CN109592576A - A kind of built-in fitting for building hanger - Google Patents
A kind of built-in fitting for building hanger Download PDFInfo
- Publication number
- CN109592576A CN109592576A CN201710925086.2A CN201710925086A CN109592576A CN 109592576 A CN109592576 A CN 109592576A CN 201710925086 A CN201710925086 A CN 201710925086A CN 109592576 A CN109592576 A CN 109592576A
- Authority
- CN
- China
- Prior art keywords
- tower crane
- chassis
- under
- operating platform
- guardrail
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/62—Constructional features or details
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C2700/00—Cranes
- B66C2700/03—Cranes with arms or jibs; Multiple cranes
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
The present invention relates to technical field of building construction, a kind of built-in fitting for building hanger is specifically disclosed, including standard section of tower crane, the more square tubes being parallel to each other are equipped with above the standard section of tower crane, the square tube is fixedly arranged above under(-)chassis, four corners of the under(-)chassis are respectively provided with the fixing piece of fixed guardrail, are connected between the guardrail by fastener.The invention has the advantages that the operating platform is installed on tower crane, installation is simple, time and labour saving, and safety standards, produces once and is used multiple times, realizes the Reusability of operating platform.
Description
Technical field
The present invention relates to technical field of building construction, particularly relate to a kind of built-in fitting for building hanger.
Background technique
In construction, tower crane is critically important handbarrow.The height of tower crane will be with the elevated height of building.When
Free end height is reduced it is necessary to which attached wall is arranged when the free end height of tower crane is more than specified value, tower crane is enable to use safely.
It when attached wall is arranged, needs that operating platform is arranged on tower body in advance, with convenient working personnel safety operation.In the prior art,
The way of operating platform is temporarily set up with steel pipe, with with setting, is set up more casual.With stepping up for Building technology,
The height of project under construction is higher and higher, and attached wall will be repeatedly arranged, and operating platform also will repeatedly be set up therewith, is set up neither with steel pipe
Safe and lack of standardization while also wasting manpower and material resources, set up and are once used only once, cannot have enough to meet the need and be used for multiple times, economic benefit
It is low.
Summary of the invention
The object of the present invention is to provide a kind of built-in fittings for building hanger, and which solve the above problems, it is only necessary in attached wall
When installation, bottom frame assembly is completed, time and labour saving, and safety standards, produce once and be used multiple times.
To achieve the goals above, present invention employs technical solutions below: a kind of built-in fitting for building hanger, including
Standard section of tower crane, the standard section of tower crane top are equipped with the more square tubes being parallel to each other, and the square tube is fixedly arranged above bottom frame
Frame, four corners of the under(-)chassis are respectively provided with the fixing piece of fixed guardrail, pass through button between the guardrail
Part connection.
Wherein, it is fixed between the standard section of tower crane and square tube by anchor ear.
Wherein, the square tube is bolted with under(-)chassis.
Wherein, the fixing piece is the steel pipe for being welded in under(-)chassis corner, and the guardrail is formed by steel pipe combination,
In its steel pipe for being inserted into under(-)chassis corner, for fixing guardrail.
Wherein, bamboo slab rubber is equipped on the under(-)chassis.
The beneficial effects of the present invention are: using after above-mentioned mold, which is installed on tower crane, installation letter
It is single, time and labour saving, and safety standards, it produces once and is used multiple times, realize the Reusability of operating platform.
Detailed description of the invention
Technical solution in order to illustrate the embodiments of the present invention more clearly, below will be to needed in embodiment description
Attached drawing is briefly described, it should be apparent that, the accompanying drawings in the following description is only the present invention in order to illustrate more clearly of this hair
Bright embodiment or technical solution in the prior art, below will be p- required for describing the embodiments or the prior art attached
Figure is briefly described, for those of ordinary skill in the art, without creative efforts, can be with root
Other attached drawings are obtained according to these attached drawings.
Fig. 1 is the structural diagram of the present invention.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other
Embodiment shall fall within the protection scope of the present invention.
A kind of built-in fitting of building hanger as shown in Figure 1, including standard section of tower crane (1), on the standard section of tower crane (1)
Side is equipped with the more square tubes (3) being parallel to each other, and the square tube (3) is fixedly arranged above under(-)chassis (2), the under(-)chassis (2)
Four corners are respectively provided with the fixing piece of fixed guardrail (6), are connected between the guardrail (6) by fastener (7).
Fixed by anchor ear (4) between the standard section of tower crane (1) and square tube (3), the square tube (3) and under(-)chassis (2) pass through spiral shell
Bolt is fixed.The operating platform is installed on tower crane, installation is simple, time and labour saving, and safety standards, and producing once can
It is used for multiple times, realizes the Reusability of operating platform.
Wherein, the fixing piece is the steel pipe for being welded in under(-)chassis (2) corner, and the guardrail (6) is by steel pipe
It closes, is inserted into the steel pipe of under(-)chassis (2) corner, for fixing guardrail (6).
When making the operating platform:
1, operating platform is set up
The square tube (3) that two 50 × 50 will be completed the process is connect using U-shaped hoop with standard section of tower crane (1).
2, under(-)chassis assembles
Two longer rectangle bottom frame is connect with M12 bolt with supporting square tube (3) first, secondly by two shorter length
Rectangular bottom framework is determined frame with the rectangle fixed with M12 bolt and is connect, and tower crane attached wall operating platform under(-)chassis is formed
(2).Using the preferable bolt of quality, guarantee that the connection of rectangle bottom framework is firm, bolt location is positioned using 12 drill bit of bench drill Ф
Drilling.15mm thickness bamboo slab rubber (5) closed bottom frame (2) hole is laid with after being completed.
3, operating platform periphery guardrail is installed
The guardrail lower part of welding forming is inserted into 30 steel pipe of Ф welded on rectangle bottom framework, two panels guardrail
(6) top connection is connected integral using dedicated fastener (7).Dedicated fastener (7) is bent using the band iron of 5mm thickness, two panels
Band iron is connected with bolt.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention
Within mind and principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.
Claims (5)
1. a kind of built-in fitting for building hanger, including standard section of tower crane (1), which is characterized in that above the standard section of tower crane (1)
Equipped with the more square tubes being parallel to each other (3), the square tube (3) is fixedly arranged above under(-)chassis (2), the under(-)chassis (2) four
A corner is respectively provided with the fixing piece of fixed guardrail (6), is connected between the guardrail (6) by fastener (7).
2. tower crane attached wall operating platform according to claim 1, it is characterised in that: the standard section of tower crane (1) and square tube
(3) fixed by anchor ear (4) between.
3. tower crane attached wall operating platform according to claim 1, it is characterised in that: the square tube (3) and under(-)chassis (2)
It is bolted.
4. tower crane attached wall operating platform according to claim 1, it is characterised in that: the fixing piece is to be welded in bottom frame
The steel pipe of frame (2) corner, the guardrail (6) are formed by steel pipe combination, are inserted into the steel pipe of under(-)chassis (2) corner
In.
5. tower crane attached wall operating platform according to claim 1, it is characterised in that: be equipped on the under(-)chassis (2)
Bamboo slab rubber (5).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710925086.2A CN109592576A (en) | 2017-10-02 | 2017-10-02 | A kind of built-in fitting for building hanger |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710925086.2A CN109592576A (en) | 2017-10-02 | 2017-10-02 | A kind of built-in fitting for building hanger |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109592576A true CN109592576A (en) | 2019-04-09 |
Family
ID=65956574
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710925086.2A Pending CN109592576A (en) | 2017-10-02 | 2017-10-02 | A kind of built-in fitting for building hanger |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109592576A (en) |
-
2017
- 2017-10-02 CN CN201710925086.2A patent/CN109592576A/en active Pending
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208202530U (en) | A kind of new type scaffold wall-connecting piece | |
CN203808484U (en) | Integrated cantilevered and attached external scaffolding | |
CN105525750A (en) | Construction method of door lintel and aluminum alloy door lintel formwork | |
CN206289945U (en) | A kind of assembled Portable safety crosshead | |
CN201190408Y (en) | Tool type exterior scaffolding of section steel fastening tube | |
CN205063330U (en) | Close clearance double shear wall movement joint template | |
CN206220251U (en) | Glass cupola steel construction | |
CN109592576A (en) | A kind of built-in fitting for building hanger | |
CN201553566U (en) | Assembled tower crane adhering device | |
CN209523198U (en) | A kind of underpinning structure supporting lattice column | |
CN204001702U (en) | A kind of J-shaped wall plastic formwork | |
CN217439520U (en) | Wall connecting piece for outer scaffold drawknot | |
CN109592575A (en) | A kind of building hanger | |
CN109592582A (en) | Activity wall-attaching equipment and its movable wall-attached frame | |
CN202718375U (en) | Installation and operation platform of high-altitude cantilever structure | |
CN109896436A (en) | A kind of operating device that building tower crane security performance is high | |
CN109896441A (en) | A kind of operating device that building tower crane security performance is high | |
CN109594757A (en) | A kind of multifunctional wrench convenient for high altitude operation | |
CN205134546U (en) | But quick detachable I -steel built -in fitting of encorbelmenting of cyclic utilization | |
CN109516387A (en) | A kind of operating device that building tower crane security performance is high | |
CN205134921U (en) | Building outer wall concrete constructional column hangs construction platform | |
CN204754207U (en) | Aluminium alloy door lintel template | |
CN108222503A (en) | A kind of combined large pier stud steel form | |
CN209227802U (en) | The template of piece back-grouting holds solid system in a kind of assembled architecture system | |
CN112942777A (en) | Ultrahigh-layer periphery protection cyclic telescopic detachable cantilever structure and mounting method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |