CN109680611A - A kind of deck unit erection gantry with automatic aligning pressure-bearing shearing resistance - Google Patents

A kind of deck unit erection gantry with automatic aligning pressure-bearing shearing resistance Download PDF

Info

Publication number
CN109680611A
CN109680611A CN201811492313.8A CN201811492313A CN109680611A CN 109680611 A CN109680611 A CN 109680611A CN 201811492313 A CN201811492313 A CN 201811492313A CN 109680611 A CN109680611 A CN 109680611A
Authority
CN
China
Prior art keywords
pressure
end carriage
bottom plate
bearing shearing
top plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811492313.8A
Other languages
Chinese (zh)
Other versions
CN109680611B (en
Inventor
朱东明
李慧明
李正兵
向华
梁辉
张延辉
夏朝鹃
杨志明
赵梦春
郑奕
徐振峰
闵理
陈逸
罗亚容
陈洁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Jiujiang Bridge Engineering Co Ltd
Original Assignee
China Railway Jiujiang Bridge Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Jiujiang Bridge Engineering Co Ltd filed Critical China Railway Jiujiang Bridge Engineering Co Ltd
Priority to CN201811492313.8A priority Critical patent/CN109680611B/en
Publication of CN109680611A publication Critical patent/CN109680611A/en
Application granted granted Critical
Publication of CN109680611B publication Critical patent/CN109680611B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Abstract

A kind of deck unit erection gantry with automatic aligning pressure-bearing shearing resistance, including the suspender being connect with end carriage, suspender lower end is fixed with heavy mail, is equipped with cord clip on the downside of the end carriage both ends, end carriage lower end is additionally provided with multiple pressure-bearing shearing-resistance blocks, the pressure-bearing shearing-resistance blocks include top plate, top plate lower end is fixed with bottom plate, and 4 corners on top plate upper surface are equipped with anti-hook, and top plate is further fixed on pin shaft on upper surface, the end carriage bottom end face is equipped with end carriage bottom plate, and end carriage bottom plate is equipped with multiple rows of pin shaft hole corresponding with pin shaft.The present invention is used to solve in bolt fixing method between traditional pressure-bearing shearing-resistance blocks and end carriage, and bolt interporal lacuna is small, location difficulty, and the problem of need to repeatedly tighten bolt, have it is easy to operate, the characteristics of improving work efficiency.

Description

A kind of deck unit erection gantry with automatic aligning pressure-bearing shearing resistance
Technical field
The present invention relates to a kind of deck unit erection gantries with automatic aligning pressure-bearing shearing resistance.
Background technique
Deck unit erection gantry is a kind of suspension bridge construction special equipment, and working method is provided across two main push-towing ropes of suspension bridge On, the girder steel under bridge is promoted, is installed, currently, deck unit erection gantry have been widely used in the construction of Chinese large-sized suspension bridge. As China's deck unit erection gantry designing technique and construction technology are more and more mature, under the premise of meeting construction feasibility, reliability, Construction party requires the convenience that deck unit erection gantry operates also higher and higher.
It is general on deck unit erection gantry that all there is pressure-bearing shearing resistance system, pressure-bearing shearing-resistance blocks are loaded on to the lower section of end carriage, when cable load is hung Before machine lifting, pressure-bearing shearing-resistance blocks need to be pressed on the main push-towing rope in front of cord clip, and by the rear end of pressure-bearing shearing-resistance blocks and cord clip On the one hand on the other hand front end fitting, the main push-towing rope gradient is caused by pressure-bearing shearing-resistance blocks by loop wheel machine weight transfer to main push-towing rope Sliding force be transferred on main push-towing rope cord clip.Since the position that deck unit erection gantry is stood when every section of girder steel is promoted is different, to guarantee The rear end of pressure-bearing shearing-resistance blocks is bonded with the front end of cord clip, need to often adjust front-rear position of the pressure-bearing shearing-resistance blocks on end carriage. And the mode that pressure-bearing shearing-resistance blocks and end carriage bottom plate are often connected by screw bolts by previous deck unit erection gantry, pressure-bearing shearing-resistance blocks are adjusted every time When position, it is both needed to remove multiple bolts, pressure-bearing shearing-resistance blocks is shifted, are positioned, then re-tighten bolt, operating procedure is numerous It is trivial.And due to sliding force need to by multiple bolt uniform forces, bolt interporal lacuna design value generally no more than 0.5mm, The requirement of bolt hole aligning accuracy is very high, this just brings bigger inconvenience to positioning process.To sum up, the pressure-bearing being connected by screw bolts Shearing-resistance blocks can bring very big difficulty to the operation of field worker, and have certain shadow to the construction efficiency of deck unit erection gantry It rings.
Summary of the invention
Its purpose of the invention, which is that, provides a kind of deck unit erection gantry with automatic aligning pressure-bearing shearing resistance, solves tradition and rises Positioning, problem difficult to install when heavy-duty machine pressure-bearing shearing-resistance blocks switching position, with easy to operate, mode of transfer force is reliable, work effect The high feature of rate.
It adopts the technical scheme that achieve the above object, a kind of deck unit erection gantry with automatic aligning pressure-bearing shearing resistance, Including the suspender connecting with end carriage, suspender lower end is fixed with heavy mail, is equipped with cord clip on the downside of the end carriage both ends, end carriage lower end is also Equipped with multiple pressure-bearing shearing-resistance blocks, the pressure-bearing shearing-resistance blocks include top plate, and top plate lower end is fixed with bottom plate, and bottom plate lower end is equipped with master Cable, main push-towing rope are fixed on the lower end of bottom plate through cord clip, and 4 corners on top plate upper surface are equipped with anti-hook, go back on top plate upper surface It is fixed with pin shaft, the end carriage bottom end face is equipped with end carriage bottom plate, and end carriage bottom plate is equipped with multiple rows of pin corresponding with pin shaft Axis hole.
Beneficial effect
The present invention has the following advantages that compared with prior art.
It is an advantage of the invention that solving in the bolt fixing method between traditional pressure-bearing shearing-resistance blocks and end carriage, between bolt hole Gap is small, positioning, difficult to install, and the problem of need to repeatedly tighten bolt, have it is easy to operate, the advantages of improving work efficiency.
Detailed description of the invention
The invention will be further described with reference to the accompanying drawing.
Fig. 1 is the structural diagram of the present invention;
Fig. 2 is part-structure side view of the invention;
Fig. 3 is the partial structure diagram of pressure-bearing shearing-resistance blocks in the present invention;
Fig. 4 is the structural schematic diagram in the present invention between pressure-bearing shearing-resistance blocks and main push-towing rope.
Specific embodiment
With reference to the accompanying drawing, the present invention is further illustrated.
A kind of deck unit erection gantry with automatic aligning pressure-bearing shearing resistance, including the suspender 4 connecting with end carriage 1,4 lower end of suspender is solid Surely there is heavy mail 5, as Figure 1-Figure 4, be equipped with cord clip 3 on the downside of 1 both ends of end carriage, 1 lower end of end carriage is additionally provided with multiple pressure-bearings Shearing-resistance blocks 2, the pressure-bearing shearing-resistance blocks 2 include top plate 10, and 10 lower end of top plate is fixed with bottom plate 11, and 11 lower end of bottom plate is equipped with main push-towing rope 12, main push-towing rope 12 is fixed on the lower end of bottom plate 11 through cord clip 3, and 4 corners on 10 upper surface of top plate are equipped with anti-hook 9, top plate 10 Be further fixed on pin shaft 8 on upper surface, 1 bottom end face of end carriage is equipped with end carriage bottom plate 7, end carriage bottom plate 7 be equipped with it is multiple rows of with The corresponding pin shaft hole 6 of pin shaft 8.
The pressure-bearing shearing-resistance blocks 2 are 3, and are evenly distributed between 2 cord clips 3.
The top of the pin shaft 8 is pyramidal structure, and pin shaft 8 is 4, and is fixed on the middle position of 10 upper surface of top plate, Pin shaft hole 6 on corresponding end carriage bottom plate 7 is more than the amount of pin shaft 8.
The contact surface of the bottom plate 11 and main push-towing rope 12 is arc structure, to adapt to the shape of main push-towing rope 12.
In the present invention, including 1 end carriage, 1,3 pressure-bearing shearing-resistance blocks 2, pressure-bearing shearing-resistance blocks 2 be installed on 1 lower section of end carriage before, In, rear three positions, the pressure-bearing shearing-resistance blocks 2 include that bottom plate 11,10,4, top plate pin shaft 8,4 instead hook 9, are set below bottom plate 11 For arc structure, to adapt to the shape of main push-towing rope 12 on suspension bridge, bottom plate 11 is fixedly arranged above top plate 10, leans on centre above top plate 10 Position is fixed with 4 pin shafts 8, and the top of pin shaft 8 is pyramidal structure, and the position at 4 angles is leaned on to be fixed with 4 instead above top plate 10 9 are hooked, the end carriage bottom plate 7 of 1 bottom of end carriage is equipped with multiple rows of pin shaft hole 6, for matching with the pin shaft 8 in pressure-bearing shearing-resistance blocks 3 It closes.
Due to needing demolition, installation 10 or more bolts when existing pressure-bearing shear resistance system changes position every time, and bolt hole fills With precision within 0.5mm, assembly difficulty is very big, and traditional bolted pressure-bearing shear resistance system is changed to pin shaft by the present invention The pressure-bearing shearing-resistance blocks 2 of formula connection, and special structure is used, weight when need to only be pushed using deck unit erection gantry when changing position every time Power automatic aligning is not required to demolition, installation bolt, have it is easy to operate, the characteristics of improving work efficiency.

Claims (4)

1. a kind of deck unit erection gantry with automatic aligning pressure-bearing shearing resistance, including the suspender (4) being connect with end carriage (1), under suspender (4) End is fixed with heavy mail (5), which is characterized in that is equipped with cord clip (3) on the downside of end carriage (1) both ends, end carriage (1) lower end is additionally provided with Multiple pressure-bearing shearing-resistance blocks (2), the pressure-bearing shearing-resistance blocks (2) include top plate (10), and top plate (10) lower end is fixed with bottom plate (11), bottom Plate (11) lower end is equipped with main push-towing rope (12), and main push-towing rope (12) is fixed on the lower end of bottom plate (11) through cord clip (3), on top plate (10) upper surface 4 corners be equipped with it is anti-hook (9), be further fixed on pin shaft (8) on top plate (10) upper surface, on end carriage (1) bottom end face Equipped with end carriage bottom plate (7), end carriage bottom plate (7) is equipped with multiple rows of pin shaft hole (6) corresponding with pin shaft (8).
2. a kind of deck unit erection gantry with automatic aligning pressure-bearing shearing resistance according to claim 1, which is characterized in that described to hold Pressing shearing-resistance blocks (2) is 3, and is evenly distributed between 2 cord clips (3).
3. a kind of deck unit erection gantry with automatic aligning pressure-bearing shearing resistance according to claim 1, which is characterized in that the pin Axis (8) is 4, and is fixed on the middle position of top plate (10) upper surface, pin shaft hole (6) ratio on corresponding end carriage bottom plate (7) The amount of pin shaft (8) is more.
4. a kind of deck unit erection gantry with automatic aligning pressure-bearing shearing resistance according to claim 1, which is characterized in that the bottom Plate (11) and the contact surface of main push-towing rope (12) are arc structure, to adapt to the shape of main push-towing rope (12).
CN201811492313.8A 2018-12-07 2018-12-07 Cable-carrying crane with automatic alignment pressure-bearing shearing resistance Active CN109680611B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811492313.8A CN109680611B (en) 2018-12-07 2018-12-07 Cable-carrying crane with automatic alignment pressure-bearing shearing resistance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811492313.8A CN109680611B (en) 2018-12-07 2018-12-07 Cable-carrying crane with automatic alignment pressure-bearing shearing resistance

Publications (2)

Publication Number Publication Date
CN109680611A true CN109680611A (en) 2019-04-26
CN109680611B CN109680611B (en) 2023-10-20

Family

ID=66186516

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811492313.8A Active CN109680611B (en) 2018-12-07 2018-12-07 Cable-carrying crane with automatic alignment pressure-bearing shearing resistance

Country Status (1)

Country Link
CN (1) CN109680611B (en)

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10237821A (en) * 1997-02-26 1998-09-08 Ishikawajima Harima Heavy Ind Co Ltd Device for carrying and installing suspension bridge cable band
KR20060054732A (en) * 2004-11-16 2006-05-23 주식회사한국삭도 The cable crane for a civil engineering and construction working
CN201292509Y (en) * 2008-09-18 2009-08-19 湖南路桥建设集团公司 Suspension bridge main girder construction segment conveying facilities
CN101559905A (en) * 2009-05-12 2009-10-21 广东省长大公路工程有限公司 Deck unit erection gantry
CN101863423A (en) * 2010-06-23 2010-10-20 广东省长大公路工程有限公司 Steel box beam cable carrying lifter for construction of suspension bridge
CN102154987A (en) * 2011-04-11 2011-08-17 西南交通大学 On-cable walking-type self-walking system
CN202073039U (en) * 2011-04-11 2011-12-14 西南交通大学 Mechanical automatic cable clamping device for cable operation
CN103224198A (en) * 2013-05-21 2013-07-31 中铁九桥工程有限公司 Hydraulic travelling-pedrail type cable crane capable of travelling with load
CN105002831A (en) * 2015-08-13 2015-10-28 贵州路桥集团有限公司 Wheel-rail type loading and traveling cable crane
CN106917354A (en) * 2017-01-21 2017-07-04 广西大学 Cable carrying crane combining hoisting and walking
CN108203932A (en) * 2018-03-15 2018-06-26 西京学院 A kind of galvanized wire for suspension bridge Lift-on/Lift-off System and its installation method
CN209538035U (en) * 2018-12-07 2019-10-25 中铁九桥工程有限公司 A kind of deck unit erection gantry device with automatic aligning pressure-bearing shearing resistance

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10237821A (en) * 1997-02-26 1998-09-08 Ishikawajima Harima Heavy Ind Co Ltd Device for carrying and installing suspension bridge cable band
KR20060054732A (en) * 2004-11-16 2006-05-23 주식회사한국삭도 The cable crane for a civil engineering and construction working
CN201292509Y (en) * 2008-09-18 2009-08-19 湖南路桥建设集团公司 Suspension bridge main girder construction segment conveying facilities
CN101559905A (en) * 2009-05-12 2009-10-21 广东省长大公路工程有限公司 Deck unit erection gantry
CN101863423A (en) * 2010-06-23 2010-10-20 广东省长大公路工程有限公司 Steel box beam cable carrying lifter for construction of suspension bridge
CN102154987A (en) * 2011-04-11 2011-08-17 西南交通大学 On-cable walking-type self-walking system
CN202073039U (en) * 2011-04-11 2011-12-14 西南交通大学 Mechanical automatic cable clamping device for cable operation
CN103224198A (en) * 2013-05-21 2013-07-31 中铁九桥工程有限公司 Hydraulic travelling-pedrail type cable crane capable of travelling with load
CN105002831A (en) * 2015-08-13 2015-10-28 贵州路桥集团有限公司 Wheel-rail type loading and traveling cable crane
CN106917354A (en) * 2017-01-21 2017-07-04 广西大学 Cable carrying crane combining hoisting and walking
CN108203932A (en) * 2018-03-15 2018-06-26 西京学院 A kind of galvanized wire for suspension bridge Lift-on/Lift-off System and its installation method
CN209538035U (en) * 2018-12-07 2019-10-25 中铁九桥工程有限公司 A kind of deck unit erection gantry device with automatic aligning pressure-bearing shearing resistance

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘显晖;邓年春;陈立;李海峰;伍柳毅;: "缆载吊机安全性设计与试验及施工关键技术", 装备制造技术, no. 02 *
燕文涛;: "沪通长江大桥主航道桥钢桁梁锚箱施工技术", 世界桥梁, no. 01 *
纪长春;: "某悬索桥300 t缆载吊机机构组成及安拆工艺分析", 机电信息, no. 33 *

Also Published As

Publication number Publication date
CN109680611B (en) 2023-10-20

Similar Documents

Publication Publication Date Title
CN201999655U (en) Conversion device connecting tower crane and self-jacking construction platform
CN209538035U (en) A kind of deck unit erection gantry device with automatic aligning pressure-bearing shearing resistance
CN109680611A (en) A kind of deck unit erection gantry with automatic aligning pressure-bearing shearing resistance
CN202978098U (en) Overhead ground wire lifter
CN202245723U (en) Split type lifting fixture for unit plate block of curtain wall
CN209277011U (en) Suspension bridge steel truss girder micromatic setting
CN210103341U (en) Boom lower chord connecting structure
CN102275812A (en) Eccentric lifting appliance
CN202265304U (en) Hoisting device for support insulator
CN202510468U (en) Horse head pin safety device of oil pumping unit
CN107740443B (en) The prefabricated ring beam of town road inspection shaft and well seat mounting apparatus and installation method
CN201367303Y (en) Side bearing sling
CN210764029U (en) Hoisting tool for repairing pipe bracket valve
CN205772897U (en) The movable pulley yoke of marine crane
CN209364522U (en) A kind of generator upper spider jack sleeve dial-out utility
CN216038136U (en) Novel many hoists quick change device
CN209337953U (en) A kind of more suspension hook Hoisting Balance Beam of Crane of adjustable lifting length
CN214531840U (en) Pin-connected panel elevartor shaft hoisting frame
CN208292500U (en) A kind of explosion-proof steel plate hoisting clamp
CN217179812U (en) Formwork support upright rod axial force monitoring device on high formwork supporting monitoring system
CN220593002U (en) Grinding roller assembly dismounting device
CN210103355U (en) Hoisting device
CN215592321U (en) U-shaped clamp for transferring and hoisting scaffold steel pipe
CN209974129U (en) Hoisting device for flange
CN213392106U (en) Balancing device for hydraulic pumping unit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant