CN109537465A - A kind of assembled cushion cap pier stud joint model and the cementation of fissures construction technology using it - Google Patents

A kind of assembled cushion cap pier stud joint model and the cementation of fissures construction technology using it Download PDF

Info

Publication number
CN109537465A
CN109537465A CN201811508450.6A CN201811508450A CN109537465A CN 109537465 A CN109537465 A CN 109537465A CN 201811508450 A CN201811508450 A CN 201811508450A CN 109537465 A CN109537465 A CN 109537465A
Authority
CN
China
Prior art keywords
cushion cap
template
cementation
joint model
pier stud
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811508450.6A
Other languages
Chinese (zh)
Other versions
CN109537465B (en
Inventor
李永胜
巴特尔
何永军
邹熠
欧剑辉
徐彦朋
邵玉鹏
李献民
李伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CONSTRUCTION TECHNOLOGY INSTITUTE OF FHEC OF CCCC
CCCC First Highway Engineering Group Co Ltd
Original Assignee
CONSTRUCTION TECHNOLOGY INSTITUTE OF FHEC OF CCCC
CCCC First Highway Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CONSTRUCTION TECHNOLOGY INSTITUTE OF FHEC OF CCCC, CCCC First Highway Engineering Group Co Ltd filed Critical CONSTRUCTION TECHNOLOGY INSTITUTE OF FHEC OF CCCC
Priority to CN201811508450.6A priority Critical patent/CN109537465B/en
Publication of CN109537465A publication Critical patent/CN109537465A/en
Application granted granted Critical
Publication of CN109537465B publication Critical patent/CN109537465B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a kind of assembled cushion cap pier stud joint model and use its cementation of fissures construction technology, it is related to the objective demand of prefabrication and assembly construction construction bridges connection seam pouring construction, the boundary condition of gap-grouting material when analog cast in situs of the present invention, belong to Application in Building technical field, the present invention is easy to make, detail structure simulates the boundary condition of gap-grouting material, template slit width adjusting range meets design drawing requirement, gap-grouting material usage amount is less, both the determination to mixing plant parameter had been met, it can test again to the construction technology of gap-grouting material, pass through intensity detection after cutting after demoulding to the observation of the appearance of a sample and material, it can intuitively accurate interpretation to the performance of gap-grouting material, it has broad application prospects.

Description

A kind of assembled cushion cap pier stud joint model and the cementation of fissures construction technology using it
Technical field
The present invention relates to the objective demand of prefabrication and assembly construction construction bridges connection seam pouring construction, analog scene of the present invention The boundary condition of gap-grouting material when pouring belongs to Application in Building technical field, specifically a kind of assembled cushion cap pier stud seam mould Type and the cementation of fissures construction technology for using it.
Background technique
In China, the prefabricated building technology of bridge superstructure comparative maturity, and built in a large amount of bridge If middle use, and substructure is the key that current prefabricated assembled bridge, particularly with Beijing Gao Zhenqu, the company of substructure Connecing form, mechanical property and resistance to shock is the most key link, carries out prefabricated assembled connecting sewing ultra-high performance concrete The key technologies experimental study such as cementation of fissures construction technology, for bridge construction Project design and site construction technology provide basis and according to According to.
Whether self-compacting concrete can reach the requirement of dense packing effect template under conditions of relying solely on itself gravity, it Workability plays a crucial role, and excellent workability is itself and the most fundamental difference of normal concrete.At present from close Real concrete self-characteristic and prefabrication and assembly construction construction bridges connection seam special structure form still have following technological difficulties: 1. connecting It is limited to connect joint gap, pouring construction technique needs to study;2. joint grouting there may be and undetectable perfusion leakiness Problem avoids hidden danger of quality.
For this purpose, it is proposed that a kind of assembled cushion cap pier stud joint model and using its cementation of fissures construction technology, using wood Matter rib modeling interface ripple makees the high technical problem of difficulty to solve interface ripple wheat flour.
Summary of the invention
The purpose of the present invention is to provide a kind of assembled cushion cap pier stud joint model and using its cementation of fissures construction technology, To solve the problems mentioned in the above background technology.
To achieve the above object, the invention provides the following technical scheme:
A kind of assembled cushion cap pier stud joint model, including Precast Pier Columns and cushion cap, the Precast Pier Columns are arranged in cushion cap On;It further include reserved slot, concrete perfusion, alligator and template, the reserved slot is arranged on cushion cap, the Precast Pier Columns It is fixed in reserved slot by concrete perfusion and alligator, the template modeling interface corrugated surface, the interface corrugated surface is The contact surface of cushion cap and Precast Pier Columns when seam pours in assembled architecture is using the benefit of corrugated surface: improve pour it is close Reality.
As a further solution of the present invention: rib is provided in the template, the rib and template are wooden material Matter, rib are pasted onto template.
As a further solution of the present invention: the rib in template using straight line slot type be distributed, rib in template Upper spacing is 5cm, and rib is with a thickness of 0.5cm;The template is 1.8cm thick coating plate, and the inner side and outer side of template is to face directly, Template width is 15cm, and it is excessive to simulate 45 degree of slopes along the two sides milling of rib length direction for template.
A kind of cementation of fissures construction technology using assembled cushion cap pier stud joint model, includes the following steps:
1) stirring instrument selection: moveable forced formula blender is used;
2) it stirs: cementitious matter first being stirred into flow regime, add steel fibre and stirring is allowed to be evenly distributed, perfusion is mixed Solidifying soil, which stirs evenly, makes it in flow regime;
3) it the cementation of fissures: is irrigated according to minimum crack pouring width 6cm;The cementation of fissures of assembled cushion cap and Precast Pier Columns is applied in completion Work;
4) demoulding: form removal examines the closely knit situation of concrete perfusion by range estimation means and indoor detection test It surveys.
As a further solution of the present invention: the stirred volume of the moveable forced formula blender used in the step 1) 0.3~0.6m3, vibration frequency 5.5kw.
As a further solution of the present invention: being by the mixing time that cementitious matter stirs into flow regime in the step 2) 2min;It is 4min that steel fibre, which is added, and stirs the mixing time for being allowed to be evenly distributed.
As a further solution of the present invention: the mode being perfused in the step 3) is irrigated using blanking funnel mode It pours.
A kind of application of assembled cushion cap pier stud joint model as described above in assembled architecture.
Compared with prior art, the beneficial effects of the present invention are:
A kind of assembled cushion cap pier stud joint model of the present invention and the cementation of fissures construction technology using it, the assembled are held Pier column joint model can pour different slit widths, simulate Embedding Material actual boundary condition, determine that material construction refers to Controlling value is marked, template slit width adjusting range meets design drawing requirement, and gap-grouting material usage amount is less, has both met to mixing plant The determination of parameter, and capable of testing to the construction technology of gap-grouting material, by after demoulding to the observation of the appearance of a sample and material Intensity detection after material cutting, can intuitively accurate interpretation to the performance of gap-grouting material;It is of the present invention to use assembled cushion cap The cementation of fissures construction technological process of pier stud joint model is simple, easy to make, has broad application prospects.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of assembled cushion cap pier stud joint model in the present invention.
Fig. 2 is the structural schematic diagram of the interface corrugated surface of assembled cushion cap pier stud joint model in the present invention.
Fig. 3 is the positive structure diagram of the template of assembled cushion cap pier stud joint model in the present invention.
Fig. 4 is the overlooking structure diagram of the template of assembled cushion cap pier stud joint model in the present invention.
Fig. 5 is the left view structural representation of the template of assembled cushion cap pier stud joint model in the present invention.
In figure: 1- Precast Pier Columns, 2- reserve slot, 3- alligator, 4- concrete perfusion, 5- cushion cap, the interface 6- corrugated surface, 7- Template, 8- rib.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Embodiment one
Please refer to Fig. 1~5, in the embodiment of the present invention, a kind of assembled cushion cap pier stud joint model, including Precast Pier Columns 1 With cushion cap 5, the Precast Pier Columns 1 are arranged on cushion cap 5;It further include reserving slot 2, concrete perfusion 4, alligator 3 and template 7, The reserved slot 2 is arranged on cushion cap 5, and the Precast Pier Columns 1 are fixed on reserved slot 2 by concrete perfusion 4 and alligator 3 In, the 7 modeling interface corrugated surface 6 of template, the interface corrugated surface 6 is seam cushion cap 5 and pre- when pouring in assembled architecture The contact surface of pier stud 1 processed is: improving the density poured using the benefit of corrugated surface.
In the embodiment of the present invention, rib 8 is provided in the template 7, the rib 8 and template 7 are wooden material, rib Item 8 is pasted onto template 7.
In the embodiment of the present invention, the rib 8 in template 7 using straight line slot type be distributed, rib 8 in template 7 between Away from for 5cm, rib 8 is with a thickness of 0.5cm;The template 7 is 1.8cm thick coating plate, and the inner side and outer side of template 7 is to face directly, 7 width of template is 15cm, and it is excessive to simulate 45 degree of slopes along 8 length direction two sides milling of rib for template 7.
Embodiment two
In the embodiment of the present invention, a kind of cementation of fissures construction technology using assembled cushion cap pier stud joint model is provided, it is described Assembled cushion cap pier stud joint model structure it is identical as described in embodiment one, the cementation of fissures construction technology includes as follows Step:
1) stirring instrument selection: moveable forced formula blender is used;
2) it stirs: cementitious matter first being stirred into flow regime, add steel fibre and stirring is allowed to be evenly distributed, perfusion is mixed Solidifying soil 4, which stirs evenly, makes it in flow regime;
3) it the cementation of fissures: is irrigated according to minimum crack pouring width 6cm;Complete the cementation of fissures to assembled cushion cap 5 and Precast Pier Columns 1 Construction;
4) demoulding: form removal 7 carries out the closely knit situation of concrete perfusion 4 by range estimation means and indoor detection test Detection.
In the embodiment of the present invention, the stirred volume 0.3 of the moveable forced formula blender used in the step 1)~ 0.6m3, vibration frequency 5.5kw.
In the embodiment of the present invention, cementitious matter is stirred into the mixing time of flow regime for 2min in the step 2);Add Entering steel fibre and stirring the mixing time for being allowed to be evenly distributed is 4min.
In the embodiment of the present invention, the mode being perfused in the step 3) is irrigated using blanking funnel mode to be poured.
It is obvious to a person skilled in the art that invention is not limited to the details of the above exemplary embodiments, Er Qie In the case where without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the present invention is by appended power Benefit requires rather than above description limits, it is intended that all by what is fallen within the meaning and scope of the equivalent elements of the claims Variation is included within the present invention.Any reference signs in the claims should not be construed as limiting the involved claims.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art The other embodiments being understood that.

Claims (8)

1. a kind of assembled cushion cap pier stud joint model, including Precast Pier Columns (1) and cushion cap (5), Precast Pier Columns (1) setting On cushion cap (5);It is characterized in that, further include reserving slot (2), concrete perfusion (4), alligator (3) and template (7), it is described Reserved slot (2) are arranged on cushion cap (5), and the Precast Pier Columns (1) are fixed on pre- by concrete perfusion (4) and alligator (3) It stays in slot (2), template (7) the modeling interface corrugated surface (6), the interface corrugated surface (6) is seam in assembled architecture The contact surface of cushion cap (5) and Precast Pier Columns (1) when pouring.
2. assembled cushion cap pier stud joint model according to claim 1, which is characterized in that be arranged on the template (7) Have rib (8), the rib (8) and template (7) are wooden material, and rib (8) is pasted on template (7).
3. assembled cushion cap pier stud joint model according to claim 2, which is characterized in that the rib (8) is in template (7) it is distributed on using straight line slot type, the spacing on template (7) of rib (8) is 5cm, and rib (8) is with a thickness of 0.5cm;The mould Plate (7) is 1.8cm thick coating plate, and the inner side and outer side of template (7) is to face directly, and template (7) width is 15cm, template (7) edge Rib (8) length direction two sides milling, 45 degree of slopes of simulation are excessive.
4. a kind of cementation of fissures construction technology using the assembled cushion cap pier stud joint model as described in right 1-3 is any, feature It is, includes the following steps:
1) stirring instrument selection: moveable forced formula blender is used;
2) it stirs: cementitious matter first being stirred into flow regime, add steel fibre and stirring is allowed to be evenly distributed, concrete perfusion (4) stirring evenly makes it in flow regime;
3) it the cementation of fissures: is irrigated according to minimum crack pouring width 6cm;Complete the cementation of fissures to assembled cushion cap (5) and Precast Pier Columns (1) Construction;
4) demoulding: form removal (7) carries out the closely knit situation of concrete perfusion (4) by range estimation means and indoor detection test Detection.
5. the cementation of fissures construction technology according to claim 4 using assembled cushion cap pier stud joint model, which is characterized in that 0.3~0.6m of stirred volume of the moveable forced formula blender used in the step 1)3, vibration frequency 5.5kw.
6. the cementation of fissures construction technology according to claim 4 using assembled cushion cap pier stud joint model, which is characterized in that Cementitious matter is stirred into the mixing time of flow regime for 2min in the step 2);Steel fibre is added and stirs and is allowed to distribution Even mixing time is 4min.
7. the cementation of fissures construction technology according to claim 4 using assembled cushion cap pier stud joint model, which is characterized in that The mode being perfused in the step 3) is irrigated using blanking funnel mode and is poured.
8. a kind of application of the assembled cushion cap pier stud joint model in assembled architecture as described in right 1-3 is any.
CN201811508450.6A 2018-12-11 2018-12-11 Assembled bearing platform pier column joint model and joint filling construction process using same Active CN109537465B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811508450.6A CN109537465B (en) 2018-12-11 2018-12-11 Assembled bearing platform pier column joint model and joint filling construction process using same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811508450.6A CN109537465B (en) 2018-12-11 2018-12-11 Assembled bearing platform pier column joint model and joint filling construction process using same

Publications (2)

Publication Number Publication Date
CN109537465A true CN109537465A (en) 2019-03-29
CN109537465B CN109537465B (en) 2024-04-30

Family

ID=65854276

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811508450.6A Active CN109537465B (en) 2018-12-11 2018-12-11 Assembled bearing platform pier column joint model and joint filling construction process using same

Country Status (1)

Country Link
CN (1) CN109537465B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111873128A (en) * 2020-08-06 2020-11-03 河北首科铁路器材有限公司 Combined enhanced concrete corbel column and preparation method thereof

Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU1707270A (en) * 1970-06-01 1972-01-06 Thegeneral Tire & Rubber Company Elastomeric expansion joint
AT303595B (en) * 1969-10-24 1972-11-27 Rudolf Kranebitter Ing Device for the production of concrete beams, in particular reinforced concrete beams
BR7201548U (en) * 1992-09-16 1993-07-13 Jorge Gabrielli Zacharias Cali PROVISION INTRODUCED IN THE EXPANSION BOARD
RU119752U1 (en) * 2012-05-17 2012-08-27 Блум Интернешионал, ЛЛК SEAMLESS BRIDGE
CN103753693A (en) * 2013-10-31 2014-04-30 中交第一航务工程局有限公司 Vertical matching manufacturing method for precast concrete members
CN203792476U (en) * 2014-03-26 2014-08-27 中交一航局第五工程有限公司 Concrete prefabricated part dry joint printing die
CN104260199A (en) * 2014-09-26 2015-01-07 中铁二十局集团第五工程有限公司 Prefabricating construction process for corrugated steel web prestressed concrete I-shaped beam
CN105220808A (en) * 2015-09-11 2016-01-06 杭州江润科技有限公司 Large-span prestressed arch bar site prefabrication construction method of installation
CN106869017A (en) * 2017-04-05 2017-06-20 北京工业大学 A kind of pier bottom sets the precast assembly bridge pier-cushion cap node connected mode and its practice of flexible layer
CN206635791U (en) * 2017-01-23 2017-11-14 沈阳建筑大学 A kind of packaged type bridges pillarwork
CN107447647A (en) * 2017-07-25 2017-12-08 武汉理工大学 Assembled bridge pier and its construction method
CN107905092A (en) * 2017-11-02 2018-04-13 东南大学 A kind of prefabricated assembled bridge pier and its assembling and construction method
CN108547216A (en) * 2018-06-12 2018-09-18 北京市市政工程设计研究总院有限公司 Bridge prefabrication performance of concrete column confined and bridge foundation alligator bell and spigot frame and construction method
BG3023U1 (en) * 2018-08-07 2018-10-31 "Юпитер 05" Оод Expansion joint coupling module in restraint systems for bridge structures
CN108797351A (en) * 2018-06-06 2018-11-13 上海市城市建设设计研究总院(集团)有限公司 U muscle, which interlocks, overlaps the determination method of longitudinal seam compression bar width
CN209584847U (en) * 2018-12-11 2019-11-05 中交一公局土木工程建筑研究院有限公司 A kind of assembled cushion cap pier stud reserves seam vertical masonry joint model template and casting system

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101713237B (en) * 2009-11-17 2011-06-29 中国建筑第八工程局有限公司 Construction method of large-volume original decorative large pier stud fair-faced concrete
BG3031U1 (en) * 2018-08-13 2018-11-15 „Юпитер - 05“ Оод Coupling module for expansion joints in elastic restraint systems for bridges

Patent Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AT303595B (en) * 1969-10-24 1972-11-27 Rudolf Kranebitter Ing Device for the production of concrete beams, in particular reinforced concrete beams
AU1707270A (en) * 1970-06-01 1972-01-06 Thegeneral Tire & Rubber Company Elastomeric expansion joint
BR7201548U (en) * 1992-09-16 1993-07-13 Jorge Gabrielli Zacharias Cali PROVISION INTRODUCED IN THE EXPANSION BOARD
RU119752U1 (en) * 2012-05-17 2012-08-27 Блум Интернешионал, ЛЛК SEAMLESS BRIDGE
CN103753693A (en) * 2013-10-31 2014-04-30 中交第一航务工程局有限公司 Vertical matching manufacturing method for precast concrete members
CN203792476U (en) * 2014-03-26 2014-08-27 中交一航局第五工程有限公司 Concrete prefabricated part dry joint printing die
CN104260199A (en) * 2014-09-26 2015-01-07 中铁二十局集团第五工程有限公司 Prefabricating construction process for corrugated steel web prestressed concrete I-shaped beam
CN105220808A (en) * 2015-09-11 2016-01-06 杭州江润科技有限公司 Large-span prestressed arch bar site prefabrication construction method of installation
CN206635791U (en) * 2017-01-23 2017-11-14 沈阳建筑大学 A kind of packaged type bridges pillarwork
CN106869017A (en) * 2017-04-05 2017-06-20 北京工业大学 A kind of pier bottom sets the precast assembly bridge pier-cushion cap node connected mode and its practice of flexible layer
CN107447647A (en) * 2017-07-25 2017-12-08 武汉理工大学 Assembled bridge pier and its construction method
CN107905092A (en) * 2017-11-02 2018-04-13 东南大学 A kind of prefabricated assembled bridge pier and its assembling and construction method
CN108797351A (en) * 2018-06-06 2018-11-13 上海市城市建设设计研究总院(集团)有限公司 U muscle, which interlocks, overlaps the determination method of longitudinal seam compression bar width
CN108547216A (en) * 2018-06-12 2018-09-18 北京市市政工程设计研究总院有限公司 Bridge prefabrication performance of concrete column confined and bridge foundation alligator bell and spigot frame and construction method
BG3023U1 (en) * 2018-08-07 2018-10-31 "Юпитер 05" Оод Expansion joint coupling module in restraint systems for bridge structures
CN209584847U (en) * 2018-12-11 2019-11-05 中交一公局土木工程建筑研究院有限公司 A kind of assembled cushion cap pier stud reserves seam vertical masonry joint model template and casting system

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
李蓉等: "大伙房输水工程长大隧洞衬砌结构接缝新型防水系统研究", 中国建筑防水, vol. 27, no. 4, pages 22 - 25 *
王书涛等: "水泥混凝土路面接缝传力杆设置应用研究", 公路, vol. 61, no. 8, pages 52 - 55 *
贾俊峰等: "后张预应力节段拼装CFST桥墩抗侧力学行为试验", 中国公路学报, vol. 30, no. 3, pages 236 - 245 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111873128A (en) * 2020-08-06 2020-11-03 河北首科铁路器材有限公司 Combined enhanced concrete corbel column and preparation method thereof
CN111873128B (en) * 2020-08-06 2021-10-29 河北首科铁路器材有限公司 Combined enhanced concrete corbel column and preparation method thereof

Also Published As

Publication number Publication date
CN109537465B (en) 2024-04-30

Similar Documents

Publication Publication Date Title
CN109811931A (en) A kind of fabricated shear wall building structure and its construction method based on BIM
CN102289980B (en) Method for preparing preset cracks in hydrofracture simulation specimen
CN110287513A (en) A kind of built-in fitting construction method based on BIM technology
CN103645081A (en) Sawtooth-shaped structure surface sample making mould with adjustable angle and size
CN104818792A (en) Measurement, control and construction method for curved roof formwork system
CN110750819A (en) Discrete element and finite difference method coupled asphalt mixture simulation modeling method
CN114108917B (en) Height-adjustable assembly type composite floor slab construction method
CN105651572A (en) Preparation method for filling blind joint-containing columnar joint rock mass sample
CN203236589U (en) Sectional type quick release prefabricated bridge deck slab side mould device
CN109680706A (en) A kind of assembled cushion cap pier stake prototype and the cementation of fissures construction technology using it
CN108547335A (en) A kind of assembly superposed type pipe gallery test model and preparation method thereof
CN209584848U (en) Seam prototype template and casting system are reserved in a kind of assembled cushion cap pier stake
CN109537465A (en) A kind of assembled cushion cap pier stud joint model and the cementation of fissures construction technology using it
CN111877814A (en) Construction method for prefabricating bare concrete stand plate
CN209584847U (en) A kind of assembled cushion cap pier stud reserves seam vertical masonry joint model template and casting system
CN209538012U (en) Seam prototype template and casting system are reserved in a kind of assembled bent cap pier stake
Grünewald et al. 12 Deliberate deformation of concrete after casting
CN210562902U (en) T-shaped steel floor plate of integrated house
CN109440652A (en) A kind of assembled bent cap pier stake prototype and the cementation of fissures construction technology using it
CN104652280B (en) Overlength, after water fish ridge wall one-time continuous moulding irrigation method and overlength fish ridge wall thereof
CN110042958A (en) A kind of steel bar template integration T shape wall member and production method
CN108951439A (en) A kind of prefabricated assembled box culvert construction of waterproof layer method
CN108640607A (en) A kind of high-durability clear-water concrete and its construction method
CN109680612A (en) A kind of assembled bent cap pier stud vertical masonry joint model and the cementation of fissures construction technology using it
CN208283027U (en) A kind of assembly superposed type pipe gallery test model

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant