CN109252514A - Construction method of the high-pressure rotary jet grouting pile in artificial Backfilled Stone Layer - Google Patents

Construction method of the high-pressure rotary jet grouting pile in artificial Backfilled Stone Layer Download PDF

Info

Publication number
CN109252514A
CN109252514A CN201710574651.5A CN201710574651A CN109252514A CN 109252514 A CN109252514 A CN 109252514A CN 201710574651 A CN201710574651 A CN 201710574651A CN 109252514 A CN109252514 A CN 109252514A
Authority
CN
China
Prior art keywords
drill bit
pressure
hole
stone layer
jet grouting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710574651.5A
Other languages
Chinese (zh)
Inventor
姚喜民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN201710574651.5A priority Critical patent/CN109252514A/en
Publication of CN109252514A publication Critical patent/CN109252514A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention discloses a kind of construction method of high-pressure rotary jet grouting pile in artificial Backfilled Stone Layer, it is smooth that this method carries out site elevation first, surveys fixed pile, while stake machine and background devices are in place;The preparation cement slurry that mobility is small, setting time is short;High spray booth vehicle or outdoor Down-hole rolling rig simultaneously drilling rod in place install air hammer, and drill bit is made to be directed at hole location center;Compressed air is provided by compressed air pump, starts high spray booth vehicle or outdoor Down-hole rolling rig by air hammer pilot hole, stops pilot hole after passing through Backfilled Stone Layer;Air hammer is changed to two-tube drill bit and simultaneously interviews spray, two-tube drill bit band low pressure cement slurry enters pilot hole;To projected depth, it is sent into compressed air and cement slurry, after slurries to be implanted are emerged, is promoted in injection from bottom to top until design height, stops supplying gas and starching, propose two-tube drill bit, complete construction.This method improves rod boring function, avoids equipment damage, reduces construction cost, effectively improves construction efficiency.

Description

Construction method of the high-pressure rotary jet grouting pile in artificial Backfilled Stone Layer
Technical field
The present invention relates to a kind of construction method of high-pressure rotary jet grouting pile in artificial Backfilled Stone Layer.
Background technique
With the development of urban construction, coastal cities constantly carry out large-scale marine reclamation land, mostly former in reclaimation area domain Place belongs to coastal tidal landforms, and the later period carries out extensive artificial sea reclamation, and landfill material is mainly granite block stone composition, General block stone diameter is 20~80cm, and maximum gauge can exceed that 1m, volume content are about 55~80%, by broken between block stone Stone, dust and cohesive soil filling, and thickness is uneven, it is loosely organized to slightly close.The pore ground water of artificial Backfilled Stone Layer is the same as week simultaneously There are certain hydraulic connections for side river and seawater.When carrying out Foundation Pit Construction in such region, high pressure is revolved between support pile The construction of churning pile water stopping curtain because block stone and underground water there are due to bring constructional difficulties.Conventional high-pressure rotary jet grouting pile rod boring Function is limited, is suitble to carry out drilling construction in soil layer class, easily leads to equipment damage for artificial Backfilled Stone Layer, raising is constructed into This, reduces construction efficiency.
Summary of the invention
Technical problem to be solved by the invention is to provide a kind of construction method of high-pressure rotary jet grouting pile in artificial Backfilled Stone Layer, This method overcomes high-pressure rotary jet grouting pile drilling rod to be appropriate only for the defect of soil layer class drilling construction, improves rod boring function, avoids setting Standby damage, reduces construction cost, effectively improves construction efficiency.
In order to solve the above technical problems, construction method of the high-pressure rotary jet grouting pile of the present invention in artificial Backfilled Stone Layer includes following step It is rapid:
Step 1: preparation of construction, smooth site elevation is more than 30cm for pile crown height difference to whole pile crowns are exposed, will be overproof Partial cutaway controls coordinate according to design, and the accurate measurement high-pressure rotary jet grouting pile position in scene is simultaneously marked, and stake machine is in place, and measures High-pressure rotary jet grouting pile aperture elevation controls stake top absolute altitude, while stake machine backstage high-pressure pump, stirring stock tank and compressed air pump installation are adjusted Examination is in place;
Step 2: the preparation cement slurry that mobility is small, setting time is short, the stirring resting period of striaght cement slurry, from preparation It is less than 2.5 hours to the time being finished;
Step 3: drawing hole construction, high spray booth vehicle or outdoor Down-hole rolling rig are in place, and high spray booth vehicle or outdoor Down-hole rolling rig are placed in Scene is accurately surveyed in the hole location set, is installed air hammer in high spray booth vehicle or outdoor Down-hole rolling rig drilling rod, is made drill bit alignment hole Position center, and drill rod axis perpendicular alignmnet hole location center;
Step 4: providing compressed air by compressed air pump, starts high spray booth vehicle or outdoor Down-hole rolling rig, pass through air hammer Pilot hole stops pilot hole after air hammer drill bit passes through Backfilled Stone Layer;
Step 5: jet groutinl, is changed to two-tube rotation for the air hammer that high spray booth vehicle or outdoor Down-hole rolling rig drilling rod are installed Drill bit is sprayed, two-tube drill bit carries out compressed air, the examination spray of high pressure cement slurry, after ground interview spray is qualified, two-tube rotation on ground Spray drill bit band low pressure cement slurry enters pilot hole;
Step 6: being sprayed after, to after projected depth, be sent into satisfactory compressed air and cement slurry under two-tube drill bit 1~3min, after slurries to be implanted are emerged, promotion speed as required promotes two-tube drill bit in injection from bottom to top, directly To design height, stopping is supplied gas and is starched, and proposes two-tube drill bit, completes Construction of High Pressure Jet Grouting Pile.
Further, in the preparation of construction, Pile of High-pressure Spiral Jet position deviation≤50mm of measurement.
Further, the cement material of the cement slurry uses P.O.42.5R ordinary portland cement, the water of cement slurry Gray scale is 1.5, is additionally incorporated the triethanolamine of 2wt ‰, and mixing time is no less than 180s.
Further, the verticality of the high spray booth vehicle or outdoor Down-hole rolling rig drilling rod and hole location is not more than 1.5%.
Further, the compressed air pump is screw air compressor, 0.7~0. 8MPa of air pressure, capacity be greater than 22 cubes/ min。
Further, the aspirated pressure of the two-tube drill bit is 0.7~0.8MPa, air demand is 1~2m3/ min, water Slurry body pressure is 28~30MPa, stock volume is 80~120L/min, promotion speed of the two-tube drill bit in mud It is 5~8cm/min for 4~5cm/min, in the promotion speed of Backfilled Stone Layer, the two-tube drill bit lifting process revolving speed is 5~ 8r/min。
Since construction method of the high-pressure rotary jet grouting pile of the present invention in artificial Backfilled Stone Layer uses above-mentioned technical proposal, i.e. this method is first Preparation of construction is first carried out, site elevation is smooth, surveys fixed pile, while stake machine and background devices are in place;Preparation mobility is small, condenses Time short cement slurry;High spray booth vehicle or outdoor Down-hole rolling rig are in place, and high spray booth vehicle or outdoor Down-hole rolling rig drilling rod install gas Dynamic impactor, makes drill bit be directed at hole location center;Compressed air is provided by compressed air pump, starts high spray booth vehicle or outdoor hidden hole drilling Vehicle stops pilot hole after air hammer drill bit passes through Backfilled Stone Layer by air hammer pilot hole;Air hammer is changed to Two-tube drill bit simultaneously interviews spray, and two-tube drill bit band low pressure cement slurry enters pilot hole;To projected depth, it is sent into pressure Contracting air and cement slurry after slurries to be implanted are emerged, promote two-tube drill bit in injection from bottom to top, until design is high Degree, stopping are supplied gas and are starched, and propose two-tube drill bit, complete Construction of High Pressure Jet Grouting Pile.This method overcomes high-pressure rotary jet grouting pile drilling rod It is appropriate only for the defect of soil layer class drilling construction, rod boring function is improved, avoids equipment damage, reduce construction cost, have Effect improves construction efficiency.
Specific embodiment
Construction method of the high-pressure rotary jet grouting pile of the present invention in artificial Backfilled Stone Layer includes the following steps:
Step 1: preparation of construction, smooth site elevation is more than 30cm for pile crown height difference to whole pile crowns are exposed, will be overproof Partial cutaway controls coordinate according to design, and the accurate measurement high-pressure rotary jet grouting pile position in scene is simultaneously marked, and stake machine is in place, and measures High-pressure rotary jet grouting pile aperture elevation controls stake top absolute altitude, while stake machine backstage high-pressure pump, stirring stock tank and compressed air pump installation are adjusted Examination is in place;
Step 2: the preparation cement slurry that mobility is small, setting time is short, to accelerate the condensation of the cement slurry in Backfilled Stone Layer, The stirring resting period of striaght cement slurry made the time being finished to the utmost by oneself less than 2.5 hours;
Step 3: drawing hole construction, high spray booth vehicle or outdoor Down-hole rolling rig are in place, and high spray booth vehicle or outdoor Down-hole rolling rig are placed in Scene is accurately surveyed in the hole location set, is installed air hammer in high spray booth vehicle or outdoor Down-hole rolling rig drilling rod, is made drill bit alignment hole Position center, and drill rod axis perpendicular alignmnet hole location center;
Step 4: providing compressed air by compressed air pump, starts high spray booth vehicle or outdoor Down-hole rolling rig, pass through air hammer Pilot hole stops pilot hole after air hammer drill bit passes through Backfilled Stone Layer;
Step 5: jet groutinl, is changed to two-tube rotation for the air hammer that high spray booth vehicle or outdoor Down-hole rolling rig drilling rod are installed Drill bit is sprayed, two-tube drill bit carries out compressed air, the examination spray of high pressure cement slurry, after ground interview spray is qualified, two-tube rotation on ground Spray drill bit band low pressure cement slurry enters pilot hole;
Step 6: being sprayed after, to after projected depth, be sent into satisfactory compressed air and cement slurry under two-tube drill bit 1~3min, after slurries to be implanted are emerged, promotion speed as required promotes two-tube drill bit in injection from bottom to top, directly To design height, stopping is supplied gas and is starched, and proposes two-tube drill bit, completes Construction of High Pressure Jet Grouting Pile.
Preferably, in the preparation of construction, Pile of High-pressure Spiral Jet position deviation≤50mm of measurement.
Preferably, the cement material of the cement slurry uses P.O.42.5R ordinary portland cement, the water of cement slurry Gray scale is 1.5, is additionally incorporated the triethanolamine of 2wt ‰, and mixing time is no less than 180s.
Preferably, the verticality of the high spray booth vehicle or outdoor Down-hole rolling rig drilling rod and hole location is not more than 1.5%.
Preferably, the compressed air pump is screw air compressor, 0.7~0. 8MPa of air pressure, capacity be greater than 22 cubes/ min。
Preferably, the aspirated pressure of the two-tube drill bit is 0.7~0.8MPa, air demand is 1~2m3/ min, water Slurry body pressure is 28~30MPa, stock volume is 80~120L/min, promotion speed of the two-tube drill bit in mud It is 5~8cm/min for 4~5cm/min, in the promotion speed of Backfilled Stone Layer, the two-tube drill bit lifting process revolving speed is 5~ 8r/min。
The revolving speed of cement slurry blender and the ability of mixing and stirring should be adapted with the plasma discharge amount of high-pressure injection pump in this method, and Should ensure that uniformly, continuously mixing slurries, guarantee the continuous for starching demand of high pressure jet grouting.Drilling machine installation is positioned to standard Really, horizontal, firm, to guarantee that drilling reaches the verticality of design requirement, level correction must be made after drilling machine is in place.Jet grouting mistake Cheng Zhong, operating personnel must check whether the construction parameters such as flow, tolerance, pressure and the promotion speed of slip casting meet the moment and set Meter requires, and makes a record at any time.It should be noted that slurry situation is returned on ground when jet groutinl in Backfilled Stone Layer, if ground is without emitting Slurry or leakage amount are few, should reduce promotion speed, so that cement slurry can be sufficient filling with gap between block stone, guarantee sealing curtain The construction effect of curtain.To solve to occur depressed phenomenon because of bleed at the top of concrement, whenever AEI After End of Injection, immediately in spray-hole Interior progress static pressure filling grouting, until aperture liquid level no longer sinks.It, should be timely after being ejected into design height construction Each flushing of pipeline is clean, must not there are residues, with anti-clogging.
This method for high spray booth vehicle or outdoor Down-hole rolling rig can not voluntarily drilling construction region of rockfilling, by using gas Dynamic impactor pore-forming carries out Construction of High Pressure Jet Grouting Pile after passing through Backfilled Stone Layer, then using two-tube drill bit, is suitable for artificial Extensive sea reclamation region carries out Construction of High Pressure Jet Grouting Pile, and especially there are the artificial Backfilled Stone Layers of larger thickness, block stone for solution The construction problem of high-pressure rotary jet grouting pile pore-forming is carried out in layer.

Claims (6)

1. a kind of construction method of high-pressure rotary jet grouting pile in artificial Backfilled Stone Layer, it is characterised in that this method includes the following steps:
Step 1: preparation of construction, smooth site elevation is more than 30cm for pile crown height difference to whole pile crowns are exposed, will be overproof Partial cutaway controls coordinate according to design, and the accurate measurement high-pressure rotary jet grouting pile position in scene is simultaneously marked, and stake machine is in place, and measures High-pressure rotary jet grouting pile aperture elevation controls stake top absolute altitude, while stake machine backstage high-pressure pump, stirring stock tank and compressed air pump installation are adjusted Examination is in place;
Step 2: the preparation cement slurry that mobility is small, setting time is short, the stirring resting period of striaght cement slurry, from preparation It is less than 2.5 hours to the time being finished;
Step 3: drawing hole construction, high spray booth vehicle or outdoor Down-hole rolling rig are in place, and high spray booth vehicle or outdoor Down-hole rolling rig are placed in Scene is accurately surveyed in the hole location set, is installed air hammer in high spray booth vehicle or outdoor Down-hole rolling rig drilling rod, is made drill bit alignment hole Position center, and drill rod axis perpendicular alignmnet hole location center;
Step 4: providing compressed air by compressed air pump, starts high spray booth vehicle or outdoor Down-hole rolling rig, pass through air hammer Pilot hole stops pilot hole after air hammer drill bit passes through Backfilled Stone Layer;
Step 5: jet groutinl, is changed to two-tube rotation for the air hammer that high spray booth vehicle or outdoor Down-hole rolling rig drilling rod are installed Drill bit is sprayed, two-tube drill bit carries out compressed air, the examination spray of high pressure cement slurry, after ground interview spray is qualified, two-tube rotation on ground Spray drill bit band low pressure cement slurry enters pilot hole;
Step 6: being sprayed after, to after projected depth, be sent into satisfactory compressed air and cement slurry under two-tube drill bit 1~3min, after slurries to be implanted are emerged, promotion speed as required promotes two-tube drill bit in injection from bottom to top, directly To design height, stopping is supplied gas and is starched, and proposes two-tube drill bit, completes Construction of High Pressure Jet Grouting Pile.
2. construction method of the high-pressure rotary jet grouting pile according to claim 1 in artificial Backfilled Stone Layer, it is characterised in that: described to apply During working drawing is standby, Pile of High-pressure Spiral Jet position deviation≤50mm of measurement.
3. construction method of the high-pressure rotary jet grouting pile according to claim 1 in artificial Backfilled Stone Layer, it is characterised in that: the water The cement material of slurry body uses P.O.42.5R ordinary portland cement, and the ratio of mud of cement slurry is 1.5, is additionally incorporated The triethanolamine of 2wt ‰, and mixing time is no less than 180s.
4. construction method of the high-pressure rotary jet grouting pile according to claim 1 in artificial Backfilled Stone Layer, it is characterised in that: the height The verticality of spray booth vehicle or outdoor Down-hole rolling rig drilling rod and hole location is not more than 1.5%.
5. construction method of the high-pressure rotary jet grouting pile according to claim 1 in artificial Backfilled Stone Layer, it is characterised in that: the pressure Contracting air pump is screw air compressor, and 0.7~0. 8MPa of air pressure, capacity is greater than 22 cubes/min.
6. construction method of the high-pressure rotary jet grouting pile according to claim 1 in artificial Backfilled Stone Layer, it is characterised in that: described double The aspirated pressure of pipe drill bit is 0.7~0.8MPa, air demand is 1~2m3/ min, cement slurry pressure be 28~30MPa, Stock volume is 80~120L/min, and the two-tube drill bit is 4~5cm/min, in Backfilled Stone Layer in the promotion speed of mud Promotion speed be 5~8cm/min, the two-tube drill bit lifting process revolving speed be 5~8r/min.
CN201710574651.5A 2017-07-14 2017-07-14 Construction method of the high-pressure rotary jet grouting pile in artificial Backfilled Stone Layer Pending CN109252514A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710574651.5A CN109252514A (en) 2017-07-14 2017-07-14 Construction method of the high-pressure rotary jet grouting pile in artificial Backfilled Stone Layer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710574651.5A CN109252514A (en) 2017-07-14 2017-07-14 Construction method of the high-pressure rotary jet grouting pile in artificial Backfilled Stone Layer

Publications (1)

Publication Number Publication Date
CN109252514A true CN109252514A (en) 2019-01-22

Family

ID=65051307

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710574651.5A Pending CN109252514A (en) 2017-07-14 2017-07-14 Construction method of the high-pressure rotary jet grouting pile in artificial Backfilled Stone Layer

Country Status (1)

Country Link
CN (1) CN109252514A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114352189A (en) * 2022-01-07 2022-04-15 中铁二十局集团第六工程有限公司 Construction method of jet grouting pile
CN114541375A (en) * 2022-03-02 2022-05-27 广东水电二局股份有限公司 Construction method of double-pipe jet grouting pile

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104631470A (en) * 2014-12-26 2015-05-20 合肥建工集团有限公司 Deep foundation pit combination retaining and protecting construction method for geology with high water level and large particle size sand gravel
CN106320331A (en) * 2016-09-23 2017-01-11 中交第航务工程局有限公司 Construction method for penetrating block stone layer of pore-forming system of high-pressure jet grouting pile
CN107338789A (en) * 2016-12-28 2017-11-10 福建建工集团有限责任公司 A kind of construction method of down-the-hole percussion triple-pipe high pressure jet grouting stake

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104631470A (en) * 2014-12-26 2015-05-20 合肥建工集团有限公司 Deep foundation pit combination retaining and protecting construction method for geology with high water level and large particle size sand gravel
CN106320331A (en) * 2016-09-23 2017-01-11 中交第航务工程局有限公司 Construction method for penetrating block stone layer of pore-forming system of high-pressure jet grouting pile
CN107338789A (en) * 2016-12-28 2017-11-10 福建建工集团有限责任公司 A kind of construction method of down-the-hole percussion triple-pipe high pressure jet grouting stake

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
董志民: "高压气动潜孔锤跟管钻进技术在填石层中的应用与分析", 《工程勘察》 *
马明等: "《水利水电工程钻探与工程施工治理技术》", 31 August 2009 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114352189A (en) * 2022-01-07 2022-04-15 中铁二十局集团第六工程有限公司 Construction method of jet grouting pile
CN114352189B (en) * 2022-01-07 2024-03-15 中铁二十局集团第六工程有限公司 Construction method of jet grouting pile
CN114541375A (en) * 2022-03-02 2022-05-27 广东水电二局股份有限公司 Construction method of double-pipe jet grouting pile
CN114541375B (en) * 2022-03-02 2023-08-11 广东水电二局股份有限公司 Construction method of double-pipe jet grouting pile

Similar Documents

Publication Publication Date Title
CN103343544B (en) Construction method for large-scale open caisson
CN102418344B (en) Injector, drill bit combination structure and combination drilling tool
CN104594348B (en) Enlarged footing bellows anchor pole and construction method thereof
CN1193141C (en) Combined grouting construction process of reinforcing foundation
CN104343455B (en) Long-distance curved jacking pipe and pipe roof construction technique
CN105964678A (en) Soil and groundwater in-situ remediation system and method through in-situ infusion and high-pressure jet grouting injection
CN106759297A (en) A kind of construction method of support pile and three pipe high-pressure rotary jet grouting pile deep basal pits
CN108517877B (en) Supporting construction method combining consolidation grouting of hybrid filling ultra-deep foundation pit with double-row steel pipe piles
CN102011397A (en) Construction process of concrete form water-stopping occlusion pile
CN106734178A (en) Comprehensive restoration system and method for polluted site
CN114233385B (en) Treatment method for mud-bursting water of inclined shaft
CN106122589A (en) A kind of earth pressure balance method
CN107191188B (en) Bedrock section bad aquifer positioning and targeting grouting vertical shaft wall structure, construction device and construction method
CN203361143U (en) Combination structure of high-pressure jet grouting pile and prestressed pipe pile
CN113338361A (en) Deviation rectifying method for settlement of overlying building caused by subway construction in soft soil stratum
CN114808990A (en) High-pressure pre-filling karst cave pile foundation construction method
CN109252514A (en) Construction method of the high-pressure rotary jet grouting pile in artificial Backfilled Stone Layer
CN208033274U (en) A kind of triple churning equipment of soil remediation
CN110735642A (en) shield originating end combined type reinforcing structure and construction method thereof
Chen et al. Construction technology of large diameter underwater shield tunnel
CN102733366A (en) Soft soil curing construction method
CN109881696B (en) HPPG (high Performance Poly propylene glycol) bottom sealing construction method
CN109518676B (en) Method for treating large-pore loose foundation soil through micro-gas explosion grouting
CN105926626A (en) Construction process for super-long vibration jet-grouting pile of pneumatic down-the-hole hammer, and equipment thereof
CN104727206A (en) Soft subgrade grouting treatment constructing method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190122