CN109386289A - 一种爆破、封孔、注浆一体化施工方法 - Google Patents
一种爆破、封孔、注浆一体化施工方法 Download PDFInfo
- Publication number
- CN109386289A CN109386289A CN201910003187.3A CN201910003187A CN109386289A CN 109386289 A CN109386289 A CN 109386289A CN 201910003187 A CN201910003187 A CN 201910003187A CN 109386289 A CN109386289 A CN 109386289A
- Authority
- CN
- China
- Prior art keywords
- explosion
- pvc pipe
- hole
- upper section
- lower section
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/006—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B33/00—Sealing or packing boreholes or wells
- E21B33/10—Sealing or packing boreholes or wells in the borehole
- E21B33/13—Methods or devices for cementing, for plugging holes, crevices, or the like
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/001—Improving soil or rock, e.g. by freezing; Injections
Abstract
本发明公开了一种爆破、封孔、注浆一体化施工方法,包括如下步骤:S1、钻爆破注浆孔;S2、在爆破注浆孔中放入PVC管;S3、在所述下段中装入若干炸药包,各个炸药包沿所述下段的长度方向间隔布置;S4、爆破;S5、爆破后,对所述PVC管的上段进行注浆,浆液在压力作用下通过上段的管壁上的通孔渗入地层,对地层进行加固。本发明可以实现爆破、封孔和注浆一体化施工,实现连贯的工序,有助于缩短工期、节省人力成本。
Description
技术领域
本发明涉及盾构施工技术领域,具体涉及一种爆破、封孔、注浆一体化施工方法。
背景技术
在花岗岩地层中,隧道断面存在花岗岩球状风化体或坚硬岩体侵入隧道的情况,工程中可采用钻孔爆破的办法将岩体破碎后,盾构再掘进通过。但爆破后必须对爆破孔进行封堵,且对爆破后的地层进行注浆加固,以防后续盾构掘进产生漏浆、漏气、滞排等问题。
目前,工程中对于爆破、封孔及后续的注浆加固都是分开的,在各工序间不连贯,通常是爆破完成后,在地面重新对爆破孔进行注浆封堵,后续地层加固还需重新钻孔注浆。工序上的不连贯会带来的工期的浪费,还会导致重复钻孔,增加地面开挖力度。
发明内容
针对现有技术的不足,本发明旨在提供一种爆破、封孔、注浆一体化施工方法,可以实现爆破、封孔和注浆一体化施工,实现连贯的工序,有助于缩短工期、节省人力成本。
为了实现上述目的,本发明采用如下技术方案:
一种爆破、封孔、注浆一体化施工方法,包括如下步骤:
S1、钻爆破注浆孔:所述爆破注浆孔的上端与地面连通,下端穿过隧道顶板达到岩体以下或当需要处理的是隧道底部的基岩侵入时达到隧道底板以下;其中所述爆破注浆孔位于隧道顶板以上的部分为注浆部分,位于隧道顶板以下的部分为爆破部分;
S2、在爆破注浆孔中放入PVC管,所述PVC管分为上段和下段,所述PVC管的上段位于隧道顶板以上,下段位于所述隧道顶板以下,两者之间相连接;所述PVC管的上段的管壁均匀布设有若干通孔;
S3、在所述PVC管的下段中装入若干炸药包,各个岩体均有炸药包的位置与之相对应,且所述PVC管的下段中还采用下段堵塞物进行堵塞,所述堵塞物包括砂子、混凝土和包装好的水泥;所述PVC管的上段和下段之间的连接处设置有封孔炸药包,所述封孔炸药包用于炸断所述PVC管的上段和下段之间的连接;
S4、爆破时,先引爆所述封孔炸药包,将PVC管的上段和下段的连接炸断,然后引爆其他炸药包,所述PVC管的下段在爆破过程被炸碎,包装好的水泥在爆破冲击作用下包装裂开,水泥、砂子和混凝土在爆破部分内进一步完成融合,从而实现爆破部分的封堵;
S5、爆破后,通过所述PVC管的上段的上端进行注浆,浆液在压力作用下通过PVC管的上段的管壁上的通孔渗入地层,对地层进行加固。
进一步地,步骤S1中,所述爆破注浆孔的下端穿过隧道顶板达到岩体以下至少1.5m处或当需要处理的是隧道底部的基岩侵入时达到隧道底板以下至少1.5m处。
进一步地,步骤S2中,所述上段和下段之间为弱性连接。
进一步地,步骤S2中,所述PVC的上段的上端通过地面固定件与地面相固定。
进一步地,步骤S3中,所述PVC管的上段中采用上段堵塞物进行堵塞。
本发明的有益效果在于:本发明可以实现爆破、封孔和注浆一体化施工,实现连贯的工序,有助于缩短工期、节省人力成本。
附图说明
图1为本发明实施例中的实施示意图。
具体实施方式
以下将结合附图对本发明作进一步的描述,需要说明的是,本实施例以本技术方案为前提,给出了详细的实施方式和具体的操作过程,但本发明的保护范围并不限于本实施例。
一种爆破、封孔、注浆一体化施工方法,包括如下步骤:
S1、钻爆破注浆孔:所述爆破注浆孔的上端与地面100连通,下端穿过隧道顶板101达到岩体102以下1.5m处或当需要处理的是隧道底部的基岩侵入时达到隧道底板103以下1.5m处;其中所述爆破注浆孔位于隧道顶板101以上的部分为注浆部分,位于隧道顶板101以下的部分为爆破部分;如图1所示;
S2、在爆破注浆孔中放入PVC管,所述PVC管分为上段104和下段105,所述PVC管的上段104位于隧道顶板101以上(即位于注浆部分内),下段105位于所述隧道顶板101以下(即位于爆破部分内),两者之间弱性连接(例如可将PVC管的上段和下段的连接部分设置成比其他部分薄);所述PVC管的上段的管壁均匀布设有若干通孔108;
在本实施例中,所述PVC的上段的上端通过地面固定件109与地面相固定。
S3、在所述PVC管的下段中装入若干炸药包106,各个岩体均有炸药包的位置与之相对应(可根据岩块体量整段或者分段布置),且所述PVC管的下段中还采用下段堵塞物110进行堵塞,所述堵塞物包括砂子、混凝土和包装好的水泥(可采用纸袋进行包装);所述PVC管的上段104和下段105之间的弱性连接处设置有封孔炸药包107,所述封孔炸药包107用于炸断所述PVC管的上段和下段之间的连接;
在本实施例中,所述PVC管的上段中设有上段堵塞物111,具体可以采用碎石。
S4、爆破时,先引爆所述封孔炸药包,将PVC管的上段和下段的连接炸断,然后引爆其他炸药包,所述PVC管的下段在爆破过程被炸碎,包装好的水泥在爆破冲击作用下包装裂开,水泥、砂子和混凝土在爆破部分内进一步完成融合,从而实现爆破部分的封堵;
S5、爆破后,对PVC管的上段进行适当清孔,通过所述PVC管的上段的上端进行注浆,浆液在压力作用下通过PVC管的上段的管壁上的通孔渗入地层,对地层进行加固。
对于本领域的技术人员来说,可以根据以上的技术方案和构思,给出各种相应的改变和变形,而所有的这些改变和变形,都应该包括在本发明权利要求的保护范围之内。
Claims (5)
1.一种爆破、封孔、注浆一体化施工方法,其特征在于,包括如下步骤:
S1、钻爆破注浆孔:所述爆破注浆孔的上端与地面连通,下端穿过隧道顶板达到岩体以下或当需要处理的是隧道底部的基岩侵入时达到隧道底板以下;其中所述爆破注浆孔位于隧道顶板以上的部分为注浆部分,位于隧道顶板以下的部分为爆破部分;
S2、在爆破注浆孔中放入PVC管,所述PVC管分为上段和下段,所述PVC管的上段位于隧道顶板以上,下段位于所述隧道顶板以下,两者之间相连接;所述PVC管的上段的管壁均匀布设有若干通孔;
S3、在所述PVC管的下段中装入若干炸药包,各个岩体均有炸药包的位置与之相对应,且所述PVC管的下段中还采用下段堵塞物进行堵塞,所述堵塞物包括砂子、混凝土和包装好的水泥;所述PVC管的上段和下段之间的连接处设置有封孔炸药包,所述封孔炸药包用于炸断所述PVC管的上段和下段之间的连接;
S4、爆破时,先引爆所述封孔炸药包,将PVC管的上段和下段的连接炸断,然后引爆其他炸药包,所述PVC管的下段在爆破过程被炸碎,包装好的水泥在爆破冲击作用下包装裂开,水泥、砂子和混凝土在爆破部分内进一步完成融合,从而实现爆破部分的封堵;
S5、爆破后,通过所述PVC管的上段的上端进行注浆,浆液在压力作用下通过PVC管的上段的管壁上的通孔渗入地层,对地层进行加固。
2.根据权利要求1所述的方法,其特征在于,步骤S1中,所述爆破注浆孔的下端穿过隧道顶板达到岩体以下至少1.5m处或当需要处理的是隧道底部的基岩侵入时达到隧道底板以下至少1.5m处。
3.根据权利要求1所述的方法,其特征在于,步骤S2中,所述上段和下段之间为弱性连接。
4.根据权利要求1所述的方法,其特征在于,步骤S2中,所述PVC的上段的上端通过地面固定件与地面相固定。
5.根据权利要求1所述的方法,其特征在于,步骤S3中,所述PVC管的上段中采用上段堵塞物进行堵塞。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910003187.3A CN109386289B (zh) | 2019-01-03 | 2019-01-03 | 一种爆破、封孔、注浆一体化施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910003187.3A CN109386289B (zh) | 2019-01-03 | 2019-01-03 | 一种爆破、封孔、注浆一体化施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109386289A true CN109386289A (zh) | 2019-02-26 |
CN109386289B CN109386289B (zh) | 2020-09-01 |
Family
ID=65430929
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910003187.3A Active CN109386289B (zh) | 2019-01-03 | 2019-01-03 | 一种爆破、封孔、注浆一体化施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109386289B (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110656947A (zh) * | 2019-10-30 | 2020-01-07 | 中铁隧道局集团有限公司 | 海底基岩凸起段的掘进方法 |
CN110685716A (zh) * | 2019-10-12 | 2020-01-14 | 中铁隧道局集团有限公司 | 孤石爆破处理后的袖阀管注浆方法 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101713624A (zh) * | 2009-11-17 | 2010-05-26 | 广东爆破工程有限公司 | 地下隐蔽岩体地面钻孔爆破破碎方法 |
CN102518442A (zh) * | 2011-12-14 | 2012-06-27 | 中铁十二局集团第二工程有限公司 | 一种盾构掘进溶沟地段孤石群的处理方法 |
KR101368999B1 (ko) * | 2010-06-30 | 2014-02-28 | 유재호 | 관거매설공의 보강이 가능한 관거 추진장치 및 이를 이용한 관거 시공 공법 |
DE102014110132B3 (de) * | 2014-07-18 | 2015-10-15 | Werner Möbius Engineering GmbH | Schildvortriebsmaschine (SVM) und Verfahren zum Lockern und/oder Zerkleinern von Steinen in einer SVM |
CN106524844A (zh) * | 2016-09-26 | 2017-03-22 | 中铁十六局集团北京轨道交通工程建设有限公司 | 一种盾构隧道沿线孤石勘查和爆破处理的施工方法 |
CN109000525A (zh) * | 2018-08-15 | 2018-12-14 | 中铁十六局集团有限公司 | 一种盾构掘进上软下硬地层预裂爆破施工方法 |
CN109026037A (zh) * | 2018-09-25 | 2018-12-18 | 中铁十二局集团有限公司 | 盾构隧道遇基岩孤石地层预处理施工方法 |
-
2019
- 2019-01-03 CN CN201910003187.3A patent/CN109386289B/zh active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101713624A (zh) * | 2009-11-17 | 2010-05-26 | 广东爆破工程有限公司 | 地下隐蔽岩体地面钻孔爆破破碎方法 |
KR101368999B1 (ko) * | 2010-06-30 | 2014-02-28 | 유재호 | 관거매설공의 보강이 가능한 관거 추진장치 및 이를 이용한 관거 시공 공법 |
CN102518442A (zh) * | 2011-12-14 | 2012-06-27 | 中铁十二局集团第二工程有限公司 | 一种盾构掘进溶沟地段孤石群的处理方法 |
DE102014110132B3 (de) * | 2014-07-18 | 2015-10-15 | Werner Möbius Engineering GmbH | Schildvortriebsmaschine (SVM) und Verfahren zum Lockern und/oder Zerkleinern von Steinen in einer SVM |
CN106524844A (zh) * | 2016-09-26 | 2017-03-22 | 中铁十六局集团北京轨道交通工程建设有限公司 | 一种盾构隧道沿线孤石勘查和爆破处理的施工方法 |
CN109000525A (zh) * | 2018-08-15 | 2018-12-14 | 中铁十六局集团有限公司 | 一种盾构掘进上软下硬地层预裂爆破施工方法 |
CN109026037A (zh) * | 2018-09-25 | 2018-12-18 | 中铁十二局集团有限公司 | 盾构隧道遇基岩孤石地层预处理施工方法 |
Non-Patent Citations (1)
Title |
---|
吴载清: "跨海盾构区间孤石及基岩凸起处理施工关键技术", 《江西建材》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110685716A (zh) * | 2019-10-12 | 2020-01-14 | 中铁隧道局集团有限公司 | 孤石爆破处理后的袖阀管注浆方法 |
CN110656947A (zh) * | 2019-10-30 | 2020-01-07 | 中铁隧道局集团有限公司 | 海底基岩凸起段的掘进方法 |
CN110656947B (zh) * | 2019-10-30 | 2021-07-23 | 中铁隧道局集团有限公司 | 海底基岩凸起段的掘进方法 |
Also Published As
Publication number | Publication date |
---|---|
CN109386289B (zh) | 2020-09-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101603431B (zh) | 一种突出危险煤层石门揭煤加固方法 | |
CN106703814A (zh) | 暗挖地铁车站洞桩施工方法 | |
CN106643361A (zh) | 超大暗挖隧道双侧壁上下导坑开挖施工方法 | |
CN107023300A (zh) | 一种采用棚护法建造地铁车站的施工方法 | |
AU2021355609B2 (en) | Method for mining by filling and caving | |
CN110130936B (zh) | 一种盾构掘进过程中突遇未处理溶洞或裂隙的施工方法 | |
CN106869936A (zh) | 一种适于陡坡地形的露天采矿新方法 | |
CN106401645A (zh) | 一种基于钻孔卸压的深部高应力巷道卸压支护协调控制方法 | |
CN103306713A (zh) | 一种高突煤层穿层钻孔网络化加固方法 | |
CN109209392A (zh) | 适用于大断面隧道ⅳ-ⅴ级围岩的全环开挖方法 | |
CN114233385B (zh) | 一种斜井井筒突泥涌水的治理方法 | |
CN109026026A (zh) | 下穿既有管廊的大断面多线多连拱暗挖隧道群的施工方法 | |
CN108678772A (zh) | 一种用于富水砂砾层巷道的多级层次支护装置及其施工方法 | |
CN103899351A (zh) | 一种处理复杂采空区的充填加固方法 | |
CN104033160A (zh) | 一种适用于软土地层的浅埋暗挖隧道新型支护方法 | |
CN106014443B (zh) | 一种预防沿空留巷的巷道底鼓及墙体滑移的方法 | |
CN105156114A (zh) | 一种交岔点处巷道的扩修及加固方法 | |
CN109386289A (zh) | 一种爆破、封孔、注浆一体化施工方法 | |
CN109057802A (zh) | 大断面浅埋隧道下穿高速公路施工方法 | |
KR101746654B1 (ko) | 광산 대규모 채굴공동 보강을 위한 골재 그라우트 기둥 시공 방법 | |
Yuan et al. | The effect of burnt rock on inclined shaft in shallow coal seam and its control technology | |
CN107165641B (zh) | 薄层破碎硬质岩石地层中大倾角扶梯通道反方向暗挖施工方法 | |
CN105888708A (zh) | 一种基于雷达探测技术的巷道冒顶区探测及处理方法 | |
CN105672309A (zh) | 岩溶地区嵌岩桩成孔可回收超长钢护筒护壁方法 | |
CN111271066B (zh) | 一种偏压进洞的斜交正做施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |