cm larger than the actual area to be processed;
b. digging and chiseling the reinforced concrete in the secondary lining (3) area without damaging the waterproof board (2);
c. cutting off the waterproof board (2) of the area to be actually processed, supplementing and excavating the original primary supporting layer and surrounding rocks to the design requirement, and spraying concrete to form the primary supporting layer (1);
d. patching the waterproof layer at the excavated part by using a waterproof board which is larger than the excavated part of the secondary lining (3), wherein a sharp protrusion is processed before patching, or mortar is adopted for leveling so as to prevent the waterproof board from puncturing a new waterproof layer;
e. after the waterproof board (2) is repaired, a layer of sealing paste is constructed to ensure that the waterproof board does not leak or penetrate water;
f. chiseling the inner side surface of the secondary lining (3) at the excavated position into a rough surface with the concave-convex difference not less than 0.6mm, laying anchor bolts for drilling holes with the hole depth of 15-25 cm and the diameter of 25-32 mm, cleaning the holes, injecting a chemical anchoring adhesive, and implanting rust-removing anchor bolts with the diameter of 18-25 mm, wherein the implantation depth is 15cm, and the binding force is required to be more than 40 KN;
g. cleaning the waterproof board, and sealing and sticking the waterproof board comprehensively to prevent water and prevent local damage;
h. cleaning the inner side surface of the secondary lining (3) at the excavated part, uniformly brushing an interface agent, and laying a reinforcing mesh to ensure that the anchor is firmly welded with the anchor;
j. building a mould to construct a secondary lining (3), and building the mould to construct the secondary lining (3) by adopting C25 self-compacting fine-grain micro-expansive concrete;
k. dismantling a steel mould, cutting and modifying;
the C25 self-compacting fine-particle micro-expansion concrete is formed by mixing 8-12% of grouting agent into self-compacting fine-particle micro-expansion concrete, wherein the self-compacting fine-particle micro-expansion concrete is prepared from cement: sand: crushing stone: the water is mixed according to the mass ratio of 1:1.94:3.16: 0.48.
CN201811537104.0A 2018-08-15 2018-12-14 Comprehensive restoration method for tunnel lining two-lining concrete waterproof board exposure Active CN109681243B (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN2018109293275 2018-08-15
CN201810929327 2018-08-15

Publications (2)

Publication Number Publication Date
CN109681243A CN109681243A (en) 2019-04-26
CN109681243B true CN109681243B (en) 2020-08-07

Family

ID=66186125

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811537104.0A Active CN109681243B (en) 2018-08-15 2018-12-14 Comprehensive restoration method for tunnel lining two-lining concrete waterproof board exposure

Country Status (1)

Country Link
CN (1) CN109681243B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110486053A (en) * 2019-09-05 2019-11-22 贵阳建筑勘察设计有限公司 A kind of urban track traffic shallow tunnel fault of construction treatment construction method
CN110985053B (en) * 2019-12-20 2022-07-08 西南交通大学 Method for renovating large cavity behind support of operating tunnel

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104373138A (en) * 2014-10-13 2015-02-25 中南大学 Waterproof layer rebuilding construction method in repairing of tunnel lining structure
CN105178980A (en) * 2015-09-07 2015-12-23 中南大学 Skylight-forming lining structure repair method for tunnels
CN106677803A (en) * 2017-02-03 2017-05-17 长安大学 Structure and method for treating severe disengagement, cracking and other defects of tunnel lining
CN107575245A (en) * 2017-08-21 2018-01-12 中铁隧道集团二处有限公司 A kind of laying method of anchor bar of waterproof plate in tunnels

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104373138A (en) * 2014-10-13 2015-02-25 中南大学 Waterproof layer rebuilding construction method in repairing of tunnel lining structure
CN105178980A (en) * 2015-09-07 2015-12-23 中南大学 Skylight-forming lining structure repair method for tunnels
CN106677803A (en) * 2017-02-03 2017-05-17 长安大学 Structure and method for treating severe disengagement, cracking and other defects of tunnel lining
CN107575245A (en) * 2017-08-21 2018-01-12 中铁隧道集团二处有限公司 A kind of laying method of anchor bar of waterproof plate in tunnels

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
隧道常见质量缺陷整治方法;吴光辉;《企业技术开发》;20140301;第33卷(第7期);第32-34页 *

Also Published As

Publication number Publication date
CN109681243A (en) 2019-04-26

Similar Documents

Publication Publication Date Title
CN104846810B (en) Self-circulating posterior grouting bored pile construction method
CN107542108B (en) A kind of reverse construction method of building basement structure
CN109681235B (en) Method for repairing highway tunnel lining cavity with poor surrounding rock
CN110485470A (en) A kind of default push pipe door opening of water rich strata and the sliding rear rectangle active well and its construction method for leaning on wall
CN104831734B (en) A kind of deep basal pit building rotary churning pile Composition Soil Nailing Walls construction method
CN112609703B (en) Soil nailing wall support construction process
CN109681243B (en) Comprehensive restoration method for tunnel lining two-lining concrete waterproof board exposure
CN110485468B (en) Permanent circular working well with water-rich stratum preset jacking pipe door opening and construction method thereof
CN109371861A (en) A kind of culvert of reinforced concrete subsiding crack infiltration Treatment Methods and repair structure
CN105065037A (en) Double-layer arch center support construction method for highway soft rock tunnel
CN111119195A (en) Foundation pit soil nail shotcrete support construction method
CN110486053A (en) A kind of urban track traffic shallow tunnel fault of construction treatment construction method
CN111560941A (en) Karst landform cavity treatment method
CN209324375U (en) A kind of reparation structure of the poor highway tunnel lining cavity of pair of country rock
KR100489515B1 (en) Panel for repairing, reinforcing con'c body and method of using the same
CN112080972A (en) Method for repairing road surface by adopting grouting to reinforce roadbed
CN110344448A (en) A kind of blocking method of the deep hole perfusion grouting material of basement bottom board large-scale water leakage
CN206800909U (en) A kind of assembled terrace in construction site
CN207211188U (en) Outer wall of underground structure HCMW engineering methods overlap wall
CN112281927A (en) Construction method for treating leakage of independent foundation of frame column
CN112195970A (en) River-crossing tunnel engineering waterproof construction method
CN110747861A (en) High-water-level deep foundation pit excavation construction method
CN111042843A (en) Pre-anchoring method for underground excavated tunnel
CN109653764B (en) Method for repairing tunnel water seepage flow whitening
CN110485465A (en) A kind of water rich strata presets the round-seal reservoir and its construction method of push pipe door opening

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Kou Jun

Inventor after: Jian Zhuqing

Inventor after: Sun Dunjiang

Inventor after: Zhu Chenghong

Inventor after: Su Jing

Inventor after: Li Qiquan

Inventor after: Lin Shiquan

Inventor after: Chen Zhen

Inventor after: Chen Hang

Inventor after: Tang Ying

Inventor after: Chen Pingyan

Inventor after: Wu Guishuan

Inventor after: Chen Lirong

Inventor after: Chen Jinsheng

Inventor before: Kou Jun

Inventor before: Jian Zhuqing

Inventor before: Sun Dunjiang

Inventor before: Zhu Chenghong

Inventor before: Su Qing

Inventor before: Li Qiquan

Inventor before: Lin Shiquan

Inventor before: Chen Zhen

Inventor before: Chen Hang

Inventor before: Tang Ying

Inventor before: Chen Pingyan

Inventor before: Wu Guishuan

Inventor before: Chen Lirong

Inventor before: Chen Jinsheng

CB03 Change of inventor or designer information
CP03 Change of name, title or address

Address after: 350008 Building 5, fuwanpian standard workshop, Jinshan industrial concentration area, No. 869, Panyu Road, Gaishan Town, Cangshan District, Fuzhou City, Fujian Province

Patentee after: Fujian Luhai Engineering Technology Co.,Ltd.

Address before: 350000 workshop No.5, Fuwan area, Jinshan industrial concentration area, no.869, Panyu Road, Gaishan Town, Cangshan District, Fuzhou City, Fujian Province

Patentee before: FUJIAN LUHAI ENGINEERING INVESTIGATION & DESIGN CO.,LTD.

CP03 Change of name, title or address