CN208033274U - A kind of triple churning equipment of soil remediation - Google Patents

A kind of triple churning equipment of soil remediation Download PDF

Info

Publication number
CN208033274U
CN208033274U CN201721884519.6U CN201721884519U CN208033274U CN 208033274 U CN208033274 U CN 208033274U CN 201721884519 U CN201721884519 U CN 201721884519U CN 208033274 U CN208033274 U CN 208033274U
Authority
CN
China
Prior art keywords
churning
high pressure
triple
soil
utility
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721884519.6U
Other languages
Chinese (zh)
Inventor
程功弼
梁广秋
徐金旺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Gaiya Environmental Science And Technology Co Ltd
Original Assignee
Jiangsu Gaiya Environmental Science And Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Gaiya Environmental Science And Technology Co Ltd filed Critical Jiangsu Gaiya Environmental Science And Technology Co Ltd
Priority to CN201721884519.6U priority Critical patent/CN208033274U/en
Application granted granted Critical
Publication of CN208033274U publication Critical patent/CN208033274U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Earth Drilling (AREA)

Abstract

The utility model discloses a kind of triple churning equipment of soil remediation, including repairing drilling machine, endless track installation, hydraulic support system, derrick, power head, level board support, triple churning systems, triple churning systems include high pressure killer injecting pump, air compressor machine, high pressure water-injection pump, churning pipe equipment described in the utility model using triple high-pressure rotary-spray pipes carry out high pressure water, pressure-air, high pressure medicament injection, high-pressure jet has higher destructive power to soil, can further increase the spray regime of high-pressure jet.The utility model can adjust the spray penetration of churning pipe according to the drilling depth for repairing drilling machine simultaneously, increase the reparation depth and repair coverage of soil.The utility model is using pilot hole drilling tool drilling sand-pebble layer simultaneously, therefore the utility model is not limited to the soil environment of different hardness, equally has good effect in the complicated hard geological conditions such as clay, silt, sand, muck soil.

Description

A kind of triple churning equipment of soil remediation
Technical field
The utility model is related to a kind of soil remediation construction method more particularly to a kind of triple churning equipment of soil remediation.
Background technology
With the development of industrial economy, the pollution control of soil pollution getting worse, especially deep soil is to repairing skill The requirement of art is higher and higher.Soil remediation medicament combination triple-pipe high pressure jet grouting stake is will to repair medicament with the nozzle of high-pressure rotary It sprays into soil layer to mix with the soil body, is a kind of method of rehabilitating soil, be used for the reparation of deep soil.Rotary churning pile is mainly used for reinforcing ground Base improves the shearing strength of ground, improves the deformation performance of foundation soil, makes it under superstructure load action, unlikely destruction Or excessive deformation is generated, improve the engineerings such as hydraulics and the stability of slope of foundation soil.Rotary churning pile is to utilize drilling machine by churning Grouting Pipe and nozzle brill are placed in a bottom design altitude, keep liquid stream acquisition huge by high-voltage generator in advance prepared slurries It after big energy, is ejected from the nozzle high speed of slip casting tube edge, forms the liquid stream of one energy height concentration, make slurries and soil Body is thoroughly mixed, and the column induration only soil that certain diameter is formed in soil is reinforced.However rotary churning pile is in soil Research in terms of reparation is very few.
Utility model content
To solve the above-mentioned problems, the purpose of this utility model is to provide a kind of triple churning equipment of soil remediation, profits Soil remediation is carried out with rotary churning pile, improves the remediation efficiency of soil.
To achieve the above object, the utility model adopts the following technical solution:
A kind of triple churning equipment of soil remediation, including:Repair drilling machine, endless track installation, hydraulic support system, well Frame, power head, level board support, triple churning systems, the reparation drilling machine is arranged on the endless track installation, described to repair Pilot hole drilling tool is provided on multiple drilling machine, the derrick is welded in the level board support, the hydraulic support system(9)One End is fixedly connected with the reparation drilling machine, the other end is flexibly connected with the derrick, and the power head is arranged on the derrick And opposite derrick slides up and down;Triple churning systems include high pressure killer injecting pump, air compressor machine, high pressure water-injection pump, churning pipe, institute It states churning pipe to be arranged on the power head, the liquid outlet phase that the liquid feeding end of the high pressure killer injecting pump passes through return duct and medicament barrel Connection, outlet end are connected by high-voltage tube with churning pipe, and the air output end of the air compressor machine passes through high-pressure air hose and churning Pipe is connected, and the liquid feeding end of the high pressure water-injection pump is connected by return duct with the liquid outlet of water tank, outlet end passes through high pressure Pipe is connected with churning pipe, and the bottom end side wall of the churning pipe is equipped with multigroup delivery outlet, and high pressure is equipped on every group of delivery outlet Air scoop, the high pressure mouth of a river and high pressure medicament mouth, the pressure-air mouth, the high pressure mouth of a river and high pressure medicament mouth and horizontal plane are at difference Angle sprayed.
Further, the churning pipe is external to the delivery outlet or more and is arranged with casing.
Preferably, bottom end relative symmetry setting of the multigroup delivery outlet in churning pipe.
Derrick described in the utility model is mainly realized by oil cylinder control and moves up and down and deflect, more to adapt to Kind of landform, provides to support and move up and down for power head and provides track.
Power head described in the utility model is moved up and down along derrick track by hydraulic cylinder, it can be achieved that pilot hole, broken rock, rotation The functions such as spray.
A kind of triple churning methods of soil remediation carried out using triple churning equipment described in the utility model, including with Lower step:
Step 1, levelling of the land
Clear up the barrier of construction site, smooth construction site;And check high-tension apparatus and pipeline in triple churning equipment Integrity;
Step 2, surveying setting-out
Unwrapping wire is measured according to the fender post physical location constructed, determines the stake position of triple churnings;
Step 3, reparation drilling machine are in place
Behind the stake position for determining triple churnings, the reparation drilling machine is carried out in place, leveling and centering are carried out to repairing drilling machine, Adjust the verticality of drilling machine so that drilling rod is consistent with stake position;
Step 4, probing pilot hole
Using drill hole of drilling machine is repaired, drilling tool is taken out after drilling, changes and arrives predetermined depth under churning pipe;During down tube, Prevent silt from blocking rotation jet nozzle using safeguard procedures;
Medicament is repaired in injection after sand-pebble layer uses pilot hole drilling tool, drilling to reach design hole depth, then extracts casing, is repaiied Multiple medicament according to construction machinery, technique and should pass through soil layer situation and carry out mix-design and experiment, prepare use at the scene.
Step 5, whitewashing are promoted
To after projected depth under churning pipe, conveying high-pressure water first, then convey and repair medicament and compressed air and repairs medicine Agent can send 30s late compared to compressed air, 1~3min of the quiet spray in original place later, scheduled injection pressure to be achieved(25~30MPa) With whitewashing amount(80~120L/min), and aperture is emerged after slurries, then by it is predetermined promoted, rotation or swing speed(70 ~160mm/min), spraying operation is carried out from bottom to top, until design height(13m)It can stop to send water, gas, medicament, propose rotation Jet pipe;Must pay attention at the moment checking flow, pressure, tolerance and the rotation of medicament, pendulum, promoting the parameters such as speed in course of injection is It is no to meet the requirements, and make a record at any time, draw operation process curve;
Step 6, cleaning apparatus:
After revolving lance lift to designed elevation, injection finishes, should be clean by each flushing of pipeline in time, manages in interior, machine not Remaining reparation medicament is obtained, with anti-clogging;Slurries are usually changed into water, are sprayed on the ground, so as in slush pump churning pipe Medicament is all discharged, until there is clear water;
Step 7, telephone-moving to new bore position:
After jet grouting, the plants such as reparation drilling machine are moved on on new bore position, carry out the constructing operation in next hole.
Preferably, the safeguard procedures in the step 4 are using plastic foil or adhesive plaster wrapping rotation jet nozzle or side low pressure Water, gas, slurry side down tube, water pressure is sent to be no more than 1MPa.
Advantageous effect:The utility model discloses a kind of triple churning equipment of soil remediation, equipment described in the utility model The injection of high pressure water, pressure-air, high pressure medicament is carried out using triple high-pressure rotary-spray pipes, high-pressure jet has soil higher Destructive power can further increase the spray regime of high-pressure jet.The utility model can be according to the drilling depth for repairing drilling machine simultaneously The spray penetration for adjusting churning pipe, increases the reparation depth and repair coverage of soil.The utility model uses pilot hole drilling tool simultaneously Drill sand-pebble layer, therefore the utility model is not limited to the soil environment of different hardness, in clay, silt, sand, Muddy Bottoms The complexity hard geological conditions such as soil equally has good effect.
Description of the drawings
In order to illustrate more clearly of the technical solution of the embodiment of the present application, required use in being described below to embodiment Attached drawing be briefly described, it should be apparent that, the accompanying drawings in the following description is only some embodiments described in the application, For those of ordinary skill in the art, without creative efforts, it can also be obtained according to these attached drawings Other attached drawings.
Fig. 1 is the structural schematic diagram of the utility model.
Fig. 2 is the structural schematic diagram of the utility model pilot hole drilling tool.
Wherein:1, high pressure killer injecting pump;2, air compressor machine;3, high pressure water-injection pump;4, drilling machine is repaired;5, churning pipe;51, high pressure is empty Gas port;52, the high pressure mouth of a river;53, high pressure medicament mouth;6, pilot hole drilling tool;7, casing;8, endless track installation;9, hydraulic pressure support system System;10, level board supports;11, derrick;12, power head.
Specific implementation mode
The utility model is further described with reference to specific embodiment, but examples are merely exemplary, it is not right The scope of the utility model constitutes any restrictions.It will be understood by those skilled in the art that without departing from the utility model Can the details and form of technical solutions of the utility model be modified or be replaced under spirit and scope, but these are changed and replace It changes and each falls in the scope of protection of the utility model.
A kind of triple churning equipment of soil remediation, including:Repair drilling machine 4, endless track installation 8, hydraulic support system 9, Derrick 11, power head 12, level board support 10, triple churning systems, the reparation drilling machine 4 are arranged in the endless track installation On 8, pilot hole drilling tool 6 is provided on the reparation drilling machine 4, the derrick 11 is welded in the level board support 10, the liquid One end of pressure support system 9 is connected with the reparation drilling machine 4, the other end is connected with the derrick 11, the power head 12 It is arranged on the derrick 11 and opposite derrick 11 slides up and down;Triple churning systems include high pressure killer injecting pump 1, air compressor machine 2, high pressure water-injection pump 3, churning pipe 5, the churning pipe 5 are arranged on the power head 12, the liquid feeding end of the high pressure killer injecting pump 1 It is connected with the liquid outlet of medicament barrel by return duct, outlet end is connected by high-voltage tube with churning pipe 5, the air compressor machine 2 Air output end be connected with churning pipe 5 by high-pressure air hose, the liquid feeding end of the high pressure water-injection pump 3 passes through return duct and water The liquid outlet of case is connected, outlet end is connected by high-voltage tube with churning pipe 5, and the bottom end side wall of the churning pipe 5 is equipped with Multigroup delivery outlet, pressure-air mouth 51, the high pressure mouth of a river 52 and high pressure medicament mouth 53 are equipped on every group of delivery outlet, and the high pressure is empty Gas port 51, the high pressure mouth of a river 52 and high pressure medicament mouth 53 are sprayed from horizontal plane at different angles.
Further, the churning pipe 5 is external to the delivery outlet or more and is arranged with casing 7.
Preferably, bottom end relative symmetry setting of the multigroup delivery outlet in churning pipe 5.
The operation principle of the utility model is:(1)Drilling machine overall system integration is repaired above endless track installation, is repaired Drilling machine is marched to by endless track installation and formulates injection point, is risen drilling tool by hydraulic support system, adjustment angle side To perpendicular alignmnet point, positioning is supported by level board support;(2)Using drill hole of drilling machine is repaired, drilling tool is taken out after drilling, It changes and arrives predetermined depth under churning pipe;During down tube, prevent silt from blocking rotation jet nozzle using safeguard procedures;In sand ovum Medicament is repaired in injection after stone stratum uses pilot hole drilling tool, drilling to reach design hole depth, then extracts casing, and repairing medicament should be according to applying It work machinery, technique and passes through soil layer situation and carries out mix-design and experiment, prepare use at the scene;(3)To setting under churning pipe After counting depth, conveying high-pressure water first, then convey and repair medicament and compressed air.

Claims (3)

1. a kind of triple churning equipment of soil remediation, which is characterized in that including repairing drilling machine(4), endless track installation(8), liquid Press support system(9), derrick(11), power head(12), level board support(10), triple churning systems, the reparation drilling machine(4) It is arranged in the endless track installation(8)On, the reparation drilling machine(4)On be provided with pilot hole drilling tool(6), the derrick(11)Weldering It is connected on the level board support(10)On, the hydraulic support system(9)One end and the reparation drilling machine(4)Be fixedly connected, The other end and the derrick(11)Flexible connection, the power head(12)It is arranged in the derrick(11)Upper and opposite derrick(11) It slides up and down;Triple churning systems include high pressure killer injecting pump(1), air compressor machine(2), high pressure water-injection pump(3), churning pipe(5), The churning pipe(5)It is arranged in the power head(12)On, the high pressure killer injecting pump(1)Liquid feeding end pass through return duct and medicament The liquid outlet of bucket is connected, outlet end passes through high-voltage tube and churning pipe(5)It is connected, the air compressor machine(2)Air output end Pass through high-pressure air hose and churning pipe(5)It is connected, the high pressure water-injection pump(3)Liquid feeding end liquid is gone out by return duct and water tank Mouth is connected, outlet end passes through high-voltage tube and churning pipe(5)It is connected, the churning pipe(5)Bottom end side wall be equipped with it is multigroup Delivery outlet is equipped with pressure-air mouth on every group of delivery outlet(51), the high pressure mouth of a river(52)With high pressure medicament mouth(53), the high pressure Air scoop(51), the high pressure mouth of a river(52)With high pressure medicament mouth(53)It is sprayed at different angles from horizontal plane.
2. the triple churning equipment of a kind of soil remediation according to claim 1, which is characterized in that the churning pipe(5)Outside Portion is arranged with casing more than the delivery outlet(7).
3. the triple churning equipment of a kind of soil remediation according to claim 1, which is characterized in that multigroup delivery outlet exists Churning pipe(5)The setting of bottom end relative symmetry.
CN201721884519.6U 2017-12-28 2017-12-28 A kind of triple churning equipment of soil remediation Active CN208033274U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721884519.6U CN208033274U (en) 2017-12-28 2017-12-28 A kind of triple churning equipment of soil remediation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721884519.6U CN208033274U (en) 2017-12-28 2017-12-28 A kind of triple churning equipment of soil remediation

Publications (1)

Publication Number Publication Date
CN208033274U true CN208033274U (en) 2018-11-02

Family

ID=63955607

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721884519.6U Active CN208033274U (en) 2017-12-28 2017-12-28 A kind of triple churning equipment of soil remediation

Country Status (1)

Country Link
CN (1) CN208033274U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108080409A (en) * 2017-12-28 2018-05-29 江苏盖亚环境科技股份有限公司 A kind of triple churning device and method thereof of soil remediation
CN108978649A (en) * 2018-08-07 2018-12-11 佛山市房建集团有限公司 High pressure jet grouting foundation construction technique
CN109821880A (en) * 2019-02-13 2019-05-31 云南天朗环境科技有限公司 A kind of soil high-pressure rotary-spray renovation technique and device

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108080409A (en) * 2017-12-28 2018-05-29 江苏盖亚环境科技股份有限公司 A kind of triple churning device and method thereof of soil remediation
CN108978649A (en) * 2018-08-07 2018-12-11 佛山市房建集团有限公司 High pressure jet grouting foundation construction technique
CN109821880A (en) * 2019-02-13 2019-05-31 云南天朗环境科技有限公司 A kind of soil high-pressure rotary-spray renovation technique and device
CN109821880B (en) * 2019-02-13 2022-03-29 云南天朗环境科技有限公司 High-pressure rotary spraying repair process and device for soil

Similar Documents

Publication Publication Date Title
CN108080409A (en) A kind of triple churning device and method thereof of soil remediation
CN102322058B (en) Construction process and equipment for downhole impacting high-pressure jet grouting pile
CN104631470B (en) The large particle diameter sand gravel of high water level geology deep basal pit combination supporting construction method
CN1324200C (en) Seepage control consolidation method and apparatus for reciprocating high-pressure injection grouting foundation
CN104612695B (en) One acutely collapses shaft wall restoring and fastening method
CN104533449B (en) A kind of tunnel excavation stand and apply the adit construction method of this stand
CN207777770U (en) A kind of precast spliced pipe fitting jacking system
CN208033274U (en) A kind of triple churning equipment of soil remediation
CN112502777B (en) Method for treating tunnel inrush roof collapse and door closing
CN103343544A (en) Construction method for large-scale open caisson
CN101962949A (en) Long spiral double-pipe high-pressure stir-jet grouting pile construction method and device
CN109778835A (en) A kind of displaced type rotary jet grouting stratum consolidation method
CN107795749A (en) A kind of precast spliced pipe fitting jacking system and its construction method
CN110195604B (en) Construction method for tunnel main tunnel TBM (tunnel boring machine) tunneling section
CN107299633A (en) A kind of utilization High-pressure Spiral Spray Technology improves the construction method of the bearing capacity of stake
CN1986974A (en) Pressure reducing horizontal reinforcing process for soft soil layer
CN203361143U (en) Combination structure of high-pressure jet grouting pile and prestressed pipe pile
CN107152042A (en) Churning clump of piles occlusion reinforcing engineering method is tilted for wearing the micro-disturbance in house under shield
CN102261079A (en) Construction method for foundation pit waterproof curtain
CN204533812U (en) A kind of slurry-water balance type jacking construction system
CN108894247A (en) A kind of Metro Connection Passage periphery soil body subsidence pressure circle spray reinforcement structure and construction method
CN201649093U (en) Long spiral dual-pipe high-pressure stirring-spraying pile construction device
CN103147435A (en) Method for treating construction engineering foundation in gob
CN106869153B (en) A kind of method of the quick soft soil foundation treatment of well-points dewatering
CN106592514A (en) Construction method of old city riverway piling wall integrated vertical type retaining wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant