CN109372242A - A kind of construction of lift well security improvement stage apparatus and application method - Google Patents
A kind of construction of lift well security improvement stage apparatus and application method Download PDFInfo
- Publication number
- CN109372242A CN109372242A CN201811149829.2A CN201811149829A CN109372242A CN 109372242 A CN109372242 A CN 109372242A CN 201811149829 A CN201811149829 A CN 201811149829A CN 109372242 A CN109372242 A CN 109372242A
- Authority
- CN
- China
- Prior art keywords
- girder
- stage apparatus
- construction
- lift well
- square steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G3/00—Scaffolds essentially supported by building constructions, e.g. adjustable in height
- E04G3/28—Mobile scaffolds; Scaffolds with mobile platforms
- E04G3/30—Mobile scaffolds; Scaffolds with mobile platforms suspended by flexible supporting elements, e.g. cables
- E04G3/305—Mobile scaffolds; Scaffolds with mobile platforms suspended by flexible supporting elements, e.g. cables specially adapted for tanks, silos or similar vessels
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G3/00—Scaffolds essentially supported by building constructions, e.g. adjustable in height
- E04G3/28—Mobile scaffolds; Scaffolds with mobile platforms
- E04G3/30—Mobile scaffolds; Scaffolds with mobile platforms suspended by flexible supporting elements, e.g. cables
- E04G3/32—Hoisting devices; Safety devices
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Types And Forms Of Lifts (AREA)
Abstract
The present invention relates to a kind of construction of lift well security improvement stage apparatus and application methods, including girder and secondary beam, the girder is in two to be arranged side by side, several secondary beams are provided between two girders, the downside of the girder is vertically provided with two round tube columns, the lower end of the round tube column is erected on the I-shaped gooseneck below girder, the both ends of the I-shaped gooseneck are inserted into lower layer's hole to be provided of hoistway wall, scalable square steel beam is axially arranged in the both ends of the girder, the inner end of the scalable square steel beam is provided with spring and is connected with wirerope.The present invention can have enough to meet the need reuse, be conducive to safety construction, be conducive to carry out energy conservation and environmental protection green building site construction, make simple constructing operation and be easy.
Description
Technical field
The present invention relates to housing construction fields in architectural engineering, more particularly to a kind of construction of lift well security improvement
Stage apparatus and application method.
Background technique
General Bases in High Building Construction frame-shear structure or shear wall structure are intended to setting armored concrete elevator, in construction with
The raising safety management difficulty of building height be continuously increased.It mostly uses assembly scaffold to set up operating platform at present, has
Using door opening steelframe brace type platform, since Safety assurance measures are single therefore there are more hidden danger.
Summary of the invention
Technical problem to be solved by the invention is to provide a kind of construction of lift well security improvement stage apparatus and users
Method can have enough to meet the need reuse, be conducive to safety construction, be conducive to carry out energy conservation and environmental protection green building site construction, production letter
Single constructing operation is easy.
The present invention relates to a kind of construction of lift well security improvement stage apparatus, including girder and secondary beam, the girder is in
Two to be arranged side by side are provided with several secondary beams between two girders, and the downside of the girder is vertically provided with two
Round tube column, the lower end of the round tube column are erected on the I-shaped gooseneck below girder, the I-shaped gooseneck
Both ends are inserted into lower layer's hole to be provided of hoistway wall, and scalable square steel beam is axially arranged in the both ends of the girder, described
The inner end of scalable square steel beam is provided with spring and is connected with wirerope.
Further, the both ends of the girder are provided with orientation pulley close to the position of scalable square steel beam, described
Wirerope is around orientation pulley arrangements.
Further, X-shaped intercolumniation steel pipe support part is provided between adjacent round tube column.
Further, the lower end of the round tube column is equipped with downward opening inverse u-shaped steel part, the inverse u-shaped steel
Part is placed on I-shaped gooseneck.
Further, the both ends of the I-shaped gooseneck are welded with hollow and with internal thread cuboid cylinder side by side
Body, the cuboid cylinder inner bore are vertically equipped with screw rod.
Further, more secondary beams form rectangular frame structure, and the marginal position of the rectangular frame structure is equipped with several
A positioning runner, the positioning runner include the telescopic rod for supporting runner and connection support runner, the telescopic rod setting
Inside rectangular support and there is spring supporting, the positioning runner is in contact with hoistway wall.
A kind of application method of construction of lift well security improvement stage apparatus, the specific steps are as follows:
(a) lower layer's I-shaped gooseneck is installed, the both ends of I-shaped gooseneck are inserted into lower layer's hole to be provided of hoistway wall;
(b) the both ends height of I-shaped gooseneck is adjusted by rotation screw rod;
(c) secondary beam, girder and round tube column, the scalable square steel beam at girder both ends are installed and are in pop-up state;
(d) all wirerope are ticked by suspender, are mentioned on suspender, retract scalable square steel beam by wirerope,
Entire stage apparatus is mentioned;
(e) stage apparatus is promoted to designated position, scalable square steel beam is moved to the upper layer hole to be provided of hoistway wall
In, suspender is withdrawn, and scalable square steel beam automatic spring realizes the fixation of entire stage apparatus;
(f) circulate operation.
The utility model has the advantages that the present invention relates to a kind of construction of lift well security improvement stage apparatus and application methods, using lower layer
Girder steel support, the scalable girder steel Auxiliary support in upper layer, eight supporting point double-layer safeties are conducive to exclude security risk, can have enough to meet the need
It reuses, is conducive to safety construction, be conducive to carry out energy conservation and environmental protection green building site construction, make simple constructing operation and hold
Easily.
Detailed description of the invention
Fig. 1 is main structure figure of the invention;
Fig. 2 is the use state diagram of scalable square steel beam of the invention;
Fig. 3 is the schematic top plan view of I-shaped gooseneck of the invention;
Fig. 4 is the main structure figure of round tube column of the invention;
Fig. 5 is the lower end structure figure of round tube column of the invention;
Fig. 6 is I-steel beam-end side block diagram of the invention;
Fig. 7 is I-steel beam-end overlooking structure figure of the invention;
Fig. 8 is the arragement construction top view of secondary beam of the invention;
Fig. 9 is the structure chart of positioning runner of the invention.
Diagram: 1, hoistway wall;2, girder;3, round tube column;4, X-shaped intercolumniation steel pipe support part;5, I-shaped gooseneck;6,
Wirerope;7: secondary beam;8: positioning runner;9, cuboid cylinder body;10, suspender;11, pulley is oriented;12, scalable square steel beam.
Specific embodiment
Present invention will be further explained below with reference to specific examples.It should be understood that these embodiments are merely to illustrate the present invention
Rather than it limits the scope of the invention.In addition, it should also be understood that, after reading the content taught by the present invention, those skilled in the art
Member can make various changes or modifications the present invention, and such equivalent forms equally fall within the application the appended claims and limited
Range.
As shown in figs 1-9, embodiments of the present invention are related to a kind of construction of lift well security improvement stage apparatus, including master
Beam 2 and secondary beam 7, the girder 2 are in two to be arranged side by side, are provided with several secondary beams 7 between two girders 2, described
The downside of girder 2 is vertically provided with two round tube columns 3, and the lower end of the round tube column 3 is erected at the work of 2 lower section of girder
On word gooseneck 5, the both ends of the I-shaped gooseneck 5 are inserted into lower layer's hole to be provided of hoistway wall 1, the girder 2
Both ends scalable square steel beam 12 is axially set, the inner end of the scalable square steel beam 12 is provided with spring and is connected with steel
Cord 6.
The both ends of the girder 2 are provided with orientation pulley 11, the steel wire close to the position of scalable square steel beam 12
Rope 6 is arranged around orientation pulley 11.
X-shaped intercolumniation steel pipe support part 4 is provided between adjacent round tube column 3, in the stability for guaranteeing frame body, two layers total
8 points of support ensures to promote stage apparatus safe and reliable.
The lower end of the round tube column 3 is equipped with downward opening inverse u-shaped steel part, and the inverse u-shaped steel part is placed on
On I-shaped gooseneck 5, stage apparatus frame body is promoted to support safety.
The both ends of the I-shaped gooseneck 5 be welded with side by side it is hollow and with internal thread cuboid cylinder body 9, it is described
9 inner hole of cuboid cylinder body screw rod is vertically installed, by the height for fine-tuning the adjustable I-shaped gooseneck 5 of screw rod.
More secondary beams 7 form rectangular frame structure, and the marginal position of the rectangular frame structure is equipped with several positioning and turns
Wheel 8, the positioning runner 8 include the telescopic rod of support runner and connection support runner, and the telescopic rod is arranged rectangular
Inside support and there is spring supporting, the positioning runner 8 is in contact with hoistway wall 1.
As a kind of embodiment of the invention, installation process is as follows:
(a) lower layer's I-shaped gooseneck 5 is installed, the both ends of I-shaped gooseneck 5 are inserted into lower layer's hole to be provided of hoistway wall 1
In;
(b) the both ends height of I-shaped gooseneck 5 is adjusted by rotation screw rod;
(c) secondary beam 7, girder 2 and round tube column 3, the scalable square steel beam 12 at 2 both ends of girder are installed and are in pop-up state;
(d) all wirerope 6 are ticked by suspender 10, suspender 10 above mentions, and makes scalable square steel beam by wirerope 6
12 retract, and entire stage apparatus is mentioned;
(e) stage apparatus is promoted to designated position, the upper layer that scalable square steel beam 12 is moved to hoistway wall 1 is reserved
In hole, suspender 10 is withdrawn, and scalable 12 automatic spring of square steel beam realizes the fixation of entire stage apparatus;
(f) circulate operation.
The present invention is supported using lower layer's girder steel, the scalable girder steel Auxiliary support in upper layer, and eight supporting point double-layer safeties are advantageous
In excluding security risk, reuse can be had enough to meet the need, safety construction is conducive to, be conducive to carry out energy conservation and environmental protection green building site
Construction makes simple constructing operation and is easy.
Claims (7)
1. a kind of construction of lift well security improvement stage apparatus, including girder (2) and secondary beam (7), which is characterized in that the master
Beam (2) is in two to be arranged side by side, is provided with several secondary beams (7), the downside of the girder (2) between two girders (2)
Two round tube columns (3) are vertically provided with, the lower end of the round tube column (3) is erected at the I-steel below girder (2)
On crossbeam (5), the both ends of the I-shaped gooseneck (5) are inserted into lower layer's hole to be provided of hoistway wall (1), the girder
(2) both ends are axially arranged scalable square steel beam (12), the inner end of the scalable square steel beam (12) be provided with spring and
It is connected with wirerope (6).
2. construction of lift well security improvement stage apparatus according to claim 1, it is characterised in that: the girder (2)
Both ends close to the position of scalable square steel beam (12) be provided with orientation pulley (11), the wirerope (6) around orientation slide
Take turns (11) arrangement.
3. construction of lift well security improvement stage apparatus according to claim 1, it is characterised in that: adjacent round tube column
(3) X-shaped intercolumniation steel pipe support part (4) is provided between.
4. construction of lift well security improvement stage apparatus according to claim 1, it is characterised in that: the round tube column
(3) lower end is equipped with downward opening inverse u-shaped steel part, and the inverse u-shaped steel part is placed on I-shaped gooseneck (5).
5. construction of lift well security improvement stage apparatus according to claim 4, it is characterised in that: the I-steel is horizontal
The both ends of beam (5) be welded with side by side it is hollow and with internal thread cuboid cylinder body (9), in the cuboid cylinder body (9)
Hole is vertically equipped with screw rod.
6. construction of lift well security improvement stage apparatus according to claim 1, it is characterised in that: more secondary beam (7) groups
Rectangular frame structure, the marginal position of the rectangular frame structure are equipped with several positioning runner (8), the positioning runner
It (8) include the telescopic rod for supporting runner and connection support runner, the telescopic rod is arranged inside rectangular support and has spring
Support, the positioning runner (8) are in contact with hoistway wall (1).
7. a kind of application method of construction of lift well security improvement stage apparatus according to claim 1, which is characterized in that
Specific step is as follows:
(a) lower layer's I-shaped gooseneck (5) are installed, the lower layer that the both ends of I-shaped gooseneck (5) are inserted into hoistway wall (1) is reserved
In hole;
(b) the both ends height of I-shaped gooseneck (5) is adjusted by rotation screw rod;
(c) secondary beam (7), girder (2) and round tube column (3) are installed, the scalable square steel beam (12) at girder (2) both ends is in pop-up
State;
(d) it is ticked by suspender (10) all wirerope (6), suspender (10) above mentions, and makes scalable side by wirerope (6)
Girder steel (12) retracts, and entire stage apparatus is mentioned;
(e) stage apparatus is promoted to designated position, the upper layer that scalable square steel beam (12) is moved to hoistway wall (1) is reserved
In hole, suspender (10) is withdrawn, and scalable square steel beam (12) automatic spring realizes the fixation of entire stage apparatus;
(f) circulate operation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811149829.2A CN109372242B (en) | 2018-09-29 | 2018-09-29 | Elevator shaft construction safety lifting platform device and using method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811149829.2A CN109372242B (en) | 2018-09-29 | 2018-09-29 | Elevator shaft construction safety lifting platform device and using method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109372242A true CN109372242A (en) | 2019-02-22 |
CN109372242B CN109372242B (en) | 2020-11-20 |
Family
ID=65403068
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811149829.2A Active CN109372242B (en) | 2018-09-29 | 2018-09-29 | Elevator shaft construction safety lifting platform device and using method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109372242B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113266142A (en) * | 2021-04-30 | 2021-08-17 | 中交第四公路工程局有限公司 | Rapid lifting platform for elevator shaft construction |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4886286B2 (en) * | 2005-12-06 | 2012-02-29 | ジャパン スチールス インターナショナル株式会社 | Temporary scaffolding unit |
CN203499229U (en) * | 2013-08-23 | 2014-03-26 | 中建三局第一建设工程有限责任公司 | Operating platform for construction of elevator shaft |
CN203878965U (en) * | 2014-06-09 | 2014-10-15 | 中建四局第六建筑工程有限公司 | Device for construction of elevator shaft |
CN206174441U (en) * | 2016-11-04 | 2017-05-17 | 中建八局第一建设有限公司 | Elevator shaft operation platform |
WO2018005515A1 (en) * | 2016-06-28 | 2018-01-04 | Safeworks, Llc | Lean-to rigging apparatus for shaft installation |
-
2018
- 2018-09-29 CN CN201811149829.2A patent/CN109372242B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4886286B2 (en) * | 2005-12-06 | 2012-02-29 | ジャパン スチールス インターナショナル株式会社 | Temporary scaffolding unit |
CN203499229U (en) * | 2013-08-23 | 2014-03-26 | 中建三局第一建设工程有限责任公司 | Operating platform for construction of elevator shaft |
CN203878965U (en) * | 2014-06-09 | 2014-10-15 | 中建四局第六建筑工程有限公司 | Device for construction of elevator shaft |
WO2018005515A1 (en) * | 2016-06-28 | 2018-01-04 | Safeworks, Llc | Lean-to rigging apparatus for shaft installation |
CN206174441U (en) * | 2016-11-04 | 2017-05-17 | 中建八局第一建设有限公司 | Elevator shaft operation platform |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113266142A (en) * | 2021-04-30 | 2021-08-17 | 中交第四公路工程局有限公司 | Rapid lifting platform for elevator shaft construction |
CN113266142B (en) * | 2021-04-30 | 2022-04-19 | 中交第四公路工程局有限公司 | Rapid lifting platform for elevator shaft construction |
Also Published As
Publication number | Publication date |
---|---|
CN109372242B (en) | 2020-11-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106939707B (en) | A kind of restricted clearance large-scale steel structure supporting platform from method for improving | |
CN108532769B (en) | Jacking construction method of assembled additional elevator shaft structure | |
CN106437130A (en) | Inner roof external climbing type formwork construction platform for super high-rise building construction | |
CN207144449U (en) | A kind of hoistway operation platform | |
CN205077885U (en) | Hydraulic intelligent climbing protection platform for core tube of building | |
CN108033367B (en) | Synchronous lifting device and lifting method for steel column and cylinder frame alternately supported steel platform and tower crane | |
CN206233541U (en) | A kind of interior top external climbing mould bases operation platform for construction of super highrise building | |
CN105201195A (en) | Liftable supporting leg type elevator shaft construction platform and method | |
CN103388401A (en) | Steel post operation platform and construction method thereof | |
CN110565937A (en) | Door type integral lifting steel platform | |
CN205955160U (en) | Antiskid lattice formula elevartor shaft removes operation platform | |
CN104989111A (en) | Construction method for steel structure high-rise hoisting | |
CN205575428U (en) | Component hoisting system | |
CN204625045U (en) | A kind of steel structure hoisting door shaped stent formula hanging apparatus | |
CN201762973U (en) | Lifting scaffold | |
CN109372242A (en) | A kind of construction of lift well security improvement stage apparatus and application method | |
CN106522541B (en) | A kind of template suspension centre spandrel girder of steel platform and the hanging method of template system | |
CN108625292B (en) | Template assembling platform of prefabricated stand column | |
CN116537063A (en) | Tower column system on ladle concrete and construction method | |
CN206220534U (en) | The pump line support meanss of concrete pumping equipment | |
CN211257773U (en) | Door type integral lifting steel platform | |
CN205134921U (en) | Building outer wall concrete constructional column hangs construction platform | |
CN111455854B (en) | Semi-automatic protective shed frame used in construction of viaduct crossing railway and erection method | |
CN106368434A (en) | Supporting device for pumping tube of concrete pumping equipment and construction method | |
CN203701552U (en) | Attached scaffold for lifted through worm, gear and screw rod |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |