- China
- Prior art keywords
- locker
- otic placode
- plate
- mounting plate
- steel construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 42
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 32
- 239000010959 steel Substances 0.000 title claims abstract description 32
- 239000007787 solid Substances 0.000 claims 1
- 238000009434 installation Methods 0.000 abstract description 4
- 230000009286 beneficial effect Effects 0.000 abstract description 2
- 238000009435 building construction Methods 0.000 abstract description 2
- 238000000034 method Methods 0.000 description 4
- 238000010586 diagram Methods 0.000 description 3
- 238000000151 deposition Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 239000004570 mortar (masonry) Substances 0.000 description 2
- 208000019901 Anxiety disease Diseases 0.000 description 1
- 230000036506 anxiety Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000007717 exclusion Effects 0.000 description 1
- 239000012634 fragment Substances 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 230000036316 preload Effects 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
- Clamps And Clips (AREA)
Abstract
The invention discloses a kind of lockers for steel construction horizontal sliding, belong to the realm of building construction, including locker otic placode, locker ontology and locking wedge block, locker ontology is fixedly mounted below locker otic placode, locker ontology lower surface is equipped with the locking sliding slot for being used for installation locking voussoir and passing through for track, locking sliding slot the right and left is inclined ramp, locks and is equipped with symmetrical two locking wedge blocks on sliding slot;Locking wedge block is integrally in the shape of a right-angled ladder, and inclined side is contacted with inclined ramp;Adjusting screw rod is fixedly installed on locker otic placode, adjusting screw rod one end is cased with preloading spring, and preloading spring one end is fixedly connected on adjusting screw rod, and the other end is fixedly connected on locking wedge block.The beneficial effects of the present invention are: carrying out horizontal sliding construction using this locker, horizontal sliding function and steel construction are separated, have the characteristics that structure is simple, versatile, occupying little space is very suitable to narrow field environment, installation and easy to operate.
Description
Technical field
The present invention relates to the realm of building construction more particularly to a kind of lockers for steel construction horizontal sliding.
Background technique
For large span complex steel structure engineering, such as stadiums, terminal, exhibition center Long Span Roof Structures,
Since field condition is more complicated, can not be using full hall scaffold construction or fragment lifting due to narrow field, duration anxiety etc.
Etc. forms of construction work, relatively be suitble to using slip mode construct.
Slipping and assembling platform generally ride upon large-span steel it is long to certain side, be sliding element platform for lining, and
The starting point for implementing sliding can carry out down a piece of sliding after completing the assembly of a sliding element and sliding out platform for lining
The assembly of unit.After piston shoes are removed in sliding design position, support is fixed in substructure, repeats this process until having constructed
At.
As the application for a patent for invention of Publication No. CN107142966A discloses a kind of top dress cunning for reverse construction
Rail horizontal transporter and its construction method, including be installed on the floor bottom surface of reverse construction upper layer track, sliding
Device, lifting rope and transport vehicle, transport vehicle are lifted on the carriage by lifting rope, and carriage is installed on the track
It goes up and can have and moved along track.The patent using lifting by the way of, have that structure is complicated, is not used to narrow field
In environment, rock the problems such as serious.
For another example the utility model that notification number is CN207701143U discloses the complete tooling construction of two lining integration of one kind and sets
It is standby, including guarded drainage construction part, two lining sliding slots by window enter mould pour part, vault band mould mortar depositing construction part and auxiliary move
Part, the auxiliary movable part along being arranged in parallel to trimmed tunnel bottom surface central axes direction, and on the auxiliary movable part by
It is interior to outer set gradually guarded drainage construction part, two lining sliding slots by window enter mould pour part and vault band mould mortar depositing construction part;
The auxiliary movable part is set as including biserial slideway, movable block, column, crossbeam and retaining mechanism;The column is set as
Telescopic column.It exists in the environment that structure is complicated, is not suitable for narrow field, the problems such as troublesome in poeration.
Summary of the invention
For overcome in the prior art building apply middle horizontal sliding device exist structure is complicated, be not suitable for narrow field environment,
The problems such as inconvenient for installation and operation, the present invention provides a kind of lockers for steel construction horizontal sliding, including locker
Otic placode, locker ontology and locking wedge block, the locker ontology are fixedly mounted below the locker otic placode, the locking
Device ontology lower surface is equipped with the locking sliding slot for installing the locking wedge block and passing through for track, described locking sliding slot or so two
While being inclined ramp, symmetrical two locking wedge blocks are installed on the locking sliding slot;The locking wedge block is whole
In the shape of a right-angled ladder, inclined side is contacted with the inclined ramp;It is fixedly installed with adjusting screw rod on the locker otic placode, institute
It states adjusting screw rod and is cased with preloading spring close to described locking wedge block one end, described preloading spring one end is fixedly connected on the adjusting
On screw rod, the other end is fixedly connected on the locking wedge block.
Cooperated using locking wedge block, inclined ramp and preloading spring to lock and unlock track from track two sides, it is real
Now to the clamping of track and loosen, and by the way that hydraulic cylinder is mounted on the pushing tow realized before and after locker otic placode on side to steel construction
With pull, to reach horizontal sliding of the steel construction along track length direction.
Further, three right-angle sides of the locking wedge block are parallel with three sides on the locker ontology respectively, and two
The locking wedge block is equipped among adjacent both sides for installing orbital pass in orbit.
Further, the locker otic placode includes front ear plate, rear otic placode, front ear plate mounting plate, rear otic placode mounting plate, locking
Device ontology mounting plate and support plate, the locker ontology mounting plate lower surface are equipped with the locker ontology, the vestibule
Plate mounting plate and it is described after otic placode mounting plate be fixedly mounted on the locker ontology mounting plate front and rear sides and with the locking
Device ontology mounting plate is vertical, and the front ear plate and the rear otic placode are separately mounted to the front ear plate mounting plate and the rear otic placode
On mounting plate;The support plate is mounted on the locker ontology mounting plate upper surface, and its front and rear sides is fixedly mounted on
On the front ear plate mounting plate and the rear otic placode mounting plate.
Further, the adjusting screw rod is fixedly mounted on the rear otic placode mounting plate, and the preloading spring is covered described
Adjusting screw rod front end.
Further, be separately installed at left and right sides of locker ontology lower surface for by the locking wedge block support in institute
The voussoir supporting plate in locking sliding slot is stated, the voussoir supporting plate is fixedly mounted on the locker ontology by the first bolt.
Further, the front ear plate mounting plate is fixedly installed with antidumping hook plate close to the front ear plate on one side.
Further, the antidumping hook plate includes hook plate mounting portion and curved hook portion, and the hook plate mounting portion passes through second
The antidumping hook plate is fixedly mounted on the front ear plate mounting plate by bolt, and the curved hook portion setting is pacified in the hook plate
Fill subordinate portion close to track side and by track support on it.
Further, the front ear plate mounting plate and the rear otic placode mounting plate are equipped with the front ear plate passed through for track below
Slot and rear otic placode slot, the curved hook portion are arranged in the front ear plate groove location.
Since track passes through among front ear plate slot and rear otic placode slot, upside and the left and right sides are limited in front ear plate
In slot and rear otic placode slot, and by installing antidumping hook plate at otic placode groove location, can effectively it limit on the downside of track, to make
Obtaining locker can not topple from track.
Further, the angle of the inclined ramp and track length direction is 15 ~ 30 °.
Further, the front ear plate and the rear otic placode are equipped with the mounting hole for installing hydraulic cylinder.
When hydraulic cylinder is mounted on front ear plate, when hydraulic cylinder stretches cylinder, locker otic placode integrally moves backward, due to locking
It is connected between voussoir and rear otic placode mounting plate by preloading spring, the speed moved backward is less than locker otic placode, and edge is inclined
Inclined ramp, which travels forward, pushes track side surfaces to, until track side surfaces are adjacent to, and by the friction of locking wedge block and track side surfaces
Power is by track locking;When contracting cylinder, locker otic placode integrally travels forward, due to leading between locking wedge block and rear otic placode mounting plate
Preloading spring is crossed to connect and be close to track side surfaces, the speed to travel forward is less than locker otic placode, and along inclined ramp to
After move away from track side surfaces, locker and track are detached from.
When hydraulic cylinder is mounted on rear otic placode, when hydraulic cylinder contracting cylinder, locker otic placode integrally moves backward, due to locking
It is connected between voussoir and rear otic placode mounting plate by preloading spring, the speed moved backward is less than locker otic placode, and edge is inclined
Inclined ramp, which travels forward, pushes track side surfaces to, until track side surfaces are adjacent to, and by the friction of locking wedge block and track side surfaces
Power is by track locking;When stretching cylinder, locker otic placode integrally travels forward, due to leading between locking wedge block and rear otic placode mounting plate
Preloading spring is crossed to connect and be close to track side surfaces, the speed to travel forward is less than locker otic placode, and along inclined ramp to
After move away from track side surfaces, locker and track are detached from.
Compared with prior art, the beneficial effects of the present invention are:
(1) cooperated using locking wedge block, inclined ramp and preloading spring to lock and unlock track from track two sides, realized
Clamping to track and loosen, and realized on side before and after locker otic placode to the pushing tow of steel construction by the way that hydraulic cylinder to be mounted on and
It pulls, to reach horizontal sliding of the steel construction along track length direction;
(2) pass through among front ear plate slot and rear otic placode slot due to track, upside and the left and right sides are limited in front ear plate
In slot and rear otic placode slot, and by installing antidumping hook plate at otic placode groove location, can effectively it limit on the downside of track, to make
Obtaining locker can not topple from track;
(3) horizontal sliding construction is carried out using this locker, horizontal sliding function and steel construction is separated, there is structure letter
It is single, versatile, occupy little space be very suitable to narrow field environment, installation and it is easy to operate the features such as.
Detailed description of the invention
Fig. 1 is the present invention preferably locker three-dimensional structure diagram;
Fig. 2 is the present invention preferably locker ontology and locking wedge block matching chart;
Fig. 3 is the present invention preferably locker otic placode structure chart;
Fig. 4 is the present invention preferably antidumping hook plate structure chart;
Fig. 5 is the present invention preferably pushing tow steel construction schematic diagram;
Fig. 6 is that the present invention preferably pulls steel construction schematic diagram.
Specific embodiment
With reference to embodiments and attached drawing, the present invention will be described in further detail.It should be appreciated that described herein
Specific examples are only used to explain the present invention, is not intended to limit the present invention.
As illustrated in fig. 1 and 2, the locker for steel construction horizontal sliding includes locker otic placode 1,2 and of locker ontology
Locking wedge block 3, the locker ontology 2 are fixedly mounted on 1 lower section of locker otic placode, 2 lower surface of locker ontology
Equipped with the locking sliding slot 21 for installing the locking wedge block 3 and passing through for track 4, described 21 the right and left of locking sliding slot is to incline
Inclined ramp 22 is equipped with symmetrical two locking wedge blocks 3 on the locking sliding slot 21;The locking wedge block 3 is whole
In the shape of a right-angled ladder, inclined side is contacted with the inclined ramp 22;Adjusting screw rod is fixedly installed on the locker otic placode 1
5, the adjusting screw rod 5 is cased with preloading spring 51 close to described 3 one end of locking wedge block, and described 51 one end of preloading spring is fixedly connected
On the adjusting screw rod 5, the other end is fixedly connected on the locking wedge block 3.Using locking wedge block, inclined ramp and preload
Spring, which is cooperated from track two sides, locks and unlocks track, realizes to the clamping of track and loosens, and by by hydraulic cylinder
It is mounted on and realizes the pushing tow to steel construction on the side of locker otic placode front and back and pull, to reach steel construction along track length direction
Horizontal sliding.
3 three right-angle sides of locking wedge block are parallel with three sides on the locker ontology 2 respectively, two locking wedges
The orbital pass 31 for being mounted on track 4 is equipped among the adjacent both sides of block 3.
Referring to Fig. 3, locker otic placode 1 includes front ear plate 11, rear otic placode 12, front ear plate mounting plate 13, rear otic placode mounting plate
14, locker ontology mounting plate 15 and support plate 16,15 lower surface of locker ontology mounting plate are equipped with the locker
Ontology 2, the front ear plate mounting plate 13 and the rear otic placode mounting plate 14 are fixedly mounted on the locker ontology mounting plate 15
Front and rear sides and vertical with the locker ontology mounting plate 15, the front ear plate 11 and it is described after otic placode 12 be separately mounted to institute
It states on front ear plate mounting plate 13 and the rear otic placode mounting plate 14;The support plate 16 is mounted on the locker ontology mounting plate
On 15 upper surfaces, and its front and rear sides is fixedly mounted on the front ear plate mounting plate 13 and the rear otic placode mounting plate 14.It adjusts
Section screw rod 5 is fixedly mounted on the rear otic placode mounting plate 14, and 51 sets of the preloading spring in 5 front end of adjusting screw rod.
It is separately installed at left and right sides of 2 lower surface of locker ontology for sliding 3 support of locking wedge block in the locking
Voussoir supporting plate 6 in slot 21, the voussoir supporting plate 6 are fixedly mounted on the locker ontology 2 by the first bolt 61.
Front ear plate mounting plate 13 is fixedly installed with antidumping hook plate 7 close to the front ear plate 11 on one side.Referring to fig. 4, resist and incline
Covering hook plate 7 includes hook plate mounting portion 71 and curved hook portion 72, and the hook plate mounting portion 71 anti-is inclined by the second bolt 73 by described
It covers hook plate 71 to be fixedly mounted on the front ear plate mounting plate 13, the curved hook portion 72 is arranged under the hook plate mounting portion 71
Portion close to 4 side of track and by 4 support of track on it.
Front ear plate mounting plate 13 and the rear otic placode mounting plate 14 are equipped with the vestibule board slot 131 passed through for track 4 below
With rear otic placode slot 141, the curved hook portion 71 is arranged in 131 position of vestibule board slot.Due to track from front ear plate slot and after
Passing through among otic placode slot, upside and the left and right sides are limited in vestibule board slot and rear otic placode slot, and by otic placode slot
Antidumping hook plate is installed at position, can effectively be limited on the downside of track, so that locker can not topple from track.
The angle of inclined ramp 22 and 4 length direction of track is 15 ~ 30 °.
Front ear plate 11 and the rear otic placode 12 are equipped with the mounting hole 111 for installing hydraulic cylinder.
Referring to Fig. 5, when hydraulic cylinder 20 is mounted on front ear plate, when hydraulic cylinder 20 stretches cylinder, locker otic placode is whole backward
Movement, due to being connected between locking wedge block and rear otic placode mounting plate by preloading spring, the speed moved backward is less than locking
Device otic placode, and travel forward along inclined ramp and push track side surfaces to, until track side surfaces are adjacent to, and rely on locking wedge block and rail
The frictional force of road side is by track locking, to realize the locking of locker 10 Yu track 4, hydraulic cylinder 20 pushes steel construction at this time
30 travel forward;When contracting cylinder, locker otic placode integrally travels forward, due to passing through between locking wedge block and rear otic placode mounting plate
Preloading spring connects and is close to track side surfaces, and the speed to travel forward is less than locker otic placode, and backward along inclined ramp
Track side surfaces are moved away from, locker 10 and track 4 are detached from, and locker 10 travels forward, and complete a pushing tow steel construction forward
30 process.
Referring to Fig. 6, when hydraulic cylinder 20 is mounted on rear otic placode, when 20 contracting cylinder of hydraulic cylinder, locker otic placode is whole backward
Movement, due to being connected between locking wedge block and rear otic placode mounting plate by preloading spring, the speed moved backward is less than locking
Device otic placode, and travel forward along inclined ramp and push track side surfaces to, until track side surfaces are adjacent to, and rely on locking wedge block and rail
The frictional force of road side is by track locking, to realize the locking of locker 10 Yu track 4, hydraulic cylinder 20 pushes steel construction at this time
30 travel forward;When stretching cylinder, locker otic placode integrally travels forward, due to passing through between locking wedge block and rear otic placode mounting plate
Preloading spring connects and is close to track side surfaces, and the speed to travel forward is less than locker otic placode, and backward along inclined ramp
Track side surfaces are moved away from, locker 10 and track 4 are detached from, and locker 10 travels forward, and completes one and pulls steel construction forward
30 process.
The preferred embodiment of the present invention has shown and described in above description, as previously described, it should be understood that the present invention is not office
Be limited to form disclosed herein, should not be regarded as an exclusion of other examples, and can be used for various other combinations, modification and
Environment, and can be changed within that scope of the inventive concept describe herein by the above teachings or related fields of technology or knowledge
It is dynamic.And changes and modifications made by those skilled in the art do not depart from the spirit and scope of the present invention, then it all should be appended by the present invention
In scope of protection of the claims.
Claims (10)
1. a kind of locker for steel construction horizontal sliding, which is characterized in that including locker otic placode, locker ontology and lock
Tight voussoir, the locker ontology are fixedly mounted below the locker otic placode, and locker ontology lower surface, which is equipped with, to be used
In the locking sliding slot installing the locking wedge block and passing through for track, described locking sliding slot the right and left is inclined ramp, described
Symmetrical two locking wedge blocks are installed on locking sliding slot;The locking wedge block is integrally in the shape of a right-angled ladder, inclines
Bevel edge is contacted with the inclined ramp;Adjusting screw rod is fixedly installed on the locker otic placode, the adjusting screw rod is close to institute
It states locking wedge block one end and is cased with preloading spring, described preloading spring one end is fixedly connected on the adjusting screw rod, and the other end is solid
Surely it is connected on the locking wedge block.
2. a kind of locker for steel construction horizontal sliding according to claim 1, which is characterized in that the locking wedge
Three right-angle sides of block are parallel with three sides on the locker ontology respectively, and two locking wedge blocks are set among adjacent both sides
There is the orbital pass for being mounted on track.
3. a kind of locker for steel construction horizontal sliding according to claim 2, which is characterized in that the locker
Otic placode includes front ear plate, rear otic placode, front ear plate mounting plate, rear otic placode mounting plate, locker ontology mounting plate and support plate, described
Locker ontology mounting plate lower surface is equipped with the locker ontology, the front ear plate mounting plate and the rear otic placode mounting plate
It is fixedly mounted on the locker ontology mounting plate front and rear sides and, the front ear plate vertical with the locker ontology mounting plate
It is separately mounted on the front ear plate mounting plate and the rear otic placode mounting plate with the rear otic placode;The support plate is mounted on institute
It states on locker ontology mounting plate upper surface, and its front and rear sides is fixedly mounted on the front ear plate mounting plate and the rear otic placode
On mounting plate.
4. a kind of locker for steel construction horizontal sliding according to claim 3, which is characterized in that the adjusting spiral shell
Bar is fixedly mounted on the rear otic placode mounting plate, and the preloading spring is covered in the adjusting screw rod front end.
5. a kind of locker for steel construction horizontal sliding according to claim 4, which is characterized in that the locker
It is separately installed at left and right sides of ontology lower surface for the voussoir supporting plate by the locking wedge block support in the locking sliding slot, institute
Voussoir supporting plate is stated to be fixedly mounted on the locker ontology by the first bolt.
6. a kind of locker for steel construction horizontal sliding according to claim 5, which is characterized in that the front ear plate
Mounting plate is fixedly installed with antidumping hook plate close to the front ear plate on one side.
7. a kind of locker for steel construction horizontal sliding according to claim 6, which is characterized in that the antidumping
Hook plate includes hook plate mounting portion and curved hook portion, and the hook plate mounting portion, which is fixed the antidumping hook plate by the second bolt, pacifies
On the front ear plate mounting plate, curved hook portion setting is in hook plate mounting portion lower part close to track side and by rail
Road support is on it.
8. a kind of locker for steel construction horizontal sliding according to claim 7, which is characterized in that the front ear plate
Mounting plate and the rear otic placode mounting plate are equipped with the vestibule board slot and rear otic placode slot passed through for track, the curved hook portion below
It is arranged in the front ear plate groove location.
9. a kind of locker for steel construction horizontal sliding according to claim 8, which is characterized in that the inclination is slided
The angle of road and track length direction is 15~30 °.
10. a kind of locker for steel construction horizontal sliding according to claim 9, which is characterized in that the vestibule
Plate and the rear otic placode are equipped with the mounting hole for installing hydraulic cylinder.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811258412.XA CN109339464B (en) | 2018-10-26 | 2018-10-26 | Locking device for horizontal sliding of steel structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811258412.XA CN109339464B (en) | 2018-10-26 | 2018-10-26 | Locking device for horizontal sliding of steel structure |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109339464A true CN109339464A (en) | 2019-02-15 |
CN109339464B CN109339464B (en) | 2024-04-09 |
Family
ID=65311951
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811258412.XA Active CN109339464B (en) | 2018-10-26 | 2018-10-26 | Locking device for horizontal sliding of steel structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109339464B (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109231071A (en) * | 2018-09-28 | 2019-01-18 | 中国化学工程第六建设有限公司 | Steel structure modularization construction process |
CN110512876A (en) * | 2019-08-28 | 2019-11-29 | 浙江精工钢结构集团有限公司 | A kind of heavy grade upward slope gliding construction method of steel construction |
CN112049433A (en) * | 2020-08-11 | 2020-12-08 | 上海隧道工程有限公司 | Steel truss pushing attitude control equipment and attitude control method thereof |
CN114592700A (en) * | 2022-02-28 | 2022-06-07 | 中建八局新型建造工程有限公司 | Auxiliary mounting and positioning device for steel structure roller type sliding shoes |
CN115450326A (en) * | 2022-10-27 | 2022-12-09 | 中南大学 | Incremental launching slide block type detachable module steel structure node and construction method thereof |
CN116076270A (en) * | 2023-02-10 | 2023-05-09 | 杭州利环环境集团有限公司 | Assembled flower bed capable of rapidly lifting river banks and park landscapes and construction method thereof |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201220283Y (en) * | 2008-07-03 | 2009-04-15 | 嘉兴永佳精密机械制造有限公司 | Locking mechanism of precision boring head |
JP2013076253A (en) * | 2011-09-30 | 2013-04-25 | Lalique:Kk | Floating prevention structure for scaffold board |
CN203079644U (en) * | 2012-11-26 | 2013-07-24 | 上海同济宝冶建设机器人有限公司 | Hydraulic gliding device |
CN106567550A (en) * | 2016-11-04 | 2017-04-19 | 同济大学 | Full-automatic bidirectional hydraulic rail clamping device |
CN209482738U (en) * | 2018-10-26 | 2019-10-11 | 中国建筑股份有限公司 | A kind of locker for steel construction horizontal sliding |
-
2018
- 2018-10-26 CN CN201811258412.XA patent/CN109339464B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201220283Y (en) * | 2008-07-03 | 2009-04-15 | 嘉兴永佳精密机械制造有限公司 | Locking mechanism of precision boring head |
JP2013076253A (en) * | 2011-09-30 | 2013-04-25 | Lalique:Kk | Floating prevention structure for scaffold board |
CN203079644U (en) * | 2012-11-26 | 2013-07-24 | 上海同济宝冶建设机器人有限公司 | Hydraulic gliding device |
CN106567550A (en) * | 2016-11-04 | 2017-04-19 | 同济大学 | Full-automatic bidirectional hydraulic rail clamping device |
CN209482738U (en) * | 2018-10-26 | 2019-10-11 | 中国建筑股份有限公司 | A kind of locker for steel construction horizontal sliding |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109231071A (en) * | 2018-09-28 | 2019-01-18 | 中国化学工程第六建设有限公司 | Steel structure modularization construction process |
CN110512876A (en) * | 2019-08-28 | 2019-11-29 | 浙江精工钢结构集团有限公司 | A kind of heavy grade upward slope gliding construction method of steel construction |
CN112049433A (en) * | 2020-08-11 | 2020-12-08 | 上海隧道工程有限公司 | Steel truss pushing attitude control equipment and attitude control method thereof |
CN114592700A (en) * | 2022-02-28 | 2022-06-07 | 中建八局新型建造工程有限公司 | Auxiliary mounting and positioning device for steel structure roller type sliding shoes |
CN114592700B (en) * | 2022-02-28 | 2023-12-08 | 中建八局新型建造工程有限公司 | Auxiliary installation positioning device for steel structure roller type sliding shoes |
CN115450326A (en) * | 2022-10-27 | 2022-12-09 | 中南大学 | Incremental launching slide block type detachable module steel structure node and construction method thereof |
CN115450326B (en) * | 2022-10-27 | 2024-04-26 | 中南大学 | Pushing sliding block type detachable module steel structure node and construction method thereof |
CN116076270A (en) * | 2023-02-10 | 2023-05-09 | 杭州利环环境集团有限公司 | Assembled flower bed capable of rapidly lifting river banks and park landscapes and construction method thereof |
CN116076270B (en) * | 2023-02-10 | 2024-05-03 | 杭州利环环境集团有限公司 | Assembled flower bed capable of rapidly lifting river banks and park landscapes and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN109339464B (en) | 2024-04-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109339464A (en) | A kind of locker for steel construction horizontal sliding | |
CN202324576U (en) | Rail-mounted platform system used for installing cornice and ceiling aluminium sheet curtain wall | |
CN209482738U (en) | A kind of locker for steel construction horizontal sliding | |
CN207003637U (en) | A kind of telescopic movable platform | |
CN113235890B (en) | Concrete ground leveling device | |
CN112943291A (en) | Multifunctional multi-section working platform vehicle for tunnel excavation | |
CN204960432U (en) | Underground vertical lifting stereo garage | |
CN217107006U (en) | Air pushing device of subway single-crossover shield machine | |
CN214783467U (en) | High-efficient interception buried type lifting road pile | |
DE10007656A1 (en) | Device for arranging and converting e.g. multi-function rooms such as sports halls etc. | |
CN105257041A (en) | Underground vertical lifting type stereo garage | |
CN211816944U (en) | Steel structure combination beam for assembly type building | |
CN204956680U (en) | Area reinforces shelter of loading and unloading certainly that blocks pole | |
KR101770230B1 (en) | Form traveller | |
CA2557554A1 (en) | A method and a device for the rail traffic on multiply, parallel guide-ways also as toys | |
CN108945175B (en) | Wall bicycle frame and using method thereof | |
CN219241266U (en) | Rail type integral moving scaffold | |
CN216196980U (en) | Stereo garage | |
JP2021046769A (en) | Bogie equipped with rail feeder | |
CN112593574B (en) | Hidden support construction device | |
CN210944411U (en) | Steel rope system for passenger elevator | |
CN211772779U (en) | Trestle support column mechanism for steel structure | |
CN221162840U (en) | Material transferring support for building construction | |
CN220600642U (en) | Horizontal adjustable push bench for municipal construction | |
DE102018129016A1 (en) | Prefabricated concrete component and loading system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |