CN109365875A - A kind of overhead horizontal drilling construction method - Google Patents
A kind of overhead horizontal drilling construction method Download PDFInfo
- Publication number
- CN109365875A CN109365875A CN201811515441.XA CN201811515441A CN109365875A CN 109365875 A CN109365875 A CN 109365875A CN 201811515441 A CN201811515441 A CN 201811515441A CN 109365875 A CN109365875 A CN 109365875A
- Authority
- CN
- China
- Prior art keywords
- rod
- workbench
- slide plate
- connecting rod
- support rod
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B25—HAND TOOLS; PORTABLE POWER-DRIVEN TOOLS; MANIPULATORS
- B25H—WORKSHOP EQUIPMENT, e.g. FOR MARKING-OUT WORK; STORAGE MEANS FOR WORKSHOPS
- B25H1/00—Work benches; Portable stands or supports for positioning portable tools or work to be operated on thereby
- B25H1/0021—Stands, supports or guiding devices for positioning portable tools or for securing them to the work
- B25H1/0035—Extensible supports, e.g. telescopic
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Processing Of Stones Or Stones Resemblance Materials (AREA)
Abstract
The present invention relates to a kind of overhead horizontal drilling construction methods, overhead horizontal drilling aid is made first, including double leval jib lifting device, workbench, spring, slide plate, triatic stay, hand rod, the double leval jib lifting device includes column, upper connecting rod, lower link, support rod, base plate, pin shaft, the column, upper connecting rod, lower link and support rod are connected by pin shaft, when vertical direction is moved above and below, support rod links with it upper connecting rod;The workbench is mounted on the upper end of support rod, and surface is placed with slide plate on it, and slide plate is connected by the spring with baffle;Triatic stay is connected to the lower end of support rod;Hand rod is connected to its middle part of the upper end of upper connecting rod and is equipped with control switch, first electric drill is fixed on slide plate with belt when construction, move the device into required boring sites in curing it is lower to, pressing hand rod rises workbench, boring sites in curing is held out against with drill bit afterwards in place, control switch is pressed and completes boring work.
Description
Technical field
The present invention relates to a kind of overhead horizontal drilling construction methods, belong to building engineering construction field.
Background technique
In Building Construction especially when carrying out decorative engineering construction, it will usually encounter metope indoors
The case where eminence drills, in the prior art, when drilling usually require first to set up a rack platform, arrive on subsequent construction personnel
Bore operation is carried out on the platform taken, and is according to said method constructed, it is high because needing construction personnel station electric hand drill on platform to carry out
Idle job, large labor intensity, construction efficiency are low.
Summary of the invention
The present invention in view of the shortcomings of the prior art, proposing a kind of easy to operate, apply by a kind of overhead horizontal drilling easy to use
Work method.
The technical problem to be solved in the present invention is that providing a kind of overhead horizontal drilling construction method, high-altitude water is made first
Flat drilling aid, described device include double leval jib lifting device, workbench, spring, slide plate, triatic stay, hand rod,
The double leval jib lifting device includes column, upper connecting rod, lower link, support rod, base plate, pin shaft, under the support rod
End respectively bored with the upper end of the column there are two the identical circular hole of pitch-row;It is connected on base plate in the lower end of the column,
The lower end of the column is equipped with reinforcing rod, and the other end of the reinforcing rod is connected on base plate;Under the base plate
Face is connected with 2 universal wheels;A circular hole is respectively bored at the both ends of the lower link, one end and medium position in the upper connecting rod
It is respectively drilled with a circular hole, and guarantees in the upper connecting rod pitch-row phase of two circular holes in the pitch-row and the lower link of two circular holes
Together;Column, upper connecting rod, lower link and the support rod of the double leval jib lifting device pass through pin corresponding with opened circular hole thereon
Axis is connected, and guarantees the support when the top for pressing the upper connecting rod with hand is moved upwardly or downwardly
Bar carries out downward or upward movement in vertical direction;The workbench is mounted on the support rod of 2 double leval jib lifting devices
Upper end, be connected with stiffened panel at workbench bottom both ends and itself and double leval jib lifting device be connected, described
The upper surface of workbench is equipped with baffle;The slide plate is processed at L-shaped by steel plate, is placed on workbench, on it table
Respectively 2 belts of connection, the lateral surface of the facade of the slide plate are connected with spring, the other end of the spring on the inside of face and its facade
It is connected with the baffle;The triatic stay is connected to the lower end of the support rod of 2 double leval jib lifting devices;It is described hand steered
Bar is connected to the upper end of the upper connecting rod of 2 double leval jib lifting devices, and control switch is equipped in the middle part of hand rod, the control
System switch is connected with electric drill by conducting wire and can control the movement of electric drill.Electric drill is first placed on the upper surface of slide plate simultaneously when construction
With belt by electric drill and slide plate fixation, then overhead horizontal drilling aid is moved under required boring sites in curing
To pressing hand rod downwards with hand rises workbench, with the drill bit connected on electric drill after being moved to required boring sites in curing
Required boring sites in curing is held out against, control switch is then pressed and completes boring work.
Beneficial good effect of the invention: operation of the present invention is simple, constructs convenient and efficient, can effectively improve high-altitude
The construction efficiency of horizontal drilling, labor intensity are low.
Detailed description of the invention
Fig. 1: assembling schematic diagram of the present invention
Fig. 2: double leval jib lifting device structural schematic diagram
Specific embodiment
Embodiment one: referring to Fig. 1, Fig. 2, the present invention relates to a kind of overhead horizontal drilling construction methods, first production high-altitude
Horizontal drilling auxiliary device, described device include double leval jib lifting device 1, workbench 2, spring 4, slide plate 5, triatic stay
11, hand rod 9, the double leval jib lifting device 1 include column 1-1, upper connecting rod 1-5, lower link 1-6, support rod 1-7, pedestal
Plate 1-3, pin shaft 1-8 are respectively bored in the lower end of the support rod 1-7 and the upper end of the column 1-1 there are two the identical circle of pitch-row
Hole;It is connected on base plate 1-3 in the lower end of the column 1-1, reinforcing rod 1-2 is installed in the lower end of the column 1-1,
The other end of the reinforcing rod 1-2 is connected on base plate 1-3;2 universal wheel 1- are connected with below the base plate 1-3
4;A circular hole is respectively bored at the both ends of the lower link 1-6, is respectively drilled with one in one end of the upper connecting rod 1-5 and medium position
Circular hole, and guarantee that the pitch-row of upper two circular holes of the upper connecting rod 1-5 is identical with the pitch-row of upper two circular holes of the lower link 1-6;
Column 1-1, upper connecting rod 1-5, lower link 1-6 and the support rod 1-7 of the double leval jib lifting device 1 by with opened circle thereon
The corresponding pin shaft 1-8 in hole is connected, and guarantee when with the top that hand presses the upper connecting rod 1-5 be carried out it is upward or to
When lower movement, the support rod 1-7 carries out downward or upward movement in vertical direction;The workbench 2 is mounted on 2
The upper end of the support rod 1-7 of double leval jib lifting device 1 is connected with stiffened panel 8 for itself and four at the 2 bottom both ends of workbench
Connecting rod lifting device 1 is connected, and is equipped with baffle 3 in the upper surface of the workbench 2;The slide plate 5 is processed by steel plate
It is at L-shaped, it is placed on workbench 2,2 belts 7 is respectively connected on the inside of surface and its facade on it, in the vertical of the slide plate 5
The lateral surface in face is connected with spring 4, and the other end of the spring 4 is connected with the baffle 3;The triatic stay 11 connects
In the lower end of the support rod 1-7 of 2 double leval jib lifting devices 1;The hand rod 9 is connected to the upper of 2 double leval jib lifting devices 1
The upper end of connecting rod 1-5, and control switch 10 is installed at the middle part of hand rod 9, the control switch 10 passes through conducting wire and electric drill 6
It is connected and can control the movement of electric drill 6.Electric drill 6 is first placed on the upper surface of slide plate 5 and with belt 7 by 6 He of electric drill when construction
Overhead horizontal drilling aid 1 is then moved to the lower to being pressed downwards with hand of required boring sites in curing by 5 fixation of slide plate
Start handrail 9 make workbench 2 rise, hold out against required brill with the drill bit connected on electric drill 6 after being moved to required boring sites in curing
Hole position then presses control switch 10 and completes boring work.
The above shows and describes the basic principle, main features and advantages of the invention.The technology of the industry
Personnel are it should be appreciated that the present invention is not limited to the above embodiments, and the above embodiments and description only describe this
The principle of invention, under the premise of not departing from essence spirit of the invention and range, various changes and improvements may be made to the invention,
Nailing equipment can also be placed on slide plate as described in the invention and completes the work of overhead horizontal nailing, these changes and improvements are all
It falls into the range of claimed invention.The claimed scope of the invention is by appended claims and its equivalent circle
It is fixed.
Claims (3)
1. a kind of overhead horizontal drilling construction method, first production overhead horizontal drilling aid, described device includes four companies
Bar lifting device (1), workbench (2), spring (4), slide plate (5), triatic stay (11), hand rod (9), the double leval jib mention
Rising device (1) includes column (1-1), upper connecting rod (1-5), lower link (1-6), support rod (1-7), base plate (1-3), pin shaft
(1-8) is respectively bored in the lower end of the support rod (1-7) and the upper end of the column (1-1) there are two the identical circular hole of pitch-row;?
The lower end of the column (1-1) is connected on base plate (1-3), is equipped with reinforcing rod (1- in the lower end of the column (1-1)
2), the other end of the reinforcing rod (1-2) is connected on base plate (1-3);One is respectively bored at the both ends of the lower link (1-6)
Circular hole is respectively drilled with a circular hole in one end of the upper connecting rod (1-5) and medium position, and guarantees on the upper connecting rod (1-5)
The pitch-row of two circular holes is identical with the pitch-row of upper two circular holes of the lower link (1-6);The double leval jib lifting device (1) is stood
Column (1-1), upper connecting rod (1-5), lower link (1-6) and support rod (1-7) pass through pin shaft (1- corresponding with opened circular hole thereon
8) it is connected, and guarantees when the top for pressing the upper connecting rod (1-5) with hand is moved upwardly or downwardly, it is described
Support rod (1-7) carries out downward or upward movement in vertical direction;The workbench (2) is mounted on 2 double leval jibs and is promoted
The upper end of the support rod (1-7) of device (1) is connected with stiffened panel (8) for itself and four companies at the workbench (2) bottom both ends
Bar lifting device (1) is connected, and is equipped with baffle (3) in the upper surface of the workbench (2);The slide plate (5) is by steel
Plate processing is at L-shaped, is placed on workbench (2), 2 belts (7) is respectively connected on the inside of surface and its facade on it, described
The lateral surface of the facade of slide plate (5) is connected with spring (4), and the other end of the spring (4) is connected with the baffle (3);
The triatic stay (11) is connected to the lower end of the support rod (1-7) of 2 double leval jib lifting devices (1);The hand rod (9) is even
It connects in the upper end of the upper connecting rod (1-5) of 2 double leval jib lifting devices (1), and control switch is installed in the middle part of hand rod (9)
(10), the control switch (10) is connected with electric drill (6) and be can control the movement of electric drill (6) by conducting wire;It first will be electric when construction
It bores (6) and is placed on the upper surface of slide plate (5) and with belt (7) by electric drill (6) and slide plate (5) fixation, then by high-altitude water
Flat drilling aid (1) is moved to the lower to pressing hand rod (9) downwards with hand makes workbench (2) of required boring sites in curing
Rise, holds out against required boring sites in curing with the drill bit connected on electric drill (6) after being moved to required boring sites in curing, then press control
It switchs (10) and completes boring work.
2. a kind of overhead horizontal drilling construction method as described in claim 1, it is characterized in that: in the base plate (1-3)
It is connected with 2 universal wheels (1-4) below.
3. a kind of overhead horizontal drilling construction method as claimed in claim 1 or 2, it is characterized in that: can also on the slide plate (5)
The work of overhead horizontal nailing is completed to place nailing equipment.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811515441.XA CN109365875A (en) | 2018-12-11 | 2018-12-11 | A kind of overhead horizontal drilling construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811515441.XA CN109365875A (en) | 2018-12-11 | 2018-12-11 | A kind of overhead horizontal drilling construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109365875A true CN109365875A (en) | 2019-02-22 |
Family
ID=65373420
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811515441.XA Pending CN109365875A (en) | 2018-12-11 | 2018-12-11 | A kind of overhead horizontal drilling construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109365875A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112404520A (en) * | 2020-10-30 | 2021-02-26 | 河北华丰能源科技发展有限公司 | High-altitude drill rod support |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB335284A (en) * | 1929-06-28 | 1930-09-25 | Edwin Lewis Connell | Drilling or tapping machines |
CN101947783A (en) * | 2010-05-28 | 2011-01-19 | 徐州海伦哲专用车辆股份有限公司 | Multifunctional aloft-work mechanical arm |
CN203156100U (en) * | 2013-01-25 | 2013-08-28 | 中铁八局集团建筑工程有限公司 | Drilling instrument for suspended ceiling construction |
CN204843050U (en) * | 2015-06-16 | 2015-12-09 | 中为建筑工程有限公司 | High altitude drilling equipment |
CN107246239A (en) * | 2017-05-15 | 2017-10-13 | 合肥市规划设计研究院 | A kind of decorative engineering eminence drilling equipment |
CN206717081U (en) * | 2017-01-16 | 2017-12-08 | 中国铁建电气化局集团第五工程有限公司 | A kind of subway work roof drilling equipment |
CN207086976U (en) * | 2017-06-30 | 2018-03-13 | 唐山钢铁集团有限责任公司 | A kind of architectural engineering drilling bracket |
CN107876836A (en) * | 2017-10-16 | 2018-04-06 | 中国十七冶集团有限公司 | Drilling equipment without operating platform |
CN108098014A (en) * | 2017-12-25 | 2018-06-01 | 郑州格瑞塔电子信息技术有限公司 | A kind of lift drill hole on wall device that can adjust drilling depth |
CN108746760A (en) * | 2018-07-19 | 2018-11-06 | 上海建工七建集团有限公司 | A kind of simple punching device and its construction method |
CN208073366U (en) * | 2017-12-30 | 2018-11-09 | 中为建筑工程有限公司 | A kind of horizontal aperture apparatus of high-altitude brill |
-
2018
- 2018-12-11 CN CN201811515441.XA patent/CN109365875A/en active Pending
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB335284A (en) * | 1929-06-28 | 1930-09-25 | Edwin Lewis Connell | Drilling or tapping machines |
CN101947783A (en) * | 2010-05-28 | 2011-01-19 | 徐州海伦哲专用车辆股份有限公司 | Multifunctional aloft-work mechanical arm |
CN203156100U (en) * | 2013-01-25 | 2013-08-28 | 中铁八局集团建筑工程有限公司 | Drilling instrument for suspended ceiling construction |
CN204843050U (en) * | 2015-06-16 | 2015-12-09 | 中为建筑工程有限公司 | High altitude drilling equipment |
CN206717081U (en) * | 2017-01-16 | 2017-12-08 | 中国铁建电气化局集团第五工程有限公司 | A kind of subway work roof drilling equipment |
CN107246239A (en) * | 2017-05-15 | 2017-10-13 | 合肥市规划设计研究院 | A kind of decorative engineering eminence drilling equipment |
CN207086976U (en) * | 2017-06-30 | 2018-03-13 | 唐山钢铁集团有限责任公司 | A kind of architectural engineering drilling bracket |
CN107876836A (en) * | 2017-10-16 | 2018-04-06 | 中国十七冶集团有限公司 | Drilling equipment without operating platform |
CN108098014A (en) * | 2017-12-25 | 2018-06-01 | 郑州格瑞塔电子信息技术有限公司 | A kind of lift drill hole on wall device that can adjust drilling depth |
CN208073366U (en) * | 2017-12-30 | 2018-11-09 | 中为建筑工程有限公司 | A kind of horizontal aperture apparatus of high-altitude brill |
CN108746760A (en) * | 2018-07-19 | 2018-11-06 | 上海建工七建集团有限公司 | A kind of simple punching device and its construction method |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112404520A (en) * | 2020-10-30 | 2021-02-26 | 河北华丰能源科技发展有限公司 | High-altitude drill rod support |
CN112404520B (en) * | 2020-10-30 | 2021-11-12 | 河北华丰能源科技发展有限公司 | High-altitude drill rod support |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105834471A (en) | Drilling machine for hardware machining | |
CN102720448B (en) | Device and method for connecting drill rod with three-joint unit | |
CN107598215A (en) | A kind of transversely movable cylindrical sleeves multiposition of drill bit fixes borehole drill construction | |
CN109365873A (en) | It is a kind of to utilize double leval jib transmission device overhead horizontal drilling construction method | |
CN202673195U (en) | Device for connecting drill pipes with three-joint unit | |
CN104060951A (en) | Intelligent drilling tool moving and discharging system for marine drilling platform and application method of intelligent drilling tool moving and discharging system | |
CN204018780U (en) | A kind of double-ended double-station holes pressure-plate boring device | |
CN109365875A (en) | A kind of overhead horizontal drilling construction method | |
CN209190251U (en) | A kind of hardware drilling equipment | |
CN104552481A (en) | Furniture board surfacing and punching integrated machine | |
CN109128936A (en) | A kind of Hardware fitting fixture and drilling equipment | |
CN211708167U (en) | Steel drilling tool with drill bit replacing structure | |
CN107984553A (en) | A kind of device for being used for circular plank circle centre position automatic positioning punching | |
CN203738063U (en) | Rim on-line automatic drilling device | |
CN103042255B (en) | Pneumatic perforating assembled tool | |
CN105397727B (en) | A kind of electric pole high-altitude operations tool placement platform | |
CN107790787A (en) | The lengthening support that a kind of packaged type electric drill drills vertically upward | |
CN203863077U (en) | Improved drilling machine for producing semitrailer hanging frame | |
CN206718194U (en) | The Drilling operation device of fancy glass lamp shade | |
CN206474882U (en) | A kind of efficient pin pressing machine of cam axial end | |
CN109365870A (en) | A kind of vertical drilling construction method | |
CN109365871A (en) | It is a kind of to utilize rack gearing overhead horizontal drilling construction method | |
CN207548952U (en) | A kind of device for round plank circle centre position automatic positioning punching | |
CN209425031U (en) | A kind of non-equally porous lift hole drilling jig | |
CN202865709U (en) | Vertical positioning drilling machine used for railway maintenance |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20190222 |
|
WD01 | Invention patent application deemed withdrawn after publication |