CN109440646A - A kind of pre-buried bracket device of king-post upper beam construction bracket - Google Patents

A kind of pre-buried bracket device of king-post upper beam construction bracket Download PDF

Info

Publication number
CN109440646A
CN109440646A CN201811186309.9A CN201811186309A CN109440646A CN 109440646 A CN109440646 A CN 109440646A CN 201811186309 A CN201811186309 A CN 201811186309A CN 109440646 A CN109440646 A CN 109440646A
Authority
CN
China
Prior art keywords
bracket
buried
backing plate
king
steel slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811186309.9A
Other languages
Chinese (zh)
Inventor
林丹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201811186309.9A priority Critical patent/CN109440646A/en
Publication of CN109440646A publication Critical patent/CN109440646A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/14Towers; Anchors ; Connection of cables to bridge parts; Saddle supports

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention is a kind of pre-buried bracket device of king-post upper beam construction bracket, including pre-buried bracket stress surface, pre-embedded steel slab, bracket backing plate, bracket gusset, bracket backing plate.The pre-buried bracket stress surface provides impetus;The pre-embedded steel slab is to be inserted into high pier construction concrete with a thickness of 5-15cm thick steel plate, and quantity, length, the size highly according to offer support force of pre-embedded steel slab are determining;The bracket backing plate is the steel plate with a thickness of 2-4cm lain in a horizontal plane in immediately below pre-embedded steel slab, is welded with pre-embedded steel slab;Bracket backing plate is close to high pier concrete surface, and upper end intersects vertically and welds with bracket backing plate.Bracket gusset is triangular steel plate, vertical to place, and is welded with ox bracket backing plate and bracket backing plate, is respectively provided with one piece of bracket gusset under every piece of pre-embedded steel slab.

Description

A kind of pre-buried bracket device of king-post upper beam construction bracket
Technical field:
The present invention relates to bridge substructure construction field more particularly to the pre-buried bracket dresses of king-post upper beam construction bracket It sets.
Background technique:
Upper beam construction is the important partitioned project of bridge construction.
Being constantly progressive and develop with Chinese society, conventional bridge is no longer satisfied the needs of traffic, therefore, oblique pull This extra-large bridge of bridge, suspension bridge becomes the important component of current urban traffic road.Cable-stayed bridge, suspension cable bridge tower pier stud Upper beam height is high, and conventional floor stand needs steel-pipe pile, and high-altitude is spliced section by section, not only wastes material, artificial, it is also desirable to longer Installation and remove the period, and there are many security risk factors in work progress.
Under this form, high pier king-post upper beam gradually becomes the important selection of upper beam construction, but upper cross using bracket Beam construction needs stress of taking root on king-post using bracket.Therefore, how to ensure to be set as on high tower tower body bracket construction by The device of power becomes the key of king-post bracket construction.
Summary of the invention:
The technical problems to be solved by the present invention are: providing a pre-buried bracket device of king-post upper beam construction bracket, it is intended to Enough bearing capacities are provided for king-post upper beam bracket, bracket is allow to weigh the various loads in upper beam work progress.
In order to solve the above-mentioned technical problem, the present invention is achieved by the following technical solutions: the pre-buried bracket stress Face provides impetus;In described pre-embedded steel slab insertion high pier construction concrete;The bracket backing plate 1 is pre-buried to lie in a horizontal plane in The steel plate with a thickness of 2-4cm immediately below steel plate is welded with pre-embedded steel slab;Bracket backing plate 2 is close to high pier concrete surface, and upper end is same Bracket backing plate 1 intersects vertically and welds.Bracket gusset is triangular steel plate, vertical to place, with ox bracket backing plate 1 and bracket backing plate 2 weld, and are respectively provided with one piece of bracket gusset under every piece of pre-embedded steel slab.
Preferably, pre-buried bracket stress surface provides impetus, and bracket is integrally welded with pre-buried bracket stress surface;
Preferably, described pre-embedded steel slab is to be inserted into high pier construction concrete, pre-buried steel with a thickness of 5-15cm thick steel plate The length of plate, the size highly according to offer support force are determining, and quantity is two or more, but in unified absolute altitude;
Preferably, the bracket backing plate 1 is welded to connect with pre-embedded steel slab.
Preferably, the bracket backing plate 2 is close to king-post concrete surface according to upper end is welded with bracket backing plate 1.
Preferably, the bracket gusset is right angled triangle, and the same pre-embedded steel slab of quantity is mounted on immediately below pre-embedded steel slab, It is welded respectively with bracket backing plate 1 and bracket backing plate 2 on two sides.
Preferably, the bracket gusset lateral is angle steel, and with bracket link of boards, lateral between different bracket gussets should be On one horizontal line.
The invention has the beneficial effects that: pre-embedded steel slab is main bearing member, and with a thickness of 5-15cm, pre-buried hole is less than King-post main reinforcement spacing, therefore pre-embedded steel slab installation will not separate king-post steel plate;Bracket backing plate 1 is mounted below pre-embedded steel slab, can Multiple pre-embedded steel slabs to link into an integrated entity well, and play the role of stress distribution;The installation of bracket gusset can be fine Ground reduces the bending stress that pre-embedded steel slab is subject to, and the pressure that pre-embedded steel slab is subject to, which is converted into, pushes away the level of king-post surface concrete Power;Bracket backing plate 2 is close to concrete cylinder, and welds with bracket gusset and bracket backing plate, can be transmitted to bracket gusset The power of king-post concrete surface plays the role of stress dispersion;Bracket gusset lateral is integral by each link of boards, can be well Improve the stability of bracket gusset.Pre-buried bracket overall structure stable connection, each member stress is succinct, and structure is simple, but can To bear great load.
Detailed description of the invention:
The following further describes the present invention with reference to the drawings.
Fig. 1 is upper beam bracket overall floor plan, for a kind of pre-buried bracket of king-post upper beam construction bracket of the present invention Setting position schematic diagram;
Fig. 2 is for a kind of pre-buried bracket device side elevational view of king-post upper beam construction bracket of the present invention;
Fig. 3 is for a kind of pre-buried bracket device front elevation view of king-post upper beam construction bracket of the present invention;
In figure: 1, king-post concrete surface;2, pre-buried bracket stress surface;3, pre-embedded steel slab;4, bracket backing plate 1;5, bracket muscle Plate;6, bracket backing plate 2;7, bracket gusset lateral.
Specific embodiment:
Fig. 1 be upper beam construction bracket, Fig. 2, Fig. 3 be pre-buried bracket side elevation and front elevation view, including pre-buried bracket by Power face, pre-embedded steel slab, bracket backing plate 1, bracket gusset, bracket backing plate 2, bracket gusset lateral.The pre-buried bracket stress surface will Bracket is connected with bracket;The pre-embedded steel slab is main bearing member, is inserted into the length in concrete and is greater than outside concrete Length;Bracket backing plate 1, bracket backing plate 2, bracket gusset and the interconnection of bracket gusset lateral under pre-embedded steel slab is integral, rises Fine stress and intermal force are arrived.
It is integral in rear long paperback after the accurate processing and fabricating of pre-buried each component of bracket device, then integral installation to king-post. Its specific mounting means is as follows:
Before pre-buried bracket installation, it should when king-post concrete construction, pre-buried box is set in design position, it is pre-buried Box is made of steel plate, need to be installed in place in king-post concrete construction and be must assure that pre-buried box fixation, it is ensured that most Pre-buried bracket installation site is accurate eventually.
Bracket provides job platform and armored concrete mounting bracket for upper beam construction, is tiltedly propped up by main spandrel girder, bracket Leg and web member composition.Spandrel girder and supporting leg are the main bearing member of bracket, and the master that pre-buried bracket is mainly same as above crossbar bracket holds Chong Liang is connected with oblique supporting leg, completes the transmitting of power.After pre-buried box is installed in place, pre-buried bracket device integral installation is arrived Position, then will be in bracket integral installation to pre-buried bracket.
By pre-buried bracket device, upper beam is directly anchored on king-post, since its king-post height is high, keeps bracket fine Ground reduces waste of material caused by bracket installation from top to bottom and artificial, mechanical investment, considerably reduces construction cost.
It is emphasized that: the above is only presently preferred embodiments of the present invention, not make in any form to the present invention Limitation, any simple modification, equivalent change and modification to the above embodiments according to the technical essence of the invention, All of which are still within the scope of the technical scheme of the invention.

Claims (6)

1. a kind of pre-buried bracket device of king-post upper beam construction bracket, which is characterized in that including pre-buried bracket stress surface (2), in advance Bury steel plate (3), bracket backing plate 1 (4), bracket gusset (5), bracket backing plate 2 (6).
2. the pre-buried bracket device of a kind of king-post upper beam construction bracket according to claim 1, which is characterized in that described pre- It buries bracket stress surface (2) and impetus is provided.
3. the pre-buried bracket device of a kind of king-post upper beam construction bracket according to claim 1, which is characterized in that described Pre-embedded steel slab (3) is to be inserted into high pier construction concrete, quantity, length, the height of pre-embedded steel slab with a thickness of 5-15cm thick steel plate It is determined according to the size for providing support force.
4. the pre-buried bracket device of a kind of king-post upper beam construction bracket according to claim 1, which is characterized in that the ox Leg backing plate 1 (4) is the steel plate with a thickness of 2-4cm lain in a horizontal plane in immediately below pre-embedded steel slab, is welded with pre-embedded steel slab.
5. the pre-buried bracket device of a kind of king-post upper beam construction bracket according to claim 1, which is characterized in that bracket pad Plate 2 (6) is close to high pier concrete surface, and upper end intersects vertically and welds with bracket backing plate 1 (4).
6. the pre-buried bracket device of a kind of king-post upper beam construction bracket according to claim 1, which is characterized in that bracket muscle Plate (5) is triangular steel plate, vertical to place, and is welded with ox bracket backing plate 1 and bracket backing plate 2, is respectively provided under every piece of pre-embedded steel slab One piece of bracket gusset.
CN201811186309.9A 2018-10-10 2018-10-10 A kind of pre-buried bracket device of king-post upper beam construction bracket Pending CN109440646A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811186309.9A CN109440646A (en) 2018-10-10 2018-10-10 A kind of pre-buried bracket device of king-post upper beam construction bracket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811186309.9A CN109440646A (en) 2018-10-10 2018-10-10 A kind of pre-buried bracket device of king-post upper beam construction bracket

Publications (1)

Publication Number Publication Date
CN109440646A true CN109440646A (en) 2019-03-08

Family

ID=65544970

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811186309.9A Pending CN109440646A (en) 2018-10-10 2018-10-10 A kind of pre-buried bracket device of king-post upper beam construction bracket

Country Status (1)

Country Link
CN (1) CN109440646A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110318344A (en) * 2019-06-28 2019-10-11 中交二航局第四工程有限公司 A kind of No. 0 block bracket of novel steel box-girder and No. 0 block erection construction method
CN113417372A (en) * 2021-07-01 2021-09-21 中铁大桥局第七工程有限公司 Concrete tower column embedded bracket system and installation method
CN114684624A (en) * 2022-03-29 2022-07-01 山东电力工程咨询院有限公司 Few-column sectional chimney-penetrating coal conveying trestle system and method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101314862B1 (en) * 2012-08-10 2013-10-04 해강산업주식회사 Concrete form apparatus
CN104532749A (en) * 2014-12-18 2015-04-22 中铁建设集团有限公司 Support used for construction of upper beam of main tower of suspension bridge
CN205636474U (en) * 2016-04-29 2016-10-12 贵州桥梁建设集团有限责任公司 Assembled bracket structure
CN106677070A (en) * 2016-12-31 2017-05-17 中铁局集团有限公司 Construction support and method for overhead large-span heavy-duty cross beam

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101314862B1 (en) * 2012-08-10 2013-10-04 해강산업주식회사 Concrete form apparatus
CN104532749A (en) * 2014-12-18 2015-04-22 中铁建设集团有限公司 Support used for construction of upper beam of main tower of suspension bridge
CN205636474U (en) * 2016-04-29 2016-10-12 贵州桥梁建设集团有限责任公司 Assembled bracket structure
CN106677070A (en) * 2016-12-31 2017-05-17 中铁局集团有限公司 Construction support and method for overhead large-span heavy-duty cross beam

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110318344A (en) * 2019-06-28 2019-10-11 中交二航局第四工程有限公司 A kind of No. 0 block bracket of novel steel box-girder and No. 0 block erection construction method
CN110318344B (en) * 2019-06-28 2024-04-19 中交二航局第四工程有限公司 Novel steel box girder No. 0 block support and No. 0 block erection construction method
CN113417372A (en) * 2021-07-01 2021-09-21 中铁大桥局第七工程有限公司 Concrete tower column embedded bracket system and installation method
CN113417372B (en) * 2021-07-01 2023-02-28 中铁大桥局第七工程有限公司 Concrete tower column embedded bracket system and installation method
CN114684624A (en) * 2022-03-29 2022-07-01 山东电力工程咨询院有限公司 Few-column sectional chimney-penetrating coal conveying trestle system and method
CN114684624B (en) * 2022-03-29 2024-01-19 山东电力工程咨询院有限公司 Few-column sectional type chimney-penetrating coal conveying stack bridge system and method

Similar Documents

Publication Publication Date Title
CN109440646A (en) A kind of pre-buried bracket device of king-post upper beam construction bracket
CN101649604B (en) Construction bracket of 1# block of inclined pull bridge and constructing method thereof
CN102051858B (en) Jack loading triangular truss hanging basket and load test construction method thereof
CN100540809C (en) The replacing supporters for continuous beam without breaking off traffic method
CN201714050U (en) Integral triangular support operating platform for elevator shaft
CN203904851U (en) Continuous beam side span straight section hanger support system
CN203668833U (en) Steel web locating device
CN202247687U (en) Universal cast-in-situ trestle for bridge
JP5367297B2 (en) Bridge with precast cross girder and precast girder and its construction method
CN105544398A (en) Horizontal force self-balancing type splayed heavy type upper air support system and installation method thereof
CN101446076B (en) Cast-in-place support for long cantilever No. 0 block of cable-stayed bridge with tower beam consolidation and putting up method
CN110847010B (en) Construction and construction method suitable for large-span abutment rigid frame bridge
CN209194353U (en) It is a kind of to ride integral type bracket suitable for the construction of Bridge High-pier 0# block
CN212404805U (en) Combined abutment structure for temporary trestle
CN105442855B (en) A kind of high-precision buried equipment, method of large scale embedded board
CN111560842A (en) Combined abutment structure for temporary trestle
CN100497834C (en) Construction equipment for integral roof-holding highway bridge top structure
CN108570933B (en) Method for jacking short-tower cable-stayed bridge
CN105484171B (en) One kind becomes top of the slope and enters precast frame bridges and culverts external tendon prestress strengthening method
CN213805443U (en) Steel construction, frame beam structure, side slope reinforced structure and reinforcement and support structure
CN212641179U (en) Connecting joint structure of rear steel longitudinal beam and old concrete cross beam
CN211772914U (en) Pre-buried box structure of 0# piece bracket of continuous beam
CN114000410A (en) Anti-overturning structure of steel box girder
CN210953063U (en) Weighing platform structure
CN207331470U (en) A kind of embedded box anchors assembled bracket

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
DD01 Delivery of document by public notice

Addressee: Lin Dan

Document name: Notification that Application Deemed to be Withdrawn

DD01 Delivery of document by public notice
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190308

WD01 Invention patent application deemed withdrawn after publication