CN109667377A - The construction method and prestressed concrete overlapped slab of prestressed concrete overlapped slab - Google Patents

The construction method and prestressed concrete overlapped slab of prestressed concrete overlapped slab Download PDF

Info

Publication number
CN109667377A
CN109667377A CN201910083969.2A CN201910083969A CN109667377A CN 109667377 A CN109667377 A CN 109667377A CN 201910083969 A CN201910083969 A CN 201910083969A CN 109667377 A CN109667377 A CN 109667377A
Authority
CN
China
Prior art keywords
thin slab
prestressed
concrete
prestressed thin
slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910083969.2A
Other languages
Chinese (zh)
Other versions
CN109667377B (en
Inventor
杨新磊
马雨
张勃
王海良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Chengjian University
Original Assignee
Tianjin Chengjian University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Chengjian University filed Critical Tianjin Chengjian University
Priority to CN201910083969.2A priority Critical patent/CN109667377B/en
Publication of CN109667377A publication Critical patent/CN109667377A/en
Application granted granted Critical
Publication of CN109667377B publication Critical patent/CN109667377B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/32Floor structures wholly cast in situ with or without form units or reinforcements
    • E04B5/36Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor
    • E04B5/38Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor with slab-shaped form units acting simultaneously as reinforcement; Form slabs with reinforcements extending laterally outside the element
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/48Special adaptations of floors for incorporating ducts, e.g. for heating or ventilating

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
  • Road Paving Structures (AREA)

Abstract

The present invention relates to the construction method and prestressed concrete overlapped slab of prestressed concrete overlapped slab, construction method are as follows: the precast prestressed thin plate of S1, in the multiple concrete reinforcement blocks of prestressed thin slab ontology upper end formed by integrally casting;S2 at the construction field (site), has connected the steel pipe of booster action on prestressed thin slab;Smooth adjusting is carried out to prestressed thin slab in S3 necessity situation;S4 is laid with transverse steel and longitudinal reinforcement and equipment installation above the prestressed thin slab between concrete reinforcement block;S5 is to pour bed die in prestressed thin slab upper end casting concrete with prestressed thin slab, and concreting to the position flushed with concrete reinforcement block upper end forms concrete folding layer;S6 removal connects the bolt of prestressed thin slab and steel pipe, takes steel pipe away, and prestressed thin slab, vertically and horizontally reinforcing bar and rear pouring concrete form prestressed concrete overlapped slab.This construction method saves construction form bracing, the deflection deformation adjustment after prestressed thin slab is put can be achieved, easy to operate, construction cost is low.

Description

The construction method and prestressed concrete overlapped slab of prestressed concrete overlapped slab
Technical field
The present invention relates to assembled arthitecutral structure field, it is related to overlapping plate technique, specific prestressed concrete overlapped slab Construction method and prestressed concrete overlapped slab.
Background technique
A kind of preferable structure type that superimposed sheet is prefabricated and cast-in-place concrete combines.Prestressed thin slab is cast-in-place with top Concrete layer is combined into an entirety, works together.Prestressed thin slab is used as the bed die of cast-in-place concrete layer, then does not need another Outer shuttering supporting;Superimposed sheet has globality, the rigidity of cast-in-situ floor are big, crack resistance is good, do not increase reinforcing bar consume, save mould Plate.So superimposed sheet is then in booming period in China's floor using in development.Existing China mainly uses steel bar girder Superimposed sheet and PK prestressing force superimposed sheet.
(1) steel bar girder superimposed sheet can increase the rigidity before superimposed sheet overlaps and bearing capacity significantly, good using designing Good steel bar girder can satisfy the strength and stiffness needed before overlapping;Steel bar girder support frame, globality can be very good.But It is that steel bar girder overlapping board member manufacture craft is more complicated;Need excessive live floor falsework.Due to truss bars More complicated, equipment installation can lay inconvenience, and the protective layer of equipment installation is also not sufficiently thick;Due to steel bar girder superimposed sheet Reinforcing bar has excessive Exposed reinforcement outside plate, will cause the waste of reinforcing bar.
(2) PK superimposed sheet uses prestressing force prefabricated plate with ribbing, and thin plate can bear construction loads, saves template and support, Elongate holes are reserved on rib, reinforcing bar and pipeline can be worn in hole, form two-way reinforcement floor, use broken line in the edge joint position of thin plate Reinforcing bar cracking resistance improves the cracking resistance of floor.Due to be provided with rib of slab so that prefabricated components in transport and work progress not Frangibility, and can effectively control prestressing camber value.Since PK superimposed sheet uses pre-tensioning system technique, preset thin plate concrete Reach and carry out prestressing force after 75% design strength and put, board bottom still prestressing camber is unstable;Double-T shaped section rib, double square Section rib, rib holes transverse reinforcement, embolism extinguishing effect have much room for improvement.Since the rib of slab of PK plate and the gap of thin plate are not big enough, equipment pipe After line setting, protective layer thickness is inadequate.
It retrieves, does not retrieve and this patent analogous technical scheme through the prior art.
Summary of the invention
It is an object of the present invention to provide a kind of prestressed concrete overlapped slab in place of overcome the deficiencies in the prior art Construction method, which can save construction form bracing, the deflection deformation adjustment after prestressed thin slab is put can be achieved, It is easy to operate, construction cost is low, the prestressed concrete overlapped slab as made from the construction method is smooth, can be convenient for equipment installation It arranges and the protective layer of pipeline can be made to reach most enough thickness.
Above-mentioned purpose of the invention is realized by following technical solution:
A kind of construction method of prestressed concrete overlapped slab, which is characterized in that including following construction procedure:
The precast prestressed thin plate of S1, in the multiple concrete reinforcement blocks of prestressed thin slab ontology upper end formed by integrally casting, concrete Reinforcement block is disposed in proximity to prestressed thin slab ontology both ends and medium position and arranges along the longitudinal direction of prestressed thin slab by row Column, in the reserved bolt hole in the center of each concrete reinforcement block position corresponding with prestressed thin slab ontology;
S2 at the construction field (site), has connected the steel pipe of booster action: each of on prestressed thin slab on prestressed thin slab A bolt is installed in prepared screw-bolt hole from bottom to top, and gasket is installed between nuts and the lower end surface of prestressed thin slab, Bolt from the upper end that concrete reinforcement block stretches out installs steel pipe and by nut check, steel pipe along prestressed thin slab long side Direction is arranged in parallel;
Smooth adjusting is carried out to prestressed thin slab in S3 necessity situation:
After prestressed thin slab is put, it may appear that three kinds of situations: 1, deflection deformation does not occur for prestressed thin slab;2, prestressing force Thin plate both sides are constant, and middle part bends downward deformation;3, prestressed thin slab both sides are constant, and middle part bends upwardly-deformed; For the first case, it does not need to carry out flatness adjusting, only needs to install the upper of position in each bolt of steel pipe in step 2 Side's connection upper nut;For second situation, installs in the bolts at two ends of steel pipe and be separately connected above and below position Portion's nut and lower nuts are fixedly connected with the two-end part of steel pipe with the both sides of prestressed thin slab, and the middle part bolt of steel pipe It installs position and only connects upper nut above, which is screwed, until the bolt in middle part bolt mounting hole Upper protruded length is consistent with protruded length on the bolt in bolts at two ends mounting hole, is pulled up tune in the middle part of prestressed thin slab at this time It is flat;For the third situation: being installed in the middle part bolt of steel pipe and be separately connected upper nut and lower part above and below position Nut makes to be fixedly connected in the middle part of the middle part of steel pipe and prestressed thin slab, and the bolts at two ends mounting hole position of steel pipe is only upper Side's connection upper nut, screws the upper nut at both ends, until protruded length on the bolt in bolts at two ends mounting hole Consistent with spiral shell length outer on the bolt in the bolt mounting hole of middle part, the both sides of prestressed thin slab are pulled up leveling at this time;
S4 is laid with laterally above the prestressed thin slab after prestressed thin slab reaches formation state between concrete reinforcement block Reinforcing bar, longitudinal reinforcement and equipment installation;
S5 is qualified through detection after the completion of reinforcing bar and equipment installation are all laid with, and meets design requirement, then thin with prestressing force Plate is to pour bed die in prestressed thin slab upper end casting concrete, concreting to the position flushed with concrete reinforcement block upper end It sets, forms concrete folding layer;
S6 backs out the nut of joint steel pipe and prestressed thin slab after concrete curing, takes steel pipe away and removal is installed on Bolt in prepared screw-bolt hole and the gasket on bolt is covered, prestressed thin slab, vertically and horizontally reinforcing bar and rear pouring concrete form pre- Prestressed concrete superimposed sheet.
The second object of the present invention is in place of overcome the deficiencies in the prior art, provides a kind of prestressed concrete overlapping Plate, the superimposed sheet structure is simple, carries out equipment installation laying convenient for constructing, facilitating inside, increases the protection of equipment installation Thickness degree.
A kind of prestressed concrete overlapped slab, it is characterised in that: the superimposed sheet is by above-mentioned prestressed concrete overlapped slab Construction method be made, the superimposed sheet is by prestressed thin slab, the vertical, horizontal reinforcing bar and equipment pipe that are layed on prestressed thin slab Line, after-pouring are formed in the concrete folding on prestressed thin slab;
The prestressed thin slab is by prestressed thin slab ontology and formed by integrally casting in the multiple mixed of prestressed thin slab ontology upper end Solidifying soil reinforcement block is constituted;The vertical, horizontal reinforcing bar and equipment installation are layed between concrete reinforcement block.
And, the concrete reinforcement block is rectangular block structure.
The advantages and positive effects of the present invention are:
1, this construction method joint steel pipe above the concrete reinforcement block of prestressed thin slab, makes the rigidity of prestressed thin slab It increases substantially, so as to bear biggish construction loads, the support of floor can be reduced in this way, in this embodiment it is not even necessary to the branch of floor Support, has achieved the purpose that less construction form bracing;
2, this construction method passes through in the case where deflection deformation occurs after prestressed thin slab is put and adjusts corresponding position spiral shell Upper square nut on bolt is, it can be achieved that the leveling of prestressed thin slab ensure that convenient for the construction of postorder prestressed concrete overlapped slab The product quality of construction.
3, due to adjust prestressed thin slab not usually, nuts can form Concentrated load to prestressed thin slab, By adding gasket between nuts and the lower end of prestressed thin slab, can be crushed to avoid office bad.
4, bolt, steel pipe, gasket, upper square nut and the lower square nut used in this construction method, in concrete folding layer It after the completion of pouring, can remove, realize and reuse, reduce construction cost, save construction expenditure.
5, this prestressed concrete overlapped slab uses the structure of formed by integrally casting concrete reinforcement block on prestressed thin slab ontology, The rigidity of prestressed thin slab is increased, is not easily broken prestressed thin slab in transit, in addition, structure is simplified, compared to Complicated truss superimposed sheet facilitates construction production.
6, this prestressed concrete overlapped slab uses the structure of formed by integrally casting concrete reinforcement block on prestressed thin slab ontology, Before concrete folding layer pours, can sufficiently it be laid with laterally and longitudinally between the concrete reinforcement block of prestressed thin slab ontology upper end Reinforcing bar, the superimposed sheet after making casting concrete become two-way slab, in addition, due to there is sufficient cloth in prestressed thin slab ontology upper end If space, to also facilitate the laying of equipment installation, the protective layer thickness of equipment installation is greatly improved.
7, this prestressed concrete overlapped slab is made by above-mentioned construction method, ensure that prestressed concrete overlapped slab Flatness.
Detailed description of the invention
Fig. 1 is the Construction State solid of prestressed concrete overlapped slab of the present invention with reference to figure;
Fig. 2 is the Construction State Plane reference figure of prestressed concrete overlapped slab of the present invention;
Fig. 3 is the structural schematic diagram of prestressed concrete overlapped slab of the present invention;
Fig. 4 is the structural schematic diagram of prestressed thin slab of the present invention.
Specific embodiment
The invention will be further described with reference to the accompanying drawing and by specific embodiment, and following embodiment is descriptive , it is not restrictive, this does not limit the scope of protection of the present invention.
A kind of construction method of prestressed concrete overlapped slab, referring to Figure 1-4, inventive point are as follows: including constructing as follows Step:
The precast prestressed thin plate 1 of S1, in the upper end the prestressed thin slab ontology 1-1 multiple concrete reinforcement block 1-2 of formed by integrally casting, Concrete reinforcement block is disposed in proximity to prestressed thin slab ontology both ends and medium position and the longitudinal direction along prestressed thin slab By rows, in the reserved bolt hole 1-2- in the center of each concrete reinforcement block position corresponding with prestressed thin slab ontology 1.When prefabricated, according to the rigidity needs of floor, the quantity of strict control concrete reinforcement block, it is ensured that the rigidity of prestressed thin slab Sufficiently large, guarantee does not fracture in transit.
S2 at the construction field (site), has connected the steel pipe 6 of booster action: each of on prestressed thin slab on prestressed thin slab A bolt 8 is installed in prepared screw-bolt hole from bottom to top, and gasket 9 is installed between nuts and the lower end surface of prestressed thin slab, From the upper end that concrete reinforcement block stretches out install steel pipe in bolt and by nut check, steel pipe along prestressed thin slab length Edge direction is arranged in parallel.
Smooth adjusting is carried out to prestressed thin slab in S3 necessity situation:
After prestressed thin slab is put, it may appear that three kinds of situations: 1, deflection deformation does not occur for prestressed thin slab;2, prestressing force Thin plate both sides are constant, and middle part bends downward deformation;3, prestressed thin slab both sides are constant, and middle part bends upwardly-deformed; For the first case, it does not need to carry out flatness adjusting, only needs to install the upper of position in each bolt of steel pipe in step 2 Side's connection upper nut;For second situation, installs in the bolts at two ends of steel pipe and be separately connected above and below position Portion's nut 7 and lower nuts 5, are fixedly connected with the two-end part of steel pipe with the both sides of prestressed thin slab, and the middle part spiral shell of steel pipe Bolt installs position and only connects upper nut above, screws to the upper nut, until the spiral shell in middle part bolt mounting hole Protruded length is consistent with protruded length on the bolt in bolts at two ends mounting hole on bolt, is pulled up in the middle part of prestressed thin slab at this time Leveling;For the third situation: being installed in the middle part bolt of steel pipe and be separately connected upper nut above and below position under Portion's nut makes to be fixedly connected in the middle part of the middle part of steel pipe and prestressed thin slab, and the bolts at two ends mounting hole position of steel pipe only exists Top connects upper nut, and the upper nut at more both ends is screwed, until exposed length on the bolt in bolts at two ends mounting hole Degree is consistent with outer spiral shell length on the bolt in the bolt mounting hole of middle part, and the both sides of prestressed thin slab are pulled up leveling at this time.It is above-mentioned The bolt being threaded onto each prepared screw-bolt hole need to use the bolt of same size.
S4 is laid with laterally above the prestressed thin slab after prestressed thin slab reaches formation state between concrete reinforcement block Reinforcing bar 2 and longitudinal reinforcement 4, specifically, being first laid with row reinforcing bar and longitudinal reinforcement still has abundance after the completion of being laid with reinforcing bar Space installation apparatus pipeline, since coagulation reinforcement block height is sufficiently large, then the protective layer thickness of equipment installation can also increase.Equipment Pipeline includes electric line, water pipeline etc..
S5 is qualified through detection after the completion of reinforcing bar and equipment installation are all laid with, and meets design requirement, then thin with prestressing force Plate is to pour bed die in prestressed thin slab upper end casting concrete, concreting to the position flushed with concrete reinforcement block upper end It sets, forms concrete folding layer 3.
S6 backs out the nut of joint steel pipe and prestressed thin slab after concrete curing, takes steel pipe away and removal is installed on Bolt in prepared screw-bolt hole and the gasket on bolt is covered, prestressed thin slab, vertically and horizontally reinforcing bar and rear pouring concrete form pre- Prestressed concrete superimposed sheet.
A kind of prestressed concrete overlapped slab, referring to Figure 1-4, the superimposed sheet is by above-mentioned prestressed concrete overlapped slab Construction method be made, superimposed sheet structure are as follows: by prestressed thin slab, the vertical, horizontal reinforcing bar being layed on prestressed thin slab and set Standby pipeline, after-pouring are formed in the concrete folding on prestressed thin slab.
The prestressed thin slab is by prestressed thin slab ontology and formed by integrally casting in the multiple mixed of prestressed thin slab ontology upper end Solidifying soil reinforcement block is constituted;The vertical, horizontal reinforcing bar and equipment installation are layed between concrete reinforcement block.
The characteristics of above-mentioned concrete reinforcement block preferably uses rectangular block structure, has shape regular, is convenient for pouring construction.
Although disclosing the embodiment of the present invention and attached drawing for the purpose of illustration, those skilled in the art can be managed Solution: do not departing from the present invention and spirit and scope of the appended claims in, various substitutions, changes and modifications be all it is possible, Therefore, the scope of the present invention is not limited to the embodiment and attached drawing disclosure of that.

Claims (3)

1. a kind of construction method of prestressed concrete overlapped slab, which is characterized in that including following construction procedure:
The precast prestressed thin plate of S1, in the multiple concrete reinforcement blocks of prestressed thin slab ontology upper end formed by integrally casting, concrete is reinforced Block be disposed in proximity to prestressed thin slab ontology both ends and medium position and along the longitudinal direction of prestressed thin slab by rows, In the reserved bolt hole in the center of each concrete reinforcement block position corresponding with prestressed thin slab ontology;
S2 at the construction field (site), has connected the steel pipe of booster action on prestressed thin slab: reserving each of on prestressed thin slab A bolt is installed in bolt hole from bottom to top, and gasket is installed between nuts and the lower end surface of prestressed thin slab, in bolt Install steel pipe from the upper end that concrete reinforcement block stretches out and by nut check, steel pipe along prestressed thin slab longitudinal direction It is arranged in parallel;
Smooth adjusting is carried out to prestressed thin slab in S3 necessity situation:
After prestressed thin slab is put, it may appear that three kinds of situations: 1, deflection deformation does not occur for prestressed thin slab;2, prestressed thin slab Both sides are constant, and middle part bends downward deformation;3, prestressed thin slab both sides are constant, and middle part bends upwardly-deformed;For The first situation does not need to carry out flatness adjusting, only needs to install in each bolt of steel pipe in step 2 and connect above position Connect upper nut;For second situation, is installed in the bolts at two ends of steel pipe and be separately connected top spiral shell above and below position Female and lower nuts, are fixedly connected with the two-end part of steel pipe with the both sides of prestressed thin slab, and the middle part bolt of steel pipe installs Position only connects upper nut above, screws to the upper nut, until outer on the bolt in middle part bolt mounting hole It is consistent with protruded length on the bolt in bolts at two ends mounting hole to reveal length, is pulled up leveling in the middle part of prestressed thin slab at this time; For the third situation: being installed in the middle part bolt of steel pipe and be separately connected upper nut and lower part spiral shell above and below position Mother makes to be fixedly connected in the middle part of the middle part of steel pipe and prestressed thin slab, and the bolts at two ends mounting hole position of steel pipe is only above Connect upper nut, the upper nut at both ends is screwed, until bolts at two ends mounting hole in bolt on protruded length with Outer spiral shell length is consistent on bolt in the bolt mounting hole of middle part, and the both sides of prestressed thin slab are pulled up leveling at this time;
S4 is laid with lateral steel above the prestressed thin slab after prestressed thin slab reaches formation state between concrete reinforcement block Muscle, longitudinal reinforcement and equipment installation;
S5 is qualified through detection after the completion of reinforcing bar and equipment installation are all laid with, and meets design requirement, then with prestressed thin slab To pour bed die in prestressed thin slab upper end casting concrete, concreting to the position flushed with concrete reinforcement block upper end It sets, forms concrete folding layer;
S6 backs out the nut of joint steel pipe and prestressed thin slab after concrete curing, take steel pipe away and removal be installed on it is pre- It stays the bolt in bolt hole and covers the gasket on bolt, prestressed thin slab, vertically and horizontally reinforcing bar and rear pouring concrete form pre- answer Power concrete folding plate.
2. a kind of prestressed concrete overlapped slab, it is characterised in that: the superimposed sheet is by prestressed concrete described in claim 1 The construction method of native superimposed sheet is made, and the superimposed sheet is by prestressed thin slab, the vertical, horizontal reinforcing bar being layed on prestressed thin slab It is formed with equipment installation, after-pouring in the concrete folding on prestressed thin slab;
The prestressed thin slab is by prestressed thin slab ontology and formed by integrally casting in multiple concrete of prestressed thin slab ontology upper end Reinforcement block is constituted;The vertical, horizontal reinforcing bar and equipment installation are layed between concrete reinforcement block.
3. prestressed concrete overlapped slab according to claim 2, it is characterised in that: the concrete reinforcement block is rectangular Block structure.
CN201910083969.2A 2019-01-29 2019-01-29 Construction method of prestressed concrete laminated slab and prestressed concrete laminated slab Active CN109667377B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910083969.2A CN109667377B (en) 2019-01-29 2019-01-29 Construction method of prestressed concrete laminated slab and prestressed concrete laminated slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910083969.2A CN109667377B (en) 2019-01-29 2019-01-29 Construction method of prestressed concrete laminated slab and prestressed concrete laminated slab

Publications (2)

Publication Number Publication Date
CN109667377A true CN109667377A (en) 2019-04-23
CN109667377B CN109667377B (en) 2023-11-24

Family

ID=66150864

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910083969.2A Active CN109667377B (en) 2019-01-29 2019-01-29 Construction method of prestressed concrete laminated slab and prestressed concrete laminated slab

Country Status (1)

Country Link
CN (1) CN109667377B (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110185182A (en) * 2019-06-13 2019-08-30 天津城建大学 Concrete folding plate construction is with being stably connected with structure and construction method
CN110725457A (en) * 2019-11-18 2020-01-24 上海中森建筑与工程设计顾问有限公司 Detachable-support assembled composite floor slab and construction method thereof
CN110748066A (en) * 2019-11-27 2020-02-04 山东德建集团有限公司 Support-free laminated slab comprising truss and truss machining device and method
CN112962848A (en) * 2021-02-05 2021-06-15 江苏广兴集团建筑装配科技有限公司 Laminated floor slab with improved bearing strength
CN112976256A (en) * 2021-02-05 2021-06-18 王示 Production process of prestressed concrete laminated slab bottom plate
CN113137075A (en) * 2021-04-27 2021-07-20 荣华(青岛)建设科技有限公司 Detachable tool for controlling reverse arch value of laminated slab and using method thereof
CN113175142A (en) * 2021-05-14 2021-07-27 重庆中科建筑科技(集团)有限公司 Construction method of composite floor slab with detachable additional stiffness part
CN113250362A (en) * 2021-06-01 2021-08-13 武汉理工大学 Concrete composite floor slab and supporting structure thereof
CN113882570A (en) * 2021-10-29 2022-01-04 筑友智造建设科技集团有限公司 Prefabricated base plate with removable ribs and production method of laminated slab
CN113931364A (en) * 2021-10-29 2022-01-14 筑友智造建设科技集团有限公司 Construction method of prestressed thin plate with detachable ribs and laminated slab
CN113958049A (en) * 2021-11-23 2022-01-21 重庆大学 Scissor fork type building steel frame and laminated slab connecting structure
CN114837337A (en) * 2022-06-21 2022-08-02 中建科技(济南)有限公司 Prestress laminated bottom plate with turnover ribs and production and construction process
CN115431397A (en) * 2021-06-01 2022-12-06 广东博智林机器人有限公司 Production process and production equipment system for concrete prefabricated bottom plate
CN118048996A (en) * 2024-03-26 2024-05-17 杭州友巢结构设计事务所有限公司 Concrete laminated slab with detachable steel pipe ribs

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1284402A (en) * 1968-08-06 1972-08-09 Rheinbau Gmbh Improvements in and relating to building constructions
CN101793074A (en) * 2009-12-16 2010-08-04 中国建筑东北设计研究院有限公司 Fish-bellied type prestressed concrete two-way composite slab
KR101329490B1 (en) * 2012-12-28 2013-11-13 서울시립대학교 산학협력단 Installation structure for controlling deflection of deck plate of slim floor with altering support point and construction method thereof
CN104074293A (en) * 2014-07-16 2014-10-01 赵春樵 Reinforced-concrete prefabricated dense-rib sheet and constructing method
CN109083320A (en) * 2018-09-26 2018-12-25 重庆普珞沃建筑科技有限公司 Combine prefabricated panel and laminated floor slab structure and laminated floor slab construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1284402A (en) * 1968-08-06 1972-08-09 Rheinbau Gmbh Improvements in and relating to building constructions
CN101793074A (en) * 2009-12-16 2010-08-04 中国建筑东北设计研究院有限公司 Fish-bellied type prestressed concrete two-way composite slab
KR101329490B1 (en) * 2012-12-28 2013-11-13 서울시립대학교 산학협력단 Installation structure for controlling deflection of deck plate of slim floor with altering support point and construction method thereof
CN104074293A (en) * 2014-07-16 2014-10-01 赵春樵 Reinforced-concrete prefabricated dense-rib sheet and constructing method
CN109083320A (en) * 2018-09-26 2018-12-25 重庆普珞沃建筑科技有限公司 Combine prefabricated panel and laminated floor slab structure and laminated floor slab construction method

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110185182A (en) * 2019-06-13 2019-08-30 天津城建大学 Concrete folding plate construction is with being stably connected with structure and construction method
CN110725457A (en) * 2019-11-18 2020-01-24 上海中森建筑与工程设计顾问有限公司 Detachable-support assembled composite floor slab and construction method thereof
CN110748066A (en) * 2019-11-27 2020-02-04 山东德建集团有限公司 Support-free laminated slab comprising truss and truss machining device and method
CN112962848B (en) * 2021-02-05 2022-09-06 江苏广兴集团建筑装配科技有限公司 Laminated floor slab with improved bearing strength
CN112976256A (en) * 2021-02-05 2021-06-18 王示 Production process of prestressed concrete laminated slab bottom plate
CN112962848A (en) * 2021-02-05 2021-06-15 江苏广兴集团建筑装配科技有限公司 Laminated floor slab with improved bearing strength
CN113137075A (en) * 2021-04-27 2021-07-20 荣华(青岛)建设科技有限公司 Detachable tool for controlling reverse arch value of laminated slab and using method thereof
CN113175142A (en) * 2021-05-14 2021-07-27 重庆中科建筑科技(集团)有限公司 Construction method of composite floor slab with detachable additional stiffness part
CN113250362A (en) * 2021-06-01 2021-08-13 武汉理工大学 Concrete composite floor slab and supporting structure thereof
CN115431397A (en) * 2021-06-01 2022-12-06 广东博智林机器人有限公司 Production process and production equipment system for concrete prefabricated bottom plate
CN113882570A (en) * 2021-10-29 2022-01-04 筑友智造建设科技集团有限公司 Prefabricated base plate with removable ribs and production method of laminated slab
CN113931364A (en) * 2021-10-29 2022-01-14 筑友智造建设科技集团有限公司 Construction method of prestressed thin plate with detachable ribs and laminated slab
CN113958049A (en) * 2021-11-23 2022-01-21 重庆大学 Scissor fork type building steel frame and laminated slab connecting structure
CN113958049B (en) * 2021-11-23 2022-12-27 重庆大学 Scissor fork type building steel frame and laminated slab connecting structure
CN114837337A (en) * 2022-06-21 2022-08-02 中建科技(济南)有限公司 Prestress laminated bottom plate with turnover ribs and production and construction process
CN118048996A (en) * 2024-03-26 2024-05-17 杭州友巢结构设计事务所有限公司 Concrete laminated slab with detachable steel pipe ribs

Also Published As

Publication number Publication date
CN109667377B (en) 2023-11-24

Similar Documents

Publication Publication Date Title
CN109667377A (en) The construction method and prestressed concrete overlapped slab of prestressed concrete overlapped slab
CN100526573C (en) Construction method of structure conversion layer concrete girder steel bracket formwork support
CN104963290A (en) Mold supporting structure for variable cross-section cast-in-place box girder at section combining horizontal and longitudinal curves, and construction method of the mold supporting structure
CN211517947U (en) Bridge case roof beam is prefabricated with shaped steel pedestal
CN111691582A (en) Close-spliced vertical joint structure of superposed shear wall and construction method
CN108149819B (en) Integrated superposed outer wall of building bottom reinforcing area and production and construction method thereof
CN107327050A (en) A kind of avoid-dismantle outer wall of basement flange single side formwork device and construction method
CN109469259A (en) The two-sided compound action beam of exchangeable part assembled steel-concrete
CN205530888U (en) Utilize built -in cast in situ concrete superstructure structure that supports pipe die of NZ
CN114575593A (en) Adjustable plate buckling formwork support frame for super-load small-clearance beam and construction method thereof
CN207812307U (en) The construction system of Cable stayed Bridge Main Tower and steel anchor beam
CN204875533U (en) Flat cast -in -place case roof beam of curve combination section variable cross section mode structure of indulging
CN103711199A (en) Method and structure for processing construction joints at large-section beam and column joints
CN105442737B (en) A kind of complex heat-preservation floorboard and its construction method
CN209703806U (en) A kind of prestressed concrete overlapped slab
CN110185182A (en) Concrete folding plate construction is with being stably connected with structure and construction method
CN217734853U (en) Adjustable plate buckling template support frame for super-load small-clear-distance beam
CN102936953A (en) Construction method of bridging-arm stiffened steel structure template
CN216109354U (en) Conversion layer steel column mounting structure
CN214530768U (en) Cast-in-place utility tunnel template bearing structure
CN212562028U (en) Close vertical seam structure of piecing together of superimposed shear wall
CN104847111B (en) Construction method for coupling beam between shear wall limbs
CN212388856U (en) Cast-in-place clear water concrete batter post structure of prestressing force
CN205296821U (en) Oblique roofing formwork system of heavy grade cast in situ concrete
CN210621630U (en) Concrete panel rock-fill dam

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20190423

Assignee: Tianjin United Chuangxing Technology Development Co.,Ltd.

Assignor: Tianjin Chengjian University

Contract record no.: X2024120000021

Denomination of invention: The construction method of prestressed concrete composite panels and prestressed concrete composite panels

Granted publication date: 20231124

License type: Common License

Record date: 20240126

Application publication date: 20190423

Assignee: Tianjin Liankai Technology Co.,Ltd.

Assignor: Tianjin Chengjian University

Contract record no.: X2024120000020

Denomination of invention: The construction method of prestressed concrete composite panels and prestressed concrete composite panels

Granted publication date: 20231124

License type: Common License

Record date: 20240129

Application publication date: 20190423

Assignee: Tianjin Xingdu Space Network Technology Co.,Ltd.

Assignor: Tianjin Chengjian University

Contract record no.: X2024120000019

Denomination of invention: The construction method of prestressed concrete composite panels and prestressed concrete composite panels

Granted publication date: 20231124

License type: Common License

Record date: 20240129

Application publication date: 20190423

Assignee: Yunneng Zhongchuang Investment Management (Tianjin) Co.,Ltd.

Assignor: Tianjin Chengjian University

Contract record no.: X2024120000018

Denomination of invention: The construction method of prestressed concrete composite panels and prestressed concrete composite panels

Granted publication date: 20231124

License type: Common License

Record date: 20240129

Application publication date: 20190423

Assignee: Tianjin 1919 Technology Co.,Ltd.

Assignor: Tianjin Chengjian University

Contract record no.: X2024120000017

Denomination of invention: The construction method of prestressed concrete composite panels and prestressed concrete composite panels

Granted publication date: 20231124

License type: Common License

Record date: 20240129

Application publication date: 20190423

Assignee: Liantai Kechuang (Tianjin) Co.,Ltd.

Assignor: Tianjin Chengjian University

Contract record no.: X2024120000016

Denomination of invention: The construction method of prestressed concrete composite panels and prestressed concrete composite panels

Granted publication date: 20231124

License type: Common License

Record date: 20240129

Application publication date: 20190423

Assignee: Gongneng Enterprise Management Consulting (Tianjin) Co.,Ltd.

Assignor: Tianjin Chengjian University

Contract record no.: X2024120000023

Denomination of invention: The construction method of prestressed concrete composite panels and prestressed concrete composite panels

Granted publication date: 20231124

License type: Common License

Record date: 20240126

Application publication date: 20190423

Assignee: Tianjin Huihe Investment Management Co.,Ltd.

Assignor: Tianjin Chengjian University

Contract record no.: X2024120000022

Denomination of invention: The construction method of prestressed concrete composite panels and prestressed concrete composite panels

Granted publication date: 20231124

License type: Common License

Record date: 20240126

EE01 Entry into force of recordation of patent licensing contract