CN109374049A - A kind of tunnel wall rock deformation monitoring alarm - Google Patents

A kind of tunnel wall rock deformation monitoring alarm Download PDF

Info

Publication number
CN109374049A
CN109374049A CN201811253185.1A CN201811253185A CN109374049A CN 109374049 A CN109374049 A CN 109374049A CN 201811253185 A CN201811253185 A CN 201811253185A CN 109374049 A CN109374049 A CN 109374049A
Authority
CN
China
Prior art keywords
module
monitoring
signal
sensor group
communication module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811253185.1A
Other languages
Chinese (zh)
Inventor
高明忠
马辉
张志龙
谢晶
陈领
刘强
李聪
陈海亮
彭高友
陆彤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan University
Original Assignee
Sichuan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan University filed Critical Sichuan University
Priority to CN201811253185.1A priority Critical patent/CN109374049A/en
Publication of CN109374049A publication Critical patent/CN109374049A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01DMEASURING NOT SPECIALLY ADAPTED FOR A SPECIFIC VARIABLE; ARRANGEMENTS FOR MEASURING TWO OR MORE VARIABLES NOT COVERED IN A SINGLE OTHER SUBCLASS; TARIFF METERING APPARATUS; MEASURING OR TESTING NOT OTHERWISE PROVIDED FOR
    • G01D21/00Measuring or testing not otherwise provided for
    • G01D21/02Measuring two or more variables by means not covered by a single other subclass
    • GPHYSICS
    • G08SIGNALLING
    • G08CTRANSMISSION SYSTEMS FOR MEASURED VALUES, CONTROL OR SIMILAR SIGNALS
    • G08C17/00Arrangements for transmitting signals characterised by the use of a wireless electrical link
    • G08C17/02Arrangements for transmitting signals characterised by the use of a wireless electrical link using a radio link

Abstract

The invention discloses a kind of tunnel wall rock deformation monitoring alarms, including sequentially connected sensor group, automatic collection control module, locating module, communication module, monitoring and signal processing software module, long-distance radio communication module and live acoustooptic alarm system module, automatic collection control module be used for control sensor components not acquire signal period and transmission signal frequency, sensor group sends monitoring and signal processing software module for collected signal by communication module, monitoring and signal processing software module are for handling the signal collected, and according to the actual situation output signal respectively to text display screen, long-distance radio communication module and live acoustooptic alarm system module, the remote signal of long-distance radio communication module output signal to construction headquarters receives terminal.The present invention provides the safety coefficient of constructing tunnel operation significantly, to ensure the life of people and the safety of property, is conducive to the promotion and implementation application of large area.

Description

A kind of tunnel wall rock deformation monitoring alarm
Technical field
The present invention relates to tunnel surrounding monitoring technical field, specially a kind of tunnel wall rock deformation monitoring alarm.
Background technique
With the fast development of nation-building, there are some new features in current highway, railway tunnel: section is big, Tunnel is long, complex geologic conditions, and the poor strata condition of side easily causes Tunnel Landslide, water burst in face of tunnel piercing.These because Element not only technically brings great difficulty to constructing tunnel, also usually because burst accident leads to personal injury, construction delay, To cause huge economic loss, while also resulting in the great attention of state supervision department.
Country's tunnel surrounding monitoring at present measures first is that generalling use contact class device, and inefficiency consumes a large amount of people Power and financial resources, and observation effect is bad, there are problems that human factor influence is excessive causes monitoring result to be distorted;Second is that some are used More advanced BJSD-3 laser tunnel cross-section detector, total station etc., but do not have auto-alarm function, it is unable to real-time monitoring, There is man's activity.
Summary of the invention
The purpose of the present invention is to provide a kind of tunnel wall rock deformation monitoring alarms, to solve in above-mentioned background technique The problem of proposition.
In order to solve the above technical problem, the present invention provides following technical solutions: a kind of tunnel wall rock deformation monitoring, alarming Device, including sequentially connected sensor group, automatic collection control module, locating module, communication module, monitoring and signal processing Software module, long-distance radio communication module and live acoustooptic alarm system module, the sensor group, automatic collection control mould Block, locating module, communication module, monitoring and signal processing software module, long-distance radio communication module and live sound-light alarm system System module is connected with the power supply module respectively, and the sensor group for monitoring displacement deformation, the pressure change of country rock inner wall respectively Change, concrete strain power changes, temperature change and variation in water pressure information, the automatic collection control module are used to control the biography Sensor group acquires the period of signal respectively and sends the frequency of the signal, the locating module and monitoring and signal processing software Module connection, for obtaining the country rock position gone wrong in real time, the sensor group passes through communication module for collected signal It is sent to monitoring and signal processing software module, the monitoring and signal processing software module are for handling the letter collected Number, and according to the actual situation output signal respectively to text display screen, long-distance radio communication module and live acoustooptic alarm system The remote signal of module, the long-distance radio communication module output signal to construction headquarters receives terminal.
Further, the locating module includes the wireless biography that signal strength is sended over for incuding other positioning devices Sensor group and the location processor that position calculating is carried out according to the induction result of wireless sensor.
Further, the sensor group include convergence gauge, total station, displacement sensor, pressure cell, anchor ergometer, Reinforcing rib meter, strain gauge, temperature sensor and osmometer, and the convergence gauge, total station, displacement sensor, pressure cell, anchor pole are surveyed Power meter, reinforcing rib meter, strain gauge, temperature sensor and osmometer are connect with automatic collection control module respectively.
Further, the automatic collection control module includes sequentially connected timer and controller, the timer It is connect with sensor group, the controller is connect with communication module.
Further, the period of the automatic collection control module control sensor group IV grades of country rock signals of acquisition is 20min-3h。
Further, the period that the automatic collection control module control sensor group acquires V grades of country rock signals is 7min- 10min。
Further, the monitoring and signal processing software module include single-chip microcontroller.
Compared with prior art, the beneficial effects obtained by the present invention are as follows being: the present invention passes through in tunnel surrounding monitoring section Various sensors, the related data of real-time automatic collecting country rock are installed, automatic collection control module controls sensor and acquires signal Period and send the frequency of signal, monitoring and signal processing software module are transferred signals to by communication module, monitoring and Signal processing software module receives and processes data, and compares with associated tunnel job specfication, the threshold value of regulatory requirements, connects Close or data beyond threshold value issue alarm signal, and warning construction personnel takes care, can be pre- in time when something goes wrong It is alert, while can also enter the site of an accident without personnel and be provided with a large amount of relevant information, the safety of system is improved, in addition, Other than it can monitor the state of country rock, moreover it is possible to have positioning function, locating module can obtain the country rock to go wrong in real time Position, enables staff orientation problem position rapidly, and the present invention can monitor the unstable country rock of construction tunnel in real time Deformation is to be issued on warning information to avoid the generation of accident.
Detailed description of the invention
Attached drawing is used to provide further understanding of the present invention, and constitutes part of specification, with reality of the invention It applies example to be used to explain the present invention together, not be construed as limiting the invention.In the accompanying drawings:
Fig. 1 is the structural diagram of the present invention.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Referring to Fig. 1, the present invention provides a kind of technical solution: a kind of tunnel wall rock deformation monitoring alarm, including it is suitable It is sensor group, automatic collection control module, locating module, communication module, monitoring and the signal processing software module of secondary connection, remote Journey wireless communication module and live acoustooptic alarm system module, the sensor group, automatic collection control module, locating module, Communication module, monitoring and signal processing software module, long-distance radio communication module and live acoustooptic alarm system module respectively with Power module is connected, and the sensor group for monitoring displacement deformation, pressure change, the concrete strain of country rock inner wall respectively Power variation, temperature change and variation in water pressure information, the automatic collection control module are not adopted for controlling the sensor components Collect the period of signal and send the frequency of the signal, the locating module is connect with monitoring and signal processing software module, is used In obtaining the country rock position gone wrong in real time, the sensor group by communication module by collected signal be sent to monitoring and Signal processing software module, the monitoring and signal processing software module are used to handle the signal collected, and according to reality Border situation output signal is described remote respectively to text display screen, long-distance radio communication module and live acoustooptic alarm system module The remote signal that journey wireless communication module outputs signal to construction headquarters receives terminal.
Specifically, the locating module includes the wireless sensing for sending over signal strength for incuding other positioning devices Device group and the location processor that position calculating is carried out according to the induction result of wireless sensor, locating module can obtain out in real time The country rock position of problem, enable staff rapidly orientation problem position.
Specifically, sensor group includes for monitoring the convergent convergence gauge of tunnel surrounding;For monitoring vault sinking, earth's surface The automatic total instruments of sinking;For monitoring the multi-point displacement sensor of country rock body sedimentation;For monitoring pressure from surrounding rock and two layers The pressure cell of pressure between shield;For monitoring the anchor ergometer of anchor axial force;For monitoring the reinforcing rib meter of reinforcement stresses;With In the strain gauge of monitoring steel arch-shelf strain;For monitoring the concrete strain gauge of two lining concrete stresses;For monitoring explosion shake Dynamic acceleration transducer;For monitoring the osmometer of seepage pressure;For monitoring the flowmeter of water flow;For monitoring tunnel The temperature sensor of temperature change in hole.By sensor group to the information such as the deformation, rock mass sedimentation, pressure of country rock inner wall into Row acquisition sends monitoring and signal processing software module for collected information using communication module, at monitoring and signal Reason software module the relevant information of country rock is handled, if there is information do not meet associated tunnel job specfication, regulation is wanted The data asked, monitoring and signal processing software module control live acoustooptic alarm system module and issue alarm signal, warning construction Personnel take care.
Specifically, country rock inner wall displacement measurement is the displacement for monitoring country rock different depth, the loosening of country rock after excavating is judged Range.Monitoring measurement section is set according to tunnel surrounding geological conditions, 5 gaging holes, hole is arranged in side wall and arch in each section Deep 3.5-5m, aperture are Ф 50, and every hole buries 3 steel chord type multipoint displacement meters, so that each measuring point is combined closely with the wall of a borehole, rock It drives measuring point to move together when layer is mobile, measures the displacement of country rock different depth.It is assumed that farthest point layout is in stabilizing surrounding rock It is interior, and then shift value of each measuring point relative to farthest measuring point can be found out.When the depth of burying degree of farthest measuring point is bigger, originally experience The influence of excavation is smaller, and measured shift value is closer to absolute value.
Specifically, anchor ergometer is according to tunnel surrounding geological conditions or setting monitoring measurement section, it is all in each section Radial bore is pressed on side, arranges 5 gaging holes in tunnel-side and arch, the steel chord type bolt shaft of 3 measuring points of installation in each gaging hole Power meter, the axle power of measuring anchor rod different depth.Slip casting keeps anchor axial force meter close with country rock in hole, installs stable use Digital readout instrument, which is surveyed, reads initial reading.
Specifically, bracing members internal force measurement is to monitor the stress condition of bracing members, steel arch-shelf and pneumatically placed concrete are understood to enclosing The combination supporting effect of rock;The actual working state for understanding steel arch-shelf, decides whether to take reinforcement measure depending on concrete condition; Judge preliminary bracing bearing capacity.Bracing members internal force using reinforcing rib meter measure, each monitoring section along tunnel vault, two haunches and Totally 5 reinforcing rib meters are monitored two abutment walls, pay attention to carrying out watering cooling in the welding process, embedded to finish and survey after the stabilization that cools down Read initial reading.
Specifically, each monitoring section along tunnel vault, two haunches and two abutment walls totally 5 positions in gunite concrete and Concrete strain gauge is buried in secondary lining concrete to be measured.It is fixed when embedded with Steel bar rack, makes concrete strain gauge Impact direction is the tangential direction of tunnel contour.
Specifically, needing to be monitored concussion of blasting, using acceleration transducer when Nearby Structure builds tunnel Dynamometry concussion of blasting.
Specifically, if there is tunnel occur earth's surface infiltration situation, need to seepage pressure, water flow is monitored, and is adopted Seepage pressure and water flow are monitored respectively with osmometer and flowmeter.Temperature sensor is used to monitor the real-time temperature in Tunnel Degree.
In the present embodiment, the frequency in the period of automatic collection control module control sensor group acquisition signal and transmission signal Rate.Automatic collection control module includes sequentially connected timer and controller, and timer is used for acquisition signal period and hair The frequency for the number of delivering letters carries out timing, controller control sensor group work after reaching the time for controller.Presently relevant rule Model, regulatory requirements the monitoring period be unable to satisfy the surrounding rock stability monitoring requirement of self-stable ability difference, i.e., artificial monitoring method is not It can effective monitoring weak surrounding rock stability.Tunnel Excavation Monitoring cycle T is not greater than tunnel stand up time T0, otherwise cannot be effective Monitor the stability of country rock.The relationship that time and space index from China railways tunnel based on RMR establish can be seen that The tunnel of 10.5m span, the average stand up time of V grades of country rocks only have 30 minutes, and the stabilization time of IV grades of country rocks also only has 10 Hour.It is therefore to be understood that the speed of surrouding rock deformation speed, the number of monitoring should be enough, if be less than 5 times, surrouding rock deformation The trend of curve is unobvious, and therefore, monitoring number should not be less than 5 times.Based on analysis above, it can be deduced that monitor the period and enclose Relational expression between rock stand up time, i.e. stand up time T subtract buries a little before time Ta, should be greater than pendulous frequency multiplied by monitoring cycle this It is only an adequate condition.According to above analysis, effective monitoring is carried out to rock stability, that is to say, that monitoring Period must be sufficiently small, should can just be met the requirements using automatic monitoring.Therefore, automatic collection control sensor group acquires IV grades and encloses The period of rock signal is 20min-3h.Automatic collection control module control sensor group acquire V grades of country rock signals period be 7min-10min.Different grades of Rock Mass to could carry out rock stability using different monitoring cycles effective Monitoring.
Specifically, the monitoring and signal processing software module include single-chip microcontroller.
As stated above, the present invention is by installing various sensors, real-time automatic collecting country rock in tunnel surrounding monitoring section Related data, automatic collection control module control sensor acquisition signal period and send signal frequency, pass through communication Module transfers signals to monitoring and signal processing software module, and monitoring and signal processing software module receive and process data, And compared with associated tunnel job specfication, the threshold value of regulatory requirements, alarm signal is issued close to or over the data of threshold value, Warning construction personnel takes care, when something goes wrong, can timely early warning, while also can enter the site of an accident without personnel just A large amount of relevant information is provided, the safety of system is improved, in addition, other than it can monitor the state of country rock, moreover it is possible to have Standby positioning function, locating module can obtain the country rock position gone wrong in real time, enable the rapid orientation problem of staff Position, the present invention can monitor the deformation of the unstable country rock of construction tunnel in real time to be issued on warning information to avoid thing Therefore generation.
Finally, it should be noted that the foregoing is only a preferred embodiment of the present invention, it is not intended to restrict the invention, Although the present invention is described in detail referring to the foregoing embodiments, for those skilled in the art, still may be used To modify the technical solutions described in the foregoing embodiments or equivalent replacement of some of the technical features. All within the spirits and principles of the present invention, any modification, equivalent replacement, improvement and so on should be included in of the invention Within protection scope.

Claims (7)

1. a kind of tunnel wall rock deformation monitoring alarm, it is characterised in that: including sequentially connected sensor group, automatic collection Control module, locating module, communication module, monitoring and signal processing software module, long-distance radio communication module and live acousto-optic Alarm system module, the sensor group, automatic collection control module, locating module, communication module, monitoring and signal processing are soft Part module, long-distance radio communication module and live acoustooptic alarm system module are connected with the power supply module respectively, the sensor Group for monitoring displacement deformation, pressure change, the variation of concrete strain power, temperature change and the variation in water pressure of country rock inner wall respectively Information, the automatic collection control module are used to control period and the transmission signal that the sensor components do not acquire signal Frequency, the locating module is connect with monitoring and signal processing software module, for obtaining the country rock position gone wrong in real time, The sensor group sends monitoring and signal processing software module for collected signal by communication module, the monitoring and Signal processing software module is for handling the signal collected, and output signal is shown to text respectively according to the actual situation Screen, long-distance radio communication module and live acoustooptic alarm system module, the long-distance radio communication module output signal to engineering The remote signal of headquarter receives terminal.
2. a kind of tunnel wall rock deformation monitoring alarm according to claim 1, it is characterised in that: the locating module Including sending over the wireless sensor group of signal strength and according to the induction of wireless sensor for incuding other positioning devices As a result the location processor of position calculating is carried out.
3. a kind of tunnel wall rock deformation monitoring alarm according to claim 1, it is characterised in that: the sensor group Including convergence gauge, total station, displacement sensor, pressure cell, anchor ergometer, reinforcing rib meter, strain gauge, temperature sensor and osmotic pressure Meter, and the convergence gauge, total station, displacement sensor, pressure cell, anchor ergometer, reinforcing rib meter, strain gauge, temperature sensor It is connect respectively with automatic collection control module with osmometer.
4. a kind of tunnel wall rock deformation monitoring alarm according to claim 1, it is characterised in that: the automatic collection Control module includes sequentially connected timer and controller, and the timer is connect with sensor group, the controller and logical Believe module connection.
5. a kind of tunnel wall rock deformation monitoring alarm according to claim 1, it is characterised in that: the automatic collection Control module controls sensor group and acquires the period of IV grades of country rock signals as 20min-3h.
6. a kind of tunnel wall rock deformation monitoring alarm according to claim 1, it is characterised in that: the automatic collection Control module controls sensor group and acquires the period of V grades of country rock signals as 7min-10min.
7. a kind of tunnel wall rock deformation monitoring alarm according to claim 1, it is characterised in that: the monitoring and letter Number processing software module includes single-chip microcontroller.
CN201811253185.1A 2018-10-25 2018-10-25 A kind of tunnel wall rock deformation monitoring alarm Pending CN109374049A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811253185.1A CN109374049A (en) 2018-10-25 2018-10-25 A kind of tunnel wall rock deformation monitoring alarm

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811253185.1A CN109374049A (en) 2018-10-25 2018-10-25 A kind of tunnel wall rock deformation monitoring alarm

Publications (1)

Publication Number Publication Date
CN109374049A true CN109374049A (en) 2019-02-22

Family

ID=65401519

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811253185.1A Pending CN109374049A (en) 2018-10-25 2018-10-25 A kind of tunnel wall rock deformation monitoring alarm

Country Status (1)

Country Link
CN (1) CN109374049A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110223489A (en) * 2019-05-17 2019-09-10 中电投工程研究检测评定中心有限公司 A kind of monitoring method and device of engineering object
CN110243335A (en) * 2019-07-16 2019-09-17 贵州省交通规划勘察设计研究院股份有限公司 A kind of constructing tunnel wall rock loosening ring deformation auto-monitoring prior-warning device and method
CN112632680A (en) * 2020-12-30 2021-04-09 同济大学 Large civil engineering structure water leakage condition reconstruction method based on deep learning
CN112947283A (en) * 2021-03-08 2021-06-11 潍坊科技学院 Unattended monitoring system for arch culvert engineering quality
CN113447417A (en) * 2021-06-10 2021-09-28 中铁隧道局集团路桥工程有限公司 Tunnel water seepage monitoring system and monitoring method based on BDS and 5G
CN114235034A (en) * 2021-11-29 2022-03-25 山东大学 Tunnel surrounding rock stress and steel arch frame strain integrated measurement auxiliary device and method
CN114485570A (en) * 2022-02-07 2022-05-13 中交路桥科技有限公司 Intelligent monitoring, measuring and early warning system and method for construction safety of tunnel under construction
CN116798191A (en) * 2023-07-14 2023-09-22 西安恒泰永畅交通科技有限公司 Real-time monitoring and early warning system and method for disasters in construction period of highway tunnel

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201811722U (en) * 2010-10-13 2011-04-27 中铁二十四局集团有限公司 Tunnel surrounding rock deformation monitoring and alarm device
EP2035767B1 (en) * 2006-05-31 2011-09-14 Kalman Kovari Method and device for determining displacements and/or deformations in underground working
CN206037986U (en) * 2016-08-26 2017-03-22 招商局重庆交通科研设计院有限公司 Tunnel surrouding rock deformation monitoring and early warning system
CN108279082A (en) * 2018-01-16 2018-07-13 吉林大学 A kind of monitoring of Tunnel Surrounding Rock Pressure and early warning system
CN108398100A (en) * 2018-02-28 2018-08-14 江苏中路工程检测有限公司 A kind of constructing tunnel automatic monitoring system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2035767B1 (en) * 2006-05-31 2011-09-14 Kalman Kovari Method and device for determining displacements and/or deformations in underground working
CN201811722U (en) * 2010-10-13 2011-04-27 中铁二十四局集团有限公司 Tunnel surrounding rock deformation monitoring and alarm device
CN206037986U (en) * 2016-08-26 2017-03-22 招商局重庆交通科研设计院有限公司 Tunnel surrouding rock deformation monitoring and early warning system
CN108279082A (en) * 2018-01-16 2018-07-13 吉林大学 A kind of monitoring of Tunnel Surrounding Rock Pressure and early warning system
CN108398100A (en) * 2018-02-28 2018-08-14 江苏中路工程检测有限公司 A kind of constructing tunnel automatic monitoring system

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110223489A (en) * 2019-05-17 2019-09-10 中电投工程研究检测评定中心有限公司 A kind of monitoring method and device of engineering object
CN110243335A (en) * 2019-07-16 2019-09-17 贵州省交通规划勘察设计研究院股份有限公司 A kind of constructing tunnel wall rock loosening ring deformation auto-monitoring prior-warning device and method
CN110243335B (en) * 2019-07-16 2024-03-22 贵州省交通规划勘察设计研究院股份有限公司 Automatic monitoring and early warning device and method for loose ring deformation of surrounding rock in tunnel construction
CN112632680A (en) * 2020-12-30 2021-04-09 同济大学 Large civil engineering structure water leakage condition reconstruction method based on deep learning
CN112632680B (en) * 2020-12-30 2022-08-05 同济大学 Large civil engineering structure water leakage condition reconstruction method based on deep learning
CN112947283A (en) * 2021-03-08 2021-06-11 潍坊科技学院 Unattended monitoring system for arch culvert engineering quality
CN113447417A (en) * 2021-06-10 2021-09-28 中铁隧道局集团路桥工程有限公司 Tunnel water seepage monitoring system and monitoring method based on BDS and 5G
CN114235034A (en) * 2021-11-29 2022-03-25 山东大学 Tunnel surrounding rock stress and steel arch frame strain integrated measurement auxiliary device and method
CN114485570A (en) * 2022-02-07 2022-05-13 中交路桥科技有限公司 Intelligent monitoring, measuring and early warning system and method for construction safety of tunnel under construction
CN114485570B (en) * 2022-02-07 2024-04-12 中交路桥科技有限公司 Intelligent monitoring, measuring and early warning system and method for tunnel construction safety
CN116798191A (en) * 2023-07-14 2023-09-22 西安恒泰永畅交通科技有限公司 Real-time monitoring and early warning system and method for disasters in construction period of highway tunnel

Similar Documents

Publication Publication Date Title
CN109374049A (en) A kind of tunnel wall rock deformation monitoring alarm
CN206037986U (en) Tunnel surrouding rock deformation monitoring and early warning system
CN103743441B (en) The polynary of a kind of side slope safety is coupling in line monitoring system and method
CN105974056B (en) Tunnel water bursting disaster precursor information monitoring model pilot system and test method
CN105442520B (en) Side slope and dam construction phase, the first impoundment overall process stabilization monitoring system
CN102900466B (en) Based on safety for tunnel engineering method for early warning and the system of three-dimensional digital tunnel platform
CN101270666B (en) Tunnel influence geological condition section-expanding horizontal drilling estimation and prediction method
CN108280969A (en) A kind of high slope surface deformation monitoring and warning system and its method for early warning
CN210154614U (en) Foundation pit and settlement monitoring device of peripheral stratum thereof based on BIM
CN106949877A (en) The monitoring method of ground settlement above a kind of various dimensions shield tunnel
CN108492532A (en) A kind of early warning system and its method for early warning of landslide geological disaster
CN102997886A (en) Monitoring method for remotely measuring and controlling damage depths of floor strata
CN103994846A (en) Device and method for testing surrounding rock stress field distribution
CN109184709A (en) A kind of construction of Suporting structure is slagged tap monitoring management system and method
CN102797504A (en) Remote three-dimensional digital alarm method and facility of deformation stability of primary tunnel supporting body
CN203024763U (en) Construction beam posture monitoring system
CN103046525A (en) Facility and method for mechanical stability remote intelligent monitoring and three-dimensional early warning of deep foundation pit
CN113591347A (en) Dynamic monitoring method and early warning system in high slope construction process
KR101129870B1 (en) Method for remotely monitoring variety facilities using sensors
CN203037286U (en) Surrounding rock deformation rupture evolution testing structure of underground powerhouse at high-field stress area
CN208172969U (en) A kind of high slope surface deformation monitoring and warning system
CN206635824U (en) Pit retaining monitoring system
CN105043602B (en) The monitoring of shield-tunneling construction hysteresis sedimentation and method for early warning and device in big erratic boulder stratum
CN102721406B (en) Construction beam gesture monitoring system
CN206311600U (en) A kind of geological stress changes liquid-phase detection device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190222