A kind of generation method of wall upper end pipeline
Technical field
The present invention relates to the pre-buried reserved field of assembled architecture electric specialty, especially a kind of generation of wall upper end pipeline
Method.
Background technique
It is to pass through pipeline of extending out of adding some points on software interface in the design drawing drawing process of the existing pipeline on to wall,
Or position of the wall pipeline apart from metope is manually set, it needs by capturing wall locations transmission range numerical value again, if
Count complex steps and heavy workload.
Summary of the invention
In order to solve the above technical problems, the technical scheme adopted by the invention is that: a kind of generation side of wall upper end pipeline
Method, this method comprises:
Whole exterior walls and thickness are greater than with the interior wall of 140mm: if the structural elements above wall is precast beam,
Pipeline generates butt hole in wall upper end, and pipeline is pipeline center apart from metope 65- in the position that wall upper end generates at this time
100mm, and precast beam part is thus reached on position, generates respective sleeve on precast beam, pipeline continue on reach in-situ layer again
It is attached with other equipment;If the component above wall is superimposed sheet, when pipeline is drawn from wall upper end, wall upper end
Generate adapter tube hole;In wall upper end, pipeline is located at wall middle position, and pipeline is up drawn among wall, continue on reach
In-situ layer is attached with other equipment again;
Be not more than the interior wall of 140mm for thickness: wall upper end pipeline is drawn from the intermediate of wall, pipeline continue on reach
In-situ layer is attached with other equipment again.
For and interior wall, socket be just set to that side in which side, pipeline.
Described sleeve pipe size is greater than the line size;For 16mm pipeline, 20mm pipeline, 25mm pipeline, 32mm pipeline,
Corresponding casing size is respectively 20mm casing, 25mm casing, 32mm casing, 40mm casing.
The pipeline generates elbow in vertically and horizontally upper connection.
The pipeline being laterally arranged is parallel to the horizontal plane, the pipeline and horizontal plane being vertically arranged.
Compared with prior art, the advantageous effect of present invention is that: the present invention can be according on equipment on wall and floor
Equipment or different wall on the connection of equipment determine pipe on wall by the numerical value of setting when pipeline passes through wall upper end
Position can give birth to according to the pipeline up extended up on this position in beam body corresponding position if on wall being precast beam unit
Casing is produced, sleeve position meets the requirement of assembled production, improves the efficiency of design setting model, go deployment tube by the rule of offer
Road improves the accuracy of pipe arrangement position.
Detailed description of the invention
Fig. 1 is to have the precast beam of 200mm wide on 200mm interior wall, pipeline from wall surface it is closer with a distance from it is past from wall top end
The stirrup of upper introduction pipe, pipeline and beam is collided;
Fig. 2 is the precast beam for having 200mm wide on 200mm interior wall, and pipeline is pipeline center in the position that wall upper end generates
Apart from metope 65-100mm, pipeline avoids the stirrup of beam, and maintains a certain distance with stirrup, is conducive to fixed coagulation
Soil;
Fig. 3 is piping diagram one on wall of the present invention;
Fig. 4 is piping diagram two on wall of the present invention;
Fig. 5 is piping diagram three on wall of the present invention;
Wherein, 1 is precast beam;2 be wall under beam;3 be electrical equipment;4 be pipeline;5 be butt hole.
Specific embodiment
When top connection is walked in selection, the connection of equipment and equipment meets the principle of optimal path and smooth vertical and horizontal arrangement pipeline,
Optimal path at this time refers to that two respective interfaces of equipment for walking top connection by selection extend vertical pipe straight up
Until the pipeline of floor in-situ layer part, two sections of arrival floor in-situ layers connects automatically again, pipeline is in vertical and level side
Upward connection generates elbow.
Whole exterior walls, thickness are greater than the interior wall of 140mm:
Be above wall composite beam (plate): when pipe is drawn from wall upper end, wall can generate butt hole.
If the structural elements above wall is precast beam 1, pipeline 4 can generate butt hole 5 in wall upper end, at this time
Pipeline is pipeline center apart from metope d=65-100mm (the preferred 70mm of the present invention) in the position that wall upper end generates, and thus
Reach precast beam part on position, can generate respective sleeve on precast beam, pipeline continue on reach in-situ layer and set again with other
It is standby to be attached.
The position of pipe is set as the reason of apart from metope 65-100mm: if interior wall is 200mm, wall is also 200mm wide, and beam
In the surface of wall, if pipeline i.e. white line position from equipment is up extended, meeting is as shown in Figure 1, so pipeline passes through beam
Position can be centrally generated casing with pipeline, collide with reinforcing bar on beam.In order to evade this kind of situation, pipeline on wall well
It is drawn by the position of Fig. 3, the arrangement meeting of pipeline is as shown in Fig. 2, facilitate the installation of casing on beam on beam.
Pipe close to wall side, and the center of pipe to surface of wall distance be 65-100mm.
There is upper butt hole pipe to deflect away from close to the pipe of wall up to draw at surface of wall 65-100mm.
Heart position generates corresponding casing to precast beam in the duct, and casing size is more bigger than pipeline, 16mm pipeline, 20mm
Pipeline, 25mm pipeline, 32mm pipeline correspond to corresponding casing size and respectively correspond 20mm casing, 25mm casing, 32mm casing,
40mm casing.
Casing table corresponding with casing size on 1 beam of table
If the component above wall is superimposed sheet, when pipe is drawn from wall upper end, wall can generate adapter tube hole 6.
Wall upper end, pipe is in wall middle position.
Contacted with there is adapter tube hole, there is adapter tube hole pipe just up to draw among wall, pipeline continue on reach in-situ layer
It is attached again with other equipment.
If wall is the interior wall that thickness is not more than 140mm: either adapter tube hole or upper butt hole, wall upper pipes from
The intermediate of wall is drawn, and pipeline continues through in-situ layer and is attached with other equipment, pipeline continue on reach in-situ layer again with
Other equipment is attached.