CN109424196A - Based on the technique for improving concrete pouring quality in construction - Google Patents

Based on the technique for improving concrete pouring quality in construction Download PDF

Info

Publication number
CN109424196A
CN109424196A CN201710788912.3A CN201710788912A CN109424196A CN 109424196 A CN109424196 A CN 109424196A CN 201710788912 A CN201710788912 A CN 201710788912A CN 109424196 A CN109424196 A CN 109424196A
Authority
CN
China
Prior art keywords
concrete
plus
demoulding
cement
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201710788912.3A
Other languages
Chinese (zh)
Inventor
吴洋忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Meiji Real Estate Marketing Planning Co Ltd
Original Assignee
Chengdu Meiji Real Estate Marketing Planning Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Meiji Real Estate Marketing Planning Co Ltd filed Critical Chengdu Meiji Real Estate Marketing Planning Co Ltd
Priority to CN201710788912.3A priority Critical patent/CN109424196A/en
Publication of CN109424196A publication Critical patent/CN109424196A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses based on the technique for improving concrete pouring quality in construction, using self-falling mixer, charging sequence is preferably, and first plus l/2 water consumption, then plus stone, cement, sand stir lmin, again plus remaining 1/2 water consumption continues to stir, mixing time is no less than 1.5min, and mixing time should be appropriately extended when mixing additive, a variety of materials accurate measurement, measuring accuracy: cement, water, additive are ± 2%, and aggregate is ± 3%;Concrete is transported to pouring location from stirring place, controls within 0.5~lh;The mobile spacing of poker vibrator is not preferably greater than 1.5 times of acting radial of vibrator, and door opening two sides constructional column wants vibration compacting, must not leakage;Should be after concrete cooling extremely+5 DEG C, when surface temperature of concrete and ambient temperature differences are greater than 15 DEG C after demoulding, covering curing is answered on surface, makes its Slow cooling;Demoulding when concrete strength is greater than 1MPa when room temperature.The present invention can be improved the quality after concreting, so that service life is guaranteed.

Description

Based on the technique for improving concrete pouring quality in construction
Technical field
The present invention relates to a kind of architectural construction technologies, and in particular to one kind is based on improving concreting in construction The technique of quality.
Background technique
Building is based on timber buildings, and the traditional architecture in west is based on masonry structure.Modern building is then with steel Based on reinforced concrete.
Chinese ancient architecture has simple simple and elegant style, is knot with yoke structure mainly using cogongrass, timber as construction material Structure mode (components such as column, beam, a tree, used in making timber for boats, purlin, rafter) is combined according to actual size, shape and the spacing that structure needs.It is this Building structure mode reflects the clear, orderly of ancient times patriarchal society structure and stablizes.Due to wooden material production beam column not Huge inner space is easily formed, ancient architecture just dexterously using outport place, forms garden.Garden is the base of building Our unit, it is both closed and open;Be both it is artificial and naturally, can bow and plant flowers, plants and trees, face upward and serve as a lookout Cloud life becomes the another performance of ancients " harmony between man and nature " idea, also embodies Chinese's not only implicit introversion, but also pioneer and keep forging ahead National character.The groups of building that ancient times somewhat larger building is all made of several gardens, single building and garden are along one Move towards to arrange calmly, it is A distinction should be made between what is primary and what is secondary, there is climax to have transition, become the space for the depth that has levels, has, shows a kind of Chinese and chased after The integrated beauty and deep beauty asked.Wherein palace, the building that temple one kind is more solemn, often one by one along central axes It is longitudinally arranged key construction, monosymmetric arrangement secondary structure, arrangement balancing is unfolded, fascinating.
Ancients can achieve the effect that beauty with the design techniques such as balance, harmonious, symmetrical, light and shade axis very early.Ancient times Weight artistic decoration is built, but uncomplicated, only makees emphasis decoration, such as window hood, lintel, ridge in main portions, layout is mostly to weigh Square to development, skyscraper is not weighed, until there is building pagoda, high building is just able to prevailing after Buddhism is incoming.The one of building Cutting art processing is also all processing to structural system and component, if color, decoration are in conjunction with component, constitute enrich it is gorgeous Art achievements, carved beams and painted rafter, body are graceful and colorful;Couplet written on scrolls and hung on the pillars of a hall horizontal inscribed board, excites interest and charm and reverie is infinite, ancient architecture category It is flouring, including palace, cemetery park, monastery, palace sight, gardens, bridge, tower brake etc..
Due to being not well mastered skill when the concreting of existing building, easy to crack and appearance after concreting is caused Hollowing influences later period use.
Summary of the invention
The technical problem to be solved by the present invention is to, due to being not well mastered skill, make when the concreting of existing building At easy to crack and hollowing occur after concreting, influencing the later period is used, and it is an object of the present invention to provide a kind of based in construction The technique for improving concrete pouring quality causes to mix due to being not well mastered skill when solving the concreting of existing building The problem of solidifying soil pours rear easy to crack and hollowing occurs, influences later period use.
The present invention is achieved through the following technical solutions:
Based on the technique for improving concrete pouring quality in construction, comprising the following steps:
(1) self-falling mixer is used, charging sequence is preferably, first plus l/2 water consumption, then plus stone, cement, sand stirring Lmin, then plus remaining 1/2 water consumption continue to stir, mixing time is no less than 1.5min, and mixing time should be appropriate when mixing additive Extend, a variety of materials accurate measurement, measuring accuracy: cement, water, additive are ± 2%, and aggregate is ± 3%, and the Pluvial should often survey Sand, stone moisture content are determined, to guarantee that the ratio of mud is accurate;
(2) concrete is transported to pouring location from stirring place, and perdurabgility shortens as far as possible, is preferably controlled according to temperature 0.5 Within~lh, when using commerical ready-mixed concrete, unloads again after should being sufficiently stirred, do not allow arbitrarily to add water, concrete isolates When, secondary agitation is answered before pouring, the concrete having been the beginning of coagulation should not use;
(3) the mobile spacing of poker vibrator is not preferably greater than 1.5 times of acting radial of vibrator, generally should be smaller than 50cm, Door opening two sides constructional column wants vibration compacting, must not leakage, it is each vibration point perdurabgility, with surface present laitance and no longer sink Fall to reach requirement, avoid collision reinforcing bar, template, built-in fitting, built-in pipe, Side fascia cavity water proof structure etc., discovery have deformation, Displacement, each related trades mutual cooperation are handled;
(4) should be after concrete cooling extremely+5 DEG C, surface temperature of concrete and ambient temperature differences are greater than 15 DEG C after demoulding When, covering curing is answered on surface, makes its Slow cooling;
(5) concrete strength is greater than 1MPa when room temperature, and when teletostage mixes antifreezing agent, tears open when concrete strength being made to reach 4MPa Mould, when guaranteeing demoulding, metope, corner are modified in wall not sticking to mould, not arrisdefect, not crack in time, and the timely wet curing of room temperature is supported The shield time is no less than 7d, and irrigation times should be able to keep concrete wet.
Compared with prior art, the present invention having the following advantages and benefits: the present invention can be improved concrete and pour Quality after building, so that service life is guaranteed.
Specific embodiment
To make the objectives, technical solutions, and advantages of the present invention clearer, below with reference to embodiment, the present invention is made Further to be described in detail, exemplary embodiment of the invention and its explanation for explaining only the invention, are not intended as to this The restriction of invention.
Embodiment:
Based on the technique for improving concrete pouring quality in construction, comprising the following steps:
(1) self-falling mixer is used, charging sequence is preferably, first plus l/2 water consumption, then plus stone, cement, sand stirring Lmin, then plus remaining 1/2 water consumption continue to stir, mixing time is no less than 1.5min, and mixing time should be appropriate when mixing additive Extend, a variety of materials accurate measurement, measuring accuracy: cement, water, additive are ± 2%, and aggregate is ± 3%, and the Pluvial should often survey Sand, stone moisture content are determined, to guarantee that the ratio of mud is accurate;
(2) concrete is transported to pouring location from stirring place, and perdurabgility shortens as far as possible, is preferably controlled according to temperature 0.5 Within~lh, when using commerical ready-mixed concrete, unloads again after should being sufficiently stirred, do not allow arbitrarily to add water, concrete isolates When, secondary agitation is answered before pouring, the concrete having been the beginning of coagulation should not use;
(3) the mobile spacing of poker vibrator is not preferably greater than 1.5 times of acting radial of vibrator, generally should be smaller than 50cm, Door opening two sides constructional column wants vibration compacting, must not leakage, it is each vibration point perdurabgility, with surface present laitance and no longer sink Fall to reach requirement, avoid collision reinforcing bar, template, built-in fitting, built-in pipe, Side fascia cavity water proof structure etc., discovery have deformation, Displacement, each related trades mutual cooperation are handled;
(4) should be after concrete cooling extremely+5 DEG C, surface temperature of concrete and ambient temperature differences are greater than 15 DEG C after demoulding When, covering curing is answered on surface, makes its Slow cooling;
(5) concrete strength is greater than 1MPa when room temperature, and when teletostage mixes antifreezing agent, tears open when concrete strength being made to reach 4MPa Mould, when guaranteeing demoulding, metope, corner are modified in wall not sticking to mould, not arrisdefect, not crack in time, and the timely wet curing of room temperature is supported The shield time is no less than 7d, and irrigation times should be able to keep concrete wet.
The present invention can be improved the quality after concreting, so that service life is guaranteed.
Above-described specific embodiment has carried out further the purpose of the present invention, technical scheme and beneficial effects It is described in detail, it should be understood that being not intended to limit the present invention the foregoing is merely a specific embodiment of the invention Protection scope, all within the spirits and principles of the present invention, any modification, equivalent substitution, improvement and etc. done should all include Within protection scope of the present invention.

Claims (1)

1. based on the technique for improving concrete pouring quality in construction, which comprises the following steps:
(1) self-falling mixer is used, charging sequence is preferably, first plus l/2 water consumption, then plus stone, cement, sand stirring Lmin, then plus remaining 1/2 water consumption continue to stir, mixing time is no less than 1.5min, and mixing time should be appropriate when mixing additive Extend, a variety of materials accurate measurement, measuring accuracy: cement, water, additive are ± 2%, and aggregate is ± 3%, and the Pluvial should often survey Sand, stone moisture content are determined, to guarantee that the ratio of mud is accurate;
(2) concrete is transported to pouring location from stirring place, and perdurabgility shortens as far as possible, is preferably controlled according to temperature in 0.5~lh Within, when using commerical ready-mixed concrete, unloads again after should being sufficiently stirred, do not allow arbitrarily to add water, when concrete isolates, pour Secondary agitation is answered before building, the concrete having been the beginning of coagulation should not use;
(3) the mobile spacing of poker vibrator is not preferably greater than 1.5 times of acting radial of vibrator, generally should be smaller than 50cm, door opening Mouthful two sides constructional column wants vibration compacting, must not leakage, the perdurabgility of each vibration point, laitance is presented with surface and no longer sink for Reach requirement, avoid collision reinforcing bar, template, built-in fitting, built-in pipe, Side fascia cavity water proof structure etc., discovery has deformation, moves Position, each related trades mutual cooperation are handled;
(4) should be after concrete cooling extremely+5 DEG C, when surface temperature of concrete and ambient temperature differences are greater than 15 DEG C after demoulding, table Covering curing is answered in face, makes its Slow cooling;
(5) concrete strength is greater than 1MPa when room temperature, and when teletostage mixes antifreezing agent, demoulding when concrete strength being made to reach 4MPa, protects When demonstrate,proving demoulding, metope, corner, the timely wet curing of room temperature, curing time are modified in wall not sticking to mould, not arrisdefect, not crack in time No less than 7d, irrigation times should be able to keep concrete wet.
CN201710788912.3A 2017-09-05 2017-09-05 Based on the technique for improving concrete pouring quality in construction Withdrawn CN109424196A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710788912.3A CN109424196A (en) 2017-09-05 2017-09-05 Based on the technique for improving concrete pouring quality in construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710788912.3A CN109424196A (en) 2017-09-05 2017-09-05 Based on the technique for improving concrete pouring quality in construction

Publications (1)

Publication Number Publication Date
CN109424196A true CN109424196A (en) 2019-03-05

Family

ID=65513935

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710788912.3A Withdrawn CN109424196A (en) 2017-09-05 2017-09-05 Based on the technique for improving concrete pouring quality in construction

Country Status (1)

Country Link
CN (1) CN109424196A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112282072A (en) * 2020-10-20 2021-01-29 中国建筑第八工程局有限公司 Embedding method of group heavy-duty embedded parts
CN114872197A (en) * 2022-04-19 2022-08-09 江西省交通工程集团建设有限公司 Control method for mold-entering temperature of mass concrete

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112282072A (en) * 2020-10-20 2021-01-29 中国建筑第八工程局有限公司 Embedding method of group heavy-duty embedded parts
CN114872197A (en) * 2022-04-19 2022-08-09 江西省交通工程集团建设有限公司 Control method for mold-entering temperature of mass concrete

Similar Documents

Publication Publication Date Title
CN102535846A (en) One-step forming construction process for integrally pouring housing construction
CN109424196A (en) Based on the technique for improving concrete pouring quality in construction
CN106639197B (en) A kind of split blade type assembly stair construction method
CN106278065B (en) Imitative stone decoration element and its production method
CN109424188A (en) The technique of pouring exposed concrete is used in construction
CN109424090A (en) The technique that shear wall concrete is poured and vibrated in construction
CN206189921U (en) Archaistic building
CA2547694A1 (en) Metal fiber concrete
CN109424121A (en) Based on the technique for carrying out concreting to column class formation under construction
CN109424185A (en) Form construction technology in construction
CN109424189A (en) The technique constructed in construction to rolled roofing material waterproof
CN109424187A (en) The method that concreting is carried out to beam, hardened structure in construction
JPH09175850A (en) Production of functionally reinforced cement, concrete and various moldings
CN109424788A (en) Pipe layer skill when based on to underground pipeline construction
CN109424192A (en) The technique of concrete pouring quality is improved in construction
CN109424068A (en) To cast-in-place framework concreting technique in construction
CN208701992U (en) Foamed concrete fills wall construction
CN207686119U (en) Prefabricated panel
CN109424190A (en) Based on the cross beam construction technology to oval superstructure
CN107152103A (en) A kind of clear water brick decorative wall
CN109424198A (en) Concrete pre-stress construction technology in construction
CN109424149A (en) Based on the method to brick wall tiling in building
CN204001337U (en) Close rib building roof is poured into a mould built-in mould
CN109425464A (en) Closed-water test method is carried out to pipeline after building underground piping is embedded
CN109424201A (en) Center pillar hoisting is built in single industrial premises

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20190305

WW01 Invention patent application withdrawn after publication