CN109505255A - 无现浇段大跨度连续刚构梁带支座转体施工方法 - Google Patents
无现浇段大跨度连续刚构梁带支座转体施工方法 Download PDFInfo
- Publication number
- CN109505255A CN109505255A CN201811579182.7A CN201811579182A CN109505255A CN 109505255 A CN109505255 A CN 109505255A CN 201811579182 A CN201811579182 A CN 201811579182A CN 109505255 A CN109505255 A CN 109505255A
- Authority
- CN
- China
- Prior art keywords
- construction
- cast
- bent cap
- situ segment
- segment
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
- E01D21/08—Methods or apparatus specially adapted for erecting or assembling bridges by rotational movement of the bridge or bridge sections
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明属于跨线大型桥梁施工技术领域,为了解决现有设置边跨现浇和合拢段对营业线干扰大、施工风险高等问题,提出一种无现浇段大跨度连续刚构梁带支座转体施工方法。跨线桥梁采用平行线路方向悬臂法或支架现浇法浇筑梁体,转动到位的施工方法,该发明型取消常规转体设置边跨现浇段和合拢段,避免了线路上方或邻近既有线施工风险大的问题,梁体转动前现实整梁体带支座浇筑,边墩设置高低台时,高承台等转体到位后进行浇筑施工,低承台在转体施工前浇筑完成,但支座垫石需转动到位后再进行浇筑施工,该施工方法克服了既有线上方或邻近既有线施工等问题,保证了营业线路的运行安全,降低了施工风险,保证了施工安全,提高施工效率。
Description
技术领域
本发明属于跨线桥梁施工的技术领域,具体涉及一种无现浇段大跨度连续刚构梁带支座转体施工方法。
背景技术
现今跨越既有线施工多采用悬臂挂篮施工,常规转体施工线路上方合拢等方法施工,给既有线路运行带来极大风险,且现浇段采用支架施工,临近既有线路,施工风险大、施工难度大,施工工效低下等问题,如何保证跨线桥梁的快速高效的施工,降低工程施工风险。
发明内容
本发明型为了解决跨线桥梁施工时合拢段及边跨现浇段及边跨合拢段,对既有线影响及安全风险高的问题,提出一种无现浇段大跨度连续刚构梁带支座转体施工方法。
本发明采用如下技术方案:
一种无现浇段大跨度连续刚构梁带支座转体施工方法,其特征在于,在边跨现浇段和合拢段浇筑完成后,施工过渡墩时,先将过渡墩施工到低盖梁处,然后将边跨现浇段和合拢段构成的梁体转动到过渡墩位置后,再施工高盖梁和支座垫石,最后将边跨现浇段底部的预埋支座与支座垫石连接,实现大跨度连续钢构梁的安装施工。
高盖梁和支座垫石安装于低盖梁上方,支座垫石位于高盖梁内侧且高度低于高盖梁。
所述高盖梁截面积为低盖梁截面积的一半。
本发明针对的是跨线桥梁,现有跨线桥梁采用平行线路方向悬臂法或支架现浇法浇筑梁体,转动到位的施工方法,本发明取消常规转体设置边跨现浇段和合拢段,避免了线路上方或邻近既有线施工风险大的问题,梁体转动前现实整梁体带支座浇筑,边墩设置高低台时,高承台等转体到位后进行浇筑施工,低承台在转体施工前浇筑完成,但支座垫石需转动到位后再进行浇筑施工,该施工方法克服了既有线上方或邻近既有线施工等问题,保证了营业线路的运行安全,降低了施工风险,保证了施工安全,提高施工效率。
附图说明
图1为带支座转体梁体纵断面布置图;
图2为过渡墩盖梁布置图;
图3为转体成桥纵断面图;
图中:1-1预埋支座、1-2边跨现浇段、1-3合拢段、2-1高盖梁、2-2低盖梁、2-3支座垫石。
具体实施方式
结合附图,对本发明的具体实施方式作进一步说明:
如图1、2、3所示带支座转体的无现浇段大跨度连续刚构梁,包括由边跨现浇段1-2和若干合拢段1-3浇筑构成的梁体,以及过渡支撑梁体的边墩,边跨现浇段1-2底部浇筑有预埋支座1-1,边墩顶部设有高盖梁2-1、低盖梁2-2和支座垫石2-3,高盖梁2-1和支座垫石2-3安装于低盖梁2-2上方,支座垫石2-3位于高盖梁2-1内侧且高度低于高盖梁2-1,预埋支座1-1支撑安装于支座垫石2-3上,边跨现浇段1-2限位安装于高盖梁2-1内侧。
本发明的施工原理是在转提前改变常规施工工艺,将常规施工工艺边跨现浇段、常规施工工艺合拢段两个阶段梁一次浇筑完成,并且将预埋支座在浇筑时提前预埋;过渡墩施工时,先施工到低盖梁处,高盖梁及低盖梁后浇筑,支座垫石先不施工,等梁体转动到位后再浇筑施工支座垫石,随后施工高盖梁。
本发明是针对单墩双翼大跨度跨越既有线桥梁,提出的无现浇段大跨度连续刚构梁带支座转体施工方法及其施工方法,取消了常规转体设置边跨现浇段和合拢段,避免了线路上方或邻近既有线施工风险大的问题,梁体转动前先施整梁体带支座浇筑,边墩设置高低台时,高承台等转体到位后进行浇筑施工,低承台在转体施工前浇筑完成,但支座垫石需转动到位后再进行浇筑施工,该施工方法克服了既有线上方或邻近既有线施工等问题,保证了营业线路的运行安全,降低了施工风险,保证了施工安全,提高施工效率。
Claims (3)
1.一种无现浇段大跨度连续刚构梁带支座转体施工方法,其特征在于,在边跨现浇段(1-2)和合拢段(1-3)浇筑完成后,施工过渡墩时,先将过渡墩施工到低盖梁(2-2)处,然后将边跨现浇段(1-2)和合拢段(1-3)构成的梁体转动到过渡墩位置后,再施工高盖梁(2-1)和支座垫石(2-3),最后将边跨现浇段(1-2)底部的预埋支座(1-1)与支座垫石(2-3)连接,实现大跨度连续钢构梁的安装施工。
2.根据权利要求1所述的无现浇段大跨度连续刚构梁带支座转体施工方法,其特征在于,高盖梁(2-1)和支座垫石(2-3)安装于低盖梁(2-2)上方,支座垫石(2-3)位于高盖梁(2-1)内侧且高度低于高盖梁(2-1)。
3.根据权利要求2所述的无现浇段大跨度连续刚构梁带支座转体施工方法,其特征在于,所述高盖梁(2-1)截面积为低盖梁(2-2)截面积的一半。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811579182.7A CN109505255A (zh) | 2018-12-24 | 2018-12-24 | 无现浇段大跨度连续刚构梁带支座转体施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811579182.7A CN109505255A (zh) | 2018-12-24 | 2018-12-24 | 无现浇段大跨度连续刚构梁带支座转体施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109505255A true CN109505255A (zh) | 2019-03-22 |
Family
ID=65754282
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811579182.7A Pending CN109505255A (zh) | 2018-12-24 | 2018-12-24 | 无现浇段大跨度连续刚构梁带支座转体施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109505255A (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110629675A (zh) * | 2018-08-29 | 2019-12-31 | 中铁三局集团有限公司 | 连续梁支架现浇墩顶转体与悬臂浇筑组合施工方法 |
CN115142357A (zh) * | 2022-07-18 | 2022-10-04 | 中铁工程设计咨询集团有限公司 | 一种桥梁转体结构及其施工方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102116011A (zh) * | 2011-01-07 | 2011-07-06 | 中铁四局集团第二工程有限公司 | 跨越铁路营业线钢桁梁桥无平衡重平转施工方法 |
CN103306207A (zh) * | 2013-06-18 | 2013-09-18 | 中铁三局集团有限公司 | 一种控制预应力后张箱梁支座板空腹声的方法 |
CN103437299A (zh) * | 2013-08-26 | 2013-12-11 | 中铁十一局集团第三工程有限公司 | 大跨t构单墩一次转体的施工方法 |
CN205188803U (zh) * | 2015-11-07 | 2016-04-27 | 西安公路研究院 | 一种钢板球冠聚合物砂浆结构支座 |
CN106758831A (zh) * | 2016-12-14 | 2017-05-31 | 中铁十九局集团第二工程有限公司 | 跨铁路桥转体连续梁施工方法 |
-
2018
- 2018-12-24 CN CN201811579182.7A patent/CN109505255A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102116011A (zh) * | 2011-01-07 | 2011-07-06 | 中铁四局集团第二工程有限公司 | 跨越铁路营业线钢桁梁桥无平衡重平转施工方法 |
CN103306207A (zh) * | 2013-06-18 | 2013-09-18 | 中铁三局集团有限公司 | 一种控制预应力后张箱梁支座板空腹声的方法 |
CN103437299A (zh) * | 2013-08-26 | 2013-12-11 | 中铁十一局集团第三工程有限公司 | 大跨t构单墩一次转体的施工方法 |
CN205188803U (zh) * | 2015-11-07 | 2016-04-27 | 西安公路研究院 | 一种钢板球冠聚合物砂浆结构支座 |
CN106758831A (zh) * | 2016-12-14 | 2017-05-31 | 中铁十九局集团第二工程有限公司 | 跨铁路桥转体连续梁施工方法 |
Non-Patent Citations (1)
Title |
---|
宁继康;: "2×116m大跨连续T构转体施工技术", 石家庄铁路职业技术学院学报, no. 01 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110629675A (zh) * | 2018-08-29 | 2019-12-31 | 中铁三局集团有限公司 | 连续梁支架现浇墩顶转体与悬臂浇筑组合施工方法 |
CN115142357A (zh) * | 2022-07-18 | 2022-10-04 | 中铁工程设计咨询集团有限公司 | 一种桥梁转体结构及其施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206553961U (zh) | 矮塔型斜拉桥轻型宽体复合式挂篮 | |
CN106592406A (zh) | 下承式系杆拱桥及其施工方法 | |
CN104328745B (zh) | 一种小角度上跨高铁小跨桥梁的转体装置及其施工方法 | |
CN101736692A (zh) | 铁路客运专线跨既有铁路现浇箱梁支架施工技术 | |
CN102102343A (zh) | 一种对连续箱梁弯桥纠扭的方法 | |
CN109505255A (zh) | 无现浇段大跨度连续刚构梁带支座转体施工方法 | |
CN202131563U (zh) | 钢横梁一次吊装就位组合门式桥墩 | |
CN107780337B (zh) | 现浇平衡转体门型墩及其施工方法 | |
CN104452574B (zh) | 一种匝道桥结构及其施工方法 | |
CN208965416U (zh) | 一种大跨度框构桥顶进过程既有铁路的防护结构 | |
CN105714681A (zh) | 一种悬挂式单轨交通刚构体系的实现方法和施工工艺 | |
CN209555753U (zh) | 一种拱上墩整体式防落梁构造 | |
CN104612031B (zh) | 一种钢筋混凝土连续刚构拱桥及施工方法 | |
CN206828906U (zh) | 一种用于地铁深基坑的临时路面铺盖结构 | |
CN103882802B (zh) | 一种公路跨越铁路的桥梁防护结构 | |
CN105484163A (zh) | 一种斜拉桥辅助墩墩顶节段先梁后墩施工方法 | |
CN209368692U (zh) | 带支座转体的无现浇段大跨度连续刚构梁 | |
CN104499436B (zh) | 转体桥活载抗扭平衡墩 | |
Manterola et al. | Bridge over the Cádiz bay, Spain | |
CN217300589U (zh) | 地铁盾构隧道下穿运营铁路框架桥的加固体系 | |
CN107974930A (zh) | 节段拼装平衡转体门型墩及其施工方法 | |
CN102787554B (zh) | 顺桥向抗震桥台结构 | |
CN206408510U (zh) | 下承式系杆拱桥 | |
CN205669166U (zh) | 一种采用转体施工的斜拉桥主梁断面结构 | |
CN107245960A (zh) | 一种用于城市高架桥更新的分段式施工系统及方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |