CN109629696B - Connection node and bamboo building structure of former bamboo combination wallboard of assembled and floor - Google Patents
Connection node and bamboo building structure of former bamboo combination wallboard of assembled and floor Download PDFInfo
- Publication number
- CN109629696B CN109629696B CN201811627399.0A CN201811627399A CN109629696B CN 109629696 B CN109629696 B CN 109629696B CN 201811627399 A CN201811627399 A CN 201811627399A CN 109629696 B CN109629696 B CN 109629696B
- Authority
- CN
- China
- Prior art keywords
- side plate
- wallboard
- fixed
- bamboo
- floor slab
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 235000017166 Bambusa arundinacea Nutrition 0.000 title claims abstract description 60
- 235000017491 Bambusa tulda Nutrition 0.000 title claims abstract description 60
- 235000015334 Phyllostachys viridis Nutrition 0.000 title claims abstract description 60
- 241001330002 Bambuseae Species 0.000 title claims abstract description 55
- 239000011425 bamboo Substances 0.000 title claims abstract description 55
- 239000002131 composite material Substances 0.000 claims description 10
- 239000004570 mortar (masonry) Substances 0.000 claims description 9
- 241000209128 Bambusa Species 0.000 claims description 5
- 239000002002 slurry Substances 0.000 claims description 4
- 239000003351 stiffener Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000004134 energy conservation Methods 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/388—Separate connecting elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Load-Bearing And Curtain Walls (AREA)
- Joining Of Building Structures In Genera (AREA)
Abstract
The invention discloses a connection node of an assembled raw bamboo combined wallboard and a floor slab and a bamboo building structure, which comprise the wallboard, the floor slab, a top plate, a first side plate, a second side plate and a third side plate, wherein the top plate is positioned at the top of the wallboard, the first side plate is fixed at one end of the top plate, the second side plate is fixed at the other end of the top plate, the wallboard is clamped and fixed between the first side plate and the second side plate, the end part of the third side plate is fixed at the side surface of the second side plate, the end part of the floor slab is lapped and fixed on the third side plate, and the connection node can realize the fixed connection of the wallboard and the floor.
Description
Technical Field
The invention belongs to the field of bamboo structures, and relates to a connection node of an assembled raw bamboo combined wallboard and a floor slab and a bamboo building structure.
Background
Under the global trend of energy conservation and environmental protection, bamboo has the characteristics of easy propagation, fast growth, early yield, high yield and the like, and is widely applied to building structures, particularly in some earthquake-prone areas or tourist sightseeing areas, but the floor slabs and the wall boards in the existing bamboo building structures are in lap joint, so that the firmness of connection is poor, and the service life and the safety of the whole bamboo building structure are poor.
Disclosure of Invention
The invention aims to overcome the defects of the prior art and provides a connection node of an assembled raw bamboo combined wallboard and a floor slab and a bamboo building structure, wherein the connection node and the bamboo building structure can realize the fixed connection of the wallboard and the floor slab.
In order to achieve the purpose, the connection node of the assembled raw bamboo combined wallboard and the floor slab comprises a wallboard, the floor slab, a top plate, a first side plate, a second side plate and a third side plate, wherein the top plate is positioned at the top of the wallboard, the first side plate is fixed at one end of the top plate, the second side plate is fixed at the other end of the top plate, the wallboard is clamped and fixed between the first side plate and the second side plate, the end part of the third side plate is fixed on the side surface of the second side plate, and the end part of the floor slab is lapped and fixed on the third side plate.
The first bolt penetrates through the floor slab and the third side plate to lap the floor slab and is fixed on the third side plate.
The second bolt passes first curb plate, wallboard and second curb plate in proper order with the wallboard centre gripping and be fixed in between first curb plate and the second curb plate.
The wallboard comprises light composite mortar, concrete and a plurality of raw bamboos distributed in parallel, wherein two ends of each raw bamboo are aligned respectively, a through hole for a second bolt to pass through is formed in the end part of each raw bamboo, the middle part of each raw bamboo is wrapped in the light composite mortar, and the end part of each raw bamboo is wrapped in the concrete.
The end of the raw bamboo is filled with slurry.
A sleeve is inserted into the through hole, and a second bolt penetrates through the sleeve.
The bottom surface of the end part of the floor slab is provided with a gap, and the third side plate is positioned in the gap.
The second side plate is fixed on the first side plate, and the third side plate is fixed on the second side plate.
The wallboard fixing device comprises a wallboard, a plurality of pairs of connecting pieces, a foundation and a plurality of pairs of connecting pieces, wherein the lower end of the wallboard is arranged on the foundation, two connecting pieces in each pair of connecting pieces are respectively arranged on two sides of the wallboard, and a third bolt penetrates through the two connecting pieces in each pair of connecting pieces and the wallboard to clamp and fix the wallboard between the two connecting pieces in each pair of connecting pieces.
The foundation is characterized by further comprising a plurality of anchor rods, wherein one anchor rod corresponds to one connecting piece, one end of each anchor rod is inserted into the foundation, and the other end of each anchor rod penetrates through the corresponding connecting piece.
The bamboo building structure is formed by lapping connection nodes of the assembled raw bamboo combined wallboard and the floor slab.
The invention has the following beneficial effects:
when the assembled type connection node of the raw bamboo combined wallboard and the floor and the bamboo building structure are specifically operated, the first side plate is fixed at one end of the top plate, the second side plate is fixed at the other end of the top plate, the wallboard is clamped and fixed between the first side plate and the second side plate, the end part of the third side plate is fixed on the side surface of the second side plate, and the end part of the floor is lapped and fixed on the third side plate to realize the fixed connection of the wallboard and the floor, so that the service life and the safety of the whole bamboo building structure are improved.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of a bamboo building structure that has been overlapped by the present invention;
FIG. 3 is a side view of FIG. 2;
FIG. 4 is a schematic diagram of the connection of the base 15;
fig. 5 is a schematic view of wallboard 1 as it is being prepared.
Wherein, 1 is wallboard, 2 is floor, 3 is first curb plate, 4 is the second curb plate, 5 is the third curb plate, 6 is the roof, 7 is the second bolt, 8 is concrete, 9 is the sleeve, 10 is the thick liquids, 11 is light composite mortar, 12 is stiffening rib, 13 is former bamboo, 14 is the first bolt, 15 is the basis, 16 is the connecting piece, 17 is the stock, 18 is the third bolt, 19 is the baffle, 20 is the template.
Detailed Description
The invention is described in further detail below with reference to the accompanying drawings:
referring to fig. 1, the connection node of the assembled raw bamboo composite wallboard and the floor slab of the invention comprises a wallboard 1, a floor slab 2, a top plate 6, a first side plate 3, a second side plate 4 and a third side plate 5, wherein the top plate 6 is positioned at the top of the wallboard 1, the first side plate 3 is fixed at one end of the top plate 6, the second side plate 4 is fixed at the other end of the top plate 6, the wallboard 1 is clamped and fixed between the first side plate 3 and the second side plate 4, the end of the third side plate 5 is fixed at the side of the second side plate 4, and the end of the floor slab 2 is lapped and fixed on the third side plate 5.
Specifically, the first bolt 14 passes through the floor slab 2 and the third side plate 5 to lap the floor slab 2 and fix the floor slab on the third side plate 5; the second bolt 7 passes first curb plate 3, wallboard 1 and second curb plate 4 in proper order with wallboard 1 centre gripping and be fixed in between first curb plate 3 and the second curb plate 4.
The wallboard 1 comprises light composite mortar 11, concrete 8 and a plurality of raw bamboos 13 distributed in parallel, wherein two ends of each raw bamboo 13 are aligned respectively, a through hole for a second bolt 7 to pass through is formed in the end part of each raw bamboo 13, the middle part of each raw bamboo 13 is wrapped in the light composite mortar 11, and the end part of each raw bamboo 13 is wrapped in the concrete 8; the end part of the raw bamboo 13 is filled with the slurry 10; a sleeve 9 is inserted into the through hole, and the second bolt 7 passes through the sleeve 9.
A gap is arranged on the bottom surface of the end part of the floor slab 2, and the third side plate 5 is positioned in the gap; the present invention further comprises a stiffener 12, wherein the stiffener 12 is fixed between the second and third side plates 4, 5.
Referring to fig. 4, the present invention further includes a foundation 15 and a plurality of pairs of connecting members 16 disposed on the foundation 15, wherein the lower end of the wall panel 1 is located on the foundation 15, two connecting members 16 of each pair of connecting members 16 are respectively located at both sides of the wall panel 1, and a third bolt 18 passes through two connecting members 16 of each pair of connecting members 16 and the wall panel 1 to clamp and fix the wall panel 1 between two connecting members 16 of each pair of connecting members 16; the invention also comprises a plurality of anchor rods 17, wherein one anchor rod 17 corresponds to one connecting piece 16, one end of each anchor rod 17 is inserted into the foundation 15, and the other end of each anchor rod 17 penetrates through the corresponding connecting piece 16.
Referring to fig. 2 and 3, the bamboo building structure is formed by overlapping the connection nodes of the assembled raw bamboo combined wall board and the floor slab, and the bamboo building structure with a two-layer structure can be overlapped based on the invention.
Referring to fig. 5, the construction process of the wall panel 1 of the present invention is: 1) firstly, forming a through hole in the raw bamboo 13, then inserting the sleeve 9 into the through hole, and then fixing the raw bamboo 13 on the fixing plate, wherein the distance between the upper edge and the lower edge of the raw bamboo 13 and the upper edge and the lower edge of the template 20 is adjustable; 2) the raw bamboos 13 are connected through bamboo splits, and meanwhile, the raw bamboos 13 and the bamboo splits are subjected to waterproof treatment; 3) injecting slurry 10 into the cavity at the end part of the raw bamboo 13; 4) installing baffle plates 19 at two ends of the raw bamboo 13, and pouring concrete 8 at two ends of the raw bamboo 13; 5) after the concrete 8 is solidified, the baffle 19 is removed, and then the light composite mortar 11 is poured; 6) and after the light composite mortar 11 is solidified, removing the template 20, and cutting the end part of the raw bamboo 13 to enable the end part of the raw bamboo 13 to be flush with the concrete 8.
Claims (2)
1. A connection node of an assembled raw bamboo combined wallboard and a floor slab is characterized by comprising a wallboard (1), the floor slab (2), a top plate (6), a first side plate (3), a second side plate (4) and a third side plate (5), wherein the top plate (6) is located at the top of the wallboard (1), the first side plate (3) is fixed at one end of the top plate (6), the second side plate (4) is fixed at the other end of the top plate (6), the wallboard (1) is clamped and fixed between the first side plate (3) and the second side plate (4), the end of the third side plate (5) is fixed on the side face of the second side plate (4), and the end of the floor slab (2) is lapped and fixed on the third side plate (5);
the first bolt (14) penetrates through the floor slab (2) and the third side plate (5) to lap the floor slab (2) and is fixed on the third side plate (5);
the second bolt (7) penetrates through the first side plate (3), the wallboard (1) and the second side plate (4) in sequence to clamp and fix the wallboard (1) between the first side plate (3) and the second side plate (4);
the wallboard (1) comprises light composite mortar (11), concrete (8) and a plurality of raw bamboos (13) distributed in parallel, wherein two ends of each raw bamboo (13) are aligned respectively, a through hole for a second bolt (7) to pass through is formed in the end part of each raw bamboo (13), the middle part of each raw bamboo (13) is wrapped in the light composite mortar (11), and the end part of each raw bamboo (13) is wrapped in the concrete (8);
the end part of the raw bamboo (13) is filled with the slurry (10);
a sleeve (9) is inserted into the through hole, and a second bolt (7) penetrates through the sleeve (9);
a notch is formed in the bottom surface of the end part of the floor slab (2), and the third side plate (5) is positioned in the notch;
the novel door frame also comprises a stiffening rib (12), wherein the stiffening rib (12) is fixed between the second side plate (4) and the third side plate (5);
the wallboard fixing device is characterized by further comprising a foundation (15) and a plurality of pairs of connecting pieces (16) arranged on the foundation (15), wherein the lower end of the wallboard (1) is located on the foundation (15), two connecting pieces (16) in each pair of connecting pieces (16) are respectively located on two sides of the wallboard (1), and a third bolt (18) penetrates through the two connecting pieces (16) in each pair of connecting pieces (16) and the wallboard (1) to clamp and fix the wallboard (1) between the two connecting pieces (16) in each pair of connecting pieces (16);
the anchor rod structure is characterized by further comprising a plurality of anchor rods (17), wherein one anchor rod (17) corresponds to one connecting piece (16), one end of each anchor rod (17) is inserted into the foundation (15), and the other end of each anchor rod (17) penetrates through the corresponding connecting piece (16).
2. A bamboo building structure, characterized in that, the assembled raw bamboo combined wall board and floor slab connection node overlap joint based on claim 1.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811627399.0A CN109629696B (en) | 2018-12-28 | 2018-12-28 | Connection node and bamboo building structure of former bamboo combination wallboard of assembled and floor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811627399.0A CN109629696B (en) | 2018-12-28 | 2018-12-28 | Connection node and bamboo building structure of former bamboo combination wallboard of assembled and floor |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109629696A CN109629696A (en) | 2019-04-16 |
CN109629696B true CN109629696B (en) | 2020-09-15 |
Family
ID=66079068
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811627399.0A Active CN109629696B (en) | 2018-12-28 | 2018-12-28 | Connection node and bamboo building structure of former bamboo combination wallboard of assembled and floor |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109629696B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113356372B (en) * | 2021-06-02 | 2022-11-04 | 新疆昌吉建设(集团)有限责任公司 | Right-angle connecting piece for assembly type building |
Family Cites Families (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000110249A (en) * | 1998-10-06 | 2000-04-18 | Sekisui Chem Co Ltd | Structure and method of bonding wall panel to floor panel, and building unit |
US20080098690A1 (en) * | 2006-10-29 | 2008-05-01 | Yuhong Wang | Bamboo Framework System |
JP2008144490A (en) * | 2006-12-12 | 2008-06-26 | Nikkei Panel System Kk | Angle material for panel connection |
KR100830241B1 (en) * | 2007-07-02 | 2008-05-16 | 한국건설기술연구원 | Method for hybridizing light-weight composite wall and concrete floor in light-weight composite structure using adapter |
KR20090130711A (en) * | 2008-06-16 | 2009-12-24 | 전남대학교산학협력단 | Insulating panel for construction, manufacturing method thereof and wall constructing method using this |
CN104968868B (en) * | 2012-11-19 | 2017-05-10 | 帕多瓦大学 | Wall base structure for light buildings |
CN104863291B (en) * | 2015-06-19 | 2017-05-24 | 青岛腾远设计事务所有限公司 | Manufacturing method for light weight wall |
JP3204194U (en) * | 2016-03-02 | 2016-05-19 | 株式会社福地建装 | Decorative wall material |
CN206090881U (en) * | 2016-08-29 | 2017-04-12 | 福建国强新型环保建材有限公司 | Outer wall and floor connection structure |
CN206289751U (en) * | 2016-12-20 | 2017-06-30 | 山东科技大学 | A kind of assembled steel plate concrete combined shear wall and floor support plate connecting node |
CN107740531A (en) * | 2017-08-31 | 2018-02-27 | 河北建筑工程学院 | Assembled wallboard and its attachment structure |
CN208088325U (en) * | 2018-01-31 | 2018-11-13 | 金科地产集团股份有限公司 | A kind of connection structure of steel-bamboo faced wall and basis |
CN108360901A (en) * | 2018-03-06 | 2018-08-03 | 四川大学 | Novel low layer assembled wallboard structure energy dissipating bolt joint |
-
2018
- 2018-12-28 CN CN201811627399.0A patent/CN109629696B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN109629696A (en) | 2019-04-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10837166B2 (en) | Building structure and construction method for same | |
CN101294423B (en) | Construction method for embedding thermal insulation in concrete structure exterior wall surface | |
CN103114663B (en) | Assemble type multifunctional outer wall body and production and installation method thereof | |
CN104631512B (en) | Hang modulus method after-pouring band beam-slab construction method | |
CN105484391A (en) | Construction method for manufacturing heat-preservation waterproof wall through light heat-preservation GRC disassembling-free formworks | |
CN104234271B (en) | A kind of self-insulating light wallboard system and installation method | |
CN108661225B (en) | But height-adjusting's precast concrete coincide floor | |
CN104532953A (en) | 3D printing based assembly type special-shaped column framework structure and construction method thereof | |
CN108301545A (en) | A kind of big module overlapping contignation of the assembled with space truss temporary support | |
CN104294920B (en) | The node component of a kind of U-shaped steel-concrete combination beam and special-shaped steel pipe concrete post and preparation method | |
CN108360722A (en) | A kind of half welding overlapping contignation of the big module of the assembled with plane girder temporary support | |
CN109629696B (en) | Connection node and bamboo building structure of former bamboo combination wallboard of assembled and floor | |
CN106193340A (en) | Cast-in-place prestressing without bondn ultralong floor combination type reinforcing strip anti-cracking structure and construction method | |
CN210597794U (en) | Connecting device of prefabricated plate | |
CN204356896U (en) | Based on the assembling Framed Structure with Special-Shaped Columns that 3D prints | |
CN204001289U (en) | There is the light steel keel partition that carries the arm of encorbelmenting | |
CN206233564U (en) | Drop plate formwork erection structure | |
CN214364434U (en) | Assembled constructional column suitable for prefabricated wallboard of frame construction | |
CN108301553A (en) | A kind of precast concrete board wall and preparation method thereof | |
CN104389362A (en) | Junction structure of bare concrete shear wall and inner filler wall and implementation method thereof | |
CN203939237U (en) | The one-time formed erecting device of waterproof epirelief concrete component | |
CN108222349A (en) | A kind of light steel of half assembled-foam concrete composite floor and its construction method | |
CN207513153U (en) | The beam column cast-in-place node dedicated aluminium alloy template of assembly concrete frame structure | |
CN110206299B (en) | Prestressed ribbed superimposed sheet seam matching die device and method | |
CN203729473U (en) | Lightweight thermal-sound insulation support-free floor |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |