CN109339128A - 预制式空心管桩纠偏方法 - Google Patents
预制式空心管桩纠偏方法 Download PDFInfo
- Publication number
- CN109339128A CN109339128A CN201811126242.XA CN201811126242A CN109339128A CN 109339128 A CN109339128 A CN 109339128A CN 201811126242 A CN201811126242 A CN 201811126242A CN 109339128 A CN109339128 A CN 109339128A
- Authority
- CN
- China
- Prior art keywords
- hollow shell
- shell pill
- pill
- vibration hammer
- correcting error
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D35/00—Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明涉及建筑技术领域,尤其涉及一种预制式空心管桩纠偏方法,包括以下步骤:步骤一、在相邻的两个空心管桩之间插入一个金属销,将两个空心管桩连成一个整体;步骤二、用振动锤的前端顶住空心管桩上部位置最低的一端,振动锤慢慢振动,使空心管桩垂直;步骤三、在空心管桩的上部放置一个垫块,振动锤通过垫块振动空心管桩,使相邻两个空心管桩之间的泥土排出;步骤四、取出金属销;步骤五、在空心管桩的内部放入钢筋和混凝土,封死空心管桩。通过本装置可以对倾斜的空心管桩进行纠偏,所采用的设备都是传统设备,可以大大节约施工成本,效率非常高,有效解决了目前空心管桩无法进行纠偏的难题。
Description
技术领域
本发明涉及建筑技术领域,尤其涉及一种预制式空心管桩纠偏方法。
背景技术
随着建筑科技的发展,桩基础施工领域更是日新月异。预应力高强混凝土管桩具有施工速度快、价格低、承载力高、质量稳定、养护时间短、施工方便无公害等诸多优点。近年来被广泛使用于各地基础工程,尤其是市政软土地基、湿陷性地基。现在国内除了普通的混凝土管桩,为了节约成本还出现了空心管桩,空心管桩由两节构成,两个管节之间会出现一定的倾斜,目前国家规定空心管桩的倾斜度不能超过±1%。但有些空心管桩已经存在倾斜的情况下就需要进行扶正,目前还没有一种合适的扶正方法。
发明内容
本发明的目的在于克服上述技术的不足,而提供一种预制式空心管桩纠偏方法。
本发明为实现上述目的,采用以下技术方案:
一种预制式空心管桩纠偏方法,其特征在于:包括以下步骤:步骤一、在相邻的两个空心管桩之间插入一个金属销,将两个空心管桩连成一个整体;
步骤二、用振动锤的前端顶住空心管桩上部位置最低的一端,振动锤慢慢振动,使空心管桩垂直;
步骤三、在空心管桩的上部放置一个垫块,振动锤通过垫块振动空心管桩,使相邻两个空心管桩之间的泥土排出;
步骤四、取出金属销;
步骤五、在空心管桩的内部放入钢筋和混凝土,封死空心管桩。
优选地,所述金属销的上部连接有钢丝绳。
优选地,在步骤三中,所述垫块的中部向下设有凹槽,凹槽的下部形成一个凸起,凸起的外径小于空心管桩的内径,振动锤前端插入到凹槽内,通过前后左右晃动和振动,排出相邻两个空心管桩之间的泥土。
优选地,在步骤二中,所述振动锤的前端设置一个卡块,卡块固定在振动锤的前端,卡块上带有卡槽,卡槽卡接在空心管桩的侧部夹角处。
本发明的有益效果是:相对于现有技术,通过本装置可以对倾斜的空心管桩进行纠偏,所采用的设备都是传统设备,可以大大节约施工成本,效率非常高,有效解决了目前空心管桩无法进行纠偏的难题。
附图说明
图1为本发明中步骤一和步骤二的工作状态图;
图2为本发明中步骤三的工作状体图;
图3为本发明中步骤五的工作状态图。
具体实施方式
下面结合附图及较佳实施例详细说明本发明的具体实施方式。如图1-3所示,一种预制式空心管桩纠偏方法,一般空心管桩为两节,本装置针对于两节预制空心管桩进行纠偏,具体包括以下步骤:步骤一、在相邻的两个空心管桩1之间插入一个金属销2,将两个空心管桩连成一个整体;该步骤是必须的步骤,如果不下入一个金属销后续步骤在进行时,上部的空心管桩就会整体进行移动,完全脱离下部的空心管桩,为此,经过试验,设计一根金属销,金属销的外径略小与空心管桩的内径,具有一定的重量,金属销的上部连接有钢丝绳。通过吊车将金属销下到两个空心管桩之间,这样后续再正上部空心管桩时,不会使上部的空心管桩脱离下部的空心管桩。
步骤二、用振动锤3的前端顶住空心管桩上部位置最低的一端,也就是倾斜的那一端,需要推动这端使整个空心管桩处于一个垂直度的状态。振动锤慢慢振动,使空心管桩垂直;在该步骤中,对振动锤进行了改进,所述振动锤的前端设置一个卡块4,卡块固定在振动锤的前端,卡块上带有卡槽,卡槽卡接在空心管桩的侧部夹角处。这样可以防止振动锤的力量集中到一个部位,导致空心管桩损坏。
如图2所示,步骤三、在空心管桩的上部放置一个垫块5,振动锤通过垫块振动空心管桩,使相邻两个空心管桩之间的泥土排出;所述垫块的中部向下设有凹槽6,凹槽的下部形成一个凸起7,凸起的外径小于空心管桩的内径,振动锤前端插入到凹槽内,通过前后左右晃动和振动,排出相邻两个空心管桩之间的泥土。
步骤四、取出金属销;
如图3所示,步骤五、在空心管桩的内部放入钢筋和混凝土8,封死空心管桩。本方法将空心管桩扶正后,重新注入钢筋混凝土,结构更加牢固。
以上所述仅是本发明的优选实施方式,应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以做出若干改进和润饰,这些改进和润饰也应视为本发明的保护范围。
Claims (4)
1.一种预制式空心管桩纠偏方法,其特征在于:包括以下步骤:步骤一、在相邻的两个空心管桩之间插入一个金属销,将两个空心管桩连成一个整体;
步骤二、用振动锤的前端顶住空心管桩上部位置最低的一端,振动锤慢慢振动,使空心管桩垂直;
步骤三、在空心管桩的上部放置一个垫块,振动锤通过垫块振动空心管桩,使相邻两个空心管桩之间的泥土排出;
步骤四、取出金属销;
步骤五、在空心管桩的内部放入钢筋和混凝土,封死空心管桩。
2.根据权利要求1所述的预制式空心管桩纠偏方法,其特征在于:所述金属销的上部连接有钢丝绳。
3.根据权利要求1所述的预制式空心管桩纠偏方法,其特征在于:在步骤三中,所述垫块的中部向下设有凹槽,凹槽的下部形成一个凸起,凸起的外径小于空心管桩的内径,振动锤前端插入到凹槽内,通过前后左右晃动和振动,排出相邻两个空心管桩之间的泥土。
4.根据权利要求1所述的预制式空心管桩纠偏方法,其特征在于:在步骤二中,所述振动锤的前端设置一个卡块,卡块固定在振动锤的前端,卡块上带有卡槽,卡槽卡接在空心管桩的侧部夹角处。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811126242.XA CN109339128A (zh) | 2018-09-26 | 2018-09-26 | 预制式空心管桩纠偏方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811126242.XA CN109339128A (zh) | 2018-09-26 | 2018-09-26 | 预制式空心管桩纠偏方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109339128A true CN109339128A (zh) | 2019-02-15 |
Family
ID=65306552
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811126242.XA Pending CN109339128A (zh) | 2018-09-26 | 2018-09-26 | 预制式空心管桩纠偏方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109339128A (zh) |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07292663A (ja) * | 1994-04-27 | 1995-11-07 | Shimizu Corp | 既設鋼管杭を利用した新規鋼管杭による打ち増し構造及び打ち増し工法 |
CN101793029A (zh) * | 2009-02-03 | 2010-08-04 | 叶长青 | 纠正桩偏的方法 |
CN106049500A (zh) * | 2016-05-30 | 2016-10-26 | 中交公局第二工程有限公司 | 一种振动助灌装置 |
-
2018
- 2018-09-26 CN CN201811126242.XA patent/CN109339128A/zh active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07292663A (ja) * | 1994-04-27 | 1995-11-07 | Shimizu Corp | 既設鋼管杭を利用した新規鋼管杭による打ち増し構造及び打ち増し工法 |
CN101793029A (zh) * | 2009-02-03 | 2010-08-04 | 叶长青 | 纠正桩偏的方法 |
CN106049500A (zh) * | 2016-05-30 | 2016-10-26 | 中交公局第二工程有限公司 | 一种振动助灌装置 |
Non-Patent Citations (2)
Title |
---|
殷婷婷等: "跨海大桥定位桩安装新工艺——GPS定位桩导向架技术研究介绍", 《中国高新技术企业》 * |
范晓等: "预应力管桩偏位处理方案", 《宁波大学学报(理工版)》 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103088819B (zh) | 预应力锚索施工方法 | |
CN105568856B (zh) | 一种稀索斜拉桥索梁同步施工方法 | |
CN106836463A (zh) | 承台及地梁结构的施工装置和施工方法 | |
CN106988303B (zh) | 一种桩基及其施工方法 | |
CN110106780A (zh) | 一种预制墩柱与桩基的连接结构、施工方法 | |
CN101718098B (zh) | 一种微型桩联合掏挖复合基础及其施工方法 | |
CN205776241U (zh) | 一种桁架式双排桩支护体系 | |
CN106351207A (zh) | 一种带u型后张法张拉的预制地下连续墙的施工方法 | |
CN108677930A (zh) | 一种孔桩钢筋笼的防锈蚀对中结构及其应用 | |
CN202194131U (zh) | 一种部分预应力支护悬臂桩 | |
CN109339128A (zh) | 预制式空心管桩纠偏方法 | |
CN210459261U (zh) | 一种混凝土桩基结构 | |
CN209211459U (zh) | 一种深埋pba地铁车站围护边桩 | |
CN208701659U (zh) | 一种孔桩钢筋笼的防锈蚀对中结构 | |
CN104264671A (zh) | 可回收锚杆 | |
CN209308032U (zh) | 一种土木工程施工用基桩支撑结构 | |
CN108278036B (zh) | 一种倾斜砖石古塔的纠偏方法 | |
CN108277817B (zh) | 高桩承台塔吊基础加固结构的施工方法 | |
CN206529881U (zh) | 承台及地梁结构的施工装置 | |
CN207512620U (zh) | 桥墩桩基加固结构 | |
CN106703023B (zh) | 一种液压锤击式四翼预制桩及其施工方法 | |
CN206570853U (zh) | 桩基托换中基桩与承台的连接结构 | |
CN201746830U (zh) | 长螺旋灌注桩后插笼工具 | |
CN109722984A (zh) | 一种半装配式薄壁桥墩及其装配方法 | |
CN211172060U (zh) | 一种光伏支架基础预埋钢套管的锚固结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190215 |
|
RJ01 | Rejection of invention patent application after publication |