CN201581634U - Tool for casting concrete for template used in supporting constructional column of filler wall - Google Patents
Tool for casting concrete for template used in supporting constructional column of filler wall Download PDFInfo
- Publication number
- CN201581634U CN201581634U CN 200920255148 CN200920255148U CN201581634U CN 201581634 U CN201581634 U CN 201581634U CN 200920255148 CN200920255148 CN 200920255148 CN 200920255148 U CN200920255148 U CN 200920255148U CN 201581634 U CN201581634 U CN 201581634U
- Authority
- CN
- China
- Prior art keywords
- constructional column
- tool
- template
- construction
- filler wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The utility model relates to a construction tool, in particular to a tool for casting concrete for template used in supporting a constructional column of a filler wall which solves the problems of poor quality of constructional column of filler wall caused by simple structure of tool in the prior art for the construction of the constructional column of the filler wall. The structure of the tool for casting concrete for template used in supporting the constructional column of the filler wall includes four pieces of butted constructional column templates, an L-shaped column hoop provided with a lock catch, and a hopper; a vertical square timber plank and a transverse square timber plank are arranged outside the constructional column templates; the transverse square timber plank is connected and fixed with the L-shaped column hoop; the hopper is hung at the upper end of the vertical square timber plank; and the side of the hopper near the template is provided with a knife switch. The tool for casting concrete for template used in supporting the constructional column of the filler wall has the advantages of simple equipment, easy operation of technique, lower construction cost, quick construction speed, simple construction, low cost and low consumption of construction materials.
Description
Technical field
The utility model relates to a kind of building operations instrument, is specially a kind of infilled wall constructional column and installs with template concreting instrument.
Background technology
Traditional infilled wall constructional column construction technology is simple, and the tool construction of use is simple, and is single.Cause the capital concrete to build mass defects such as leakiness, anti seismic efficiency weakness and presentation quality are general easily, and efficiency is also lower.
Summary of the invention
The utility model is simple in order to solve the tool construction that exists in the existing infilled wall constructional column construction technology, causes problems such as the infilled wall constructional column is of poor quality and provides a kind of infilled wall constructional column to install with template concreting instrument.
The utility model is realized by following technical scheme, a kind of infilled wall constructional column installs with template concreting instrument, structure comprise four butt joints the constructional column template, have L shaped tie, the funnel of snap close, it is perpendicular stupefied stupefied with lumps of wood horizontal stroke that the constructional column template is provided with the lumps of wood outward, lumps of wood horizontal stroke is stupefied to be connected and fixed by L shaped tie, articulate funnel in the perpendicular stupefied upper end of the lumps of wood, the side that funnel is pressed close to template is provided with plug-in strip.
The infilled wall constructional column formwork erection described in the utility model and the construction tool of concreting, be characterized in that the constructional column template adopts " L shaped simple and easy band iron tie " to reach the design of " capital is irritated the concrete mouth and cooperated gate with funnel ", bigger raising efficiency, finally eliminate infilled wall structure capital concrete and built uncompacted mass defect, improved anti seismic efficiency and presentation quality is good.Its feature is that construction equipment is simple, and technology is easy to operate, and construction cost is lower, and speed of application is fast, and easy construction, cost are honest and clean, and the constructional materials consumption is low.
Description of drawings
Fig. 1 is a structural representation of the present utility model
Fig. 2 is the right view of Fig. 1
Fig. 3 is the vertical view (not containing floor 4) of Fig. 1
Among the figure: the 1-snap close, 2-L shape tie, 3-constructional column template, the 4-floor, the 5-plug-in strip,
The 6-funnel, 7-lumps of wood horizontal stroke is stupefied, and the 8-lumps of wood is perpendicular stupefied
The specific embodiment
Anticipate as shown in the figure, a kind of infilled wall constructional column installs with template concreting instrument, comprise the constructional column template 3 of four butt joints, the L shaped tie 2 that has snap close 1, funnel 6, the constructional column template 3 outer lumps of wood perpendicular stupefied 8 and the lumps of wood horizontal stupefied 7 of being provided with, the lumps of wood horizontal stupefied 7 is connected and fixed by L shaped tie 2, articulate funnel 6 in perpendicular stupefied 8 upper ends of the lumps of wood, the side that funnel 6 is pressed close to template is provided with plug-in strip 5.
Use material configuration such as bamboo offset plate, the lumps of wood to become standard form according to designing requirement, adopt band iron to make L shaped simple and easy tie and cooperate snap close to be reinforced, the constructional column top is adopted funnel filling concrete to cooperate the iron sheet lock to seal and is guaranteed the concrete pouring quality.Technological process comprises: join mould according to drawing constructional column form, mould is checked and accepted, the brushing interleaving agent, and the constructional column unwrapping wire, column mould, reinforcing, correction, examination are built concrete with funnel, and the iron sheet lock seals, collects clout, unloads funnel, form removal, mold cleaning.
The construction technology main points: 1 according to constructional column figure paper size batching, and the lumps of wood keel that every side template adopts the bamboo offset plate to add two 50 * 100 are made standard form system (wide and the stickfast of bamboo offset plate of the lumps of wood 100).The outer lumps of wood of 2 posts, two side templates is perpendicular stupefiedly will to expose template 1cm, just in time blocks outboard template.3 outboard templates leave for 300 times at capital and irritate the concrete mouth, the perpendicular stupefied 1cm of exposing place draws gate slot one with a chainsaw along root at the lumps of wood of two side templates, groove depth 1.5cm, (distance is hour at the bottom of the floor as capital in order to irritate under the concrete mouth for flute length, the both sides lumps of wood is perpendicular stupefiedly will to expose template 4cm, one side is drawn the 50 thick lumps of wood logical sluice gate groove with a chainsaw along root, and opposite side still is groove depth 1.5cm, and flute length is irritates under the concrete mouth.) 3 reinforce and to make L shaped tie with the wide band iron of the thick 20mm of 4mm, long by 800, turn 100, pound flat dotting punch with one thick on indented bars of the long 16mm of 100mm and make snap close, the thick 6mm of eye, a long 24mm, the other end bow is so that tighten the lumps of wood.4 electricity consumptions are drilled in jewel hole 22mm on the infilled wall, and in order to by the band iron hoop, both sides are made horizontal stupefied of the short lumps of wood, and one of L shaped tie catches on the lumps of wood, and one fastens the lumps of wood with snap close.Outside way is identical substantially with it, and it is stupefied also to do horizontal stroke with a lumps of wood, and one of L shaped tie catches on hoop through walls, one fastens the lumps of wood with snap close, thereby forms easy tie reinforcement system, and tie spacing 600-800 together, foot one track pitch ground 200, topmost are stayed together and are irritated under the concrete mouth.
Claims (1)
1. an infilled wall constructional column installs with template concreting instrument, it is characterized in that: structure comprises the constructional column template (3) of four butt joints, the L shaped tie (2) that has snap close (1), funnel (6), the outer lumps of wood perpendicular stupefied (8) and the lumps of wood horizontal stroke stupefied (7) of being provided with of constructional column template (3), lumps of wood horizontal stroke stupefied (7) is connected and fixed by L shaped tie (2), articulate funnel (6) in the lumps of wood perpendicular stupefied (8) upper end, the side that funnel (6) is pressed close to template is provided with plug-in strip (5).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200920255148 CN201581634U (en) | 2009-12-10 | 2009-12-10 | Tool for casting concrete for template used in supporting constructional column of filler wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200920255148 CN201581634U (en) | 2009-12-10 | 2009-12-10 | Tool for casting concrete for template used in supporting constructional column of filler wall |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201581634U true CN201581634U (en) | 2010-09-15 |
Family
ID=42723632
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 200920255148 Expired - Fee Related CN201581634U (en) | 2009-12-10 | 2009-12-10 | Tool for casting concrete for template used in supporting constructional column of filler wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201581634U (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102383598A (en) * | 2011-09-23 | 2012-03-21 | 中国十七冶集团有限公司 | Method for section construction of building project constructional column |
CN102561681A (en) * | 2012-03-15 | 2012-07-11 | 陕西建工集团总公司 | Casting molding template and casting molding process for constructional columns of infilled walls |
CN103255921A (en) * | 2013-05-07 | 2013-08-21 | 中建八局第一建设有限公司青岛分公司 | Top pouring method for concrete construction columns |
CN103643798A (en) * | 2013-12-09 | 2014-03-19 | 广州市第一建筑工程有限公司 | Pouring device used for constructional column top and large- section beam column closed opening |
CN104533079A (en) * | 2015-01-17 | 2015-04-22 | 新八建设集团有限公司 | Annular hoop for fixing concrete square column template with quick assembly-disassembly and without opposite pulling rod |
CN105971272A (en) * | 2016-06-23 | 2016-09-28 | 杭州江润科技有限公司 | Fabricated type reinforced concrete constructional column adopting aluminum templates and block filling wall and construction method |
CN106481082A (en) * | 2016-11-17 | 2017-03-08 | 云南省建设投资控股集团有限公司 | A kind of improvement casting method of constructional column |
CN108643569A (en) * | 2018-05-17 | 2018-10-12 | 福建省惠东建筑工程有限公司 | A kind of Constructional Col-umn Construction equipment and its construction method |
CN109208901A (en) * | 2017-07-05 | 2019-01-15 | 五冶集团上海有限公司 | A kind of funneling formwork erection method of constructional column concreting feed inlet |
-
2009
- 2009-12-10 CN CN 200920255148 patent/CN201581634U/en not_active Expired - Fee Related
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102383598A (en) * | 2011-09-23 | 2012-03-21 | 中国十七冶集团有限公司 | Method for section construction of building project constructional column |
CN102561681A (en) * | 2012-03-15 | 2012-07-11 | 陕西建工集团总公司 | Casting molding template and casting molding process for constructional columns of infilled walls |
CN102561681B (en) * | 2012-03-15 | 2013-12-11 | 陕西建工集团总公司 | Casting molding template and casting molding process for constructional columns of infilled walls |
CN103255921A (en) * | 2013-05-07 | 2013-08-21 | 中建八局第一建设有限公司青岛分公司 | Top pouring method for concrete construction columns |
CN103643798A (en) * | 2013-12-09 | 2014-03-19 | 广州市第一建筑工程有限公司 | Pouring device used for constructional column top and large- section beam column closed opening |
CN104533079A (en) * | 2015-01-17 | 2015-04-22 | 新八建设集团有限公司 | Annular hoop for fixing concrete square column template with quick assembly-disassembly and without opposite pulling rod |
CN105971272A (en) * | 2016-06-23 | 2016-09-28 | 杭州江润科技有限公司 | Fabricated type reinforced concrete constructional column adopting aluminum templates and block filling wall and construction method |
CN106481082A (en) * | 2016-11-17 | 2017-03-08 | 云南省建设投资控股集团有限公司 | A kind of improvement casting method of constructional column |
CN109208901A (en) * | 2017-07-05 | 2019-01-15 | 五冶集团上海有限公司 | A kind of funneling formwork erection method of constructional column concreting feed inlet |
CN108643569A (en) * | 2018-05-17 | 2018-10-12 | 福建省惠东建筑工程有限公司 | A kind of Constructional Col-umn Construction equipment and its construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201581634U (en) | Tool for casting concrete for template used in supporting constructional column of filler wall | |
CN101041980B (en) | Lightweight plaster wall and integral pouring procedure thereof | |
CN209207732U (en) | Precast concrete overlaps board mold | |
CN207616844U (en) | Foundation platform precast concrete side form and molding machine | |
CN110761441A (en) | Construction method of prefabricated serrated racking concrete module of constructional column | |
CN206706844U (en) | A kind of alter-pouring strips mould plate installs construction | |
CN208343121U (en) | Prefabricated assembled steel structure concrete wallboard mould | |
CN202644992U (en) | Movable die for reserving hole in box body or wellhead for building | |
CN205712565U (en) | A kind of prefabricated two-sided wall | |
CN208792764U (en) | A kind of stock mould for concrete-constituted pile | |
CN201826253U (en) | Bridge bottom board filling device | |
CN208347063U (en) | The prefabricated double board wall units of one kind, shear-wall element and assembly concrete shear wall | |
CN104453235B (en) | Current conversion station fire wall construction technology | |
CN201176551Y (en) | Precast slab for roads | |
CN207469596U (en) | A kind of beam column outer rim is exempted to tear concrete mold open | |
CN206319404U (en) | A kind of building precast exterior sheathing | |
CN201649315U (en) | Installing structure of building exhaust pipe | |
CN202850488U (en) | Totally-enclosed-type stair template | |
CN204163232U (en) | Double layer hollow reinforce concrete wall | |
CN209723299U (en) | A kind of secondary structure constructional column exempts from erecting device | |
CN208563755U (en) | A kind of precast hollow constructional column for wall connecting | |
CN201714085U (en) | Shear wall door opening side molding plate reinforcing device | |
CN201915635U (en) | Form erecting device free of bar planting for brickwork construction | |
CN206941628U (en) | A kind of construction site enclosing prefabricated foundation | |
CN212153437U (en) | Steel bar connection structure for large-volume concrete bearing platform post-cast strip construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20100915 Termination date: 20171210 |