CN202673195U - Device for connecting drill pipes with three-joint unit - Google Patents

Device for connecting drill pipes with three-joint unit Download PDF

Info

Publication number
CN202673195U
CN202673195U CN2012202742002U CN201220274200U CN202673195U CN 202673195 U CN202673195 U CN 202673195U CN 2012202742002 U CN2012202742002 U CN 2012202742002U CN 201220274200 U CN201220274200 U CN 201220274200U CN 202673195 U CN202673195 U CN 202673195U
Authority
CN
China
Prior art keywords
drill pipe
chuck
lifting
stand
drill
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2012202742002U
Other languages
Chinese (zh)
Inventor
白丙建
贾秉彦
樊春明
高明
周天明
毕小钧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Baoji Oilfield Machinery Co Ltd
Original Assignee
Baoji Oilfield Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Baoji Oilfield Machinery Co Ltd filed Critical Baoji Oilfield Machinery Co Ltd
Priority to CN2012202742002U priority Critical patent/CN202673195U/en
Application granted granted Critical
Publication of CN202673195U publication Critical patent/CN202673195U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

本实用新型公开了一种用于钻杆接立根的装置,在钻机大门坡道旁边固定安装有立根架,在立根架内安装有液压大钳、扶正夹头、提升滑车、悬持夹头;在立根架前坡道旁的地面上固定安装有猫道,猫道内装有举升机械手;在钻机井架上安装有二层台,在其下方悬吊安装有自动井架工。本实用新型还公开了利用该装置进行钻杆接立根的方法,利用上述的装置使钻杆输送及整个接立根过程实现机械化操作,钻杆上钻台、接立根均不需占用顶驱及井口工具,节省时间,提高钻井效率;同时不需工人在危险区域作业,减轻劳动强度,避免发生人身事故。

The utility model discloses a device for connecting vertical roots of drilling rods. A vertical root frame is fixedly installed beside the ramp of the drilling rig gate, and a hydraulic tong, a righting chuck, a lifting block, and a suspension chuck are installed in the vertical root frame; A catwalk is fixedly installed on the ground next to the front ramp of the stand frame, and a lifting manipulator is installed in the catwalk; a second-story platform is installed on the derrick of the drilling rig, and an automatic derrick is installed suspended below it. The utility model also discloses a method of using the device to connect the drill pipe to the stand. The above-mentioned device is used to realize the mechanized operation of the drill pipe transportation and the whole process of connecting the stand, and the drill pipe is put on the drill floor and connected to the stand without occupying the top drive and the wellhead. Tools save time and improve drilling efficiency; at the same time, workers are not required to work in dangerous areas, reducing labor intensity and avoiding personal accidents.

Description

一种用于钻杆接立根的装置A device for connecting drill pipes to vertical roots

技术领域 technical field

本实用新型属于石油钻探设备技术领域,涉及一种用于钻杆接立根的装置。The utility model belongs to the technical field of oil drilling equipment and relates to a device for connecting a drill pipe to a vertical root.

背景技术 Background technique

目前钻井时钻杆接立根作业一般方法是:利用风动绞车将钻杆从猫道沿大门坡道拖拽上钻台,在小鼠洞内依靠风动小绞车和液压大钳配合将单根连接为立根,再依靠二层台井架工人力把钻杆立根排放到指梁内。上述的作业方式在钻杆上、下钻台时对其损坏较严重,同时需要多人配合完成,工人劳动强度大,作业时易与顶驱发生干涉,可能造成设备损坏或人身伤亡事故。At present, the general method of connecting the drill pipe to the vertical root when drilling is: use the pneumatic winch to drag the drill pipe from the catwalk along the ramp of the gate to the drill floor, and rely on the cooperation of the small wind winch and the hydraulic tongs in the mouse hole to lift the single stand. The connection is a vertical root, and then rely on the force of the second-floor derrick worker to discharge the drill pipe vertical root into the finger beam. The above-mentioned operation method seriously damages the drill pipe when it is going up and down the drill floor, and requires the cooperation of multiple people to complete it. The labor intensity of the workers is high, and it is easy to interfere with the top drive during the operation, which may cause equipment damage or personal casualties.

发明内容 Contents of the invention

本实用新型的目的是提供一种用于钻杆接立根的装置,解决了现有钻杆单根接立根时需多人配合人力作业效率低、风险高、劳动强度大的问题。The purpose of the utility model is to provide a device for connecting a drill pipe to a vertical root, which solves the problems of low efficiency, high risk, and high labor intensity when a single drill pipe is connected to a vertical root.

本实用新型所采用的技术方案是,一种用于钻杆接立根的装置,在钻机钻台面前侧、大门坡道旁边固定安装有立根架,在立根架前坡道旁的地面上固定安装有猫道,在猫道内安装有举升机械手;在立根架内安装有扶正夹头、液压大钳、提升滑车以及悬持夹头;在钻机井架上安装有二层台,在二层台下方悬吊安装有自动井架工。The technical solution adopted by the utility model is, a device for connecting the vertical root of the drill pipe, the vertical root frame is fixedly installed on the front side of the drill floor of the drilling rig, and next to the gate ramp, and is fixedly installed on the ground beside the front ramp of the vertical root frame There is a catwalk, and a lifting manipulator is installed in the catwalk; erecting chucks, hydraulic tongs, lifting blocks and suspension chucks are installed in the vertical frame; a second-level platform is installed on the derrick of the drilling rig, and the second-level platform is installed below the platform. The suspension is equipped with an automatic derrick.

本实用新型的有益效果是,显著提高了接立根作业效率,大大减轻工人劳动强度;减少钻台及二层台的操作人员,降低钻井作业劳动力成本,提高作业安全性;整套装置功能强大,只需要副司钻一人在控制台操作即可完成整个接立根作业,并将立根排放到二层台指梁内。The beneficial effect of the utility model is that it significantly improves the operation efficiency of standing roots, and greatly reduces the labor intensity of workers; reduces the number of operators on the drilling floor and the second floor platform, reduces the labor cost of drilling operations, and improves the operation safety; the whole set of devices is powerful, and only Only one assistant driller is required to operate on the console to complete the whole erection operation, and discharge the erection into the second-floor platform finger beam.

附图说明 Description of drawings

图1是本实用新型的钻杆接立根装置结构立面示意图;Fig. 1 is the structural elevation schematic diagram of the drill pipe connecting stand device of the present utility model;

图2是本实用新型的钻杆接立根装置结构俯视示意图;Fig. 2 is a schematic top view of the structure of the drill pipe erecting device of the present invention;

图3是本实用新型的钻杆接立根方法作业流程图之一;Fig. 3 is one of the operating flow diagrams of the drilling pipe erecting method of the present utility model;

图4是本实用新型的钻杆接立根方法作业流程图之二;Fig. 4 is the second of the operation flow chart of the drilling pipe erecting method of the utility model;

图5是本实用新型的钻杆接立根方法作业流程图之三;Fig. 5 is the third operation flow chart of the drill pipe erecting method of the utility model;

图6是本实用新型的钻杆接立根方法作业流程图之四;Fig. 6 is the fourth operation flow chart of the drilling pipe erecting method of the utility model;

图7是本实用新型的钻杆接立根方法作业流程图之五;Fig. 7 is the fifth of the operation flow chart of the drilling pipe erecting method of the present utility model;

图8是本实用新型的钻杆接立根方法作业流程图之六;Fig. 8 is the sixth of the operating flow chart of the drilling pipe erecting method of the present utility model;

图9是本实用新型的钻杆接立根方法作业流程图之七;Fig. 9 is the seventh of the operating flow chart of the drilling pipe erecting method of the utility model;

图10是本实用新型的钻杆接立根方法作业流程图之八;Fig. 10 is the eighth of the operating flow chart of the drill pipe connecting vertical root method of the present utility model;

图11是本实用新型的钻杆接立根方法作业流程图之九。Fig. 11 is the ninth operation flow chart of the drilling pipe erecting method of the present invention.

图中,1.猫道,2.举升机械手,3.电液控制系统,4.扶正夹头,5.提升滑车,6.液压大钳,7.立根架,8.悬持夹头,9.自动井架工,10.二层台。In the figure, 1. Catwalk, 2. Lifting manipulator, 3. Electro-hydraulic control system, 4. Uprighting chuck, 5. Lifting block, 6. Hydraulic tongs, 7. Standing frame, 8. Suspension chuck, 9. Automatic derrick, 10. Two-story platform.

具体实施方式 Detailed ways

下面结合附图和具体实施方式对本实用新型进行详细说明。The utility model will be described in detail below in conjunction with the accompanying drawings and specific embodiments.

如图1、图2所示,本实用新型的接立根装置结构是,在钻机钻台面前侧、大门坡道旁边固定安装有立根架7,在立根架7前坡道旁的地面上(基础面)固定安装有猫道1,在猫道1内安装有举升机械手2;在立根架7内安装有用于扶正钻杆单根的扶正夹头4、用于旋扣或紧扣的液压大钳6、用于提钻杆的提升滑车5以及钻杆的悬持夹头8;在钻机井架上安装有二层台10,在二层台10下方悬吊安装有自动井架工9。As shown in Fig. 1 and Fig. 2, the erection device structure of the present utility model is that an erection frame 7 is fixedly installed on the front side of the drill floor of the drilling rig and beside the gate ramp, and on the ground beside the front ramp of the erection frame 7 (foundation surface) a catwalk 1 is fixedly installed, and a lifting manipulator 2 is installed in the catwalk 1; a straightening chuck 4 for straightening a single drill pipe, and a hydraulic clamp for twisting or fastening are installed in the stand frame 7 Clamp 6, the hoisting block 5 that is used to lift drill pipe and the suspension chuck 8 of drill pipe; A two-story platform 10 is installed on the derrick of the drilling rig, and an automatic derrick worker 9 is suspended and installed below the two-story platform 10.

扶正夹头4、液压大钳6、提升滑车5以及悬持夹头8均安装在立根架7内,它们相互配合用于将钻杆单根连接为立根。Righting chuck 4, hydraulic tongs 6, lifting block 5 and suspension chuck 8 are all installed in the stand frame 7, and they cooperate with each other to be used to connect the single root of the drilling rod as a stand.

举升机械手2、扶正夹头4、提升滑车5、液压大钳6以及悬持夹头8均与电液控制系统3联通,电液控制系统3集成在地面的液压站内,接受统一的控制。The lifting manipulator 2, the righting chuck 4, the lifting block 5, the hydraulic tongs 6 and the suspension chuck 8 are all connected with the electro-hydraulic control system 3, which is integrated in the hydraulic station on the ground and accepts unified control.

自动井架工9悬吊于二层台10下方,用于将立根从立根架7内吊运到所需要的位置(二层台指梁内或井口)供钻井作业使用。The automatic derrick worker 9 is suspended below the second floor platform 10, and is used for lifting the vertical root from the vertical root frame 7 to the required position (in the second floor platform finger beam or wellhead) for drilling operations.

上述各个部件(举升机械手2、扶正夹头4、提升滑车5、液压大钳6、悬持夹头8以及自动井架工9)的执行机构均设置有位置传感器,用于位置检测或限位控制,并利用电液控制系统3对该套装置内各部件动作进行可编程控制,具有安全互锁功能。The actuators of the above components (lifting manipulator 2, righting chuck 4, lifting block 5, hydraulic tongs 6, suspension chuck 8 and automatic derrick 9) are all equipped with position sensors for position detection or limit Control, and use the electro-hydraulic control system 3 to programmably control the actions of the various components in the device, with a safety interlock function.

本实用新型装置在进行钻杆接立根的操作时,包括以下步骤:The utility model device comprises the following steps when carrying out the operation of connecting the drill pipe to the vertical root:

步骤1、单根地面传送:将钻杆放入或滚入猫道1中间的举升机械手2卡爪内,卡紧后举升机械手2在油缸的作用下举升钻杆,将单根钻杆直立在立根架7内(参见图3)。Step 1. Single ground transmission: Put or roll the drill pipe into the jaws of the lifting manipulator 2 in the middle of the catwalk 1. After clamping, the lifting manipulator 2 lifts the drill pipe under the action of the oil cylinder, and the single drill pipe The rod stands upright in the stand frame 7 (seeing figure 3).

步骤2、连接立根:立根架7内的提升滑车5下行,提升滑车5将钻杆夹持牢靠后,举升机械手2退让离开钻杆(如图4);提升滑车5上行约一单根钻杆的高度,使得钻杆下端上升到液压大钳6的高度(如图5);举升机械手2举升第二根钻杆并将第二根钻杆直立在立根架7内后,提升滑车5下行使第一根钻杆与之对好扣,液压大钳6前移分别夹持上、下钻杆的下、上接头后,举升机械手2退让离开第二根钻杆,扶正夹头4扶正第二根钻杆,通过液压大钳6将第二根钻杆与第一根钻杆连接好(如图6);之后松开扶正夹头4和液压大钳6,提升滑车5继续上提组合好的两根钻杆约一单根高度,使得第二根钻杆下端上升到液压大钳6的高度(如图7);举升机械手2举升第三根钻杆并将第三根钻杆直立在立根架7内后,提升滑车5下行使第二根钻杆与第三根钻杆组合并对好扣,液压大钳6前移分别夹持两根钻杆(第二根钻杆与第三根钻杆)组合的下、上接头后,举升机械手2退让离开第三根钻杆,扶正夹头4扶正第三根钻杆,自此通过液压大钳6将第三根钻杆和前两根钻杆组合连接好,完成第三单根的连接,自此完成整个立根连接(如图8);悬持夹头8夹持连接好的立根,提升滑车5卡爪松开,下行约一单根高度再夹持立根(如图9);提升滑车5夹好立根后将整个立根上提到钻台面以上,整个立根上端接近二层台10的高度位置,以便安装在二层台10下方的自动井架工9抓取(如图10)。Step 2. Connect the vertical root: the lifting block 5 in the vertical root frame 7 goes down, and after the lifting block 5 clamps the drill pipe firmly, the lifting manipulator 2 retreats away from the drill pipe (as shown in Figure 4); the lifting block 5 goes up about a single drill the height of the rod so that the lower end of the drill rod rises to the height of the hydraulic tongs 6 (as shown in Figure 5); after the lifting manipulator 2 lifts the second drill rod and erects the second drill rod in the stand frame 7, the block is lifted 5. Execute the first drill pipe to make a good buckle with it. After the hydraulic tongs 6 move forward to respectively clamp the lower and upper joints of the upper and lower drill pipes, the lifting manipulator 2 backs away from the second drill pipe and straightens the chuck. 4 Right the second drill pipe, connect the second drill pipe with the first drill pipe through the hydraulic tongs 6 (as shown in Figure 6); then loosen the righting chuck 4 and the hydraulic tongs 6, and lift the block 5 to continue Lift the combined two drill pipes to about a single height, so that the lower end of the second drill pipe rises to the height of the hydraulic tongs 6 (as shown in Figure 7); the lifting manipulator 2 lifts the third drill pipe and lifts the second After the three drill pipes stand upright in the stand frame 7, the second drill pipe and the third drill pipe are combined and fastened by lifting the block 5, and the hydraulic tongs 6 move forward to hold the two drill pipes (the second drill pipe respectively). After the lower and upper joints of the combination of the first drill pipe and the third drill pipe), the lifting manipulator 2 retreats away from the third drill pipe, and the righting chuck 4 straightens the third drill pipe. The three drill pipes are combined with the first two drill pipes, and the third single connection is completed, and the entire vertical root connection is completed (as shown in Figure 8); the connected vertical root is clamped by the suspension chuck 8, and the pulley is lifted by 5 clamps Loosen the claws, go down about a single height and then clamp the vertical root (as shown in Figure 9); after lifting the block 5 to clamp the vertical root, lift the entire vertical root above the drill floor, and the upper end of the entire vertical root is close to the height of the second floor platform 10, so that The automatic derrick worker 9 that is installed under the platform 10 on the second floor grabs (as shown in Figure 10).

步骤3、立根钻台传送:自动井架工9在立根架7上方抓取已连接好的立根,提升滑车5松开卡爪后,自动井架工9将立根转移到所需要的位置(二层台指梁内或井口),供钻井作业使用(如图11)。Step 3. Pipe stand transmission: the automatic derrick worker 9 grabs the connected vertical root on the top of the vertical root frame 7, and after lifting the block 5 to release the claws, the automatic derrick worker 9 transfers the vertical root to the required position (the second-floor platform refers to the inside of the beam or the wellhead) for drilling operations (as shown in Figure 11).

钻杆下钻台的步骤与上述的步骤相反。The step of getting the drill pipe down the drill floor is opposite to the above-mentioned steps.

本实用新型的钻杆接立根方法与现有常规人工操作方式相比,钻杆上、下钻台,接、卸立根均不需占用顶驱及井口工具,节省大量时间,提高钻井效率;钻杆输送及接立根过程均为机械化操作,不需工人在危险区域作业,明显减轻工人劳动强度,避免发生不安全事故。Compared with the existing conventional manual operation method, the drill pipe erecting method of the utility model does not need to occupy the top drive and wellhead tools when the drill pipe is put on and off the drill floor, and the vertical root is connected and unloaded, which saves a lot of time and improves drilling efficiency; The process of pole conveying and standing root connection is mechanized operation, which does not require workers to work in dangerous areas, significantly reduces the labor intensity of workers, and avoids unsafe accidents.

Claims (2)

1.一种用于钻杆接立根的装置,其特征在于:在钻机钻台面前侧、大门坡道旁边固定安装有立根架(7),在立根架(7)前坡道旁的地面上固定安装有猫道(1),在猫道(1)内安装有举升机械手(2);在立根架(7)内安装有扶正夹头(4)、液压大钳(6)、提升滑车(5)以及悬持夹头(8);在钻机井架上安装有二层台(10),在二层台(10)下方悬吊安装有自动井架工(9);1. A device for connecting vertical roots of drill pipes, characterized in that: a vertical root frame (7) is fixedly installed on the front side of the drill floor of the drilling rig and next to the gate ramp, and on the ground beside the front ramp of the vertical root frame (7) The catwalk (1) is fixedly installed, and the lifting manipulator (2) is installed in the catwalk (1); the erecting chuck (4), hydraulic tongs (6), and lifting tackle are installed in the stand frame (7) (5) and the suspension chuck (8); a two-story platform (10) is installed on the derrick of the drilling rig, and an automatic derrick worker (9) is suspended and installed under the two-story platform (10); 所述的举升机械手(2)、扶正夹头(4)、提升滑车(5)、液压大钳(6)以及悬持夹头(8)均与电液控制系统(3)联通。The lifting manipulator (2), righting chuck (4), lifting block (5), hydraulic tongs (6) and suspension chuck (8) are all communicated with the electro-hydraulic control system (3). 2.根据权利要求1所述的用于钻杆接立根的装置,其特征在于:所述的举升机械手(2)、扶正夹头(4)、提升滑车(5)、液压大钳(6)、悬持夹头(8)以及自动井架工(9)均设置有位置传感器。2. The device for connecting drill pipes to vertical roots according to claim 1, characterized in that: the lifting manipulator (2), the righting chuck (4), the lifting block (5), the hydraulic tongs (6 ), the suspension chuck (8) and the automatic derrick (9) are all provided with position sensors.
CN2012202742002U 2012-06-12 2012-06-12 Device for connecting drill pipes with three-joint unit Expired - Fee Related CN202673195U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012202742002U CN202673195U (en) 2012-06-12 2012-06-12 Device for connecting drill pipes with three-joint unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012202742002U CN202673195U (en) 2012-06-12 2012-06-12 Device for connecting drill pipes with three-joint unit

Publications (1)

Publication Number Publication Date
CN202673195U true CN202673195U (en) 2013-01-16

Family

ID=47494106

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012202742002U Expired - Fee Related CN202673195U (en) 2012-06-12 2012-06-12 Device for connecting drill pipes with three-joint unit

Country Status (1)

Country Link
CN (1) CN202673195U (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102720448A (en) * 2012-06-12 2012-10-10 宝鸡石油机械有限责任公司 Device and method for connecting drill rod with three-joint unit
CN103382820A (en) * 2013-07-23 2013-11-06 甘肃蓝科石化高新装备股份有限公司 Power rat hole device of marine drilling platform
CN103437723A (en) * 2013-08-29 2013-12-11 宝鸡石油机械有限责任公司 Device and method for discharging drilling machine stand
CN104278957A (en) * 2014-09-30 2015-01-14 中国石油集团川庆钻探工程有限公司长庆钻井总公司 Device for automatically moving drill pipes onto and off drill floor
CN104763356A (en) * 2015-02-04 2015-07-08 宝鸡石油机械有限责任公司 Automatic vertical tube bank lifting device
CN105422022A (en) * 2015-12-11 2016-03-23 四川中曼电气工程技术有限公司 Automatic tube distributing device of petroleum drilling machine
CN105484683A (en) * 2016-01-22 2016-04-13 中石化石油工程机械有限公司第四机械厂 Automatic discharge device for drill strings
CN105672874A (en) * 2016-02-05 2016-06-15 四川宏华石油设备有限公司 Automatic drilling machine
CN105804677A (en) * 2016-03-29 2016-07-27 四川宏华石油设备有限公司 Pipe processing device

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102720448B (en) * 2012-06-12 2014-10-22 宝鸡石油机械有限责任公司 Device and method for connecting drill rod with three-joint unit
CN102720448A (en) * 2012-06-12 2012-10-10 宝鸡石油机械有限责任公司 Device and method for connecting drill rod with three-joint unit
CN103382820B (en) * 2013-07-23 2016-01-20 甘肃蓝科石化高新装备股份有限公司 Marine drilling platform dynamic rathole device
CN103382820A (en) * 2013-07-23 2013-11-06 甘肃蓝科石化高新装备股份有限公司 Power rat hole device of marine drilling platform
CN103437723A (en) * 2013-08-29 2013-12-11 宝鸡石油机械有限责任公司 Device and method for discharging drilling machine stand
CN104278957A (en) * 2014-09-30 2015-01-14 中国石油集团川庆钻探工程有限公司长庆钻井总公司 Device for automatically moving drill pipes onto and off drill floor
CN104763356A (en) * 2015-02-04 2015-07-08 宝鸡石油机械有限责任公司 Automatic vertical tube bank lifting device
CN104763356B (en) * 2015-02-04 2017-03-15 宝鸡石油机械有限责任公司 Automatic vertical comb lifting device
CN105422022A (en) * 2015-12-11 2016-03-23 四川中曼电气工程技术有限公司 Automatic tube distributing device of petroleum drilling machine
CN105484683A (en) * 2016-01-22 2016-04-13 中石化石油工程机械有限公司第四机械厂 Automatic discharge device for drill strings
CN105672874A (en) * 2016-02-05 2016-06-15 四川宏华石油设备有限公司 Automatic drilling machine
CN105672874B (en) * 2016-02-05 2018-06-19 四川宏华石油设备有限公司 A kind of automated drilling rig
CN105804677A (en) * 2016-03-29 2016-07-27 四川宏华石油设备有限公司 Pipe processing device

Similar Documents

Publication Publication Date Title
CN102720448B (en) Device and method for connecting drill rod with three-joint unit
CN202673195U (en) Device for connecting drill pipes with three-joint unit
CN206608120U (en) Land rig connects the tubing string processing system of thribble offline
CN104563912B (en) A kind of well drilling pipe column automation operating system
CN104594829B (en) A kind of automatic rigger being applicable to double-wellhead comb operation and method
CN103437723A (en) Device and method for discharging drilling machine stand
CN205743770U (en) A kind of collapsible dynamic catwalk device
CN210977337U (en) Automatic workover rig
CN110295856B (en) Hydraulic vertical lifting automatic workover rig
CN203769680U (en) Novel automatic catwalk device
CN206360662U (en) The multi-functional tube drawbench of marine drilling platform
CN202108420U (en) Land headframe for duplex rig
CN203614056U (en) Automatic operation system of drilling tubular column
CN111520088A (en) Vehicle-mounted small workover wellhead operation device and method
CN202064840U (en) Four-drill column drill derrick
CN206928916U (en) Stacking tubing string manipulator
CN106194067A (en) Off-line sets up root device
CN102199996B (en) Stand connection method and device thereof
CN205241057U (en) Simple and easy grapple is used in pipeline hoist and mount
CN113669017B (en) Land continuous tripping drilling machine and continuous tripping operation method
CN104278957A (en) Device for automatically moving drill pipes onto and off drill floor
CN202785255U (en) Turnover hoisting tool for reinforced concrete pipe joint
CN204283250U (en) In well, tubing string removes automation equipment
CN215804392U (en) Land continuous tripping drilling machine
CN102121373B (en) Lifting system of hollow traveling block drill

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130116

Termination date: 20150612

EXPY Termination of patent right or utility model