CN109281398A - Boundling half, which is in the milk, constrains slurry anchor connection method - Google Patents
Boundling half, which is in the milk, constrains slurry anchor connection method Download PDFInfo
- Publication number
- CN109281398A CN109281398A CN201710646433.8A CN201710646433A CN109281398A CN 109281398 A CN109281398 A CN 109281398A CN 201710646433 A CN201710646433 A CN 201710646433A CN 109281398 A CN109281398 A CN 109281398A
- Authority
- CN
- China
- Prior art keywords
- boundling
- column
- prop
- connection
- milk
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/20—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
- E04B1/21—Connections specially adapted therefor
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Reinforcement Elements For Buildings (AREA)
Abstract
The present invention relates to civil engineering and environment and utilization of resources field, the connection of reinforcing bar suitable for assembled architecture, the reinforcing bar connection being particularly suitable in the precast concrete column of boundling arrangement of reinforcement.Boundling arrangement of reinforcement precast concrete column replaces the more reinforcing bars arranged along column surrounding in column four corners setting tendon, and the every side arrangement of reinforced column is more than 3 reinforcing bars, thus needs at least 8 reinforcing bars.It is size-limited, slurry anchor connection can not be used.According to sleeve connection, it is also desirable at least 8 connection reinforcing bars.The present invention is in the milk using boundling half for the connection of lower prop on boundling arrangement of reinforcement precast concrete and constrains slurry anchor connection method.The connection method is the preformed hole that upper prop is inserted by the tendon that boundling arrangement of reinforcement precast concrete lower prop is reserved, and is then injected into high-strength grout, realizes and connects between boundling armored concrete upper prop and lower prop.The connection can effectively transmit the internal force that vertical and horizontal loading generates on column, reduce the connection quantity and anchorage length of vertical reinforcement.
Description
Technical field
The present invention relates to civil engineering and environment and utilization of resources field, the connection of reinforcing bar suitable for assembled architecture,
It is particularly suitable for the connection of vertical reinforcement in the precast concrete column of boundling arrangement of reinforcement.
Background technique
General constraints slurry anchor connection uses relatively broad, the connection side in prefabricated concrete structure vertically connects at present
Method has many advantages, such as securely and reliably, at low cost.However, current general constraints slurry anchor connection still has following problems: (1) reserving
The quantity of reinforced hole is too many, cause in the construction process assembly difficulty it is larger, efficiency is lower.(2) it if bar diameter is thicker, reserves
Anchorage length of steel bar is longer, leads to the production of component, and installation and difficulty of construction are larger.
Summary of the invention
The present invention proposes a kind of new to reduce the connection quantity of vertical reinforcement and shorten the anchorage length of reserved steel bar
Type connection type, the connection type can replace the more reinforcing bars or thick of column periphery arrangement using the tendon formed compared with fine steel rib
Reinforcing bar, thus reduce the connection quantity of vertical reinforcement and shorten the anchorage length of reserved steel bar, so that assembly is simpler, efficiency
It improves, while also reducing site operation installation difficulty, can preferably be applied in practice in engineering.
The constraint slurry anchor connection method the technical scheme adopted by the invention is that boundling half is in the milk, by upper layer concrete column, under
Slip casting composition between layer concrete column and upper and lower layer precast concrete column;Upper layer concrete column include upper prop boundling reinforcing bar,
The slip casting of the preformed hole, upper prop concrete, tie hoop, the grout outlet of upper prop preformed hole upper end, upper prop preformed hole lower end of upper prop
Mouthful;Lower-layer concrete column includes the reserved boundling reinforcing bar of lower prop, lower prop concrete, tie hoop.Installation method are as follows: mix upper layer
The preformed hole of solidifying earth pillar is directly directed at the reserved tendon of lower prop and falls, using dedicated adjustment device adjustment column position and vertically
Degree, it is fixed after adjustment, and with behind the upper and lower prefabricated dress concrete column gap of layer of high-strength fast hard mortar closure, it is infused in reserved grouting port
Slurry, until grout outlet pulp, the boundling half for finally completing prefabricated post, which is in the milk, constrains slurry anchor connection.
Under normal circumstances, the more reinforcing bars arranged along column periphery are replaced in column four corners location arrangements boundling reinforcing bar.And
The outer diameter of lower prop reserved steel bar beam should be identical as the internal diameter of upper prop preformed hole, and reserved steel bar beam outer diameter tolerance is minus tolerance, in advance
Internal diameter tolerance of boxing out is principal-employment.
The preformed hole upper and lower side of upper prop is respectively provided with grout outlet and grouting port, and uses pvc pipe as the drainage pipe of slurry,
According to the diameter and depth of reserving hole, the grouting port and grout outlet of different-diameter are set;According to the grouting equipment of different model
The rubber sleeve of different-diameter is selected, guarantees the connection of grouting equipment and grouting port.
After adopting the above scheme, 1. precast concrete columns of the invention are had the advantages that compared with prior art
Vertical connection method reinforcing bar replaces more of column periphery arrangement compared with bar reinforcement by the tendon formed compared with fine steel rib, can reduce perpendicular
To the connection quantity of reinforcing bar and the anchorage length of shortening reserved steel bar, the difficulty of installation and construction is greatly reduced.2. needle of the present invention
It is in the milk to boundling arrangement of reinforcement precast concrete column using boundling half and constrains slurry anchor connection method, make boundling reinforcing bar, the spiral hoop of upper prop
The reserved steel bar beam and concrete of muscle, lower prop, form firm effect of contraction, enhance boundling arrangement of reinforcement precast concrete column
Bearing capacity and deformability.
Detailed description of the invention
Fig. 1 is upper layer precast concrete column;
Fig. 2 is lower layer's precast concrete column;
Fig. 3 upper prop and lower prop junction;
Fig. 4 is sectional view at the A-A of Fig. 3;
Fig. 5 is sectional view at the B-B of Fig. 3;
Fig. 6 is sectional view at the C-C of Fig. 3;
Fig. 7 is sectional view at the D-D of Fig. 3;
Fig. 8 is bundle holes junction connection detail;
Fig. 9 is the 3 d effect graph after upper prop is connected with lower prop using half grouting constraint slurry anchor connection method of boundling.
In figure: 1, upper layer concrete column;2, lower-layer concrete column;3, high-strength grout;4, the boundling reinforcing bar of upper prop;5, on
The preformed hole of column;6, upper prop concrete;7, tie hoop;8, slurry outlet;9, injected hole;10, the reserved steel bar beam of lower prop;11,
Lower prop concrete.
Specific embodiment
With reference to the accompanying drawing and specific embodiment the present invention will be further described:
Of the present invention is half grouting constraint slurry anchor connection method of boundling, by upper layer concrete column, lower-layer concrete
Slip casting composition between column and upper and lower layer precast concrete column;Upper layer concrete column include upper prop boundling reinforcing bar, upper prop it is pre-
Box out, upper prop concrete, tie hoop, the grout outlet of upper prop preformed hole upper end, upper prop preformed hole lower end grouting port;Lower layer is mixed
Solidifying earth pillar includes the reserved boundling reinforcing bar of lower prop, lower prop concrete, tie hoop.Installation method are as follows: by upper layer concrete column
Preformed hole is directly directed at the reserved tendon of lower prop and falls, using dedicated adjustment device adjustment column position and verticality, after adjustment
It is fixed, and after blocking the upper and lower prefabricated dress concrete column gap of layer with high-strength fast hard mortar, in reserved grouting port slip casting, up to out
Mouth pulp is starched, the boundling half for finally completing prefabricated post, which is in the milk, constrains slurry anchor connection.
It herein also refers to out for the technological staff of the art simultaneously, is not departing from the principle of the present invention feelings
It under condition, can also make improvements, these improvement all should belong within protection scope of the present invention.What is be not known in the present embodiment is each
Component part can all be realized by the prior art.
Claims (6)
- The constraint slurry anchor connection method 1. boundling half is in the milk, it is characterised in that: by upper layer concrete column (1), lower-layer concrete column (2) and above and below slip casting (3) forms between layer precast concrete column;Upper layer concrete column include upper prop boundling reinforcing bar (4), on The preformed hole (5) of column, upper prop concrete (6), tie hoop (4), upper prop preformed hole upper end grout outlet (8), upper prop preformed hole The grouting port (9) of lower end;Lower-layer concrete column includes the reserved boundling reinforcing bar (10) of lower prop, lower prop concrete (11), spiral hoop Muscle (7).Installation method are as follows: the preformed hole of upper layer concrete column is directly aligned to the reserved tendon of lower prop and is fallen, use is dedicated Device adjustment column position and verticality are adjusted, it is fixed after adjustment, and the upper and lower prefabricated dress concrete of layer is blocked with high-strength fast hard mortar After intercolumniation gap, in reserved grouting port slip casting, until grout outlet pulp, the half grouting constraint slurry anchor of boundling for finally completing prefabricated post connects It connects.
- The constraint slurry anchor connection method 2. boundling according to claim 1 half is in the milk, it is characterised in that: the upper prop boundling steel The tendon (10) that muscle (4) and lower prop are reserved can be replaced compared with fine steel rib according to requirement is calculated by more, the element mechanics after replacement Performance should reach the demand of design.
- The constraint slurry anchor connection method 3. boundling according to claim 1 half is in the milk, it is characterised in that: according to precast concrete Column cross-section size and arrangement of reinforcement, by the diameter and depth of the preformed hole (5) for calculating determining upper prop.
- The constraint slurry anchor connection method 4. boundling according to claim 1 half is in the milk, it is characterised in that: the upper layer concrete Rough surface is made in the joint face of column (1) and lower-layer concrete column (2).
- The constraint slurry anchor connection method 5. boundling according to claim 1 half is in the milk, it is characterised in that: the upper layer concrete Set the gap not less than 20mm between column (1) and lower-layer concrete column (2), and with the slip casting simultaneously of the preformed hole of upper prop, formed whole Body.
- The constraint slurry anchor connection method 6. boundling according to claim 1 half is in the milk, it is characterised in that: the upper layer concrete Column (1) replaces the more reinforcing bars arranged along column periphery in column four corners location arrangements boundling reinforcing bar.And lower prop reserved steel bar beam Outer diameter should be identical as the internal diameter of upper prop preformed hole, reserved steel bar beam outer diameter tolerance is minus tolerance, and preformed hole internal diameter allows inclined Difference is principal-employment.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710646433.8A CN109281398A (en) | 2017-07-19 | 2017-07-19 | Boundling half, which is in the milk, constrains slurry anchor connection method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710646433.8A CN109281398A (en) | 2017-07-19 | 2017-07-19 | Boundling half, which is in the milk, constrains slurry anchor connection method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109281398A true CN109281398A (en) | 2019-01-29 |
Family
ID=65185247
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710646433.8A Pending CN109281398A (en) | 2017-07-19 | 2017-07-19 | Boundling half, which is in the milk, constrains slurry anchor connection method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109281398A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109853847A (en) * | 2019-02-01 | 2019-06-07 | 广州建筑产业研究院有限公司 | A kind of prefabricated column of non-interconnected grouting |
CN111321807A (en) * | 2020-02-28 | 2020-06-23 | 南京工程学院 | Assembled frame construction post-post bundling reinforcing bar connection structure |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102008055523B3 (en) * | 2008-12-15 | 2010-04-01 | Simon Kropmeier | Bolt system for forming form-fit connection between two ferroconcrete prefabricated members, has ferroconcrete prefabricated member including bolt and sleeve with cover and base that are provided for position fixing of bolt |
CN102691365A (en) * | 2012-05-31 | 2012-09-26 | 东南大学 | Connecting structure for assembly type concrete shear wall edge member |
CN103075013A (en) * | 2013-01-21 | 2013-05-01 | 黑龙江宇辉新型建筑材料有限公司 | Building construction steel bar connection structure and connection method |
CN104453015A (en) * | 2014-11-19 | 2015-03-25 | 沈阳建筑大学 | Reinforcing bar splicing connection component comprising thin-wall sleeves constrained by spiral bars |
CN204876199U (en) * | 2015-06-26 | 2015-12-16 | 东南大学 | Restraint overlap joint structure is concentrated to precast shear wall vertical reinforcement |
CN106639040A (en) * | 2016-10-13 | 2017-05-10 | 哈尔滨工业大学 | Longitudinal bar bundled pouring long through hole pre-cast shear wall and construction method thereof |
-
2017
- 2017-07-19 CN CN201710646433.8A patent/CN109281398A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102008055523B3 (en) * | 2008-12-15 | 2010-04-01 | Simon Kropmeier | Bolt system for forming form-fit connection between two ferroconcrete prefabricated members, has ferroconcrete prefabricated member including bolt and sleeve with cover and base that are provided for position fixing of bolt |
CN102691365A (en) * | 2012-05-31 | 2012-09-26 | 东南大学 | Connecting structure for assembly type concrete shear wall edge member |
CN103075013A (en) * | 2013-01-21 | 2013-05-01 | 黑龙江宇辉新型建筑材料有限公司 | Building construction steel bar connection structure and connection method |
CN104453015A (en) * | 2014-11-19 | 2015-03-25 | 沈阳建筑大学 | Reinforcing bar splicing connection component comprising thin-wall sleeves constrained by spiral bars |
CN204876199U (en) * | 2015-06-26 | 2015-12-16 | 东南大学 | Restraint overlap joint structure is concentrated to precast shear wall vertical reinforcement |
CN106639040A (en) * | 2016-10-13 | 2017-05-10 | 哈尔滨工业大学 | Longitudinal bar bundled pouring long through hole pre-cast shear wall and construction method thereof |
Non-Patent Citations (2)
Title |
---|
李平原等主编: "《混凝土结构工程施工》", 28 February 2017, 上海交通大学出版社 * |
王宗昌编著: "《建筑工程施工质量控制与实例分析》", 31 January 2011, 中国电力出版社 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109853847A (en) * | 2019-02-01 | 2019-06-07 | 广州建筑产业研究院有限公司 | A kind of prefabricated column of non-interconnected grouting |
CN111321807A (en) * | 2020-02-28 | 2020-06-23 | 南京工程学院 | Assembled frame construction post-post bundling reinforcing bar connection structure |
CN111321807B (en) * | 2020-02-28 | 2021-11-02 | 南京工程学院 | Assembled frame construction post-post bundling reinforcing bar connection structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104453015B (en) | Thin walled cylinder body reinforcement lapping connection component containing Spiral Reinforcement Binding Course | |
CN105350584B (en) | A kind of construction method of anti-float anchor rod | |
CN105133625B (en) | Reinforced structure of tunnel transversely penetrating through sliding slope and construction method | |
CN109403371A (en) | A kind of Steep Slope Embankment retaining structure and construction method | |
CN106498950A (en) | Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system and its implementation of pile body | |
CN103603369B (en) | Construction method of anchor pile counterfort retaining wall | |
CN202543906U (en) | Precast pile with reserved grouting pipes | |
CN107060774A (en) | A kind of anti-tunnel portal wall damage device and construction method | |
CN102605767A (en) | Precast pile reserved with grouting pipe and piling process of precast pile | |
CN209368867U (en) | A kind of Steep Slope Embankment retaining structure | |
CN1067453C (en) | Supporting and protecting method for base pit, side slope, flat anchor and spray net | |
CN102304927B (en) | Prestress anchor cable buttress-type parapet suitable for rock substrate | |
CN104631440A (en) | Stiffening core lengthening foundation pit support structure for existing large-diameter bored concrete pile and construction method | |
CN106065628B (en) | Based on the major diameter running water pipe security protection construction method faced forever with reference to theory | |
CN105421449A (en) | Construction method of composite pile composed of nail-shaped active material plastic sleeve and concrete stiffened core | |
CN105040989B (en) | Anchor and its construction method for anchoring prefabricated superimposed sheet and prefabricated components | |
CN206408630U (en) | Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body | |
CN100513705C (en) | Underground beam-pile frame construction for reinforcing side slope | |
CN109281398A (en) | Boundling half, which is in the milk, constrains slurry anchor connection method | |
CN109881683A (en) | A kind of more sublevel retaining structures and its construction method for combining artificial earth fill's grouting reinforcement technique | |
CN101793027B (en) | Core-grouted static pressure anchor rod pile | |
CN106567365B (en) | Earth and rockfill dam longitudinal reinforcement construction method | |
CN107503768A (en) | The method of the oblique Soil-nailed of Small Data Sets shallow embedding tunnel overlying ground | |
CN209669718U (en) | A kind of existing hangar tunnel combination stone cut off wall structure of rockfall protection | |
CN111877369A (en) | Construction method for slope support reinforcement |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190129 |