CN106481082B - A kind of improvement casting method of constructional column - Google Patents

A kind of improvement casting method of constructional column Download PDF

Info

Publication number
CN106481082B
CN106481082B CN201611020459.3A CN201611020459A CN106481082B CN 106481082 B CN106481082 B CN 106481082B CN 201611020459 A CN201611020459 A CN 201611020459A CN 106481082 B CN106481082 B CN 106481082B
Authority
CN
China
Prior art keywords
plank sheathing
hopper
plug
strip
charging spout
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201611020459.3A
Other languages
Chinese (zh)
Other versions
CN106481082A (en
Inventor
丁明忠
陈光瑜
姜泽候
徐宇光
宋琴
黄永华
郑磊
瞿士钦
邵宗谦
许扬威
常明亮
李海鸿
万永丽
张劲松
张丽萍
王振华
付小兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Construction Investment Sixth Construction Co Ltd
Yunnan Construction and Investment Holding Group Co Ltd
Original Assignee
Yunnan Construction Investment Sixth Construction Co Ltd
Yunnan Construction and Investment Holding Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan Construction Investment Sixth Construction Co Ltd, Yunnan Construction and Investment Holding Group Co Ltd filed Critical Yunnan Construction Investment Sixth Construction Co Ltd
Priority to CN201611020459.3A priority Critical patent/CN106481082B/en
Publication of CN106481082A publication Critical patent/CN106481082A/en
Application granted granted Critical
Publication of CN106481082B publication Critical patent/CN106481082B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • E04G21/025Buckets specially adapted for use with concrete

Abstract

A kind of improvement casting method of constructional column first makes plug-in strip and hopper;It is poured in constructional column and opens a feed opening above the plank sheathing of face, distinguish machining gap on the both sides suitable for reading of feed opening, bottom of slotting among feed opening is located at the vertical slot on concreting top closure face, processes a through-hole below vertical slot;Plug-in strip tool arm is inserted into vertical slot, knife plate is close to plank sheathing inner wall, fixes plug-in strip in two perforation of U-shaped bolt insertion tool arm;The charging spout discharge end of hopper is placed on plank sheathing feed opening, the vertical surface of two triangle steel tendons skeletons composition is abutted into plank sheathing outside wall surface, top-hung is hooked on the notch on template both sides, is inserted into stationary hopper in nut and through-hole with L shape bolt;From construction column space placing concrete of the charging spout into plank sheathing, until concrete does not enter back into;U-shaped bolt is removed, beats male contact handle from lower to upper, is turn 90 degrees until knife plate turns over;L shape bolt is removed, hopper is removed.The present invention conveniently, safely, economy, pouring quality it is good.

Description

A kind of improvement casting method of constructional column
Technical field
The invention belongs to architectural engineering constructional column pouring technique fields.
Background technique
In construction, constructional column concrete pour often occur exist vibrate leakiness, top closure appearance and The problems such as size, which is not achieved, wants code requirement, and pouring construction is difficult.Common some nonstandard ways in construction, such as in constructional column Face die plate opening is poured, worker's use scoops wooden dipper and pours concrete to open bottom, and finally mixing dry concrete with hand applies capital again.This There are following many defects for kind of method: 1. worker in pouring engineering, splash more by concrete, causes waste of material, civilization is applied Work cannot also ensure;2. capital concrete strength cannot be guaranteed;2. worker is time-consuming and laborious;3. when applying capital by hand, Applying the scale styling representation come out cannot meet the requirements, and influence impression quality;4. some workers follow the line of least resistance, or even can be broken toward column cap plug The sundries such as brick, broken concrete seriously affect the quality of constructional column;5. the dry concrete plug of mixing is not tight, coagulation is influenced The intensity of soil.For the deficiency that artificial hand applies, Ye You unit in charge of construction takes some ameliorative measures, such as in supporting wooden model, branch One pours chute out, and this method not only increases the labor intensity of carpenter, and wood shuttle slot is easily damaged, also inconvenient floor It carries, after demoulding, concreter must reject capital bulge, increase labor intensity, and waste material.There are also some work orders Using novel pumping Counter procedure, but for the first time, investment is big for position, requires height to carpenter's formwork reinforcement, high to the requirement of mixing concrete, and Machine is moved in inconvenient floor from great.
Summary of the invention
Present invention aims to solve the deficiencies of the prior art, and provides a kind of it is a kind of conveniently, safely, fast, economy, pouring quality Good constructional column improves casting method, to facilitate worker's pouring construction, guarantees construction quality and construction safety.
The purpose of the present invention is achieved through the following technical solutions:
A kind of improvement casting method of constructional column, the method is as follows:
A. pre-production one is plug-in strip and a hopper;The plug-in strip includes rectangle knife plate, and vertical welding is in knife plate bottom end Intermediate outer end is the riser formula tool arm of bevel edge, the oblique handle being welded on the bevel edge of tool arm outer end, is machined with two in tool arm inner end A perforation;The hopper include the trapezoidal wedged bottom charging spout gradually to close up towards discharge end, support two of hopper it is interconnected The vertical surface of triangle steel tendons skeleton, two triangle steel tendons skeletons composition is concordant with the discharge feed side of charging spout, and the two of vertical surface It is extended down on root reinforcing bar and exceeds charging groove height and the cross bar with the hook to turn up, in two triangle steel tendons skeleton bottom ends of connection Centre is welded with a nut;
B. it pours to be located on the plank sheathing of face above concreting top closure in constructional column and opens a feed opening, in feed opening Both sides suitable for reading process a notch respectively, open a vertical slot in the centre of feed opening, the slot bottom of vertical slot is located at concreting On top closure face, a through-hole is processed below vertical slot;
C. by the tool arm insertion vertical slot of plug-in strip, knife plate is close to plank sheathing inner wall, with two of U-shaped bolt insertion tool arm In perforation, plug-in strip is fixed;
D. the charging spout discharge end of hopper is placed on plank sheathing feed opening, two triangle steel tendons skeletons is formed Vertical surface is inserted into nut and through-hole in plank sheathing outside wall surface, the notch for hanging over template both sides at top, with L shape bolt In, fix hopper;
E. the construction column space placing concrete since charging spout into plank sheathing, be poured into concrete cannot again along When charging spout trickles, charging spout is filled in continuation, strikes shake, the concrete in charging spout is pushed away toward discharge port, until concrete is not It enters back into;
F. U-shaped bolt is removed, beats male contact handle from lower to upper, barrier gate is carried out, turn 90 degrees until knife plate turns over to horizontal position, Barrier gate finishes;L shape bolt is removed, hopper is removed;Plug-in strip is collected after dismantling plank sheathing.
The method of the present invention used tool is simple, easy to manufacture, easy to carry from heavy and light, low-cost, and operability is good It is good, it is reusable.Using the method for the present invention, constructional column pouring quality can be both ensured, can also reduce labor intensity of workers, Also material is saved, after pouring, easy demoulding, Forming Quality is preferable, and top end coagulation is constructed after the constructional column demoulding poured Native flat appearance, construction size meet the requirements.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of plug-in strip;
Fig. 2 is the right view of Fig. 1;
Fig. 3 is the structural schematic diagram of hopper;
Fig. 4 is the right view of Fig. 3;
Fig. 5 is construction schematic diagram;
The Section A-A schematic diagram (being free of clamp system) that Fig. 6 is Fig. 5.
Specific embodiment
A kind of improvement casting method of constructional column, pre-production one is plug-in strip and a hopper.As shown in Figure 1 and Figure 2, institute Stating plug-in strip includes rectangle knife plate 1, and outer end of the vertical welding among knife plate bottom end is the riser formula tool arm 2 of bevel edge, is welded in knife Oblique handle 3 on the bevel edge of arm outer end, in tool arm inner end, there are two perforation 4 for processing.Knife plate and tool arm all make of steel plate, and handle can It is manufactured with reinforcing bar or steel pipe.As shown in Figure 3, Figure 4, the hopper include the trapezoidal wedged bottom charging spout 5 gradually to close up towards discharge end, Two triangle steel tendons skeletons 6 interconnected of hopper are supported, the vertical surface and charging that two triangle steel tendons skeletons form The discharge feed side of slot is concordant, is extended down on two reinforcing bars of vertical surface and exceeds charging groove height and have the hook 7 to turn up, in connection two A nut 9 is welded among the cross bar 8 of a triangle steel tendons skeleton bottom end;Charging spout aluminium alloy plate or iron sheet plate bending and At.
Casting method is as shown in Figure 5, Figure 6, in the position of constructional column to be poured, will process between the flitch 15 on both sides Plank sheathing 10 fixed with clamp system 16, first constructional column pour on face plank sheathing 10 be located at concreting top closure A feed opening 11 is opened in top, processes a notch 12 respectively on the both sides suitable for reading of feed opening, opens one in the centre of feed opening and erects The slot bottom of slot 13, vertical slot is located on concreting top closure face, and a through-hole 14 is processed below vertical slot;Then by plug-in strip Tool arm 2 be inserted into vertical slot 13, knife plate 1 is close to 10 inner wall of plank sheathing, will in two of tool arm perforation 4 of U-shaped bolt insertion Plug-in strip is fixed;The charging spout discharge end of hopper is placed on plank sheathing feed opening 11 again, by two 6 groups of triangle steel tendons skeleton At vertical surface abut plank sheathing outside wall surface, the hook 7 at top hangs on the notch 12 on template both sides, is inserted into spiral shell with L shape bolt In mother 9 and through-hole 14, hopper is fixed, to prevent framework of steel reinforcement from knocking over upwards;Later since charging spout into plank sheathing Column space placing concrete is constructed, when being poured into concrete cannot trickle along charging spout again, charging spout is filled in continuation, is struck Shake, pushes away the concrete in charging spout toward discharge port, until concrete does not enter back into.After concrete setting, removes U-shaped and insert Pin beats male contact handle from lower to upper, carries out barrier gate, turn 90 degrees until knife plate turns over to horizontal position, barrier gate finishes;L shape is removed to insert Pin, removes hopper;Plug-in strip is collected after dismantling plank sheathing, is utilized again.Hand-rail type lifting device or light can also be used in male contact handle Type hydraulic jacking device pushes.

Claims (1)

1. a kind of improvement casting method of constructional column, which is characterized in that method is as follows:
A. pre-production one is plug-in strip and a hopper;The plug-in strip includes rectangle knife plate (1), and vertical welding is in knife plate bottom end Between outer end be the riser formula tool arm (2) of bevel edge, the oblique handle (3) that is welded on the bevel edge of tool arm outer end, processed in tool arm inner end There are two perforate (4);The hopper includes the trapezoidal wedged bottom charging spout (5) gradually closed up towards discharge end, supports the two of charging spout A triangle steel tendons skeleton (6) interconnected, the discharge feed side of vertical surface and charging spout that two triangle steel tendons skeletons form Concordantly, it is extended down on two reinforcing bars of vertical surface and exceeds charging groove height and have the hook (7) to turn up, connecting two triangles A nut (9) is welded among the cross bar (8) of framework of steel reinforcement bottom end;
B. it pours to be located on face plank sheathing (10) above concreting top closure in constructional column and opens a feed opening (11), under The both sides suitable for reading of material mouth process a notch (12) respectively, open a vertical slot (13), the slot bottom position of vertical slot in the centre of feed opening In on concreting top closure face, a through-hole (14) is processed below vertical slot;
C. the tool arm of plug-in strip (2) are inserted into vertical slot (13), knife plate (1) is close to plank sheathing (10) inner wall, is inserted into U-shaped bolt In two perforation (4) of tool arm, plug-in strip is fixed;
D. the charging spout discharge end of hopper is placed on plank sheathing feed opening (11), by two triangle steel tendons skeleton (6) groups At vertical surface abut plank sheathing outside wall surface, the hook (7) at top hangs on the notch (12) on template both sides, is inserted with L shape bolt Enter in nut (9) and through-hole (14), fixes hopper;
E. the construction column space placing concrete since charging spout into plank sheathing, being poured into concrete cannot be again along charging Slot trickle when, continuation charging spout is filled, strike shake, the concrete in charging spout pushed away toward discharge port, up to concrete no longer into Enter;
F. U-shaped bolt is removed, beats male contact handle from lower to upper, barrier gate is carried out, turn 90 degrees until knife plate turns over to horizontal position, barrier gate It finishes;L shape bolt is removed, hopper is removed;Plug-in strip is collected after dismantling plank sheathing.
CN201611020459.3A 2016-11-17 2016-11-17 A kind of improvement casting method of constructional column Active CN106481082B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611020459.3A CN106481082B (en) 2016-11-17 2016-11-17 A kind of improvement casting method of constructional column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611020459.3A CN106481082B (en) 2016-11-17 2016-11-17 A kind of improvement casting method of constructional column

Publications (2)

Publication Number Publication Date
CN106481082A CN106481082A (en) 2017-03-08
CN106481082B true CN106481082B (en) 2019-01-18

Family

ID=58272763

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611020459.3A Active CN106481082B (en) 2016-11-17 2016-11-17 A kind of improvement casting method of constructional column

Country Status (1)

Country Link
CN (1) CN106481082B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109113338B (en) * 2018-09-13 2024-03-19 中铁十六局集团城市建设发展有限公司 Tool type die carrier for integrally pouring top of constructional column
CN114382290A (en) * 2022-01-13 2022-04-22 中国五冶集团有限公司 Constructional column guide pipe concrete pouring method

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11172918A (en) * 1997-12-08 1999-06-29 Kumagai Gumi Co Ltd Wall body construction method and attachment for connection of ready-mixed concrete injection hose
US6076710A (en) * 1998-11-02 2000-06-20 Yates-Funderburk Concrete Finishing, Inc. Concrete placement apparatus
CN201581634U (en) * 2009-12-10 2010-09-15 山西四建集团有限公司 Tool for casting concrete for template used in supporting constructional column of filler wall
CN102561681B (en) * 2012-03-15 2013-12-11 陕西建工集团总公司 Casting molding template and casting molding process for constructional columns of infilled walls
CN203129606U (en) * 2013-03-20 2013-08-14 广州市恒域建筑工程有限公司 Masonry infill wall constructional column concrete pouring device
CN205400043U (en) * 2016-03-04 2016-07-27 中国建筑第五工程局有限公司 Constructional column is funnel combination tool for concreting

Also Published As

Publication number Publication date
CN106481082A (en) 2017-03-08

Similar Documents

Publication Publication Date Title
CN206903215U (en) Girder with rolled steel section en cased in concrete is without scaffold formwork
CN203856202U (en) Simple pullable sizing device of reserved holes
CN106481082B (en) A kind of improvement casting method of constructional column
CN203487779U (en) Tool type stock mould for masonry constructional column concrete pouring
CN201221201Y (en) Aluminum alloy early-dismounting system
CN209163438U (en) A kind of drop plate tool formula hoisting die construction structure
CN103590599A (en) Self-compaction mode locking device and using method
CN211114798U (en) Kitchen and bathroom board descending and shaping die
CN205822780U (en) Floor setting-out hole is reserved and blocks mould
CN207469596U (en) A kind of beam column outer rim is exempted to tear concrete mold open
CN109098456A (en) A kind of aluminum alloy pattern plate Transfer pipe molding machine and construction method
CN208430643U (en) A kind of wall hole plugging device
CN206233573U (en) A kind of beam die plate reinforcing device
CN209179506U (en) It is portable to face side concreting tool retaining device
CN214163393U (en) Die device for rapidly preparing prefabricated inclined-building blocks of roof bricks
CN208907257U (en) A kind of cast-in-situ floor sealing hole tool
CN208105890U (en) A kind of concrete works wallboard pours hopper
CN208650519U (en) The flooring de-molding device of concrete surface is pried away from for internal corner formwork
CN207727997U (en) Concrete floor slab placement construction frame body platform structure for building construction
CN208981798U (en) A kind of aluminum alloy pattern plate Transfer pipe molding machine
CN206448167U (en) The recyclable template of continuous beam with high-pier transverse prestress stretching notch closure
CN205907615U (en) Underwater foundation is template mounting structure for reinforcing construction
CN208456117U (en) A kind of post-cast strip overhanging end independent support device
CN207812999U (en) Digital alloy steel framework plastic formwork
CN207392752U (en) For preventing the constructing device of grout leakage of formwork root

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant