CN109518960A - A kind of casting top slab reserved opening can have enough to meet the need shaper and its construction method - Google Patents

A kind of casting top slab reserved opening can have enough to meet the need shaper and its construction method Download PDF

Info

Publication number
CN109518960A
CN109518960A CN201910015390.2A CN201910015390A CN109518960A CN 109518960 A CN109518960 A CN 109518960A CN 201910015390 A CN201910015390 A CN 201910015390A CN 109518960 A CN109518960 A CN 109518960A
Authority
CN
China
Prior art keywords
shaper
reserved opening
main body
die main
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910015390.2A
Other languages
Chinese (zh)
Other versions
CN109518960B (en
Inventor
李彦伟
孔令熙
部海洋
黄皓
姚佳男
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN201910015390.2A priority Critical patent/CN109518960B/en
Priority claimed from CN201910015390.2A external-priority patent/CN109518960B/en
Publication of CN109518960A publication Critical patent/CN109518960A/en
Application granted granted Critical
Publication of CN109518960B publication Critical patent/CN109518960B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G15/00Forms or shutterings for making openings, cavities, slits, or channels
    • E04G15/06Forms or shutterings for making openings, cavities, slits, or channels for cavities or channels in walls of floors, e.g. for making chimneys
    • E04G15/063Re-usable forms

Abstract

A kind of casting top slab reserved opening can have enough to meet the need shaper and its construction method, include die main body, handle and lifting device;The die main body is in inverted prism-frustum-shaped, is enclosed by four sides and a bottom surface;Hole and bolt hole are offered on the bottom surface of die main body;Wherein hole is provided in the middle part of bottom surface, and bolt hole is provided with the two sides at hole;The handle is connected to the opposite side of die main body, the taking-up for concreting molding rear mold;The lifting device includes support, casing and lift lever;The support level is connected to the top of die main body, at location mid-shaft;Described sleeve pipe is connected at the openings position of the side of support, corresponding bottom surface;The lift lever is vertically adjustable to be connected in casing.The present invention, which solves traditional shaper, there is technical issues that easy to damage, turnover rate is low, it is poor easily to run mould, Forming Quality, matches mould, material of taking a lot of work layer by layer, it is cumbersome to construct and.

Description

A kind of casting top slab reserved opening can have enough to meet the need shaper and its construction method
Technical field
The present invention relates to construction casting top slab cave entrance reservation field, especially a kind of casting top slab reserved opening can week Turn shaper and its construction method.
Background technique
In modern architecture construction, top plate generally requires to reserve some interim holes, or building auxiliary positioning or pipeline Equipment installation or delivery pump pipe are reinforced.These temporary reservation holes carry out after the completion of main body construction, before decorations construction Closing, mostly has the characteristics that size is smaller, position is fixed and regular shape;To the Forming Quality requirement at these holes when construction It is relatively low, it is often ignored in construction link, cause some hidden danger of quality.Traditional top plate reserved opening uses plank sheathing It reinforces and forms with the lumps of wood, template, the lumps of wood are fixed after forming by hole size using steel nail.This shaper there are it is easy to damage, The problems such as turnover rate is low, and easily race mould, Forming Quality is poor, matches mould layer by layer, material of taking a lot of work, construction cumbersome and inefficiency, is increasing While adding construction cost, the serious waste of resource is also resulted in.
Summary of the invention
The object of the present invention is to provide a kind of casting top slab reserved openings can have enough to meet the need shaper and its construction method, to solve There are easy to damage, turnover rate is low, it is poor easily to run mould, Forming Quality, matches mould, material of taking a lot of work, construction layer by layer for certainly traditional shaper The technical issues of cumbersome and inefficiency.
To achieve the above object, the present invention adopts the following technical scheme that.
A kind of casting top slab reserved opening can have enough to meet the need shaper, include die main body, handle and lifting device;It is described Die main body is in inverted prism-frustum-shaped, is enclosed by four sides and a bottom surface;It is offered on the bottom surface of die main body Hole and bolt hole;Wherein hole is provided in the middle part of bottom surface, and bolt hole is provided with the two sides at hole;The handle is connected to mold The opposite side of main body, the taking-up for concreting molding rear mold;The lifting device includes support, casing and promotion Bar;The support level is connected to the top of die main body, at location mid-shaft;Described sleeve pipe be connected to support side, At the openings position of corresponding bottom surface;The lift lever is vertically adjustable to be connected in casing.
Preferably, the horizontal section of the die main body is in rectangle or square;The height ratio of the die main body waits for Pour the thickness greatly at least 100mm of top plate.
Preferably, the handle is in inverted U-shaped, and is welded to connect in the opposite side of die main body;Wherein, the handle of every side Top exceeds the top margin of corresponding side side.
Preferably, the lift lever is T-shaped, includes horizontal sides and vertical edge;Wherein, the vertical edge of lift lever is equipped with outer spiral shell Line.
Preferably, the inner sidewall of described sleeve pipe is equipped with the internal screw thread being adapted with external screw thread on lift lever;The promotion The vertical edge of bar is threaded in casing.
Preferably, the shape at the hole is rectangle or square;The bolt hole is spaced apart along the edge of bottom surface If.
A kind of casting top slab reserved opening can have enough to meet the need the construction method of shaper, including steps are as follows.
Step 1: unwrapping wire positions, the accurate dimension of reserved opening is determined according to the position of main shaft, is drawn on roof plate template The sideline of reserved opening out.
Step 2: determining the position of the bolt to fixing mould on roof plate template: the mould of bolt hole will be held successfully in advance Tool is placed on roof plate template, at corresponding reserved opening edge positions, is accurately positioned the position of bolt on roof plate template.
Step 3: drilling: on roof plate template, the position of corresponding bolt hole drills.
Step 4: the binding of roof steel bar.
Step 5: fixed shaper: matched bolt is penetrated bolt hole, the position of fixed shaper above top plate It sets, prevents from causing impact to shift on mold during concreting.
Step 6: pouring concrete roof, and conserve.
Step 7: removing shaper when the intensity of concrete roof reaches design strength, cleaning out, in case again It is secondary to be used in turn.
Preferably, when the size of reserved opening is less than or equal to 300mm × 300mm, roof steel bar gets around reserved opening, no Cutting;
When the size of reserved opening is greater than 300mm × 300mm, when step 4 binds roof steel bar, increase additional reinforcing bars.
Compared with prior art the invention has the characteristics that and beneficial effect.
1, the present invention relates to construction casting top slab cave entrance reservation fields, are a kind of easy to operate, low in cost, turnovers Rate is high, the regularization tool of good forming effect.
2, the present invention opens up bolt hole on the bottom surface of die main body, is fixed into using the template of nut and top plate to be poured It is whole, it prevents from causing impact to shift die main body during concreting;And it is connected in a manner of nut, it is easy to dismantle After be used in turn.
3, it is provided with lifting device in the present invention, in demoulding difficulty, rotates down lift lever, lift lever is leaned on casing Screw thread rotation moves up and down;The template surface of top plate to be poured is withstood in lift lever bottom, can band by the jacking force of lift lever Moving mold is integrally lifted up, power-assisted demoulding.
Detailed description of the invention
The present invention will be further described in detail with reference to the accompanying drawing.
Fig. 1 is the side structure schematic diagram of shaper in the present invention.
Fig. 2 is the positive structure schematic of shaper in the present invention.
Fig. 3 is the overlooking structure diagram of shaper in the present invention.
Fig. 4 is the schematic perspective view of shaper in the present invention.
Appended drawing reference: 1- die main body, the side 1.1-, the bottom surface 1.2-, 2- handle, the hole 3-, 4- bolt hole, 5- support, 6- casing, 7- lift lever.
Specific embodiment
Casting top slab reserved opening in the present embodiment can have enough to meet the need shaper, cast-in-place for fabric structure construction period The molding of concrete roof reserved opening is a kind of regularization, can turnover type template tool;As shown in Figs 1-4, this cast-in-place top Plate reserved opening can have enough to meet the need shaper, include die main body 1, handle 2 and lifting device;The die main body 1 is in inversion Prism-frustum-shaped, enclosed by four sides 1.1 and a bottom surface 1.2;Hole 3 is offered on the bottom surface of die main body 1 1.2 With bolt hole 4;Wherein, hole 3 is provided with 1.2 middle part of bottom surface, and bolt hole 4 is provided with the two sides at hole 3, the bottom of die main body 1 Aperture on portion's steel plate, the template fixation using nut and top plate to be poured is integral, is connected in a manner of nut, turnover easy to dismantle It uses;The handle 2 is connected to the opposite side of die main body 1, the taking-up for concreting molding rear mold;The promotion dress Set includes support 5, casing 6 and lift lever 7;The support 5 is connected horizontally on the top of die main body 1, close to location mid-shaft Place;Described sleeve pipe 6 is connected at 3 position of hole of the side of support 5, corresponding bottom surface 1.2;The vertical adjustable company of the lift lever 7 It connects in casing 6.
In the present embodiment, the horizontal section of the die main body 1 is in rectangle or square;The height of the die main body 1 Degree than top plate to be poured thickness greatly at least 100mm, such as pour top plate with a thickness of 100mm, the height of die main body 1 is 200mm;Die main body 1 is made into suitable for reading big, the small inverted prism-frustum-shaped of lower mouth using the sheet iron welding of 3mm thickness, so as to Reduce the frictional force of concrete and mold body, facilitates mold to take out after concrete formation.
In the present embodiment, the handle 2 is in inverted U-shaped, and is welded to connect in the opposite side of die main body 1;Wherein, every side 2 top of handle exceed the top margin of corresponding side side 1.1.
In the present embodiment, it includes horizontal sides and vertical edge that the lift lever 7 is T-shaped;Wherein, it is set on the vertical edge of lift lever 7 There is external screw thread.
In the present embodiment, the inner sidewall of described sleeve pipe 6 is equipped with the internal screw thread being adapted with external screw thread on lift lever 7;Institute The vertical edge for stating lift lever 7 is threaded in casing 6;When demoulding difficulty, lift lever 7 is rotated down, lift lever 7 is leaned on casing 6 Screw thread rotation moves up and down;The template surface of top plate to be poured is withstood in 7 bottom of lift lever, can be with by the jacking force of lift lever 7 Driven mold is integrally lifted up, power-assisted demoulding.
In the present embodiment, the shape at the hole 3 is rectangle or square, as facing for vertical axis transfer or material When reserved opening;The bolt hole 4 is opened up along the edge interval of bottom surface 1.2.
This casting top slab reserved opening can have enough to meet the need the construction method of shaper, including steps are as follows.
Step 1: unwrapping wire positions, the accurate dimension of reserved opening is determined according to the position of main shaft, and on roof plate template Draw the sideline of reserved opening.
Step 2: determining the position of the bolt to fixing mould on roof plate template: the mold for holding bolt hole 4 successfully is put It sets on roof plate template, at corresponding reserved opening edge positions, is accurately positioned the position of bolt on roof plate template.
Step 3: drilling: on roof plate template, the position of corresponding bolt hole 4 drills.
Step 4: binding roof steel bar.
Step 5: fixed shaper: matched bolt is penetrated bolt hole 4 above top plate, fixed shaper Position prevents from causing impact to shift on mold during concreting.
Step 6: pouring concrete roof, and conserve.
Step 7: removing shaper when the intensity of concrete roof reaches design strength, cleaning out, in case again It is secondary to be used in turn.
In the present embodiment, when the size of reserved opening is less than or equal to 300mm × 300mm, roof steel bar gets around hole to be provided Mouthful, it does not cut off;When the size of reserved opening is greater than 300mm × 300mm, when step 4 binds roof steel bar, increase additional Arrangement of reinforcement.
Above-described embodiment is not the exhaustion of specific embodiment, can also there is other embodiments, and above-described embodiment purpose exists In illustrating the present invention, the protection scope being not intended to limit the present invention, all applications from simple change of the present invention all fall within this In the protection scope of invention.

Claims (8)

1. a kind of casting top slab reserved opening can have enough to meet the need shaper, it is characterised in that: include die main body (1), handle (2) And lifting device;The die main body (1) is in inverted prism-frustum-shaped, by four sides (1.1) and bottom surface (1.2) enclosing At;Hole (3) and bolt hole (4) are offered on the bottom surface (1.2) of die main body (1);Wherein, hole (3) are provided with bottom surface (1.2) middle part, bolt hole (4) are provided with the two sides of hole (3);The handle (2) is connected to the opposite side of die main body (1), uses In the taking-up of concreting molding rear mold;The lifting device includes support (5), casing (6) and lift lever (7);Institute The top that support (5) is connected horizontally on die main body (1) is stated, at location mid-shaft;Described sleeve pipe (6) is connected to support (5) Side, corresponding bottom surface (1.2) hole (3) position at;The lift lever (7) is vertically adjustable to be connected in casing (6).
2. casting top slab reserved opening according to claim 1 can have enough to meet the need shaper, it is characterised in that: the mold master The horizontal section of body (1) is in rectangle or square;The height of the die main body (1) than top plate to be poured thickness greatly at least 100mm。
3. casting top slab reserved opening according to claim 1 can have enough to meet the need shaper, it is characterised in that: the handle (2) it is in inverted U-shaped, and is welded to connect in the opposite side of die main body (1);Wherein, handle (2) top of every side exceeds correspondence The top margin of side side (1.1).
4. casting top slab reserved opening according to claim 1 can have enough to meet the need shaper, it is characterised in that: the lift lever (7) T-shaped, it include horizontal sides and vertical edge;Wherein, the vertical edge of lift lever (7) is equipped with external screw thread.
5. casting top slab reserved opening according to claim 4 can have enough to meet the need shaper, it is characterised in that: described sleeve pipe (6) inner sidewall is equipped with the internal screw thread being adapted with external screw thread on lift lever (7);The vertical edge screw thread of the lift lever (7) connects It connects in casing (6).
6. casting top slab reserved opening according to claim 1 can have enough to meet the need shaper, it is characterised in that: the hole (3) shape is rectangle or square;The bolt hole (4) opens up along the edge interval of bottom surface (1.2).
7. the construction party that casting top slab reserved opening described in a kind of any one of claim 1-6 can have enough to meet the need shaper Method, which is characterized in that comprise the following steps that
Step 1: unwrapping wire positions, the accurate dimension of reserved opening is determined according to the position of main shaft, and draw on roof plate template The sideline of reserved opening;
Step 2: determining the position of the bolt to fixing mould on roof plate template: the mold for holding bolt hole (4) successfully is placed On roof plate template, at corresponding reserved opening edge positions, it is accurately positioned the position of bolt on roof plate template;
Step 3: drilling: on roof plate template, the position of corresponding bolt hole (4) drills;
Step 4: binding roof steel bar;
Step 5: fixed shaper: matched bolt being penetrated bolt hole (4) above top plate, the position of fixed shaper It sets, prevents from causing impact to shift on mold during concreting;
Step 6: pouring concrete roof, and conserve;
Step 7: removing shaper when the intensity of concrete roof reaches design strength, cleaning out, in case all again Turn to use.
8. the construction method that casting top slab reserved opening according to claim 7 can have enough to meet the need shaper, it is characterised in that:
When the size of reserved opening is less than or equal to 300mm × 300mm, roof steel bar gets around reserved opening, does not cut off;
When the size of reserved opening is greater than 300mm × 300mm, when step 4 binds roof steel bar, increase additional reinforcing bars.
CN201910015390.2A 2019-01-08 Shaping mold capable of realizing turnover of reserved hole of cast-in-situ roof and construction method of shaping mold Active CN109518960B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910015390.2A CN109518960B (en) 2019-01-08 Shaping mold capable of realizing turnover of reserved hole of cast-in-situ roof and construction method of shaping mold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910015390.2A CN109518960B (en) 2019-01-08 Shaping mold capable of realizing turnover of reserved hole of cast-in-situ roof and construction method of shaping mold

Publications (2)

Publication Number Publication Date
CN109518960A true CN109518960A (en) 2019-03-26
CN109518960B CN109518960B (en) 2024-05-10

Family

ID=

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110388052A (en) * 2019-06-17 2019-10-29 浙江省建工集团有限责任公司 The reserved construction hole erecting device of one kind and mold method
CN110397271A (en) * 2019-08-02 2019-11-01 中建四局安装工程有限公司 A kind of ferrule mold and application method for the installation of skyscraper vertical pipeline

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104047423A (en) * 2014-05-14 2014-09-17 中建七局第二建筑有限公司 Mold and construction method for precisely reserving hole in floorslab
CN203924713U (en) * 2014-06-06 2014-11-05 中国建筑第六工程局有限公司 The reservation device of hole on a kind of concrete floor
CN206144144U (en) * 2016-10-31 2017-05-03 中冶建工集团有限公司 Design mould is reserved in building surveying hole
CN207794611U (en) * 2017-12-27 2018-08-31 山东万鑫建设有限公司 Squeeze fixed horizontal reserved-hole die
EP3395521A1 (en) * 2017-04-24 2018-10-31 Carlow Precast Manufacturing A mould
CN109057326A (en) * 2018-08-16 2018-12-21 徽都建设有限公司 One kind pouring shear wall prefabricated doors and windows entrance construction method
CN209323975U (en) * 2019-01-08 2019-08-30 中国建筑第二工程局有限公司 A kind of casting top slab reserved opening can have enough to meet the need shaper

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104047423A (en) * 2014-05-14 2014-09-17 中建七局第二建筑有限公司 Mold and construction method for precisely reserving hole in floorslab
CN203924713U (en) * 2014-06-06 2014-11-05 中国建筑第六工程局有限公司 The reservation device of hole on a kind of concrete floor
CN206144144U (en) * 2016-10-31 2017-05-03 中冶建工集团有限公司 Design mould is reserved in building surveying hole
EP3395521A1 (en) * 2017-04-24 2018-10-31 Carlow Precast Manufacturing A mould
CN207794611U (en) * 2017-12-27 2018-08-31 山东万鑫建设有限公司 Squeeze fixed horizontal reserved-hole die
CN109057326A (en) * 2018-08-16 2018-12-21 徽都建设有限公司 One kind pouring shear wall prefabricated doors and windows entrance construction method
CN209323975U (en) * 2019-01-08 2019-08-30 中国建筑第二工程局有限公司 A kind of casting top slab reserved opening can have enough to meet the need shaper

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110388052A (en) * 2019-06-17 2019-10-29 浙江省建工集团有限责任公司 The reserved construction hole erecting device of one kind and mold method
CN110397271A (en) * 2019-08-02 2019-11-01 中建四局安装工程有限公司 A kind of ferrule mold and application method for the installation of skyscraper vertical pipeline

Similar Documents

Publication Publication Date Title
CN209633297U (en) A kind of mold of precast concrete wall panel
CN206667680U (en) A kind of residential construction gas flue structure
CN206233596U (en) Building block exterior wall constructional column concrete casting device
CN105888243B (en) The anti-flare device of building template
CN205822780U (en) Floor setting-out hole is reserved and blocks mould
CN209323975U (en) A kind of casting top slab reserved opening can have enough to meet the need shaper
CN213927071U (en) Simple and easy angle steel lintel strutting arrangement
CN109518960A (en) A kind of casting top slab reserved opening can have enough to meet the need shaper and its construction method
CN207376661U (en) A kind of plugging structure of poured band of outer wall of basement
CN109098456A (en) A kind of aluminum alloy pattern plate Transfer pipe molding machine and construction method
CN106481082B (en) A kind of improvement casting method of constructional column
CN109518960B (en) Shaping mold capable of realizing turnover of reserved hole of cast-in-situ roof and construction method of shaping mold
CN210369938U (en) A can have enough to meet need sleeve for pouring stake core
CN209353705U (en) What a kind of quick peace was torn open blocks up hole device to pull-type exterior wall
CN206448167U (en) The recyclable template of continuous beam with high-pier transverse prestress stretching notch closure
CN207686294U (en) Wall pours the undertaking Template Location bracing means with aluminum alloy pattern plate
CN212671212U (en) Improved concrete hopper
CN218522232U (en) Pipeline bracket root closing-up die device
CN206693618U (en) A kind of simple lintel cast-in-place mould
CN220666642U (en) High-strength concrete floor slab
CN206220057U (en) Open drain one-time-shaped mould
CN212866024U (en) Heating power trench cover plate device
CN216578433U (en) Concrete circular hole shaping die
CN210975886U (en) Subway station tunnel bottom plate chamfer template
CN220434224U (en) Aluminum alloy template material conveying opening shaping type die

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant