CN109441734A - 导管架吊运一体式施工工艺 - Google Patents
导管架吊运一体式施工工艺 Download PDFInfo
- Publication number
- CN109441734A CN109441734A CN201811085578.6A CN201811085578A CN109441734A CN 109441734 A CN109441734 A CN 109441734A CN 201811085578 A CN201811085578 A CN 201811085578A CN 109441734 A CN109441734 A CN 109441734A
- Authority
- CN
- China
- Prior art keywords
- jacket
- integral type
- track
- workboat
- loop wheel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D13/00—Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
- F03D13/40—Arrangements or methods specially adapted for transporting wind motor components
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B35/00—Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/72—Wind turbines with rotation axis in wind direction
Landscapes
- Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Sustainable Development (AREA)
- Sustainable Energy (AREA)
- General Engineering & Computer Science (AREA)
- Ocean & Marine Engineering (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
本发明一种导管架吊运一体式施工工艺,在导管架的桩管施工过程中,导管架吊运一体式施工船前往码头,利用船体(1)上的吊机(2)将码头上的导管架起吊至船尾的轨道(3)上,然后将导管架向前滑移;此时吊机(2)起吊下一导管架至轨道(3)上,直至轨道(3)上布满导管架;导管架吊运一体式施工船带着导管架航行至桩管施工完成处就位,吊机(2)起吊最靠近船尾端的导管架,使得其下方安装至桩管上,然后导管架吊运一体式施工船航行至下一桩管完成处下放导管架,直至轨道(3)上的导管架全部安装完毕后,导管架吊运一体式施工船返航装载下一批导管架。本发明一种导管架吊运一体式施工工艺,施工方便且施工成本低廉。
Description
技术领域
本发明涉及一种导管架吊运一体式施工工艺,尤其是涉及一种对导管架能够同时进行装载和起吊的施工工艺。
背景技术
目前,海上风电的安装过程中,需要先行安装导管架作为风电主机的安装及作业平台;在导管架的安装过程中,常规需要两条船,一条为拖船,装载导管架,另一条为起吊船,对导管架进行起吊和安装牵引;两者之间需要在海上协同作业,如此一来不但增加了施工的难度,需要有经验的作业人员操作两条施工船进行同步协同作业,对船体的定位和调度要求较高;二来增加了作业成本,需要两条施工船待命作业,无误极大的增加了施工企业的投入成本,因此,亟需一种施工方便且施工成本低廉的作业方式以解决上述问题。
发明内容
本发明的目的在于克服上述不足,提供一种施工方便且施工成本低廉的导管架吊运一体式施工工艺。
本发明的目的是这样实现的:
一种导管架吊运一体式施工工艺,所述工艺基于一种导管架吊运一体式施工船,所述施工船包含有船体,所述船体的甲板上平行设置有两条轨道,两条轨道延伸至船体的船尾;导管架的管脚安装于滑块上,且滑块滑动设置于轨道;所述船体上设置有吊机,吊机辅助臂架位于轨道的外侧,吊机的吊索经吊机辅助臂架后钩住导管架的顶部起吊环;
在导管架的桩管施工过程中,导管架吊运一体式施工船前往码头,利用船体上的吊机将码头上的导管架起吊至船尾的轨道上,然后将导管架向前滑移;此时吊机起吊下一导管架至轨道上,直至轨道上布满导管架;导管架吊运一体式施工船带着导管架航行至桩管施工完成处就位,吊机起吊最靠近船尾端的导管架,使得其下方安装至桩管上,然后导管架吊运一体式施工船航行至下一桩管完成处下放导管架,直至轨道上的导管架全部安装完毕后,导管架吊运一体式施工船返航装载下一批导管架。
本发明一种导管架吊运一体式施工工艺,所述船体的甲板上设置有多组绞车,所述绞车的绞索通过滑轮组机构与导管架的管脚相连接,从而为导管架的移动提供动力。
与现有技术相比,本发明的有益效果是:
本发明利用一条施工船同时进行导管架的装载、航运和起吊,对施工船适当改造后,使得其能够对装载于其甲板上的多个导管架进行滑移,从而便于在港口的装载以及在远洋的吊装,一条施工船作业施工不但成倍降低了施工成本,而且无需与其他船只进行协同作业,大大降低了施工难度,有助于提高施工效率且降低施工风险;从而有利于施工企业抢占市场占有率。
附图说明
图1为本发明一种导管架吊运一体式施工船的结构示意图。
图2为本发明一种导管架吊运一体式施工船的俯视示意简图。
其中:
船体1、吊机2、轨道3、导管架4、吊机辅助臂架5、绞车6。
具体实施方式
参见图1和图2,本发明涉及的一种导管架吊运一体式施工工艺,所述工艺基于一种导管架吊运一体式施工船,所述施工船包含有船体1,所述船体1的甲板上平行设置有两条轨道3,两条轨道3延伸至船体1的船尾;导管架4的管脚安装于滑块上,且滑块滑动设置于轨道3;所述船体1上设置有吊机2,吊机辅助臂架5位于轨道3的外侧,吊机2的吊索经吊机辅助臂架5后钩住导管架4的顶部起吊环;
进一步的,所述船体1的甲板上设置有多组绞车6,所述绞车6的绞索通过滑轮组机构与导管架4的管脚相连接,从而为导管架4的移动提供动力;
其工艺步骤为:在导管架的桩管施工过程中,导管架吊运一体式施工船前往码头,利用船体1上的吊机2将码头上的导管架起吊至船尾的轨道3上,然后将导管架向前滑移;此时吊机2起吊下一导管架至轨道3上,直至轨道3上布满导管架;导管架吊运一体式施工船带着导管架航行至桩管施工完成处就位,吊机2起吊最靠近船尾端的导管架,使得其下方安装至桩管上,然后导管架吊运一体式施工船航行至下一桩管完成处下放导管架,直至轨道3上的导管架全部安装完毕后,导管架吊运一体式施工船返航装载下一批导管架;
另外:需要注意的是,上述具体实施方式仅为本专利的一个优化方案,本领域的技术人员根据上述构思所做的任何改动或改进,均在本专利的保护范围之内。
Claims (2)
1.一种导管架吊运一体式施工工艺,其特征在于:所述工艺基于一种导管架吊运一体式施工船,所述施工船包含有船体(1),所述船体(1)的甲板上平行设置有两条轨道(3),两条轨道(3)延伸至船体(1)的船尾;导管架(4)的管脚安装于滑块上,且滑块滑动设置于轨道(3);所述船体(1)上设置有吊机(2),吊机辅助臂架(5)位于轨道(3)的外侧,吊机(2)的吊索经吊机辅助臂架(5)后钩住导管架(4)的顶部起吊环;
在导管架的桩管施工过程中,导管架吊运一体式施工船前往码头,利用船体(1)上的吊机(2)将码头上的导管架起吊至船尾的轨道(3)上,然后将导管架向前滑移;此时吊机(2)起吊下一导管架至轨道(3)上,直至轨道(3)上布满导管架;导管架吊运一体式施工船带着导管架航行至桩管施工完成处就位,吊机(2)起吊最靠近船尾端的导管架,使得其下方安装至桩管上,然后导管架吊运一体式施工船航行至下一桩管完成处下放导管架,直至轨道(3)上的导管架全部安装完毕后,导管架吊运一体式施工船返航装载下一批导管架。
2.如权利要求1所述一种导管架吊运一体式施工工艺,其特征在于:所述船体(1)的甲板上设置有多组绞车(6),所述绞车(6)的绞索通过滑轮组机构与导管架(4)的管脚相连接,从而为导管架(4)的移动提供动力。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811085578.6A CN109441734A (zh) | 2018-09-18 | 2018-09-18 | 导管架吊运一体式施工工艺 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811085578.6A CN109441734A (zh) | 2018-09-18 | 2018-09-18 | 导管架吊运一体式施工工艺 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109441734A true CN109441734A (zh) | 2019-03-08 |
Family
ID=65530454
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811085578.6A Pending CN109441734A (zh) | 2018-09-18 | 2018-09-18 | 导管架吊运一体式施工工艺 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109441734A (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112158303A (zh) * | 2020-10-12 | 2021-01-01 | 南通润吉尼海洋装备有限公司 | 多功能风电支持船 |
CN114148463A (zh) * | 2021-10-26 | 2022-03-08 | 周宏勤 | 半潜式海工安装作业平台施工工艺 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2002048547A1 (en) * | 2000-12-13 | 2002-06-20 | Mammoet Marine B.V.I.O. | Method and apparatus for placing at least one wind turbine on open water |
EP2266871A1 (en) * | 2003-04-04 | 2010-12-29 | Logima V/Svend Erik Hansen | A wind turbine with a wind turbine base, and methods of transferring or moving a wind turbine |
DE102010015412A1 (de) * | 2010-04-19 | 2011-10-20 | Liebherr-Werk Ehingen Gmbh | Verfahren zum Transport und zur Montage einer Windkraftanlage und Transport- und Montagesystem |
WO2012066789A1 (ja) * | 2010-11-18 | 2012-05-24 | 三菱重工業株式会社 | 洋上風車設置用船舶およびこれを用いた洋上風車設置方法 |
US20120219364A1 (en) * | 2009-11-27 | 2012-08-30 | Sinovel Wind Group Co., Ltd. | Vessel and method for transporting and hoisting the offshore wind turbine generator system |
US20120255478A1 (en) * | 2010-01-10 | 2012-10-11 | Nordic Yards Holding Gmbh | Ship and Method for Conveying and Setting Up Offshore Structures |
-
2018
- 2018-09-18 CN CN201811085578.6A patent/CN109441734A/zh active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2002048547A1 (en) * | 2000-12-13 | 2002-06-20 | Mammoet Marine B.V.I.O. | Method and apparatus for placing at least one wind turbine on open water |
EP2266871A1 (en) * | 2003-04-04 | 2010-12-29 | Logima V/Svend Erik Hansen | A wind turbine with a wind turbine base, and methods of transferring or moving a wind turbine |
US20120219364A1 (en) * | 2009-11-27 | 2012-08-30 | Sinovel Wind Group Co., Ltd. | Vessel and method for transporting and hoisting the offshore wind turbine generator system |
US20120255478A1 (en) * | 2010-01-10 | 2012-10-11 | Nordic Yards Holding Gmbh | Ship and Method for Conveying and Setting Up Offshore Structures |
DE102010015412A1 (de) * | 2010-04-19 | 2011-10-20 | Liebherr-Werk Ehingen Gmbh | Verfahren zum Transport und zur Montage einer Windkraftanlage und Transport- und Montagesystem |
WO2012066789A1 (ja) * | 2010-11-18 | 2012-05-24 | 三菱重工業株式会社 | 洋上風車設置用船舶およびこれを用いた洋上風車設置方法 |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112158303A (zh) * | 2020-10-12 | 2021-01-01 | 南通润吉尼海洋装备有限公司 | 多功能风电支持船 |
CN114148463A (zh) * | 2021-10-26 | 2022-03-08 | 周宏勤 | 半潜式海工安装作业平台施工工艺 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103661801B (zh) | 海洋工程水下推进器的安装辅助系统及安装方法 | |
CN102852147B (zh) | 导管架单扒杆双钩扶正方法 | |
WO2011063596A1 (zh) | 海上风力发电机组运输吊装船以及运输吊装方法 | |
CN103883273B (zh) | 利用饱和潜水支持船上的双吊机安装立管的方法 | |
CN103693170A (zh) | 一种漂浮式海上风电组装平台及用该平台组装海上风机的方法 | |
US20150217838A1 (en) | Method for lowering and hoisting of a load to or from an ocean floor | |
CN103466038A (zh) | 一种fpso单点浮筒内连接管更换方法 | |
CN209023076U (zh) | 导管架吊运一体船 | |
CN109441734A (zh) | 导管架吊运一体式施工工艺 | |
CN102213085A (zh) | 导管架立管的安装方法 | |
CN102586784B (zh) | 平台外加直流电阴极保护系统的安装方法 | |
CN103373446A (zh) | 导管架拆除船及拆除方法 | |
CN202169997U (zh) | 门架重吊船 | |
CN103879904A (zh) | 海洋起重船及其移动方法 | |
CN102826459A (zh) | 一种用于海洋平台的水下结构件吊装装置及吊装方法 | |
CN102071652B (zh) | 实施大吨位物体拖拉上岸的方法及其装置 | |
CN101954958B (zh) | 用在水泥驳船装卸船上的升降装置 | |
CN102050377B (zh) | 一种组合吊机及采油平台钻井设备的安装方法 | |
CN102562489A (zh) | 海上风机的安装方法 | |
CN101362008B (zh) | 海上平台的消防泵护管的浮袋安装法 | |
CN201694361U (zh) | 一种海上风机整体运输与安装的专用工程船 | |
CN106115508A (zh) | 一种组合式浮船吊 | |
CN208325559U (zh) | 一种观光潜器升降平台装置 | |
CN204714399U (zh) | 便于输油的多头船用塔吊 | |
CN206172843U (zh) | 一种组合式浮船吊 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190308 |
|