CN103114663B - Assemble type multifunctional outer wall body and production and installation method thereof - Google Patents
Assemble type multifunctional outer wall body and production and installation method thereof Download PDFInfo
- Publication number
- CN103114663B CN103114663B CN201310073059.9A CN201310073059A CN103114663B CN 103114663 B CN103114663 B CN 103114663B CN 201310073059 A CN201310073059 A CN 201310073059A CN 103114663 B CN103114663 B CN 103114663B
- Authority
- CN
- China
- Prior art keywords
- frame
- cement fiber
- reinforced concrete
- fine stone
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Building Environments (AREA)
- Load-Bearing And Curtain Walls (AREA)
Abstract
Description
技术领域 technical field
本发明涉及新型建筑工业化建筑墙体,具体地说是一种装配式多功能外墙体及其生产、安装方法。 The invention relates to a new type of building industrialized building wall, in particular to an assembled multifunctional outer wall and its production and installation methods.
背景技术 Background technique
我国传统建筑生产方式存在着建筑能耗较高、资源消耗大、工程质量和安全问题较多、建筑业科技含量较低、劳动生产率低、环境负荷大等问题,随着建筑市场劳动力短缺日益凸显,变革传统建筑生产方式,推行新型建筑工业化是我国建筑业可持续发展的重要途径和必然选择。目前,装配式外墙体主要以轻型型钢为龙骨,以EPS保温砂浆为保温夹层,且主要应用于钢结构建筑,存在耐久性差、热桥效应显著、造价高昂、与钢筋混凝土结构适应性差等诸多问题。 my country's traditional construction production methods have problems such as high building energy consumption, large resource consumption, many engineering quality and safety problems, low technological content in the construction industry, low labor productivity, and large environmental load. With the shortage of labor in the construction market, it has become increasingly prominent. It is an important way and an inevitable choice for the sustainable development of my country's construction industry to change the traditional construction production mode and promote the industrialization of new construction. At present, the prefabricated external wall mainly uses light steel as the keel and EPS insulation mortar as the insulation interlayer, and is mainly used in steel structure buildings. There are many problems such as poor durability, significant thermal bridge effect, high cost, and poor adaptability to reinforced concrete structures. question.
发明内容 Contents of the invention
为解决目前装配式外墙体中存在的上述缺陷,本发明提供一种适用于现浇混凝土结构体系或装配式混凝土结构体系的装配式多功能外墙体,其集围护、保温、装饰、防水等多种功能于一体。 In order to solve the above-mentioned defects in the current prefabricated exterior wall, the present invention provides a prefabricated multifunctional exterior wall suitable for cast-in-place concrete structure system or prefabricated concrete structure system, which integrates enclosure, heat preservation, decoration, Waterproof and other functions in one.
本发明采用如下的技术方案:一种装配式多功能外墙体,其特征在于:它为框架夹层复合结构,以细石钢筋混凝土框架为龙骨,框架的框格内填充泡沫混凝土并留有一窗洞,细石钢筋混凝土框架的内、外侧固定安装水泥纤维面板,所述的水泥纤维面板上设有装饰层。 The present invention adopts the following technical scheme: an assembled multifunctional exterior wall, characterized in that it is a frame sandwich composite structure, with a fine stone reinforced concrete frame as the keel, and foam concrete is filled in the grid of the frame and a window hole is left A cement fiber panel is fixedly installed on the inside and outside of the fine stone reinforced concrete frame, and a decorative layer is arranged on the cement fiber panel.
进一步,所述的细石钢筋混凝土框架为预制的整体式钢筋混凝土结构,细石钢筋混凝土框架的左、右侧埋有拉结钢筋,顶部埋有起吊环,底部埋有预埋铁件,窗洞两侧的竖向框架中埋有临时斜撑支撑点;细石钢筋混凝土框架上开有平行于墙面的线管穿孔及垂直于墙面的锚固内、外侧水泥纤维面板用的锚固通孔。框架尺寸按开间大小进行设计,为保证框架强度及满足对钢筋的防护要求,框架的宽为60-80mm,根据节能、隔音等要求对框架的厚度进行调整,可在120-240mm范围内调整。拉结钢筋用于装配式多功能外墙体与柱的拉接,起吊环用于生产及安装过程中的装吊,预埋铁件用于安装时与楼板上的预留铁件焊接,临时斜撑支撑点用于安装过程中可调型斜撑件的临时固定。 Further, the fine stone reinforced concrete frame is a prefabricated integrated reinforced concrete structure, the left and right sides of the fine stone reinforced concrete frame are buried with tie bars, the top is buried with lifting rings, and the bottom is buried with pre-embedded iron parts. Temporary support points are buried in the vertical frames on both sides; on the fine stone reinforced concrete frame, there are pipe perforations parallel to the wall and anchor through holes perpendicular to the wall for anchoring the inner and outer cement fiber panels. The size of the frame is designed according to the size of the bay. In order to ensure the strength of the frame and meet the protection requirements for steel bars, the width of the frame is 60-80mm. The thickness of the frame can be adjusted according to the requirements of energy saving and sound insulation, and can be adjusted within the range of 120-240mm. The tie bars are used for the connection between the prefabricated multifunctional exterior wall and the columns, the hoisting rings are used for hoisting during production and installation, and the pre-embedded iron parts are used for welding with the reserved iron parts on the floor during installation. The brace support points are used for temporary fixation of adjustable braces during installation.
进一步,所述的泡沫混凝土为现场浇筑的泡沫混凝土或预制的泡沫混凝土保温板,泡沫混凝土的容重为200-700kg/m3,兼具良好的保温性能、耐久性能、防火性能等。现场浇筑的泡沫混凝土有利于墙体内线管的埋设,而预制的泡沫混凝土保温板则无需养护,生产速度快。 Further, the foamed concrete is cast-in-place foamed concrete or prefabricated foamed concrete insulation board, the bulk density of the foamed concrete is 200-700kg/m 3 , and it has good thermal insulation performance, durability performance and fire prevention performance. The foam concrete poured on site is beneficial to the embedding of the line pipe in the wall, while the prefabricated foam concrete insulation board does not need maintenance and the production speed is fast.
进一步,所述水泥纤维面板的抗折强度大于10MPa,内侧水泥纤维面板厚度为5-8mm,且四边分别与细石钢筋混凝土框架四周边缘齐平;外侧水泥纤维面板具有防水功能,厚度为10-20mm,底边与细石钢筋混凝土框架底端齐平,其余三边比细石钢筋混凝土框架边缘外延120-400mm;内、外侧水泥纤维面板通过粘结砂浆与细石钢筋混凝土框架粘结,并用拉结螺栓穿过细石钢筋混凝土框架上的锚固通孔进行对拉锚固。 Further, the flexural strength of the cement fiber panel is greater than 10MPa, the thickness of the inner cement fiber panel is 5-8mm, and the four sides are respectively flush with the surrounding edges of the fine stone reinforced concrete frame; the outer cement fiber panel has waterproof function, and the thickness is 10-8mm. 20mm, the bottom edge is flush with the bottom of the fine stone reinforced concrete frame, and the remaining three sides are 120-400mm wider than the edge of the fine stone reinforced concrete frame; the inner and outer cement fiber panels are bonded to the fine stone reinforced concrete frame by bonding mortar, and The tie bolts pass through the anchor through holes on the fine stone reinforced concrete frame to carry out anti-tension anchorage.
进一步,所述的装饰层直接设于水泥纤维面板上,为涂料层或面砖。由于水泥纤维面板表面平整,可直接在水泥纤维面板上做装饰层。 Further, the decorative layer is directly arranged on the cement fiber panel, which is a paint layer or a facing brick. Due to the smooth surface of the cement fiber panel, the decorative layer can be directly made on the cement fiber panel.
上述装配式多功能外墙体的生产方法如下:首先,预制好细石钢筋混凝土框架;水平放置内侧水泥纤维面板作为底模,按需喷涂一层粘结砂浆,其上放置细石钢筋混凝土框架,埋设预埋线管,在框架的框格内现场浇筑泡沫混凝土或粘贴泡沫混凝土保温板,并留窗洞;待现浇泡沫混凝土养护完成或泡沫混凝土保温板粘贴结束后,其上再喷涂一层粘结砂浆,覆盖上外侧水泥纤维面板,使用拉结螺栓将内、外侧水泥纤维面板锚固在细石钢筋混凝土框架上;最后,按需安装窗框或整体窗,在内、外侧水泥纤维面板上安装装饰层并粘贴保护膜。 The production method of the above prefabricated multifunctional exterior wall is as follows: first, prefabricate the fine stone reinforced concrete frame; horizontally place the inner cement fiber panel as the bottom form, spray a layer of bonding mortar as required, and place the fine stone reinforced concrete frame on it , bury pre-buried pipes, pour foam concrete or paste foam concrete insulation boards in the frame grid, and leave window holes; after the cast-in-place foam concrete curing is completed or the foam concrete insulation boards are pasted, spray a layer on it Adhesive mortar, cover the outer cement fiber panels, use tie bolts to anchor the inner and outer cement fiber panels to the fine stone reinforced concrete frame; finally, install window frames or integral windows as required, on the inner and outer cement fiber panels Install the decorative layer and stick the protective film.
上述装配式多功能外墙体的安装方法如下:装配式多功能外墙体吊放就位后,通过外墙体底部的预埋铁件与楼板中预埋件焊接,并利用临时斜撑支撑点架设可调型斜撑件进行临时固定;外墙体左、右侧的拉结钢筋与后浇混凝土柱或部分后浇混凝土柱浇筑成整体,浇筑时,外墙体左、右侧的外侧水泥纤维面板作为外侧模板使用,在后浇混凝土柱与外侧面板之间设置一层保温层,减小后浇混凝土柱热桥效应;外墙体顶部的外侧水泥纤维面板作为后浇混凝土梁或部分后浇混凝土梁的外侧模板使用,在后浇混凝土梁与外侧面板之间设置一层保温材料层,减小混凝土梁的热桥效应。 The installation method of the above-mentioned prefabricated multifunctional exterior wall is as follows: After the prefabricated multifunctional exterior wall is hoisted in place, the pre-embedded iron parts at the bottom of the exterior wall are welded to the pre-embedded parts in the floor slab, and supported by temporary braces point erection of adjustable diagonal braces for temporary fixation; the tie bars on the left and right sides of the outer wall and the post-cast concrete columns or part of the post-cast concrete columns are poured as a whole. When pouring, the outer sides of the left and right sides of the outer wall The cement fiber panel is used as the outer formwork, and an insulation layer is set between the post-cast concrete column and the outer panel to reduce the thermal bridge effect of the post-cast concrete column; the outer cement fiber panel on the top of the outer wall is used as a post-cast concrete beam or part The outer formwork of the post-cast concrete beam is used, and a layer of thermal insulation material is arranged between the post-cast concrete beam and the outer panel to reduce the thermal bridge effect of the concrete beam.
进一步,为防止后浇混凝土梁应力向下传递至装配式多功能外墙体上,可在装配式多功能外墙体顶部设置一道弹性缓冲层。 Further, in order to prevent the stress of the post-cast concrete beam from being transmitted downward to the prefabricated multifunctional exterior wall, an elastic buffer layer can be arranged on the top of the prefabricated multifunctional exterior wall.
本发明具有的有益效果如下:1.本发明的装配式多功能外墙体适用于装配整体式结构建筑或现浇混凝土结构建筑,与建筑主体结构拼接牢固,整体性好; The beneficial effects of the present invention are as follows: 1. The prefabricated multifunctional exterior wall of the present invention is suitable for assembling integral structural buildings or cast-in-place concrete structural buildings, and is firmly spliced with the main structure of the building and has good integrity;
2.本发明的装配式多功能外墙体集围护、保温、装饰、防水等功能于一体,所有工序一步到位,安装过程中不必架设外手脚架,施工速度快,经济效益明显; 2. The prefabricated multifunctional exterior wall of the present invention integrates the functions of enclosure, heat preservation, decoration, waterproofing, etc., and all the processes are completed in one step, and there is no need to erect external scaffolding during the installation process. The construction speed is fast and the economic benefits are obvious;
3.本发明的装配式多功能外墙体所用材料基本为无机材料,耐久性能、防火性能好。 3. The materials used in the assembled multifunctional exterior wall of the present invention are basically inorganic materials, which have good durability and fire resistance.
附图说明 Description of drawings
图1为本发明细石钢筋混凝土框架的结构示意图; Fig. 1 is the structural representation of fine stone reinforced concrete frame of the present invention;
图2为本发明装配式多功能外墙体的结构示意图; Fig. 2 is a structural schematic diagram of the assembled multifunctional exterior wall of the present invention;
图3为本发明装配式多功能外墙体与柱拼接的示意图; Fig. 3 is a schematic diagram of the splicing of the assembled multifunctional exterior wall and the column of the present invention;
图4为本发明装配式多功能外墙体与梁、楼板拼接的示意图。 Fig. 4 is a schematic diagram of splicing of the assembled multifunctional exterior wall with beams and floors of the present invention.
具体实施方式 Detailed ways
下面结合说明书附图对本发明作进一步阐述。 The present invention will be further elaborated below in conjunction with the accompanying drawings of the description.
如图1-2所示的装配式多功能外墙体,其为框架夹层复合结构,以细石钢筋混凝土框架1为龙骨,框架的框格内填充泡沫混凝土12并留有一窗洞2,细石钢筋混凝土框架的内、外侧固定安装水泥纤维面板3、4,所述的水泥纤维面板上设有装饰层。所述的泡沫混凝土为现场浇筑的泡沫混凝土或预制的泡沫混凝土保温板,泡沫混凝土的容重为200-700kg/m3。 As shown in Figure 1-2, the assembled multifunctional exterior wall is a frame sandwich composite structure, with a fine stone reinforced concrete frame 1 as the keel, the frame lattice is filled with foam concrete 12 and a window hole 2 is left, and the fine stone Cement fiber panels 3 and 4 are fixedly installed on the inside and outside of the reinforced concrete frame, and a decorative layer is arranged on the cement fiber panels. The foam concrete is foam concrete poured on site or a prefabricated foam concrete insulation board, and the bulk density of the foam concrete is 200-700kg/m 3 .
所述的细石钢筋混凝土框架为预制的整体式钢筋混凝土结构,细石钢筋混凝土框架的左、右侧埋有拉结钢筋5,顶部埋有起吊环6,底部埋有预埋铁件7,窗洞两侧的竖向框架中埋有临时斜撑支撑点8;细石钢筋混凝土框架上开有平行于墙面的线管穿孔9及垂直于墙面的锚固内、外侧水泥纤维面板用的锚固通孔10。 The fine stone reinforced concrete frame is a prefabricated integral reinforced concrete structure, the left and right sides of the fine stone reinforced concrete frame are embedded with tie bars 5, the top is embedded with lifting rings 6, and the bottom is embedded with embedded iron parts 7, Temporary bracing support points 8 are embedded in the vertical frames on both sides of the window opening; wire pipe perforations 9 parallel to the wall surface and anchorage holes for anchoring the inner and outer cement fiber panels perpendicular to the wall surface are opened on the fine stone reinforced concrete frame. Through hole 10.
所述水泥纤维面板的抗折强度大于10MPa,内侧水泥纤维面板3厚度为5-8mm,且四边分别与细石钢筋混凝土框架四周边缘齐平;外侧水泥纤维面板4具有防水功能,厚度为10-20mm,底边与细石钢筋混凝土框架底端齐平,其余三边比细石钢筋混凝土框架边缘外延120-400mm;内、外侧水泥纤维面板通过粘结砂浆与细石钢筋混凝土框架粘结,并用拉结螺栓11穿过细石钢筋混凝土框架上的锚固通孔进行对拉锚固。 The flexural strength of the cement fiber panel is greater than 10MPa, the thickness of the inner cement fiber panel 3 is 5-8mm, and the four sides are respectively flush with the edges around the fine stone reinforced concrete frame; the outer cement fiber panel 4 has a waterproof function, and the thickness is 10-8mm. 20mm, the bottom edge is flush with the bottom of the fine stone reinforced concrete frame, and the remaining three sides are 120-400mm wider than the edge of the fine stone reinforced concrete frame; the inner and outer cement fiber panels are bonded to the fine stone reinforced concrete frame by bonding mortar, and The tie bolts 11 pass through the anchoring through holes on the fine stone reinforced concrete frame to carry out opposite pull anchorage.
上述装配式多功能外墙体的制作方法如下: The manufacturing method of the above-mentioned prefabricated multifunctional exterior wall is as follows:
如图3所示,首先,预制好细石钢筋混凝土框架,其模板可以是手工钉制的木模的,也可以是定制的整体式钢模;水平放置内侧水泥纤维面板作为底模,按需喷涂一层粘结砂浆,放置上预制的细石钢筋混凝土框架,在框格内现场浇筑泡沫混凝土或粘贴泡沫混凝土保温板,并埋设预埋线管;待现浇泡沫混凝土养护完成或泡沫混凝土粘贴结束后,其上再喷涂一层粘结砂浆,覆盖上外侧水泥纤维面板,使用拉结螺栓将内、外侧水泥纤维面板锚固在细石钢筋混凝土框架上;最后,按需安装窗框或整体窗,在内、外侧水泥纤维面板上做装饰层并粘贴保护膜。 As shown in Figure 3, first, the fine stone reinforced concrete frame is prefabricated, and its formwork can be hand-nailed wooden formwork or a custom-made integral steel formwork; the inner cement fiber panel is placed horizontally as the bottom formwork, Spray a layer of bonding mortar, place a prefabricated fine stone reinforced concrete frame, pour foam concrete or paste foam concrete insulation boards in the frame, and bury pre-buried pipes; wait for the cast-in-place foam concrete to be cured or foam concrete paste After the completion, spray a layer of bonding mortar on it, cover the outer cement fiber panel, and use tie bolts to anchor the inner and outer cement fiber panels to the fine stone reinforced concrete frame; finally, install the window frame or integral window as required , make a decorative layer on the inner and outer cement fiber panels and paste a protective film.
装配式多功能外墙体的安装过程如下: The installation process of the prefabricated multifunctional exterior wall is as follows:
如图4所示,装配式多功能外墙体吊放就位后,通过墙体底部的预埋铁件与楼板19中梁20上方的预埋件13焊接,并架设可调型斜撑件14进行临时固定;装配式多功能外墙体左、右侧的拉结钢筋5与后浇混凝土柱或部分后浇混凝土柱浇筑成整体,浇筑时,装配式多功能外墙体左、右侧的外侧面板的外延部分作为外侧模板使用,并在后浇混凝土柱与外侧面板之间放置一层保温层16,减小后浇混凝土柱的热桥效应;同样地,装配式多功能外墙体顶部的外侧面板可作为后浇混凝土梁或部分后浇混凝土梁的外侧模板使用,在后浇混凝土梁与外侧面板之间放置一层保温材料层18,减小后浇混凝土梁的热桥效应,为防止后浇混凝土梁应力向下传递至装配式多功能外墙体上,可在装配式多功能外墙体顶部设置一道弹性缓冲层。 As shown in Figure 4, after the prefabricated multifunctional exterior wall is hoisted in place, the embedded iron parts at the bottom of the wall are welded to the embedded parts 13 above the middle beam 20 of the floor 19, and adjustable diagonal braces are erected 14 for temporary fixation; the tie bars 5 on the left and right sides of the assembled multifunctional exterior wall are poured into a whole with the post-cast concrete column or part of the post-cast concrete column. When pouring, the left and right sides of the assembled multifunctional exterior wall The extension part of the outer panel is used as the outer formwork, and a layer of thermal insulation layer 16 is placed between the post-cast concrete column and the outer panel to reduce the thermal bridge effect of the post-cast concrete column; similarly, the assembled multifunctional exterior wall The outer panel at the top can be used as the outer formwork of the post-cast concrete beam or part of the post-cast concrete beam. A layer of thermal insulation material layer 18 is placed between the post-cast concrete beam and the outer panel to reduce the thermal bridge effect of the post-cast concrete beam. In order to prevent the post-cast concrete beam stress from being transmitted downward to the prefabricated multifunctional exterior wall, an elastic buffer layer can be arranged on the top of the prefabricated multifunctional exterior wall.
本发明的保护范围并不局限于上述描述,任何在本发明的启示下的其它形式产品,不论在形状或结构上作任何改变,凡是与本发明具有相同或相近的技术方案,均在本发明的保护范围之内。 The scope of protection of the present invention is not limited to the above description, any other form of product inspired by the present invention, regardless of any changes in shape or structure, and any technical solutions that are the same as or similar to the present invention, are included in the scope of the present invention. within the scope of protection.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201310073059.9A CN103114663B (en) | 2013-03-07 | 2013-03-07 | Assemble type multifunctional outer wall body and production and installation method thereof |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201310073059.9A CN103114663B (en) | 2013-03-07 | 2013-03-07 | Assemble type multifunctional outer wall body and production and installation method thereof |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN103114663A CN103114663A (en) | 2013-05-22 |
| CN103114663B true CN103114663B (en) | 2015-01-14 |
Family
ID=48413091
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201310073059.9A Expired - Fee Related CN103114663B (en) | 2013-03-07 | 2013-03-07 | Assemble type multifunctional outer wall body and production and installation method thereof |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN103114663B (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP4194631A1 (en) * | 2021-12-09 | 2023-06-14 | Lesage Developpement S.A.S. | Prefabricated composite facade panel and method for constructing a facade of a building |
| EP4390000A1 (en) | 2022-12-20 | 2024-06-26 | Lesage Developpement S.A.S. | Prefabricated hybrid construction panel, in particular for building facades |
Families Citing this family (26)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104652608B (en) * | 2015-02-05 | 2017-01-25 | 中国建筑第七工程局有限公司 | A connection structure between an assembled exterior wall and beams |
| CN104675012B (en) * | 2015-03-17 | 2017-09-05 | 西安建筑科技大学 | The assembled polypropylene fibre sludge ceramsite concrete wall and its construction method connected based on horse tooth trough |
| CN105317110A (en) * | 2015-11-06 | 2016-02-10 | 中建钢构有限公司 | Integrated assembly type steel structure building |
| CN105604238B (en) * | 2015-11-20 | 2017-10-17 | 河北途牛建筑科技有限公司 | A kind of light wall, floor, the making of roof boarding and installation method |
| CN105421656B (en) * | 2015-12-08 | 2017-05-17 | 徐州中煤(宁夏)钢结构建设有限公司 | External wall board installation structure of embedded type steel structure assembled house |
| CN105464283A (en) * | 2016-01-05 | 2016-04-06 | 博思集团股份有限公司 | Assembled wallboard and assembled station room |
| CN105672535A (en) * | 2016-03-23 | 2016-06-15 | 哈尔滨鸿盛房屋节能体系研发中心 | Steel structure assembled type EPS (Electric Power Storage) module sandwiched heat-insulation composite wall body |
| CN105888099A (en) * | 2016-06-03 | 2016-08-24 | 湖南省建筑工程集团总公司 | Heat preservation and decoration integrated composite wall serving as building outer wall and construction method of integrated composite wall |
| CN106638940B (en) * | 2016-12-30 | 2019-02-05 | 青建集团股份公司 | A kind of assembled high residential building concrete prefabricated element construction |
| CN106930433A (en) * | 2017-03-20 | 2017-07-07 | 张宗楼 | Large-scale lateral aperture overall assembled wallboard |
| CN108951939A (en) * | 2017-05-25 | 2018-12-07 | 赵俊儒 | A kind of assembled-type house multifunctional wall body and its processing method |
| CN108425451B (en) * | 2018-02-14 | 2020-04-14 | 清华大学建筑设计研究院有限公司 | Integrally cast and hung integrated wallboard and quick-assembly wall structure thereof |
| CN108316525B (en) * | 2018-04-28 | 2023-09-08 | 中建科技河南有限公司 | Integral combined heat-insulating outer wall and construction method thereof |
| CN108756052A (en) * | 2018-06-15 | 2018-11-06 | 湖南省异格建筑节能工程有限公司 | A kind of cast-in-place foamed concrete PVC skeletons combined wall and its construction method |
| CN109138220B (en) * | 2018-07-27 | 2020-02-18 | 肇庆三乐集成房屋制造有限公司 | Fiber cement board composite assembled skeleton, wall components and prefabricated steel-concrete shear wall |
| CN109680865A (en) * | 2018-11-15 | 2019-04-26 | 安徽金诺创新科技有限公司 | A kind of low layer assembling type steel structure house combined wall board |
| CN110616828A (en) * | 2019-10-20 | 2019-12-27 | 中建四局第六建筑工程有限公司 | Steel rib-fiber concrete wall structure |
| CN110905117B (en) * | 2019-12-06 | 2021-09-24 | 山东平安建筑工业化科技有限公司 | Precast concrete wallboard |
| CN111519835B (en) * | 2020-05-20 | 2023-05-26 | 周印涛 | Assembled wall body heat preservation integrated structure and wall body heat preservation decoration integrated structure |
| CN113880511A (en) * | 2020-07-03 | 2022-01-04 | 江苏东曌建筑产业创新发展研究院有限公司 | Waterproof protection material for assembled prefabricated outer wall surface layer and manufacturing method |
| CN112012377B (en) * | 2020-07-20 | 2021-09-03 | 浙江省建筑科学设计研究院有限公司 | Assembled building outer wall |
| CN112302214A (en) * | 2020-11-03 | 2021-02-02 | 广州市华阳国际工程设计有限公司 | A prefabricated frame type composite wall structure |
| CN113187151A (en) * | 2021-05-10 | 2021-07-30 | 哈尔滨鸿盛建筑材料制造股份有限公司 | Frame filling wallboard and wall structure |
| CN114197741B (en) * | 2021-12-16 | 2023-02-03 | 蕉岭县骏龙建材有限公司 | Energy-saving heat-insulation sound-insulation autoclaved aerated panel |
| CN115749120A (en) * | 2022-12-17 | 2023-03-07 | 北京鑫元一建设科技开发有限公司 | Steel construction assembly type outer wall large plate for building |
| FR3155845B1 (en) | 2023-11-29 | 2026-02-06 | Lesage Dev | Prefabricated building panel |
Family Cites Families (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US6625947B1 (en) * | 2001-11-30 | 2003-09-30 | Ferrall Burgett | Insulated concrete wall system and method of making same |
| CN201738494U (en) * | 2010-06-04 | 2011-02-09 | 北京万科企业有限公司 | Prefabricated composite wall slab with door/window opening |
| CN202401612U (en) * | 2011-09-05 | 2012-08-29 | 徐学东 | Concrete frame with sandwiched wood cement board assembly type light-weight wallboard |
| CN102425240A (en) * | 2011-09-06 | 2012-04-25 | 浙江省建筑科学设计研究院有限公司 | Large-size anti-cracking foamed cement single-sided composite insulation board |
| CN102561585B (en) * | 2012-03-06 | 2014-10-29 | 程松林 | External wall slab of prefabricated cast-in-place composite concrete shear wall and manufacture and installation methods |
| CN202706258U (en) * | 2012-07-17 | 2013-01-30 | 徐学东 | Fully-assembled detachable concrete wallboard |
| CN203066294U (en) * | 2013-03-07 | 2013-07-17 | 浙江省建筑科学设计研究院有限公司 | Assembled multifunctional outer wall body |
-
2013
- 2013-03-07 CN CN201310073059.9A patent/CN103114663B/en not_active Expired - Fee Related
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP4194631A1 (en) * | 2021-12-09 | 2023-06-14 | Lesage Developpement S.A.S. | Prefabricated composite facade panel and method for constructing a facade of a building |
| FR3130300A1 (en) * | 2021-12-09 | 2023-06-16 | Lesage Developpement | Prefabricated composite facade panel and method of constructing a facade of a building |
| EP4390000A1 (en) | 2022-12-20 | 2024-06-26 | Lesage Developpement S.A.S. | Prefabricated hybrid construction panel, in particular for building facades |
Also Published As
| Publication number | Publication date |
|---|---|
| CN103114663A (en) | 2013-05-22 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103114663B (en) | Assemble type multifunctional outer wall body and production and installation method thereof | |
| CN102505779B (en) | A modular hoisting and assembling wall system and its construction method | |
| CN106013811B (en) | A kind of installation method of assembled architecture | |
| CN105714963B (en) | Inorganic light composite heat-insulation integrated exterior wall cladding system and installation method thereof | |
| CN106436893A (en) | Fully-prefabricated structure and construction method thereof | |
| CN204531076U (en) | Light steel latticework cast-in-place foamed concrete combined wall | |
| EP4582233A1 (en) | Prefabricated component formed by reverse laying and production process therefor | |
| CN101586366A (en) | Connecting structure and construction method of precast concrete plates and beams, and building comprising same | |
| CN215253698U (en) | Ceramsite foam concrete exterior wall hanging plate in assembly type building | |
| CN106223529B (en) | A kind of out-hung panel and preparation method thereof of the compound wood wool board of lightgage steel joist | |
| CN110468967B (en) | Connecting node of oversized overweight prefabricated cladding plate and main body structure beam and construction method | |
| CN209429309U (en) | A kind of sandwich heat preservation overlapped shear wall L shape connecting node construction | |
| CN111549812A (en) | Cast-in-place prefabricated formwork-free thermal insulation integrated house | |
| CN203066294U (en) | Assembled multifunctional outer wall body | |
| CN108035485A (en) | Assembled CF steam pressures porcelain powder air entrained concrete shear wall Side fascia and production method | |
| CN108316525B (en) | Integral combined heat-insulating outer wall and construction method thereof | |
| CN218758102U (en) | Energy-conserving integration assembled shear force wall | |
| CN110778016B (en) | A kind of outer protection system of prefabricated steel structure house suitable for severe cold area | |
| CN112982692A (en) | One-way superimposed sheet joint connecting structure and construction method | |
| CN205475877U (en) | Compound outer thermal insulation walling system of assembled self preservation temperature wallboard | |
| CN208415587U (en) | A kind of sandwich heat preservation overlapped shear wall T shape connecting node construction | |
| CN103255834A (en) | Prefabricated heat-preservation balcony suitable for industrial production and construction method thereof | |
| CN104533012A (en) | Bearable light plate as well as manufacturing method, combined wallboard and house thereof | |
| CN218894248U (en) | Assembled light steel combined steel wire net rack mortar-perlite-polyphenyl composite shear wall | |
| CN115977278B (en) | Prefabricated light steel composite truss supporting steel wire mesh frame mortar-perlite-polystyrene composite shear wall and construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150114 |