CN109409634A - A method of the metering of Grid Construction Project project amount is carried out based on project management APP - Google Patents

A method of the metering of Grid Construction Project project amount is carried out based on project management APP Download PDF

Info

Publication number
CN109409634A
CN109409634A CN201810968635.9A CN201810968635A CN109409634A CN 109409634 A CN109409634 A CN 109409634A CN 201810968635 A CN201810968635 A CN 201810968635A CN 109409634 A CN109409634 A CN 109409634A
Authority
CN
China
Prior art keywords
project
amount
project amount
metering
template
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810968635.9A
Other languages
Chinese (zh)
Inventor
曲英南
周沫
饶慧
朱洪涛
钟声
郭健
臧晓楠
郝丹蕊
李秉烨
郭霞
丁剑
冯鑫
聂暘
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Tianjin Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201810968635.9A priority Critical patent/CN109409634A/en
Publication of CN109409634A publication Critical patent/CN109409634A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Data Mining & Analysis (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of methods for carrying out the metering of Grid Construction Project project amount based on project management APP, the project amount for the quantities calculation specification establishment that typing is applicable according to existing power industry in APP measures template, project amount statistical table is automatically generated according to the highway bids amount inventory of a certain Grid Construction Project of importing, the construction personnel of engineering site daily on project amount statistical form according in table work load evaluation and unit make a report on project completed amount, site supervision personnel and owner audit project amount according to the timing node set in APP in time, and the project amount confirmation form of standard engineering amount inventory form can be generated at any time, improve the accuracy of project amount metering and audit, it is normative, timeliness, for progress payment, branch's clearing and the cost control of final account for completed project provide accurate foundation.

Description

A method of the metering of Grid Construction Project project amount is carried out based on project management APP
Technical field
The invention belongs to technical field of data processing, and in particular to one kind carries out power grid construction work based on project management APP The method of journey project amount metering.
Background technique
With deepening continuously for power grid construction work, Grid Construction Project scale of investment is bigger, the wider, range that is related to face more Extensively, particularly important is become for the accurate control of project cost.Project cost is by the project amount of each list item and corresponding For comprehensive unit price by being calculated, project cost control includes to progress payment, branch's clearing, auditing for construction completion account and setting The audit of meter change and Site visa-an important chain, wherein progress payment corresponds to completed stage project amount, and branch settles accounts corresponding branch The project amount of engineering, the corresponding project amount marked interior project amount and add design alteration and Site visa-an important chain of final account for completed project.As can be seen that existing The accurate metering of field Practical Project amount is the basis that project cost is precisely managed.The metering of current each construction site project amount is quasi- True property, normalization are to be improved, and work load evaluation not fully meets the applicable engineering meter of existing Grid Construction Project Specification is calculated, the format of project amount confirmation form is also not the bill of quantities form of standard, to management, the technical economy people of owner project management department Scheduled fun, branch's clearing, the final account for completed project of member's audit unit in charge of construction application bring difficulty, influence the accuracy and audit of audit Efficiency.And primary mode, construction party are taken 1 month or reported some months for completed stage project amount statistics at present Project amount Dose times and site supervision personnel audit time and project amount actually occur the time there are larger delay, hold very much Easily there is a phenomenon where project amounts to make a false report, misrepresents deliberately;Some units in charge of construction do not report specific project amount, only report engineering image into Degree lacks accurate project amount foundation so as to cause branch's clearing and progress payment audit.And the work due to counting every time Journey amount inaccuracy leads to the total project amount inaccuracy to gather, affects the accuracy of final account for completed project audit.Also, Unit of taking part in building related management personnel and technical economy personnel can not get accurate construction due to cannot often go to construction site in real time Progress and live project completed amount, also increase the difficulty of cost control.
In recent years, the rapid development of mobile Internet provides strong technical support, many enterprises for the application of cell phone application Public institution starts the cell phone application that research and development are suitable for own service.In engineering construction industry, the country is about engineering management hand The research of machine APP, Zhejiang urban construction develop " palm engineering " management system based on cell phone application, carry out to city construction engineering The safe mass visualized management of construction site.University Of Hainan has developed the project sites inspection based on Android platform Management system, inspector report site problems using cell phone application.Chinese each project management department, Tie Jian company carries out use and runs on hand " work pipe APP " on machine, user can check the project name of all projects under construction, Project contract volume, open time of completion etc. Information.But these APP do not have the function that construction site project amount is inputted, counted, summarizing.
Summary of the invention
Current construction site project amount measure it is inaccurate, lack of standardization, not in time aiming at the problem that, the invention patent proposition one The method that kind carries out the metering of Grid Construction Project project amount based on project management APP.Have developed a can run on intelligence simultaneously The quantities calculation specification that typing is applicable according to existing power industry in project management APP, APP on mobile phone and computer The project amount of establishment measures template, automatically generates project amount according to the highway bids amount inventory of a certain Grid Construction Project of importing Statistical table, the construction personnel of engineering site is daily according to the work load evaluation and list in table on project amount statistical form Project completed amount is made a report in position, and site supervision personnel and owner audit project amount, and energy according to the timing node set in APP in time The project amount confirmation form for generating standard engineering amount inventory form at any time improves accuracy, the specification of project amount metering and audit Property, timeliness, for progress payment, branch clearing and final account for completed project cost control provide accurate foundation.And phase Accurate project progress can be understood in real time and project amount is completed by closing administrative staff and technical economy personnel, carry out cost pipe in time Control;And by inventory plan project amount and Practical Project amount progress real time contrast is completed, it realizes to capital construction field engineering amount Closed loop management, guarantee construct according to plan.
A method of the metering of Grid Construction Project project amount is carried out based on project management APP, is carried out according to the following steps:
Step 1: establishment project amount measures template, and in typing project management APP, form template library;
Step 2: importing highway bids amount inventory, project amount statistical table is generated;
Step 3: construction personnel carries out making a report on for project amount, supervisor and owner-work according to project amount statistical table Measure the audit that statistical table carries out project amount;
Step 4: it is true to generate project amount when unit in charge of construction carries out progress payment, branch's clearing or final account for completed project application Recognize book.
In one the above-mentioned technical proposal the step of, the project amount metering template is the table of bill of quantities form.
In one the above-mentioned technical proposal the step of, the project amount metering template includes but is not limited to architectural engineering, power transformation The project amount metering template of engineering, work transmission line, Decorating Project.
In one the above-mentioned technical proposal the step of, the table includes project code, project name, measurement unit, calculating Rule declaration and project amount, the project amount include measurement item, the formula formed by measurement item and add up to, the measurement item Including but not limited to width, length, depth, area.
In one the above-mentioned technical proposal the step of, the project amount metering template can be edited, editable part packet Include increasing, delete, modifying for measurement item and its unit, the addition and modification of formula.
In two the above-mentioned technical proposal the step of, the project amount statistical table on the basis of project amount measures template, It is attached with Practical Project amount and audit project amount to be entered.
The advantages and benefits of the present invention are:
Construction personnel according in project amount statistical table work load evaluation and measurement unit make a report on project amount, meet The applicable quantities calculation specification of existing power industry, supervisor audit project amount according to identical rule, and generate The standard compliant bill of quantities form of project amount confirmation form, so that the metering and audit of project amount more specification, accurate.Together When, construction personnel carries out making a report on for project amount, supervisor and owner daily and audits project amount within 3 working days, compared to Tradition one month or some months measure a project amount mode, metering and audit much sooner.To improve management indirectly With owner project management department technical economy personnel to the accuracy of progress payment, branch's clearing, final account for completed project audit.
Meanwhile project amount is measured and audited using project management APP cell phone client, and it is convenient and efficient, with traditional construction list Position reports and submits papery Cost Data to compare, and saves human and material resources, time cost.
Also, since the period of project amount metering greatly shortens, the real-time of project amount metering is improved, and is conducive to point The development of portion's clearing.
And disposable statistical engineering all-work amount is no longer needed when final account for completed project, it is only necessary to the engineering that will be measured daily Amount is summarized, and is greatly reduced the statistical time of project amount, is shortened the examination & approval time of final account for completed project.
In addition, the data information of project amount is stored in cell phone application for a long time, each unit of taking part in building related personnel can be total in real time Project amount information is enjoyed, by inventory plan project amount and Practical Project amount progress real time contrast is completed, realizes to capital construction scene The closed loop management of project amount, guarantee are constructed according to plan.Cost control personnel in Supervision Project portion can grasp the newest progress of engineering Situation assigns the management instruction of cost control in time.
Detailed description of the invention
Fig. 1 is the flow chart that the present invention carries out project amount metering.
It for those of ordinary skill in the art, without creative efforts, can be according to above attached Figure obtains other relevant drawings.
Specific embodiment
In order to enable those skilled in the art to better understand the solution of the present invention, combined with specific embodiments below furtherly Bright technical solution of the present invention.
The invention patent proposes the method for carrying out the metering of construction project project amount based on project management APP, flow chart As shown in Figure 1, including following 4 steps:
1) establishment project amount measures template, by its typing project management APP, forms template library.
The project amount of current each construction site measures the standard of none unified specification, and this patent foundation is suitable for Existing Grid Construction Project meets Tianjin standard and the Engineering Quantity List Pricing guide of national grid company standard, project amount Inventory calculates the engineering that specification has worked out the different majors such as architectural engineering, power transformation engineering, work transmission line, Decorating Project Meter amount template.Project amount measure template be bill of quantities form table, list each list item project code, Project name, the measurement unit of project amount, computation rule, and it is embedded in calculation formula, the project amount of earth work measures template.Make The basic datas List of input such as length, width and height can be calculated corresponding project amount by the requirement of user's foundation template automatically.It will be each In the project amount metering template whole typing project management APP of a profession, template library is formed.Some inventories are calculated in specification No special item can also add manually new project amount metering template in template library.
2) highway bids amount inventory is imported in APP, generates project amount statistical table.
All list items that project amount metering will be listed according to highway bids amount inventory are measured.Due to highway bids Measuring inventory includes a large amount of list item, by manually item by item according to highway bids amount bill compilation project amount statistical table needs It takes a substantial amount of time.APP develops the function of automatically generating project amount statistical table.Highway bids amount inventory is imported first APP, since the project code of each list item is consistent in highway bids amount inventory and project amount metering template, APP can filter out project corresponding with highway bids amount inventory according to project code in project amount metering template library automatically And be combined, it obtains and the consistent project amount statistical table of highway bids amount list item.It is not only listed in table each The project code of list item, project name, the measurement unit of project amount, computation rule, inventory project amount (plan project amount), Practical Project amount and audit project amount 2 to be filled out also has been reserved to arrange.Wherein, Practical Project amount and audit two contents of project amount All it is embedded in quantities calculation formula.
3) site operation personnel carry out project amount daily and make a report on, and site supervision personnel audit in time, and owner project management department is timely Audit confirmation, obtains the project amount of tripartite's approval.
Site operation personnel find all list items actually occurred on the same day in project amount statistical form daily, click " Practical Project amount " position to be filled out, the project amount that can enter next stage make a report on interface.It is single according to computation rule therein and metering The basic datas such as length, width and height needed for the input of position, can automatically derive corresponding site operation Practical Project amount.Site supervision personnel " audit project amount " position to be filled out for all list items that the same day actually occurs is clicked, the project amount that can also enter next stage is filled out Press face, the project amount after filling audit, then reports owner to carry out audit confirmation, is constructed, supervised in the same fashion The project amount that reason, owner tripartite approve.To ensure that Measurement rules, unit and the format of project amount meet existing power industry Applicable quantities calculation specification also meets the audit requirement of technical economy personnel.And site supervision and owner are also defined in APP Audit time on equal no more than 3 working day, standardized auditing flow, ensure that the timeliness of audit.In addition, being recorded in table The time that project amount is made a report on and audited each time, making a report on during having retained and audit trace.
4) project amount confirmation form is generated.
The daily requirement of project amount makes a report on and audits until completion of works.Project amount confirmation form is progress payment, branch Important evidence file in clearing and final account for completed project application material.APP can add up to daily project amount, obtain Project amount, stage project amount, available total Finished engineering amount after completion of works is completed.It carrying out progress payment, dividing Format is generated when portion's clearing or final account for completed project application and meets the project amount confirmation form that technical economy audit requires, and can be downloaded and be printed, Timely, accurate foundation is provided for progress payment, branch's clearing and the application and audit of final account for completed project.
It travels in the 110kV project of transmitting and converting electricity of port in Tianjin, project amount is measured and managed using project management APP, Only 1 part of work in 30 parts of Cost Datas (progress payment, branch's clearing) that unit in charge of construction is reported to a higher authorities for approval by project management APP Journey amount metering inaccuracy, project amount accurate measurement rate have reached 96.7%, and project amount metering promptness rate has reached 100%, accordingly Ground, technical economy personnel also substantially increase the audit accuracy rate of progress payment, branch's clearing.
Project amount is measured and audited using project management APP cell phone client, it is convenient and efficient, it is reported and submitted with traditional construction unit Papery Cost Data is compared, and human and material resources, time cost are saved.Also, since the period of project amount metering contracts significantly Short, the real-time of project amount metering is improved, and is conducive to the development of branch's clearing.And it is no longer needed when final account for completed project primary Property statistical engineering all-work amount, it is only necessary to the project amount measured daily be summarized, the statistics of project amount is greatly reduced Time shortens the examination & approval time of final account for completed project.In addition, the data information of project amount is stored in cell phone application for a long time, respectively take part in building By inventory plan project amount and the progress of Practical Project amount can be completed in real time with Real-Time Sharing project amount information in unit related personnel Comparison, realizes the closed loop management to capital construction field engineering amount, and guarantee is constructed according to plan.Supervision Project portion cost manages personnel can To grasp the newest progress of engineering, the management instruction of cost control is assigned in time.
Illustrative description has been done to the present invention above, it should explanation, the case where not departing from core of the invention Under, any simple deformation, modification or other skilled in the art can not spend the equivalent replacement of creative work equal Fall into protection scope of the present invention.

Claims (6)

1. a kind of method for carrying out the metering of Grid Construction Project project amount based on project management APP, it is characterised in that: according to following Step carries out:
Step 1: establishment project amount measures template, and in typing project management APP, form template library;
Step 2: importing highway bids amount inventory, project amount statistical table is automatically generated;
Step 3: construction personnel carries out making a report on for project amount on project amount statistical table, supervisor and owner are to project amount Project amount in statistical table is audited;
Step 4: generating project amount confirmation when unit in charge of construction carries out progress payment, branch's clearing or final account for completed project application Book.
2. according to the method described in claim 1, it is characterized by: project amount metering template is bill of quantities form Table.
3. according to the method described in claim 1, it is characterized by: project amount metering template includes architectural engineering, power transformation The project amount metering template of engineering, work transmission line, Decorating Project.
4. according to the method described in claim 1, it is characterized by: the table includes project code, project name, metering list Position, computation rule explanation and project amount, the project amount include measurement item, the formula formed by measurement item and add up to, institute Stating measurement item includes width, length, depth, area.
5. according to the method described in claim 1, it is characterized by: the project amount metering template can be edited, editable Part include measurement item and its unit increase, delete, modifying and the addition and modification of formula.
6. according to the method described in claim 1, it is characterized by: the project amount statistical table is in project amount metering template On the basis of, it is attached with Practical Project amount and audit project amount to be entered.
CN201810968635.9A 2018-08-23 2018-08-23 A method of the metering of Grid Construction Project project amount is carried out based on project management APP Pending CN109409634A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810968635.9A CN109409634A (en) 2018-08-23 2018-08-23 A method of the metering of Grid Construction Project project amount is carried out based on project management APP

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810968635.9A CN109409634A (en) 2018-08-23 2018-08-23 A method of the metering of Grid Construction Project project amount is carried out based on project management APP

Publications (1)

Publication Number Publication Date
CN109409634A true CN109409634A (en) 2019-03-01

Family

ID=65463678

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810968635.9A Pending CN109409634A (en) 2018-08-23 2018-08-23 A method of the metering of Grid Construction Project project amount is carried out based on project management APP

Country Status (1)

Country Link
CN (1) CN109409634A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109948929A (en) * 2019-03-18 2019-06-28 国网安徽省电力有限公司安庆供电公司 A kind of construction method and system of power distribution network coordinated management model
CN110322226A (en) * 2019-07-03 2019-10-11 广东至衡工程管理有限公司 A kind of project supervision method and system
CN110348799A (en) * 2019-05-23 2019-10-18 北京新研汇医药研发有限公司 A kind of clinical research monitor work inspection method and system
CN110503384A (en) * 2019-07-12 2019-11-26 广州穗能通综合能源有限责任公司 Power index generation method and device, computer equipment and storage medium
CN112000724A (en) * 2020-08-27 2020-11-27 四川公路桥梁建设集团有限公司 Highway engineering collaborative computation amount information management system based on custom formula
CN112669019A (en) * 2021-01-31 2021-04-16 四川沿江攀宁高速公路有限公司 Engineering data automatic filing method based on engineering quantity list and quality inspection data correlation interaction
CN113094794A (en) * 2021-04-21 2021-07-09 四川省交通建设集团股份有限公司 Automatic metering and accounting method and system based on BIM and GIS technology
CN114792232A (en) * 2022-05-20 2022-07-26 中国长江三峡集团有限公司 Method, system and equipment for processing engineering quantity and readable storage medium
CN117391332A (en) * 2023-09-07 2024-01-12 中铁一局集团有限公司 Engineering quantity calculation list hanging method, device, computer equipment and storage medium

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101504741A (en) * 2009-02-18 2009-08-12 路桥集团国际建设股份有限公司 Intelligent metering management system and method for construction engineering
US20110014590A1 (en) * 2008-12-29 2011-01-20 Jason Scott Project Management Guidebook and Methodology
CN102722784A (en) * 2012-05-23 2012-10-10 成都鹏业软件股份有限公司 Method for setting list or quota rapidly
CN103136595A (en) * 2011-11-29 2013-06-05 北京建龙重工集团有限公司 On-line management method for project budget generation by material and labor cost analysis
CN104978307A (en) * 2015-06-25 2015-10-14 中铁四局集团有限公司 List processing method and apparatus
CN105243518A (en) * 2015-11-16 2016-01-13 苏州天地微易智能科技有限公司 Municipal engineering measurement management system and method thereof
CN106910011A (en) * 2017-02-06 2017-06-30 广东华联软件科技有限公司 A kind of Cost Index analysis method and system
CN107945000A (en) * 2017-11-24 2018-04-20 国网内蒙古东部电力有限公司 A kind of power grid technological transformation overhaul engineering settlement management system and its control method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110014590A1 (en) * 2008-12-29 2011-01-20 Jason Scott Project Management Guidebook and Methodology
CN101504741A (en) * 2009-02-18 2009-08-12 路桥集团国际建设股份有限公司 Intelligent metering management system and method for construction engineering
CN103136595A (en) * 2011-11-29 2013-06-05 北京建龙重工集团有限公司 On-line management method for project budget generation by material and labor cost analysis
CN102722784A (en) * 2012-05-23 2012-10-10 成都鹏业软件股份有限公司 Method for setting list or quota rapidly
CN104978307A (en) * 2015-06-25 2015-10-14 中铁四局集团有限公司 List processing method and apparatus
CN105243518A (en) * 2015-11-16 2016-01-13 苏州天地微易智能科技有限公司 Municipal engineering measurement management system and method thereof
CN106910011A (en) * 2017-02-06 2017-06-30 广东华联软件科技有限公司 A kind of Cost Index analysis method and system
CN107945000A (en) * 2017-11-24 2018-04-20 国网内蒙古东部电力有限公司 A kind of power grid technological transformation overhaul engineering settlement management system and its control method

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109948929A (en) * 2019-03-18 2019-06-28 国网安徽省电力有限公司安庆供电公司 A kind of construction method and system of power distribution network coordinated management model
CN110348799A (en) * 2019-05-23 2019-10-18 北京新研汇医药研发有限公司 A kind of clinical research monitor work inspection method and system
CN110322226A (en) * 2019-07-03 2019-10-11 广东至衡工程管理有限公司 A kind of project supervision method and system
CN110503384A (en) * 2019-07-12 2019-11-26 广州穗能通综合能源有限责任公司 Power index generation method and device, computer equipment and storage medium
CN110503384B (en) * 2019-07-12 2021-09-28 广州穗能通能源科技有限责任公司 Power index generation method and device, computer equipment and storage medium
CN112000724A (en) * 2020-08-27 2020-11-27 四川公路桥梁建设集团有限公司 Highway engineering collaborative computation amount information management system based on custom formula
CN112669019A (en) * 2021-01-31 2021-04-16 四川沿江攀宁高速公路有限公司 Engineering data automatic filing method based on engineering quantity list and quality inspection data correlation interaction
CN113094794A (en) * 2021-04-21 2021-07-09 四川省交通建设集团股份有限公司 Automatic metering and accounting method and system based on BIM and GIS technology
CN114792232A (en) * 2022-05-20 2022-07-26 中国长江三峡集团有限公司 Method, system and equipment for processing engineering quantity and readable storage medium
CN114792232B (en) * 2022-05-20 2023-07-14 中国长江三峡集团有限公司 Engineering quantity processing method, system, equipment and readable storage medium
CN117391332A (en) * 2023-09-07 2024-01-12 中铁一局集团有限公司 Engineering quantity calculation list hanging method, device, computer equipment and storage medium

Similar Documents

Publication Publication Date Title
CN109409634A (en) A method of the metering of Grid Construction Project project amount is carried out based on project management APP
CN113094794B (en) Automatic metering and accounting method and system based on BIM and GIS technology
CN110335017A (en) One kind being based on BIM project amount charging Informatization Cooperative working method
CN103679373A (en) Full chain budget data processing system and method for production infrastructure standard cost system
CN110942204A (en) New power grid capital construction project annual planning model construction method and system
CN107945000A (en) A kind of power grid technological transformation overhaul engineering settlement management system and its control method
CN114219289A (en) Construction cost control method based on BIM and Internet of things technology
CN105930517A (en) Tax data processing method and apparatus
CN115983803A (en) Cost subject dictionary setting method and system
CN114418369A (en) Metering payment method and system based on BIM (building information modeling)
CN108876577A (en) The system that multilingual mobile visualization collects processing information
CN111415133A (en) Shield project cost and benefit monitoring system
CN109345053A (en) A kind of electricity power engineering credit requirement methodology
CN114444913A (en) Power grid infrastructure construction engineering quantity and value quantity connection business model construction method and system
Xiao et al. Study on Construction Engineering Management Based on BIM from the perspective of big data
Cunningham The function and format of bills of quantities: an Irish context
CN113537624A (en) Rail transit engineering construction progress deviation prediction early warning management method
Kehily et al. Linking effective whole life cycle cost data to parametric building information models using BIM technologies
Zeng et al. Check for updates Research on the Application of BIM Technology in the Whole Process Cost Management of Construction Project
Han Retracted: Research on Construction Engineering Cost Management Based on BIM Technology
Marović et al. Process approach in modelling Croatian construction contract management practice
Lan BIM-based cost management of large engineering projects
Liu et al. Application of BIM technology in dynamic management and control of construction project costs
Geng et al. Comparative Study on Simulation of Grid and Non-grid Management Process of Farmland
Chen Analysis and Simulation Demonstration of Pricing Rules for Construction Projects

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190301