CN109537821A - Building method is drained outside a kind of earthing plantation pitched roof - Google Patents
Building method is drained outside a kind of earthing plantation pitched roof Download PDFInfo
- Publication number
- CN109537821A CN109537821A CN201811644504.1A CN201811644504A CN109537821A CN 109537821 A CN109537821 A CN 109537821A CN 201811644504 A CN201811644504 A CN 201811644504A CN 109537821 A CN109537821 A CN 109537821A
- Authority
- CN
- China
- Prior art keywords
- layer
- laid
- basis
- waterproof
- pitched roof
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04D—ROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
- E04D13/00—Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage; Sky-lights
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04D—ROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
- E04D11/00—Roof covering, as far as not restricted to features covered by only one of groups E04D1/00 - E04D9/00; Roof covering in ways not provided for by groups E04D1/00 - E04D9/00, e.g. built-up roofs, elevated load-supporting roof coverings
- E04D11/02—Build-up roofs, i.e. consisting of two or more layers bonded together in situ, at least one of the layers being of watertight composition
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04D—ROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
- E04D13/00—Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage; Sky-lights
- E04D13/04—Roof drainage; Drainage fittings in flat roofs, balconies or the like
- E04D13/0404—Drainage on the roof surface
- E04D13/0409—Drainage outlets, e.g. gullies
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04D—ROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
- E04D13/00—Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage; Sky-lights
- E04D13/16—Insulating devices or arrangements in so far as the roof covering is concerned, e.g. characterised by the material or composition of the roof insulating material or its integration in the roof structure
- E04D13/1606—Insulation of the roof covering characterised by its integration in the roof structure
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04D—ROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
- E04D13/00—Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage; Sky-lights
- E04D13/16—Insulating devices or arrangements in so far as the roof covering is concerned, e.g. characterised by the material or composition of the roof insulating material or its integration in the roof structure
- E04D13/1687—Insulating devices or arrangements in so far as the roof covering is concerned, e.g. characterised by the material or composition of the roof insulating material or its integration in the roof structure the insulating material having provisions for roof drainage
- E04D13/1693—Insulating devices or arrangements in so far as the roof covering is concerned, e.g. characterised by the material or composition of the roof insulating material or its integration in the roof structure the insulating material having provisions for roof drainage the upper surface of the insulating material forming an inclined surface
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
- Y02A30/24—Structural elements or technologies for improving thermal insulation
- Y02A30/254—Roof garden systems; Roof coverings with high solar reflectance
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B80/00—Architectural or constructional elements improving the thermal performance of buildings
- Y02B80/32—Roof garden systems
Abstract
The present invention relates to architectural design technical field, building method is drained outside in particular a kind of earthing plantation pitched roof, comprising the following steps: Step 1: cast-in-place concrete roof structural slab: by roofing construction sheet vibration compacting after-pouring;Step 2: being laid with heat insulation layer on the basis of roofing construction sheet: being laid with heat insulation layer using spraying hard-foam polyurethane heat-insulating material;Step 3: being laid with sloping layer on the basis of heat insulation layer: looking for slope by cement mortar screeding to falls or by light material;Step 4: being laid with general waterproof layer on the basis of sloping layer: being laid with general waterproof layer using high-polymer modified pitch, self-adhesion class waterproof roll, synthetic polymeric waterproofing material, water-repellent paint or waterproof mortar.Pitched roof proposed by the present invention has energy conservation, ecological, environmental protective, reaches heat preservation, the low consumed effect of drop, and uses outer draining, and the structure of twice waterproof layer designs, and significantly reduces roof drainage load, effectively prevents the problem of roof ponding leaks.
Description
Technical field
The present invention relates to architectural design technical field, building method is drained outside specially a kind of earthing plantation pitched roof.
Background technique
As residential environment, quality requirement are continuously improved, how tradition is broken through, in the case where meeting energy-saving requirement,
The construction of roofing will constantly bring forth new ideas, and can improve practical problem in the case where technical feasibility, process, guarantee quality, existing
The pitched roof in some houses generally constructs simple and crude, lacks waterproof layer, roof drainage load is larger, often will appear room over time
The problem of face water accumulation leaking, and the pitched roof construction in present house is unable to satisfy the life reason of energy-saving ecological environmental protection instantly
It reads, it is proposed that draining building method outside a kind of earthing plantation pitched roof.
Summary of the invention
The purpose of the present invention is to provide building method is drained outside a kind of earthing plantation pitched roof, to solve above-mentioned background skill
The problem of being proposed in art.
To achieve the above object, the invention provides the following technical scheme:
Building method is drained outside a kind of earthing plantation pitched roof, comprising the following steps:
Step 1: cast-in-place concrete roof structural slab: by roofing construction sheet vibration compacting after-pouring;
Step 2: being laid with heat insulation layer on the basis of roofing construction sheet: being laid with using spraying hard-foam polyurethane heat-insulating material
Heat insulation layer;
Step 3: being laid with sloping layer on the basis of heat insulation layer: looking for slope by cement mortar screeding to falls or by light material;
Step 4: being laid with general waterproof layer on the basis of sloping layer: using high-polymer modified pitch, self-adhesion class waterproof roll
Material, synthetic polymeric waterproofing material, water-repellent paint or waterproof mortar are laid with general waterproof layer;
Step 5: being laid with root-resistant puncturing waterproof layer on the basis of general waterproof layer: using macromolecule root-resistant puncturing waterproof
Coiled material, modified pitch class root resistant waterproof roll, polyethylene polypropylene fiber waterproof coiled material, polymer cement cementitious matter composite water-proof material
Material or high-density polyethylene geomembrane are laid with root-resistant puncturing waterproof layer;
Step 6: being laid with protective layer on the basis of root-resistant puncturing waterproof layer: being laid with protective layer using pea gravel concreten;
Step 7: being laid with water draining and accumulating layer on the basis of protective layer: being laid with water draining and accumulating layer using cobble or ceramsite material;
Step 8: being laid with filter layer on the basis of water draining and accumulating layer: the lap width for filtering layer material is greater than or equal to
150mm;
Step 9: being laid with cobble buffer strip on the basis of filter layer: being laid with cobble buffer strip using cobble, width is greater than
Or it is equal to 300mm;
Step 10: being laid with planting soil layer in the side of cobble buffer strip: shakeouing laying, layering having peace of mind after marching into the arena, and keep
Planting soil layer is consistent with the height of filter layer;
Step 11: the installation anti-skidding barricade of concrete: general waterproof layer completely spreads anti-skidding barricade;
Step 12: the outer drainpipe of installation.
As currently preferred, the material density of heat insulation layer is not more than 100kg/m in step 23, compressive strength is low
In 100kPa, and under 100kPa compressive strength, compression ratio is not greater than 10.
As currently preferred, in step 3 when roofing length of grade is less than 4m, by cement mortar screeding to falls, when roofing slope
When length is greater than 4m, slope is looked for by light material, light material uses air entrained concrete or haydite concrete.
As currently preferred, the overlapping the slot of root-resistant puncturing waterproof layer should be obturaged using sealant in step 5.
As currently preferred, when water draining and accumulating layer is laid with using cobble or haydite in step 7, particle size is uniform.
As currently preferred, filter layer is laid with smooth no wrinkle in step 8, is laid with upwards along plantation barricade, and with
Planting soil layer height is consistent.
As currently preferred, planting soil layer and anti-skidding barricade, parapet, roofing projective structure, periphery in step 9
Flashing is respectively provided with cobble buffer strip.
As currently preferred, the top nozzle of step 12 China and foreign countries drainpipe and the handover of general waterproof layer.
Compared with prior art, beneficial effects of the present invention:
Compared with traditional roof construction, pitched roof proposed by the present invention has energy conservation, ecological, environmental protective, reaches heat preservation, reduces
The effect of consumption, and outer draining is used, the structure of twice waterproof layer designs, and significantly reduces roof drainage load, effectively avoids
The problem of roof ponding leaks.
Detailed description of the invention
Fig. 1 is the structural diagram of the present invention.
In figure: roofing construction sheet 1, heat insulation layer 2, sloping layer 3, general waterproof layer 4, root-resistant puncturing waterproof layer 5, protective layer 6,
Water draining and accumulating layer 7, filter layer 8, cobble buffer strip 9, planting soil layer 10, anti-skidding barricade 11, outer drainpipe 12.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other
Embodiment shall fall within the protection scope of the present invention.
In the description of the present invention, it is to be understood that, term " center ", " longitudinal direction ", " transverse direction ", " length ", " width ",
" thickness ", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outside", " up time
The orientation or positional relationship of the instructions such as needle ", " counterclockwise " is to be based on the orientation or positional relationship shown in the drawings, and is merely for convenience of
The description present invention and simplified description, rather than the equipment of indication or suggestion meaning or element must have a particular orientation, with spy
Fixed orientation construction and operation, therefore be not considered as limiting the invention.
Embodiment 1
Building method is drained outside a kind of earthing plantation pitched roof, comprising the following steps:
Step 1: cast-in-place concrete roof structural slab 1: by 1 vibration compacting after-pouring of roofing construction sheet;
Step 2: being laid with heat insulation layer 2 on the basis of roofing construction sheet 1: using spraying hard-foam polyurethane heat-insulating material paving
If heat insulation layer 2;
Step 3: being laid with sloping layer 3 on the basis of heat insulation layer 2: being looked for by cement mortar screeding to falls or by light material
Slope;
Step 4: being laid with general waterproof layer 4 on the basis of sloping layer 3: being laid with using high-polymer modified pitch general anti-
Water layer 4;
Step 5: being laid with root-resistant puncturing waterproof layer 5 on the basis of general waterproof layer 4: anti-using macromolecule root-resistant puncturing
Water coiled material is laid with root-resistant puncturing waterproof layer 5;
Step 6: being laid with protective layer 6 on the basis of root-resistant puncturing waterproof layer 5: being laid with protective layer using pea gravel concreten
6;
Step 7: being laid with water draining and accumulating layer 7 on the basis of protective layer 6: being laid with water draining and accumulating layer 7 using cobble;
Step 8: being laid with filter layer 8 on the basis of water draining and accumulating layer 7: the lap width of 8 material of filter layer is designed as
150mm;
Step 9: being laid with cobble buffer strip 9 on the basis of filter layer 8: being laid with cobble buffer strip 9, width using cobble
It is designed as 300mm;
Step 10: being laid with planting soil layer 10 in the side of cobble buffer strip 9: shakeouing laying, layering having peace of mind after marching into the arena, and protect
It is consistent with the height of filter layer 8 to hold planting soil layer 10;
Step 11: the installation anti-skidding barricade 11 of concrete: general waterproof layer 4 completely spreads anti-skidding barricade 11;
Step 12: the outer drainpipe 12 of installation.
In the present embodiment, the material density of heat insulation layer 2 is 100kg/m in step 23, compressive strength 100kPa, and
Under 100kPa compressive strength, compression ratio 10.
In the present embodiment, in step 3 when roofing length of grade is less than 4m, by cement mortar screeding to falls, when roofing length of grade is greater than
When 4m, slope is looked for by light material, light material uses air entrained concrete or haydite concrete.
In the present embodiment, the overlapping the slot of root-resistant puncturing waterproof layer 5 should be obturaged using sealant in step 5.
In the present embodiment, when water draining and accumulating layer 7 is laid with using cobble in step 7, particle size is uniform.
In the present embodiment, filter layer 8 is laid with smooth no wrinkle in step 8, is laid with upwards along plantation barricade, and with plantation
10 height of soil layer is consistent.
In the present embodiment, planting soil layer 10 and anti-skidding barricade 11, parapet, roofing projective structure, periphery are general in step 9
Water is respectively provided with cobble buffer strip 9.
In the present embodiment, the top nozzle of step 12 China and foreign countries drainpipe 12 and general waterproof layer 4 join.
Embodiment 2
Building method is drained outside a kind of earthing plantation pitched roof, comprising the following steps:
Step 1: cast-in-place concrete roof structural slab 1: by 1 vibration compacting after-pouring of roofing construction sheet;
Step 2: being laid with heat insulation layer 2 on the basis of roofing construction sheet 1: using spraying hard-foam polyurethane heat-insulating material paving
If heat insulation layer 2;
Step 3: being laid with sloping layer 3 on the basis of heat insulation layer 2: being looked for by cement mortar screeding to falls or by light material
Slope;
Step 4: being laid with general waterproof layer 4 on the basis of sloping layer 3: being laid with one using synthetic polymeric waterproofing material
As waterproof layer 4;
Step 5: being laid with root-resistant puncturing waterproof layer 5 on the basis of general waterproof layer 4: being worn using modified pitch class resistance to
It pierces waterproof roll and is laid with root-resistant puncturing waterproof layer 5;
Step 6: being laid with protective layer 6 on the basis of root-resistant puncturing waterproof layer 5: being laid with protective layer using pea gravel concreten
6;
Step 7: being laid with water draining and accumulating layer 7 on the basis of protective layer 6: being laid with water draining and accumulating layer 7 using ceramsite material;
Step 8: being laid with filter layer 8 on the basis of water draining and accumulating layer 7: the lap width of 8 material of filter layer is designed as
180mm;
Step 9: being laid with cobble buffer strip 9 on the basis of filter layer 8: being laid with cobble buffer strip 9, width using cobble
It is designed as 320mm;
Step 10: being laid with planting soil layer 10 in the side of cobble buffer strip 9: shakeouing laying, layering having peace of mind after marching into the arena, and protect
It is consistent with the height of filter layer 8 to hold planting soil layer 10;
Step 11: the installation anti-skidding barricade 11 of concrete: general waterproof layer 4 completely spreads anti-skidding barricade 11;
Step 12: the outer drainpipe 12 of installation.
In the present embodiment, the material density of heat insulation layer 2 is 90kg/m in step 23, compressive strength 110kPa, and
Under 110kPa compressive strength, compression ratio 9.
In the present embodiment, in step 3 when roofing length of grade is less than 4m, by cement mortar screeding to falls, when roofing length of grade is greater than
When 4m, slope is looked for by light material, light material uses air entrained concrete or haydite concrete.
In the present embodiment, the overlapping the slot of root-resistant puncturing waterproof layer 5 should be obturaged using sealant in step 5.
In the present embodiment, when water draining and accumulating layer 7 is laid with using haydite in step 7, particle size is uniform.
In the present embodiment, filter layer 8 is laid with smooth no wrinkle in step 8, is laid with upwards along plantation barricade, and with plantation
10 height of soil layer is consistent.
In the present embodiment, planting soil layer 10 and anti-skidding barricade 11, parapet, roofing projective structure, periphery are general in step 9
Water is respectively provided with cobble buffer strip 9.
In the present embodiment, the top nozzle of step 12 China and foreign countries drainpipe 12 and general waterproof layer 4 join.
Embodiment 3
Building method is drained outside a kind of earthing plantation pitched roof, comprising the following steps:
Step 1: cast-in-place concrete roof structural slab 1: by 1 vibration compacting after-pouring of roofing construction sheet;
Step 2: being laid with heat insulation layer 2 on the basis of roofing construction sheet 1: using spraying hard-foam polyurethane heat-insulating material paving
If heat insulation layer 2;
Step 3: being laid with sloping layer 3 on the basis of heat insulation layer 2: being looked for by cement mortar screeding to falls or by light material
Slope;
Step 4: being laid with general waterproof layer 4 on the basis of sloping layer 3: being laid with general waterproof layer 4 using waterproof mortar;
Step 5: being laid with root-resistant puncturing waterproof layer 5 on the basis of general waterproof layer 4: using high density polyethylene (HDPE) geotechnique
Film is laid with root-resistant puncturing waterproof layer 5;
Step 6: being laid with protective layer 6 on the basis of root-resistant puncturing waterproof layer 5: being laid with protective layer using pea gravel concreten
6;
Step 7: being laid with water draining and accumulating layer 7 on the basis of protective layer 6: being laid with water draining and accumulating layer 7 using cobble;
Step 8: being laid with filter layer 8 on the basis of water draining and accumulating layer 7: the lap width of 8 material of filter layer is designed as
200mm;
Step 9: being laid with cobble buffer strip 9 on the basis of filter layer 8: being laid with cobble buffer strip 9, width using cobble
It is designed as 350mm;
Step 10: being laid with planting soil layer 10 in the side of cobble buffer strip 9: shakeouing laying, layering having peace of mind after marching into the arena, and protect
It is consistent with the height of filter layer 8 to hold planting soil layer 10;
Step 11: the installation anti-skidding barricade 11 of concrete: general waterproof layer 4 completely spreads anti-skidding barricade 11;
Step 12: the outer drainpipe 12 of installation.
In the present embodiment, the material density of heat insulation layer 2 is 80kg/m in step 23, compressive strength 120kPa, and
Under 120kPa compressive strength, compression ratio 8.
In the present embodiment, in step 3 when roofing length of grade is less than 4m, by cement mortar screeding to falls, when roofing length of grade is greater than
When 4m, slope is looked for by light material, light material uses air entrained concrete or haydite concrete.
In the present embodiment, the overlapping the slot of root-resistant puncturing waterproof layer 5 should be obturaged using sealant in step 5.
In the present embodiment, when water draining and accumulating layer 7 is laid with using cobble in step 7, particle size is uniform.
In the present embodiment, filter layer 8 is laid with smooth no wrinkle in step 8, is laid with upwards along plantation barricade, and with plantation
10 height of soil layer is consistent.
In the present embodiment, planting soil layer 10 and anti-skidding barricade 11, parapet, roofing projective structure, periphery are general in step 9
Water is respectively provided with cobble buffer strip 9.
In the present embodiment, the top nozzle of step 12 China and foreign countries drainpipe 12 and general waterproof layer 4 join.
The basic principles, main features and advantages of the present invention have been shown and described above.The technology of the industry
For personnel it should be appreciated that the present invention is not limited to the above embodiments, described in the above embodiment and specification is only the present invention
Preference, be not intended to limit the invention, without departing from the spirit and scope of the present invention, the present invention also has various
Changes and improvements, these changes and improvements all fall within the protetion scope of the claimed invention.The claimed scope of the invention is by institute
Attached claims and its equivalent thereof.
Claims (8)
1. draining building method outside a kind of earthing plantation pitched roof, it is characterised in that: the following steps are included:
Step 1: cast-in-place concrete roof structural slab (1): by roofing construction sheet (1) vibration compacting after-pouring;
Step 2: being laid with heat insulation layer (2) on the basis of roofing construction sheet (1): using spraying hard-foam polyurethane heat-insulating material paving
If heat insulation layer (2);
Step 3: being laid with sloping layer (3) on the basis of heat insulation layer (2): being looked for by cement mortar screeding to falls or by light material
Slope;
Step 4: being laid with general waterproof layer (4) on the basis of sloping layer (3): using high-polymer modified pitch, self-adhesion class waterproof
Coiled material, synthetic polymeric waterproofing material, water-repellent paint or waterproof mortar are laid with general waterproof layer (4);
Step 5: being laid with root-resistant puncturing waterproof layer (5) on the basis of general waterproof layer (4): anti-using macromolecule root-resistant puncturing
Water coiled material, modified pitch class root resistant waterproof roll, polyethylene polypropylene fiber waterproof coiled material, polymer cement cementitious matter composite water-proof
Material or high-density polyethylene geomembrane are laid with root-resistant puncturing waterproof layer (5);
Step 6: being laid with protective layer (6) on the basis of root-resistant puncturing waterproof layer (5): being laid with protective layer using pea gravel concreten
(6);
Step 7: being laid with water draining and accumulating layer (7) on the basis of protective layer (6): being laid with water draining and accumulating layer using cobble or ceramsite material
(7);
Step 8: being laid with filter layer (8) on the basis of water draining and accumulating layer (7): the lap width of filter layer (8) material is greater than or waits
In 150mm;
Step 9: being laid with cobble buffer strip (9) on the basis of filter layer (8): cobble buffer strip (9) are laid with using cobble, it is wide
Degree is greater than or equal to 300mm;
Step 10: being laid with planting soil layer (10) in the side of cobble buffer strip (9): shakeouing laying, layering having peace of mind after marching into the arena, and protect
It is consistent with the height of filter layer (8) to hold planting soil layer (10);
Step 11: the installation anti-skidding barricade of concrete (11): general waterproof layer (4) completely spreads anti-skidding barricade (11);
Step 12: the outer drainpipe (12) of installation.
2. draining building method outside earthing plantation pitched roof according to claim 1, it is characterised in that: be insulated in step 2
The material density of layer (2) is not more than 100kg/m3, compressive strength is not less than 100kPa, and under 100kPa compressive strength, compresses
Than being not greater than 10.
3. draining building method outside earthing plantation pitched roof according to claim 1, it is characterised in that: work as room in step 3
When face length of grade is less than 4m, slope, light material are looked for by light material when roofing length of grade is greater than 4m by cement mortar screeding to falls
Using air entrained concrete or haydite concrete.
4. draining building method outside earthing plantation pitched roof according to claim 1, it is characterised in that: resistance in step 5
The overlapping the slot for puncturing waterproof layer (5) should be obturaged using sealant.
5. draining building method outside earthing plantation pitched roof according to claim 1, it is characterised in that: arrange and store in step 7
When water layer (7) is laid with using cobble or haydite, particle size is uniform.
6. draining building method outside earthing plantation pitched roof according to claim 1, it is characterised in that: filtered in step 8
Layer (8) is laid with smooth no wrinkle, is laid with upwards along plantation barricade, and consistent with planting soil layer (10) height.
7. draining building method outside earthing plantation pitched roof according to claim 1, it is characterised in that: planted in step 9
Soil layer (10) and anti-skidding barricade (11), parapet, roofing projective structure, periphery flashing are respectively provided with cobble buffer strip (9).
8. draining building method outside earthing plantation pitched roof according to claim 1, it is characterised in that: step 12 China and foreign countries
The top nozzle of drainpipe (12) and general waterproof layer (4) join.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811644504.1A CN109537821A (en) | 2018-12-29 | 2018-12-29 | Building method is drained outside a kind of earthing plantation pitched roof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811644504.1A CN109537821A (en) | 2018-12-29 | 2018-12-29 | Building method is drained outside a kind of earthing plantation pitched roof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109537821A true CN109537821A (en) | 2019-03-29 |
Family
ID=65831604
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811644504.1A Pending CN109537821A (en) | 2018-12-29 | 2018-12-29 | Building method is drained outside a kind of earthing plantation pitched roof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109537821A (en) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101250929A (en) * | 2008-04-08 | 2008-08-27 | 新蒲建设集团有限公司 | Planting roofing as well as construction method thereof |
KR20150025652A (en) * | 2013-08-29 | 2015-03-11 | 디씨텍건설주식회사 | Waterproof structure for rooftop and constructing method thereof |
CN105230308A (en) * | 2015-10-30 | 2016-01-13 | 郑州大学 | Raw soil underground cave dwelling roof vegetation plantation base structure and construction technology thereof |
CN107060226A (en) * | 2017-05-12 | 2017-08-18 | 武汉建工集团股份有限公司 | A kind of construction method of planted roof construction |
CN206903071U (en) * | 2017-06-30 | 2018-01-19 | 深圳市工大国际工程设计有限公司 | A kind of discharge structure of planted roof |
CN108979017A (en) * | 2018-06-12 | 2018-12-11 | 江苏兴厦建设工程集团有限公司 | A kind of concave curved surface roof covering water-proof structure and its building technology |
-
2018
- 2018-12-29 CN CN201811644504.1A patent/CN109537821A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101250929A (en) * | 2008-04-08 | 2008-08-27 | 新蒲建设集团有限公司 | Planting roofing as well as construction method thereof |
KR20150025652A (en) * | 2013-08-29 | 2015-03-11 | 디씨텍건설주식회사 | Waterproof structure for rooftop and constructing method thereof |
CN105230308A (en) * | 2015-10-30 | 2016-01-13 | 郑州大学 | Raw soil underground cave dwelling roof vegetation plantation base structure and construction technology thereof |
CN107060226A (en) * | 2017-05-12 | 2017-08-18 | 武汉建工集团股份有限公司 | A kind of construction method of planted roof construction |
CN206903071U (en) * | 2017-06-30 | 2018-01-19 | 深圳市工大国际工程设计有限公司 | A kind of discharge structure of planted roof |
CN108979017A (en) * | 2018-06-12 | 2018-12-11 | 江苏兴厦建设工程集团有限公司 | A kind of concave curved surface roof covering water-proof structure and its building technology |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107060226B (en) | A kind of construction method of planted roof construction | |
CN201695580U (en) | Inverted roof structure | |
CN104153522B (en) | A kind of construction method of Sloping roof skyscraper asphalt shingle roofing water-proof system | |
CN102535520B (en) | Waterproof construction method of large-area civil air defense basement | |
CN101914927A (en) | Waterproof system for basement bottom board and wall surface and construction method thereof | |
CN203531260U (en) | Inverted planting roofing structure | |
CN101545307A (en) | Roof green insulation system and method thereof | |
CN106401082B (en) | A kind of planted roof discharge structure and construction method based on siphonic system | |
CN107313560B (en) | Reinforced waterproof roof of archaize building and construction method thereof | |
CN205935437U (en) | Parapet wall body structure | |
CN105386570A (en) | Breathing thermal insulation roof structure and construction method | |
CN111119416A (en) | Planting roof and construction method | |
CN102912945B (en) | Roof compound seepage-proofing steam exhausting hole detail treatment technology | |
CN206346401U (en) | A kind of planted roof discharge structure based on siphonic system | |
KR101027655B1 (en) | Rubberized asphalt pileup layers waterproofing materials with root barrier for the green roof and artificial foundation and its application method | |
CN104652716B (en) | Heat-insulating and waterproof system of planted roof and construction method thereof | |
CN101575896A (en) | Plastic self-adhesive waterproof roll material and application thereof to roof planting | |
CN206616785U (en) | Inverted roof provided with steam passing away | |
CN205617555U (en) | Roof root resistance waterproof construction is planted to basement | |
CN202672509U (en) | Inversed ceramsite concrete planting roof | |
CN218814791U (en) | Assembled roofing system | |
CN204531198U (en) | A kind of compound water-proof thermal-insulation integral system | |
CN201437622U (en) | Waterproof breathable film of composite grid reinforcing rib | |
CN208396162U (en) | A kind of thermal isolation by water storage roofing | |
CN109537821A (en) | Building method is drained outside a kind of earthing plantation pitched roof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |