CN109252433A - Method soft soil foundation intensive treatment construction and reinforce soft soil foundation foundation pit - Google Patents

Method soft soil foundation intensive treatment construction and reinforce soft soil foundation foundation pit Download PDF

Info

Publication number
CN109252433A
CN109252433A CN201810936973.4A CN201810936973A CN109252433A CN 109252433 A CN109252433 A CN 109252433A CN 201810936973 A CN201810936973 A CN 201810936973A CN 109252433 A CN109252433 A CN 109252433A
Authority
CN
China
Prior art keywords
foundation
soft soil
foundation pit
water penetration
soil foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810936973.4A
Other languages
Chinese (zh)
Inventor
王军
高紫阳
符洪涛
蔡袁强
倪俊峰
史文杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wenzhou University
Original Assignee
Wenzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wenzhou University filed Critical Wenzhou University
Priority to CN201810936973.4A priority Critical patent/CN109252433A/en
Publication of CN109252433A publication Critical patent/CN109252433A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
    • E02D3/106Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains by forming sand drains containing only loose aggregates
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/36Concrete or concrete-like piles cast in position ; Apparatus for making same making without use of mouldpipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Abstract

The invention discloses a kind of soft soil foundation intensive treatment constructions, it is characterized in that: including multiple # shape roads, multiple # font roads are separated out multiple foundation pit regions, and the position of close road has set water penetration pile in foundation pit, inserted with steel reinforcement cage in water penetration pile, and it is filled with permeable celluar concrete.Soft soil foundation intensive treatment construction improves tubular pole shear resistance, simplifies excavation of foundation pit and strengthening construction process, saving construction period and material cost.Provide the method that soft soil foundation foundation pit is reinforced using above-mentioned soft soil foundation intensive treatment construction.The technical effects of the invention are that: together with directly basement process, reinforcing are effectively combined with excavation of foundation pit, permeable celluar concrete after water penetration pile and solidification stays in the soil body together, the common bearing capacity for strengthening the soil body, the soil body is set quickly to be strengthened, the shear resistance for enhancing water penetration pile simultaneously, can be used as fender post and plays the role of earth-retaining sealing, the problem for effectively preventing setting cast-in-situ bored pile hardly possible, excavation of foundation pit and strengthening construction process are simplified, construction period and material cost are saved.

Description

Method soft soil foundation intensive treatment construction and reinforce soft soil foundation foundation pit
Technical field
The present invention relates to a kind of methods soft soil foundation intensive treatment construction and reinforce soft soil foundation foundation pit.
Background technique
With the rapid development of China's southeastern coast economic construction, population is also increased, and is increasingly increased to Land Demand. Tianjin, Jiangsu, Guangdong and Zhejiang etc. are coastal, and all once a wide range of reclaiming land around sea, these areas were mostly Muddy Bottoms class weak soil.Have Water content height, the structural feature that poor permeability, intensity is low, hole is big, low-density and tool are certain, and it is distributed often not Uniformly.By taking the coastal industrial zone in Wenzhou as an example, it is in flow regime that soil strength is low, high sensitivity, moisture content is high, compressibility is high, It is typical soft soil foundation.Since initial strength is low, large-scale construction equipment is difficult to march into the arena, and excavation of foundation pit cost is high, construction Long in time limit, posterior settlement is big.These are all that engineering increases huge difficulty.In order to meet construction requirement, a series of soft soil foundations Processing method is suggested, such as vacuum method, vacuum pre-pressed joint electric osmose, vacuum pre-pressed joint chemical reagent, vacuum preloading Combined stack-load etc., these methods have certain effect in terms of handling weak soil, therefore are widely used.But it is true Empty pre-pressed joint electro-osmosis method because its consume energy it is larger can not large-area applications, and vacuum pre-pressed joint chemical-agent technique has certain dirt Dye, the cost of vacuum combined stack-load method is again higher, thus in Practical Project using it is more be more economical vacuum method.
However, occurring the undesirable phenomenon of consolidation effect often due to the drain bar generation silting in vacuum preloading.In addition, These method for processing foundation all use plastic draining board to transmit vacuum load and as drainage channel, are retained in after treatment In the soil body, it is difficult to cast-in-situ bored pile is used, stake holes deflection is easily caused, and the shear resistance of prefabricated tubular pile is poor, it is difficult to as side slope Maintaining pile, excavation of foundation pit difficulty are huge.
Summary of the invention
In view of the deficiency of background technique, technical problem to be solved by the invention is to provide one kind can be improved tubular pole shearing resistance Ability simplifies excavation of foundation pit and strengthening construction process, the soft soil foundation intensive treatment for saving construction period and material cost Construction and the method for reinforcing soft soil foundation foundation pit.
For this purpose, the present invention is to adopt the following technical scheme that realize:
A kind of soft soil foundation intensive treatment construction, it is characterized in that: including multiple # font roads, multiple # font roads separate Multiple foundation pit regions out, the position in foundation pit close to road have set water penetration pile, inserted with steel reinforcement cage in water penetration pile, and are filled with Permeable celluar concrete.
A method of it is constructed using claim 1 soft soil foundation intensive treatment and reinforces soft soil foundation foundation pit, it is special Sign is: the following steps are included:
Step 1: # font road is laid with using compacting and landfill microlith layer first within the scope of soft soil foundation;It (please provide The method that road is formed)
Step 2: the water penetration pile with through-hole is set in the rectangular processing region that # font road is separated to form, in water penetration pile It is inside initially charged with steel reinforcement cage, refills permeable celluar concrete, and permeable celluar concrete is waited to solidify;
Step 3: the blocking with drinking-water pipe is set in water penetration pile upper end, blocking closes the upper end of water penetration pile, and the drinking-water pipe passes through Pipeline is connect with exhaust device, and covering geotextiles and sealing film, open exhaust device above the soil body of the rectangular processing region Carry out pump drainage processing;
Step 4: carrying out excavation of foundation pit, carries out amputation and levelling to the permeable tubular pole for being higher than foundation pit in digging process.
It is synchronized in the step 2 and sets drain bar, drain bar is connect with exhaust device in the step 3, drain bar Pump drainage is carried out jointly with water penetration pile.
The permeable celluar concrete includes that aggregate, cement, reinforcing agent and water mixing are formed.
The technical effects of the invention are that: together with being directly effectively combined basement process, reinforcing with excavation of foundation pit, thoroughly Permeable celluar concrete after water stake and solidification stays in the soil body together, the common bearing capacity for strengthening the soil body, keep the soil body quick To reinforcing, while the shear resistance of water penetration pile is enhanced, can be used as fender post and play the role of earth-retaining sealing, effectively prevents beating If the problem of cast-in-situ bored pile hardly possible, excavation of foundation pit and strengthening construction process are simplified, saves construction period and material cost.
Detailed description of the invention
The present invention has following attached drawing:
Structural schematic diagram before Fig. 1 excavation of foundation pit of the present invention;
Fig. 2 is the structural schematic diagram after excavation of foundation pit of the present invention;
Fig. 3 is the top view after excavation of foundation pit of the present invention;
Fig. 4 is top view before excavation of foundation pit.
Specific embodiment
Referring to Fig.1 shown in -4, a kind of soft soil foundation intensive treatment construction provided by the invention, including multiple # fonts road Road 1, multiple # font font roads 1 are separated out multiple 2 regions of foundation pit, and the position of close road has set water penetration pile 3 in foundation pit 2 With drain bar 7, waterproof stake 8 is set around entire treatment region, inserted with steel reinforcement cage in waterproof stake 8, and be filled with concrete 4。
The present invention also provides a kind of soft soil foundation intensive treatments to construct the method for reinforcing soft soil foundation foundation pit, including Following steps:
Step 1: using tamping and filling microlith layer laying # font road 1 first within the scope of soft soil foundation, place is utilized Surrounding buildings rubbish or sandstone around the soft base place laying construction road, soft soil foundation is divided into several faces The roughly equal region of product determines, the region shape split is regular as far as possible with specific reference to soft soil foundation shape, it is therefore an objective to Facilitate piling and vacuum preloading to operate, and road is tamped using excavator, it is ensured that piling machine being capable of operation;
Step 2: the water penetration pile 3 with through-hole is set in the rectangular processing region that # font road 1 is separated to form, permeable It is initially charged with steel reinforcement cage in stake 3, refills permeable celluar concrete, and permeable celluar concrete is waited to solidify;Water penetration pile can be It plays a role in the drainage when vacuumizing, while setting the waterproof stake 8 of a circle around soft soil foundation processing region, when vacuumizing, It can prevent the outer water for the treatment of region from penetrating into, guarantee treatment region vacuum degree;
Step 3: the blocking with drinking-water pipe is set in 3 upper end of water penetration pile, blocking closes the upper end of water penetration pile, so that water penetration pile 3 It can play a role in the drainage, drain bar is connect also by pipeline with exhaust device.The drinking-water pipe passes through pipeline and exhaust device Connection, the soil body top covering geotextiles 5 and sealing film 6 of rectangular processing region, opens exhaust device progress pump drainage processing;
Step 4: after pump drainage, water in water penetration pile 3 being extracted out, and waterproof stake 8 is put into steel reinforcement cage, refills concrete 4, and Concrete 4 is waited to solidify;Foundation pit 2 is carried out again to excavate, and after the completion of excavation, the permeable tubular pile head for being higher than foundation pit is cut, is cut Preceding survey crew first carries out the measurement of the level, releases actual stake top absolute altitude.Waterproof stake 8 at this time can be used as fender post use, nothing Fender post need to be set again.
In the above-described embodiments, in order to further enhance effect: can be synchronized in step 2 and set drain bar 7, in step 3 Middle drain bar 7 is connect with exhaust device, and drain bar 7 and water penetration pile 3 carry out pump drainage jointly, permeable celluar concrete 4 include aggregate, Cement, reinforcing agent and water mixing are formed.
In the present embodiment, together with being directly effectively combined with excavation of foundation pit basement process, reinforcing, 3 row of water penetration pile Water plate 7 stays in the soil body together, and the common bearing capacity for strengthening the soil body makes the soil body quickly be strengthened, waterproof stake 8 can be in pump drainage Period plays sealing function, and foundation pit exploitation period plays earth-retaining sealing effect, no longer needs to separately set fender post, the reinforcing bar in stake Cage concrete enhances the shear resistance of waterproof stake while effectively preventing setting the problem of cast-in-situ bored pile hardly possible, simplifies base Hole is excavated and strengthening construction process, saves construction period and material cost.

Claims (4)

1. a kind of soft soil foundation intensive treatment construction, it is characterized in that: including multiple # font roads, multiple # font roads point Multiple foundation pit regions are separated out, the position of close road has set water penetration pile in foundation pit, and water penetration pile is interior inserted with steel reinforcement cage, and fills There is permeable celluar concrete.
2. a kind of construct the method for reinforcing soft soil foundation foundation pit, feature using claim 1 soft soil foundation intensive treatment It is: the following steps are included:
Step 1: # font road is laid with using landfill and compacting microlith layer first within the scope of soft soil foundation;
Step 2: the water penetration pile with through-hole is set in the rectangular processing region that # font road is separated to form, in water penetration pile It is inside initially charged with steel reinforcement cage, refills permeable celluar concrete, and permeable celluar concrete is waited to solidify;
Step 3: the blocking with drinking-water pipe is set in water penetration pile upper end, blocking closes the upper end of water penetration pile, it is therefore an objective to prevent from taking out true In null process, the gas leakage of water penetration pile upper end causes vacuum degree to decline, and the drinking-water pipe is connect by pipeline with exhaust device, the side Covering geotextiles and sealing film, open exhaust device and carry out pump drainage processing above the soil body of shape processing region;
Step 4: carrying out excavation of foundation pit, after the completion of excavation, cuts to the permeable tubular pile head for being higher than foundation pit, measures people before cutting Member first carries out the measurement of the level, releases actual stake top absolute altitude.
3. according to claim 2 reinforce soft soil foundation base using claim 1 soft soil foundation intensive treatment construction The method in hole sets drain bar it is characterized in that: synchronizing in the step 2, and drain bar and exhaust device connect in the step 3 It connects, drain bar and water penetration pile carry out pump drainage jointly.
4. according to claim 2 or 3 reinforce soft soil foundation using claim 1 soft soil foundation intensive treatment construction The method of foundation pit, it is characterized in that: the permeable celluar concrete includes that aggregate, cement, reinforcing agent and water mixing are formed.
CN201810936973.4A 2018-08-16 2018-08-16 Method soft soil foundation intensive treatment construction and reinforce soft soil foundation foundation pit Pending CN109252433A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810936973.4A CN109252433A (en) 2018-08-16 2018-08-16 Method soft soil foundation intensive treatment construction and reinforce soft soil foundation foundation pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810936973.4A CN109252433A (en) 2018-08-16 2018-08-16 Method soft soil foundation intensive treatment construction and reinforce soft soil foundation foundation pit

Publications (1)

Publication Number Publication Date
CN109252433A true CN109252433A (en) 2019-01-22

Family

ID=65050243

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810936973.4A Pending CN109252433A (en) 2018-08-16 2018-08-16 Method soft soil foundation intensive treatment construction and reinforce soft soil foundation foundation pit

Country Status (1)

Country Link
CN (1) CN109252433A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110820716A (en) * 2019-12-06 2020-02-21 山西机械化建设集团有限公司 Method for dynamic compaction composite treatment of mucky soil foundation by gravel pile, drainage plate and upper filling body
CN111519484A (en) * 2020-04-15 2020-08-11 中电建路桥集团有限公司 Highway soft foundation treatment structure and construction method
CN112112151A (en) * 2020-09-04 2020-12-22 山西华晋岩土工程勘察有限公司 Foundation reinforcement treatment method
CN112227122A (en) * 2020-08-29 2021-01-15 天津鑫路桥建设工程有限公司 Roadbed reinforcing structure and construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020081507A (en) * 2001-04-18 2002-10-28 최귀봉 Paper drain board building method and stitcher for more double hole
CN102505597A (en) * 2011-09-13 2012-06-20 青岛理工大学 Novel system for treating soft foundation of high-speed railway
CN102704488A (en) * 2012-04-24 2012-10-03 王军 Novel soft soil foundation pit excavation method
CN103074883A (en) * 2013-01-11 2013-05-01 温州大学 Active type preloading combined foundation reinforcing method
CN103628468A (en) * 2013-12-24 2014-03-12 山东大学 Foundation treatment method adopting water penetration pile in combination with vacuum preloading

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020081507A (en) * 2001-04-18 2002-10-28 최귀봉 Paper drain board building method and stitcher for more double hole
CN102505597A (en) * 2011-09-13 2012-06-20 青岛理工大学 Novel system for treating soft foundation of high-speed railway
CN102704488A (en) * 2012-04-24 2012-10-03 王军 Novel soft soil foundation pit excavation method
CN103074883A (en) * 2013-01-11 2013-05-01 温州大学 Active type preloading combined foundation reinforcing method
CN103628468A (en) * 2013-12-24 2014-03-12 山东大学 Foundation treatment method adopting water penetration pile in combination with vacuum preloading

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张巨松主编: "《混凝土学》", 30 June 2017, 哈尔滨工业出版社 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110820716A (en) * 2019-12-06 2020-02-21 山西机械化建设集团有限公司 Method for dynamic compaction composite treatment of mucky soil foundation by gravel pile, drainage plate and upper filling body
CN111519484A (en) * 2020-04-15 2020-08-11 中电建路桥集团有限公司 Highway soft foundation treatment structure and construction method
CN111519484B (en) * 2020-04-15 2021-11-30 中电建路桥集团有限公司 Highway soft foundation treatment structure and construction method
CN112227122A (en) * 2020-08-29 2021-01-15 天津鑫路桥建设工程有限公司 Roadbed reinforcing structure and construction method
CN112112151A (en) * 2020-09-04 2020-12-22 山西华晋岩土工程勘察有限公司 Foundation reinforcement treatment method

Similar Documents

Publication Publication Date Title
CN103233454B (en) Processing method of soaking, vacuum preloading and slurry injecting for sand piles of collapsible loess foundation
CN105386433B (en) A kind of microorganism soil-fixing CFG pile composite foundations and construction method
CN201883438U (en) Pit-in-foundation-pit steel sheet pile foundation pit supporting structure
CN109252433A (en) Method soft soil foundation intensive treatment construction and reinforce soft soil foundation foundation pit
CN107503257B (en) One kind being close to mountain high-filled subgrade stabilization and Deformation control structure and construction method
CN105672348A (en) Construction method for cropping bridge pile foundation at sandy gravel stratum of abyssal region
CN105464074B (en) A kind of artificial digging pile high polymer grouting safeguard structure and its construction method
CN207109475U (en) It is close to mountain high-filled subgrade stabilization and Deformation control structure
CN108560542B (en) Waste tire coated building slag bidirectional reinforcement and construction method thereof
CN104499479A (en) Dig-hole pile construction method based on penetration of sand gravel backfilling layer
CN107513994A (en) One kind segmentation becomes supporting rotary digging stake and its construction method without leave
CN106812150A (en) A kind of mountain area steep slope region Road Bridge Pile Foundation construction method
CN110258538A (en) A kind of soil nailing reinforces buffer-type artificial digging pile and its construction method
CN105113478A (en) Dynamic compaction treatment method of deep foundation displacement
CN110080169A (en) A kind of construction method reclaimed fields from the sea utilized based on basement
CN109281330A (en) A kind of osmotic control method
CN107687175A (en) The vertical antifouling isolation wall construction of both sides ground local stiffening type and method
CN114575355A (en) Soil protection and descent construction method
CN208201874U (en) A kind of open-cell cloth bag grouting structure
CN105484270B (en) Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit
CN107023021A (en) A kind of design and construction method of flexible compound Diaphragm Wall Support Structure
CN107034894A (en) Post-tensioned prestressed tension beam recoverable pattern foundation pit supporting structure prefabricated pile and preparation method thereof and construction method
CN207211176U (en) A kind of big open caisson of superelevation
CN108570979A (en) A kind of construction method for building antiseepage composite foundation on dolomite stratigraph
CN213897154U (en) Soft soil foundation pit bottom curing structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190122

RJ01 Rejection of invention patent application after publication