CN102733366A - Soft soil curing construction method - Google Patents

Soft soil curing construction method Download PDF

Info

Publication number
CN102733366A
CN102733366A CN2012102346753A CN201210234675A CN102733366A CN 102733366 A CN102733366 A CN 102733366A CN 2012102346753 A CN2012102346753 A CN 2012102346753A CN 201210234675 A CN201210234675 A CN 201210234675A CN 102733366 A CN102733366 A CN 102733366A
Authority
CN
China
Prior art keywords
soil
well
bucket
charity
depth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012102346753A
Other languages
Chinese (zh)
Other versions
CN102733366B (en
Inventor
王梦恕
葛加君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU SHUNTONG CONSTRUCTION GROUP CO Ltd
Original Assignee
JIANGSU SHUNTONG CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU SHUNTONG CONSTRUCTION GROUP CO Ltd filed Critical JIANGSU SHUNTONG CONSTRUCTION GROUP CO Ltd
Priority to CN201210234675.3A priority Critical patent/CN102733366B/en
Publication of CN102733366A publication Critical patent/CN102733366A/en
Application granted granted Critical
Publication of CN102733366B publication Critical patent/CN102733366B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a soft soil curing construction method, comprising the following steps: braking and discharging water on soil surface; sinking by dewatering and draining; preparing dry fixing agents; planting into dry fixing agents; spraying foaming agents, detecting and so on. The soft soil curing construction method provided by the invention has the advantages of convenience in construction, high construction efficiency and good work effects, and a soil structure with low water content, strong degree of density and high bearing force is formed by the method, so that former soft weak soils qualitatively change.

Description

Weak soil solidifies job practices
Technical field
The present invention relates to a kind of weak soil and solidify job practices.
Background technology
In recent years; Country and Jiangsu Province rise to strategic height to the coastal economy development, pay much attention to the coastal economy development problem, and have taked a series of measures to advance the coastal economy development; And China coastline is long; Be the longest country in coastline in the world, Jiangsu is in the riverbank, the Yellow River has more than 10 counties and cities near seashore, thereby the coastal economy development potentiality is very big.But because coastal soil property is alluvial deposit, quality is soft, water content is high, the modulus in compression coefficient is big, density is poor, bearing capacity is low, this to building engineering, the highway engineering construction difficulty is big, cost is high, has restricted the coastal economy development.
Summary of the invention
The object of the present invention is to provide a kind of easy construction, the weak soil of good working effect solidifies job practices.
Technical solution of the present invention is:
A kind of weak soil solidifies job practices, it is characterized in that: comprising:
(1) soil table is stopped and decided draining: according to test report, soil moisture content >=50 o'clock dispense alum at the soil property shallow-layer, per 100 ㎡ charity 1.2kg alum, and it is even to carry out mix with every 1.2kg alum and 100kg yellow ground during charity, adopts artificial charity then; Before charity, be one with 1000 ㎡ zones and get a little, the pool of drawing water is set, the hand excavation draws water after 48 hours when charity river sulfur acid aluminium potassium.Reduce the soil layer moisture content through drawing water;
(2) draining falls in open caisson: stop through soil table and decide behind the drainage procedure or confirm soil 35%≤moisture content≤50% o'clock through test, adopt the deep-well precipitation water discharge method to carry out that the well point is arranged, the well bucket is made, the well bucket is installed, the program of drawing water; The well point is arranged as a well point is set in per 50 ㎡, and the well bucket designs according to proposed building ground level planned well bucket height, and the well bucket highly is the half the of depth of building; The well bucket is a cylinder, and well internal diameter Ф>=1m, well bucket adopt common brick to make; Mortar-chalked joint is used in the slit; The jointing mortar is pressed sand and cement proportion 3:1 configuration, and sand is medium coarse sand, and cement is 325 ordinary Portland cements; The well bucket install to adopt mechanicalness mounting shaft casing to go within the steel drum, squeezes in the soil along the pile tube machine with vibration then, holds together out steel drum then, with the draining of drawing water of sunk water pump, soil moisture in layer is reduced to below 20% behind the right bucket;
(3) solidating agent configuration:, carry out the configuration of weak soil solidating agent simultaneously carrying out deep-well when falling row; The weak soil solidating agent is made up of cement, the sand of 30-60%, the lime of 0-40%, the flyash of 0-40%, the slag of 0-20%, the gypsum of 0-8%, the 0-5% smalls silicon-base oxide of 30-40%, and various materials are stirred;
(4) implant solidating agent: adopt dried spray method to implant, promote the stirring of dusting, the demand height of rising to bores again, rises to the demand absolute altitude and shuts down, and carries out second group of implantation more in this order.Implantation depth is 50% of a depth of building, and diameter is 50cm; The implantation spacing is 1.8m;
(5) spray polyurethane foams: spray with spray infusion air gun, spraying the degree of depth is 50% of depth of building, and spraying spacing is 1.8m;
(6) accomplish expiration 25 days when above operation, detect, get into the construction-engineering project construction sequence then.
Particle diameter >=the 1mm of said alum.
Easy construction of the present invention, efficiency of construction is high, and good working effect is handled through present technique, forms the soil structures that water content is low, compactness is strong, bearing capacity is high, makes former weak soil that the variation of matter take place.
Below in conjunction with embodiment the present invention is described further.
The specific embodiment
Embodiment 1:
A kind of weak soil solidifies job practices, comprising:
(1) the soil table is stopped and is decided draining: according to test report; Soil moisture content >=50 o'clock dispense alum at soil property shallow-layer (the soil property degree of depth 20 ~ 50cm position), per 100 ㎡ charity 1.2kg alum; It is even to carry out mix with every 1.2kg alum and 100kg yellow ground during charity, adopts artificial charity then; Before charity, be one with 1000 ㎡ zones and get a little, the pool of drawing water is set, the hand excavation draws water after 48 hours when charity river sulfur acid aluminium potassium.Reduce the soil layer moisture content through drawing water;
(2) draining falls in open caisson: stop through soil table and decide behind the drainage procedure or confirm soil 35%≤moisture content≤50% o'clock through test, adopt the deep-well precipitation water discharge method to carry out that the well point is arranged, the well bucket is made, the well bucket is installed, the program of drawing water; The well point is arranged as a well point is set in per 50 ㎡, and the well bucket designs according to proposed building ground level planned well bucket height, and the well bucket highly is the half the of depth of building; The well bucket is a cylinder, and well internal diameter Ф>=1m, well bucket adopt common brick to make; Mortar-chalked joint is used in the slit; The jointing mortar is pressed sand and cement proportion 3:1 configuration, and sand is medium coarse sand, and cement is 325 ordinary Portland cements; The well bucket install to adopt mechanicalness mounting shaft casing to go within the steel drum, squeezes in the soil along the pile tube machine with vibration then, holds together out steel drum then, with the draining of drawing water of sunk water pump, soil moisture in layer is reduced to below 20% behind the right bucket;
(3) solidating agent configuration:, carry out the configuration of weak soil solidating agent simultaneously carrying out deep-well when falling row; The weak soil solidating agent is made up of 30% cement, 40% sand, 10% lime, 10% flyash, 5% slag, 3% gypsum, 2% smalls silicon-base oxide, and various materials are stirred;
(4) implant solidating agent: adopt dried spray method to implant, promote the stirring of dusting, the demand height of rising to bores again, rises to the demand absolute altitude and shuts down, and carries out second group of implantation more in this order.Implantation depth is 50% of a depth of building, and diameter is 50cm; The implantation spacing is 1.8m;
(5) spray polyurethane foams: spray with spray infusion air gun, spraying the degree of depth is 50% of depth of building, and spraying spacing is 1.8m;
(6) accomplish expiration 25 days when above operation, detect, get into the construction-engineering project construction sequence then.
Particle diameter >=the 1mm of said alum.
Embodiment 2:
The weak soil solidating agent is made up of 40% cement, 50% sand, 5% lime, 2% flyash, 1% slag, 1% gypsum, 1% smalls silicon-base oxide.All the other are with embodiment 1.
Embodiment 3:
The weak soil solidating agent is made up of 35% cement, 55% sand, 0% lime, 0% flyash, 5% slag, 1% gypsum, 4% smalls silicon-base oxide.All the other are with embodiment 1.
Embodiment 4:
The weak soil solidating agent is made up of 30% cement, 30% sand, 20% lime, 20% flyash.All the other are with embodiment 1.

Claims (2)

1. a weak soil solidifies job practices, it is characterized in that: comprising:
(1) soil table is stopped and decided draining: according to test report, soil moisture content >=50 o'clock dispense alum at the soil property shallow-layer, per 100 ㎡ charity 1.2kg alum, and it is even to carry out mix with every 1.2kg alum and 100kg yellow ground during charity, adopts artificial charity then; Before charity, be one with 1000 ㎡ zones and get a little, the pool of drawing water is set, the hand excavation draws water after 48 hours when charity river sulfur acid aluminium potassium.Reduce the soil layer moisture content through drawing water;
(2) draining falls in open caisson: stop through soil table and decide behind the drainage procedure or confirm soil 35%≤moisture content≤50% o'clock through test, adopt the deep-well precipitation water discharge method to carry out that the well point is arranged, the well bucket is made, the well bucket is installed, the program of drawing water; The well point is arranged as a well point is set in per 50 ㎡, and the well bucket designs according to proposed building ground level planned well bucket height, and the well bucket highly is the half the of depth of building; The well bucket is a cylinder, and well internal diameter Ф>=1m, well bucket adopt common brick to make; Mortar-chalked joint is used in the slit; The jointing mortar is pressed sand and cement proportion 3:1 configuration, and sand is medium coarse sand, and cement is 325 ordinary Portland cements; The well bucket install to adopt mechanicalness mounting shaft casing to go within the steel drum, squeezes in the soil along the pile tube machine with vibration then, holds together out steel drum then, with the draining of drawing water of sunk water pump, soil moisture in layer is reduced to below 20% behind the right bucket;
(3) solidating agent configuration:, carry out the configuration of weak soil solidating agent simultaneously carrying out deep-well when falling row; The weak soil solidating agent is made up of cement, the sand of 30-60%, the lime of 0-40%, the flyash of 0-40%, the slag of 0-20%, the gypsum of 0-8%, the 0-5% smalls silicon-base oxide of 30-40%, and various materials are stirred;
(4) implant solidating agent: adopt dried spray method to implant, promote the stirring of dusting, the demand height of rising to bores again, rises to the demand absolute altitude and shuts down, and carries out second group of implantation more in this order.Implantation depth is 50% of a depth of building, and diameter is 50cm; The implantation spacing is 1.8m;
(5) spray polyurethane foams: spray with spray infusion air gun, spraying the degree of depth is 50% of depth of building, and spraying spacing is 1.8m;
(6) accomplish expiration 25 days when above operation, detect, get into the construction-engineering project construction sequence then.
2. weak soil according to claim 1 solidifies job practices, it is characterized in that: the particle diameter >=1mm of said alum.
CN201210234675.3A 2012-07-09 2012-07-09 Soft soil curing construction method Active CN102733366B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210234675.3A CN102733366B (en) 2012-07-09 2012-07-09 Soft soil curing construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210234675.3A CN102733366B (en) 2012-07-09 2012-07-09 Soft soil curing construction method

Publications (2)

Publication Number Publication Date
CN102733366A true CN102733366A (en) 2012-10-17
CN102733366B CN102733366B (en) 2014-06-04

Family

ID=46989623

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210234675.3A Active CN102733366B (en) 2012-07-09 2012-07-09 Soft soil curing construction method

Country Status (1)

Country Link
CN (1) CN102733366B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103992799A (en) * 2013-09-06 2014-08-20 宁波万土环保科技有限公司 Sea mud curing agent and production method thereof
CN105780764A (en) * 2016-03-30 2016-07-20 东南大学 Light cemented soil composite mixing pile
CN108221529A (en) * 2018-01-15 2018-06-29 赤峰诚联市政工程有限责任公司 Urban road mud base squeezes curing construction method
CN108330950A (en) * 2018-02-08 2018-07-27 沙焕焕 In-situ soil is modified the method for manufacturing artificial mud stone
CN108729436A (en) * 2017-04-19 2018-11-02 连云港港口工程设计研究院有限公司 A kind of quick consolidation method suitable for silt soft foundation

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004197307A (en) * 2002-12-16 2004-07-15 Kajima Corp Soil improving method
CN101215141A (en) * 2008-01-02 2008-07-09 邓亚光 Soft soil curing agent
CN101949148A (en) * 2010-09-25 2011-01-19 中国十九冶集团有限公司武汉分公司 Method for constructing artificial dug pile at reduced well point ground water level
KR20120001856A (en) * 2010-06-30 2012-01-05 어영자 Method for reinforcing soft ground using geosynthetics and open channel

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004197307A (en) * 2002-12-16 2004-07-15 Kajima Corp Soil improving method
CN101215141A (en) * 2008-01-02 2008-07-09 邓亚光 Soft soil curing agent
KR20120001856A (en) * 2010-06-30 2012-01-05 어영자 Method for reinforcing soft ground using geosynthetics and open channel
CN101949148A (en) * 2010-09-25 2011-01-19 中国十九冶集团有限公司武汉分公司 Method for constructing artificial dug pile at reduced well point ground water level

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张云,林彬,顶静: "岩土工程泥浆固化处理技术研究", 《山西建筑》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103992799A (en) * 2013-09-06 2014-08-20 宁波万土环保科技有限公司 Sea mud curing agent and production method thereof
CN103992799B (en) * 2013-09-06 2017-10-10 宁波万土环保科技有限公司 Ooze curing agent and its production method
CN105780764A (en) * 2016-03-30 2016-07-20 东南大学 Light cemented soil composite mixing pile
CN108729436A (en) * 2017-04-19 2018-11-02 连云港港口工程设计研究院有限公司 A kind of quick consolidation method suitable for silt soft foundation
CN108221529A (en) * 2018-01-15 2018-06-29 赤峰诚联市政工程有限责任公司 Urban road mud base squeezes curing construction method
CN108330950A (en) * 2018-02-08 2018-07-27 沙焕焕 In-situ soil is modified the method for manufacturing artificial mud stone

Also Published As

Publication number Publication date
CN102733366B (en) 2014-06-04

Similar Documents

Publication Publication Date Title
CN102898107B (en) Concrete healant
CN108675699A (en) A kind of corrosion-resistant geopolymer filling concrete pile material and preparation method thereof and construction technology
CN102733366B (en) Soft soil curing construction method
CN104402339A (en) Pervious concrete and construction method thereof
CN101581093B (en) Composite high performance soil cement mortar pile construction method
CN104404838B (en) The above railway collapsible loess subgrade substrate treating method of speed 200km
CN103936347A (en) Ultra-high performance cement-based impact wear resistant material
CN111995339A (en) Anti-scouring solidified soil for ocean platform and preparation method thereof
CN107989032A (en) A kind of construction method of punching interlocking pile
CN104818707A (en) Method for solidifying and curing dredger sludge and new dredger fill by applying cotton stalks
CN106192666A (en) A kind of permeable mortar and utilize the porous pavement that permeable mortar makes
CN101845830B (en) Open caisson deviation rectification construction method
CN101935198B (en) Environment-friendly shield construction single-liquid synchronous grouting slurry
CN102155012A (en) Foundation reinforcing construction method employing powder high-pressure injection grouting
CN105347751A (en) Preparation method of high-strength concrete
CN107989049A (en) A kind of construction method of frame bank protection
CN105040683A (en) Informatization construction method for cement mixing piles
CN111676987A (en) Construction method for backfilling construction of construction fertilizer tank by vibrating, slurry-flushing and ramming method
CN103833289A (en) Quick-setting anti-crack polymeric mortar
CN111908853A (en) Self-compacting soil, preparation method thereof and construction method for backfilling municipal cavity
CN103603355B (en) The empty stake processing method of a kind of bored pile
CN110409255A (en) Town road and constructing operation method
CN105347744A (en) High-strength prefabricated reinforced concrete hollow square pile
CN101906779B (en) Supporting process of portal frame type anchor pipe soil nail spraying net and modified reinforcing cement mortar employed by same
CN105256804A (en) Preparation device and backfilling method for flow-state cement soil

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Soft soil solidification construction method

Effective date of registration: 20220427

Granted publication date: 20140604

Pledgee: China Construction Bank Corporation Rudong sub branch

Pledgor: JIANGSU SHUNTONG CONSTRUCTION GROUP Co.,Ltd.

Registration number: Y2022980004919