CN108570979A - A kind of construction method for building antiseepage composite foundation on dolomite stratigraph - Google Patents
A kind of construction method for building antiseepage composite foundation on dolomite stratigraph Download PDFInfo
- Publication number
- CN108570979A CN108570979A CN201810344159.3A CN201810344159A CN108570979A CN 108570979 A CN108570979 A CN 108570979A CN 201810344159 A CN201810344159 A CN 201810344159A CN 108570979 A CN108570979 A CN 108570979A
- Authority
- CN
- China
- Prior art keywords
- construction
- stake
- composite foundation
- stabilized macadam
- cement stabilized
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/02—Improving by compacting
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/02—Improving by compacting
- E02D3/08—Improving by compacting by inserting stones or lost bodies, e.g. compaction piles
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- Agronomy & Crop Science (AREA)
- Environmental & Geological Engineering (AREA)
- Soil Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
The present invention relates to a kind of on dolomite stratigraph builds the construction method of antiseepage composite foundation, including smooth location, stroke fixed pile, laying construction platform, drilling stake holes, drill bit and simultaneously concrete perfusion, formation pile crown, finishing pile crown, laying mattress layer into stake holes are promoted, mattress layer is made to connect the step of forming antiseepage composite foundation with cement stabilized macadam stake.Technical solution using the present invention, concrete-pile construction technology is applied in construction of hydropower plant, extend the construction technique scope of application, the composite construction formed by cement stabilized macadam stake and mattress layer greatly strengthens the structural strength and bearing capacity of antiseepage composite foundation, effectively prevents composite foundation and deforms, in addition, due to being not required to embedded reinforcing bar in cement stabilized macadam stake, project cost is greatly reduced, construction technology is simplified, saves construction cost.
Description
Technical field
The invention belongs to the realm of building construction more particularly to a kind of constructions for building antiseepage composite foundation on dolomite stratigraph
Method.
Background technology
With being continuously increased for high-rise quantity, in old urban area, construction uses well-points dewatering, causes adjacent building, pipe
The phenomenon that line, pavement cracking are sunk is commonplace, in order to protect groundwater resources, reduce waste, prevents building dam foundation pit
Outer level of ground water, which declines, induces related geological disaster, has built building, pipeline, pavement of road to surrounding and has caused various danger
Evil, waterproof are the primary measure of dam foundation pit construction precipitation and the main flow direction of future development from now on, the underground of all trades and professions
Exploitation of mineral resources, Underground Space Resource exploitation, municipal works, subway engineering, the underground anti-seepage of hydraulic structure, super large deep water
Dam foundation hole etc. engineering be unable to do without sealing, and sealing is built with deep stirring or high-pressure rotary-spray machinery, in recent years, large type drill by
In with mobility strong, transition and ground easy for installation advantage, used by large and medium-sized basic engineering construction unit, still, for
Certain constructions with multiplexed address condition, building waterproof construction can not be ignored, for example, tieing up prompt Buss with Byelorussia
For gram construction of hydropower stations project under construction, the power stations Byelorussia dimension Jie Busike are located at the west of Byelorussia Wei Jiebusikeshi
On Dvina, away from dimension Jie Busike city 8km, in the dam construction in the power stations dimension Jie Busike, by the dam dam site institute
Place area belongs to the northern branch in the highlands Byelorussia dimension Jie Busike, and landforms belong to West Germany's wiener flood land till plain, till plain
Surface is to tilt hummock, and West Germany's wiener flood land landforms are fairly obvious, and hillside fields height difference reaches 49m, and Dam Site surface layer, which is ploughed, plants soil
Layer depth about 0.2~0.3m, dam section include on the stratum that depth is 3.3~40m:Modern and ancient lakes alluvial deposits layer is comprehensive
Zoarium is on the point of lake ice glacial drift sedimentary, is on the point of lake layer position ice water and lake glacial deposit layer, glacial drift sedimentary, ice water and lake
Glacial deposit layer synthesis is moored, Devonian system dolomite contains a large amount of sandy gravel, dolomite crushed zone, geological conditions under earth's surface
Sufficiently complex, Hydropower station pivotal area builds ground substantially based on fertile soil, sandy loam, Extra-fine sand, blocky loam, and underground is held
It presses water abundant, can not meet building to ground requirement for bearing capacity, in this case, in order to ensure the construction matter of dam
Amount, dam foundation pit have the characteristics that depth is deep, area is big, how to build to meet under the geological conditions of this complexity and effectively prevent
Water is that necessary condition is created in the dry work of ground, is the key that Hydropower station pivotal area is built.
Invention content
The construction of antiseepage composite foundation is built in order to solve the above technical problems, the present invention provides a kind of on dolomite stratigraph
Method.
The present invention is achieved by the following technical programs.
The present invention provides a kind of construction method for building antiseepage composite foundation on dolomite stratigraph, includes mainly following step
Suddenly:
Step 1:Smooth location:The closed region in somewhere is selected on the ground as construction site, is removed in construction site
All vegetation keep construction site smooth using road roller roller compaction construction place;
Step 2:Draw fixed pile:Required according to construction drawing, in the smooth good construction site described in step 1, with
Several positions delimited at construction drawing opposite position, and each position is sequentially numbered and is marked;
Step 3:Laying construction platform:It is laid with an operation platform on construction ground, keeps personnel, equipment and tool logical
It crosses the operation platform and is movable to any one position;
Step 4:Creep into stake holes:Along operation platform will on drilling-machine shifter to one of stake position, adjust drilling machine tower body and
Drill bit makes drill bit of drilling machine earthward creep into after keeping it perpendicular with ground at stake position, obtains the stake holes that depth is H;
Step 5:Promote drill bit:Drill bit is proposed with constant promotion speed in the stake holes described in step 4, meanwhile,
During drill bit is promoted, to concrete perfusion between the drill bit outer surface and the stake holes inner wall, drill bit is proposed completely
Afterwards, after concrete setting, cement stabilized macadam stake is obtained in the stake holes;
Step 6:By operation platform by drilling-machine shifter to next position, step 4 is repeated to step 5, successively every
Cement stabilized macadam stake is obtained on a position;
Step 7:Form pile crown:After all cement stabilized macadam stakes are made 14 days, dug using engineering machinery broken according to all cement
Soil between stone mar, Demolition Construction platform make all cement stabilized macadam stakes be partially exposed to ground pile crown formed above;
Step 8:Modify pile crown:All pile crowns are cleared up and modified using electric pick or concrete cutting machine, remove institute
There is the soil and impurity adhered on pile crown, keeps all pile crowns identical relative to ground level;
Step 7:It is laid with mattress layer:It is laid with mattress layer between the pile crown, in compacting mattress layer, makes mattress layer and institute
Cement stabilized macadam is stated to connect to form antiseepage composite foundation.
The cement stabilized macadam stake outer diameter is not less than 600mm.
It is in quincuncial arrangement that the stake position is interior on construction ground, and two stake position centre-to-centre spacing of arbitrary neighborhood are less than 2m.
Earthward rate of penetration is 1m/min to 1.5m/min to drill bit of drilling machine described in step 4.
It is 2.5m/min that drill bit described in step 5, which promotes speed,.
Concrete described in step 5 is using cement, sand, rubble, water and additive according to 270:780:1170:180:
1.7 quality proportioning is mixed and stirred.
The operation platform be by be layed in successively on ground dry clay layer, dolomite metalling is after road roller is compacted
It is formed.
Sand gravel of the mattress layer by maximum particle size less than 3cm forms.
The beneficial effects of the present invention are:Concrete-pile construction technology is applied to water by technical solution using the present invention
During electrical engineering is built, the antiseepage composite foundation that construction method of the present invention is built may be not only suitable for Dam, can also fit
The foundation constructions operations such as sluice, workshop, clipping room for power station periphery, by soft, fragmentary dolomite stratigraph
It arranges more cement stabilized macadam stakes, then makes cement stabilized macadam stake be combined as a whole to be formed with mattress layer by being laid with mattress layer between stake
Composite construction ground, greatly strengthens the structural strength and bearing capacity of ground, and no matter load action is then in cement stabilized macadam stake
Or it can ensure that cement stabilized macadam stake, mattress layer participate in work always in composite foundation on soil between cement stabilized macadam stake, due to
The intensity and elasticity modulus of cement stabilized macadam stake pile body are larger, and under the action of load, cement stabilized macadam stake top stress compares water
Soil surface stress is big between mud broken stone pile, and cement stabilized macadam stake is made to transmit load force into deep soil, to reduce cement
The bearing load of soil between broken stone pile, effectively prevents composite foundation and deforms, further, since being not required to bury in cement stabilized macadam stake
If reinforcing bar greatly reduces project cost, construction technology is simplified, saves construction cost.
Description of the drawings
Fig. 1 is construction flow chart of the present invention;
Fig. 2 is the schematic diagram that the present invention arranges guide rod on stake position;
Fig. 3 is antiseepage composite foundation cross section structure schematic diagram of the present invention;
Fig. 4 is stake position of the present invention interior arrangement schematic diagram on construction ground.
In figure:1- positions, 2- guide rods, 3- mattress layers, 4- cement stabilized macadam stakes.
Specific implementation mode
Be described further below technical scheme of the present invention, but claimed range be not limited to it is described.
As shown in Figure 1, the present invention provide it is a kind of on dolomite stratigraph build antiseepage composite foundation construction method, including with
Lower step:
Step 1:Smooth location:The closed region in somewhere is selected on the ground as construction site, is removed in construction site
All vegetation keep construction site smooth using road roller roller compaction construction place;Further, in the construction process, it also to reserve
Drainage grade carries out the measures such as gutter, road roller is used in combination to roll original ground, to meet long-spiral drilling machine dead weight and antidumping
Requirement.
Step 2:Draw fixed pile:Required according to construction drawing, in the smooth good construction site described in step 1, with
Several positions delimited at construction drawing opposite position, and each position is sequentially numbered and is marked;The stake position exists
It is in quincuncial arrangement in construction site, two stake position centre-to-centre spacing of arbitrary neighborhood are less than 2m.Further, the step of described stroke of fixed pile
Rapid further includes using each position center as rotation center, and circumference array mode is pressed equably in adjacent position around each position
Erect 4 guide rods of arrangement.The guide rod is made using timber.As shown in Figure 2, Figure 4 shows, 4 guide rods form 4 crosses and hand over
Qualifying point is pitched, stake position is checked to examine at any time, using guide rod made of timber as label, is buried convenient for stake position
It is easy-to-look-up afterwards.
Step 3:Laying construction platform:It is laid with an operation platform on construction ground, keeps personnel, equipment and tool logical
It crosses the operation platform and is movable to any one position;The operation platform be by be layed in successively on ground dry clay layer,
Dolomite metalling is formed after road roller is compacted.The dry clay layer thickness is 50cm.The dolomite fractured-rock layer thickness is
100cm to 150cm.Since ground present position underground water is relatively more, drilling machine cannot be introduced into, and be applied therefore, it is necessary to be provided for drilling machine
Work platform, the levelling compacting of operation platform are the key that ensure drilling machine verticality.
Step 4:Creep into stake holes:Along operation platform will on drilling-machine shifter to one of stake position, adjust drilling machine tower body and
Drill bit makes drill bit of drilling machine earthward creep into after keeping it perpendicular with ground at stake position, obtains the stake holes that depth is H;Further
Ground, the drilling machine are KLB-26, KLB-23 hydraulic walking long-spiral drilling machine.Earthward rate of penetration is the drill bit of drilling machine
1m/min to 1.5m/min.In addition, drilling rod perpendicular alignmnet stake position center should be made before applying brill, it is ensured that pile verticality allowable deviation is not
More than 1%, stake position allowable deviation is not more than 5cm.It has to check for whether drill bit valve is closed before spudding in, opening is forbidden to creep into, bore
Head diameter control is in 600mm between 620mm, and when lower mobile drilling rod touches ground to drill bit, starter motor is crept into, running speed
Slow, rate of penetration is 1.0~1.5m/min or is determined according to test pile, can reduce drilling rod in this way and rock and bore
The deviation in hole, to correct in time.First slow rear fast principle is followed when such as finding that drilling rod rocks or hardly possible is bored, to answer in pore forming process
Slow down drilling depth, otherwise relatively easily lead to stake holes deflection, displacement, or even makes drilling rod, drilling tool damage.Drill bit reaches designing pile length and calibrates in advance
Gao Shi makees eye-catching label at the corresponding drilling machine tower body in power head bottom surface stop place, control stake long foundation when as construction.
In pore forming process, drilling rod generally must not be inverted and be promoted, drilling rod should be promoted to ground if you need to promote drilling rod or reversion, to apex point
Opening door must clean, debugs, seal again.When having a common boundary into soft or hard layer, it should ensure that drilling rod is vertical, slowly enter, containing brick
When block, miscellaneous fill layer or the larger soft plasticity soil layer drilling of water content, drilling rod shaking should be reduced to the greatest extent, in order to avoid varying aperture is different
Often, curent change state is paid attention to when drilling, when current value surmounts operating instruction, should promote casting in time, until curent change is
The earthwork around drilling rod when being drilled into designed elevation, should should be removed clean, drilling process by normal condition, the soil drilled out with boring with clear
In should drilling rod verticality check at any time, it is ensured that drilling rod is vertical, and performs record.
Step 5:Promote drill bit:Drill bit is proposed with constant promotion speed in the stake holes described in step 4, meanwhile,
During drill bit is promoted, to concrete perfusion between the drill bit outer surface and the stake holes inner wall, drill bit is proposed completely
Afterwards, after concrete setting, cement stabilized macadam stake is obtained in the stake holes;Further, the cement stabilized macadam stake outer diameter is not small
In 600mm.The cement stabilized macadam pile length is not less than 11 meters.It is 2.5m/min that the drill bit, which promotes speed,.The concrete is
Using cement, sand, rubble, water and additive according to 270:780:1170:180:1.7 quality proportioning is mixed and stirred.Concrete
It should be formed through mix mixing in strict accordance with the quality mixture ratio, the parameter that the slump, duration of mixing should be determined by test process
It is controlled, and must not be less than 1 minute;The concrete of stirring must assure that concrete cylindrical physical efficiency passes through rigid pipe, height
Strong flexible pipe, bend pipe and reducer pipe and reach in drilling rod core pipe.
In addition, further, discharge port is opened after pore-forming to projected depth, it is 180 to be then pressed into the slump prepared
~220mm concrete, then carries brill in Ya Guan.Guncreting carry drilling speed degree by stake diameter, ash-transmission system length of pipeline,
Once defeated ash quantity pouring into height, for the determination of the factors such as grey speed in hole for internal diameter size, separate unit blender.Pressure is filled and is carried with drilling rod
Rise cooperation quality whether, seriously affect the quality of stake, if drilling rod promoted evening valve will be caused to be difficult to open, cause to be pumped it is excessive,
Sebific duct is suppressed brokenly, if drilling rod is promoted soon, will make to generate negative pressure in hole, quicksand pours in the bearing capacity for generating sediment and weakening stake, therefore
It is required that pressure is filled wants just right with the cooperation promoted.The general speed that promoted is that 2m/min or live test piles determine.
Pressure must be carried out continuously when filling, and have certain coagulation unit weight of soil, coagulation unit weight of soil to be higher by feed inlet in pump bucket
40cm or more should notify drilling machine to stop being promoted by whistle immediately to prevent inspiration air when pumping hole concrete is less than feed inlet
Drilling rod carries out pressure filling again when concrete is stirred.During pressing filling, 1~2m sections of bottom hole carries drilling speed degree and slows down, and stage casing can be fast
A bit, top 3m slows down.Until reaching designed elevation, and stops pressure beyond designed elevation 1.0m and fill.Pressure calculates concrete before filling and uses
It measures, is checked after pile and be not less than 1.0 per fullness coefficient.
Step 6:By operation platform by drilling-machine shifter to next position, step 4 is repeated to step 5, successively every
Cement stabilized macadam stake is obtained on a position;Drilling sequences can be carried out according to the sequence of stake bit number before, can also be used laterally from
Wire center is promoted to both sides sequential lateral, longitudinal to be longitudinally propelling from works or separation along line direction.In weak soil, it is
It prevents adjacent stake to be squeezed broken or necking down, land upheaval is easily caused in cohesive soil, by field test, pile driving construction is jumped using interval and beaten
Method, but new pile of constructing is no less than 7 days with time interval of having driven piles.
Step 7:Form pile crown:After all cement stabilized macadam stakes are made 14 days, dug using engineering machinery broken according to all cement
Soil between stone mar, Demolition Construction platform make all cement stabilized macadam stakes be partially exposed to ground pile crown formed above;
Step 8:Modify pile crown:All pile crowns are cleared up and modified using electric pick or concrete cutting machine, remove institute
There is the soil and impurity adhered on pile crown, keeps all pile crowns identical relative to ground level;Further place, modifies the step of pile crown
Rapid further includes the soil cleared up using backhoe CAT excavators between the pile crown.When modifying pile crown, 0.1m3 small size backs are preferably used
It shovels CAT excavators and clears up cement stabilized macadam inter-pile soil earth, cement stabilized macadam inter-pile soil earth and broken pile crown concrete residue are cleaned out
Construction site region reduces the disturbance to cement stabilized macadam stake to the greatest extent, uses 1m3 large size backhoe CAT excavators cooperation 20t again later certainly
Automobile is unloaded to transport cement stabilized macadam inter-pile soil earth to specified cinder field.
Step 7:It is laid with mattress layer:As shown in figure 3, being laid with mattress layer between the pile crown, in compacting mattress layer, make
Mattress layer connect to form antiseepage composite foundation with the cement stabilized macadam.The mattress layer is less than the sand gravel of 3cm by maximum particle size
Composition.The mattress layer thickness is 30cm.
Concrete-pile construction technology is applied in construction of hydropower plant by technical solution using the present invention, and the present invention applies
The antiseepage composite foundation that work method is built may be not only suitable for Dam, could be applicable to the flood discharge on power station periphery
The foundation constructions operation such as lock, workshop, clipping room, by arranging more cement stabilized macadam stakes on soft, fragmentary dolomite stratigraph, then
By being laid with mattress layer between stake, makes cement stabilized macadam stake be combined as a whole to form composite construction ground with mattress layer, greatly enhance
The structural strength and bearing capacity of ground, no matter load action then soil in cement stabilized macadam stake or between cement stabilized macadam stake
On, it can ensure that cement stabilized macadam stake, mattress layer participate in work always in composite foundation, due to the intensity of cement stabilized macadam stake pile body
Larger with elasticity modulus, under the action of load, cement stabilized macadam stake top stress is answered compared to cement stabilized macadam inter-pile soil earth surface
Power is big, and cement stabilized macadam stake is made to transmit load force into deep soil, to which the carrying for reducing cement stabilized macadam inter-pile soil earth is negative
Lotus effectively prevents composite foundation and deforms, further, since being not required to embedded reinforcing bar in cement stabilized macadam stake, greatly reduces work
Journey cost, simplifies construction technology, saves construction cost.
Claims (8)
1. a kind of construction method for building antiseepage composite foundation on dolomite stratigraph, it is characterised in that:Include the following steps:
Step 1:Smooth location:The closed region in somewhere is selected on the ground as construction site, removes in construction site and owns
Vegetation keeps construction site smooth using road roller roller compaction construction place;
Step 2:Draw fixed pile:Required according to construction drawing, in the smooth good construction site described in step 1, with construction
Several positions delimited at drawing opposite position, and each position is sequentially numbered and is marked;
Step 3:Laying construction platform:It is laid with an operation platform on construction ground, personnel, equipment and tool is made to pass through this
Operation platform is movable to any one position;
Step 4:Creep into stake holes:Along operation platform by drilling-machine shifter to one of stake position, drilling machine tower body and brill are adjusted
Head makes drill bit of drilling machine earthward creep into after keeping it perpendicular with ground at stake position, obtains the stake holes that depth is H;
Step 5:Promote drill bit:Drill bit is proposed with constant promotion speed in the stake holes described in step 4, meanwhile, in drill bit
During promotion, waited for after proposing drill bit completely to concrete perfusion between the drill bit outer surface and the stake holes inner wall
After concrete setting, cement stabilized macadam stake is obtained in the stake holes;
Step 6:By operation platform by drilling-machine shifter to next position, step 4 is repeated to step 5, successively in each stake
Cement stabilized macadam stake is obtained on position;
Step 7:Form pile crown:After all cement stabilized macadam stakes are made 14 days, dug according to all cement stabilized macadam stakes using engineering machinery
Between soil, Demolition Construction platform makes all cement stabilized macadam stakes be partially exposed to ground pile crown formed above;
Step 8:Modify pile crown:All pile crowns are cleared up and modified using electric pick or concrete cutting machine, remove all piles
The soil and impurity adhered on head, keeps all pile crowns identical relative to ground level;
Step 7:It is laid with mattress layer:It is laid with mattress layer between the pile crown, in compacting mattress layer, makes mattress layer and the water
Mud rubble connects to form antiseepage composite foundation.
2. the construction method of antiseepage composite foundation is built on dolomite stratigraph as described in claim 1, it is characterised in that:It is described
Cement stabilized macadam stake outer diameter is not less than 600mm.
3. the construction method of antiseepage composite foundation is built on dolomite stratigraph as described in claim 1, it is characterised in that:It is described
It is in quincuncial arrangement that stake position is interior on construction ground, and two stake position centre-to-centre spacing of arbitrary neighborhood are less than 2m.
4. the construction method of antiseepage composite foundation is built on dolomite stratigraph as described in claim 1, it is characterised in that:Step
Earthward rate of penetration is 1m/min to 1.5m/min to drill bit of drilling machine described in four.
5. the construction method of antiseepage composite foundation is built on dolomite stratigraph as described in claim 1, it is characterised in that:Step
It is 2.5m/min that drill bit described in five, which promotes speed,.
6. the construction method of antiseepage composite foundation is built on dolomite stratigraph as described in claim 1, it is characterised in that:Step
Concrete described in five is using cement, sand, rubble, water and additive according to 270:780:1170:180:1.7 quality proportioning
It mixes and stirs.
7. the construction method of antiseepage composite foundation is built on dolomite stratigraph as claimed in claim 3, it is characterised in that:It is described
Operation platform is formed after road roller is compacted by dry clay layer, the dolomite metalling being layed in successively on ground.
8. the construction method of antiseepage composite foundation is built on dolomite stratigraph as claimed in claim 8, it is characterised in that:It is described
Sand gravel of the mattress layer by maximum particle size less than 3cm forms.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810344159.3A CN108570979A (en) | 2018-04-17 | 2018-04-17 | A kind of construction method for building antiseepage composite foundation on dolomite stratigraph |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810344159.3A CN108570979A (en) | 2018-04-17 | 2018-04-17 | A kind of construction method for building antiseepage composite foundation on dolomite stratigraph |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108570979A true CN108570979A (en) | 2018-09-25 |
Family
ID=63574935
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810344159.3A Pending CN108570979A (en) | 2018-04-17 | 2018-04-17 | A kind of construction method for building antiseepage composite foundation on dolomite stratigraph |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108570979A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112982427A (en) * | 2021-03-22 | 2021-06-18 | 云南建投第一勘察设计有限公司 | Reinforcement construction method for foundation pit dangerous case in soft soil area |
CN115463944A (en) * | 2022-08-16 | 2022-12-13 | 北京建材地质工程有限公司 | Protective pile head processing method and device, terminal equipment and medium |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1761876A1 (en) * | 1989-07-26 | 1992-09-15 | Среднеазиатский Филиал Научно-Исследовательского, Проектно-Изыскательского, Конструкторско-Технологического Института Оснований И Подземных Сооружений Им.Н.М.Герсеванова | Earthquake-proof foundation of building |
CN101818493A (en) * | 2010-03-23 | 2010-09-01 | 南通宏华建筑安装有限公司 | Construction method of compound ground base |
CN103276716A (en) * | 2013-05-23 | 2013-09-04 | 汇通路桥建设集团有限公司 | Method for stabilization and construction of transition section CFG and mattress cushion layer composite foundation |
CN107740434A (en) * | 2017-10-23 | 2018-02-27 | 中国水利水电第九工程局有限公司 | It is a kind of to be used for sandy gravel, the construction method of dolomite crushed zone dam foundation ditch water protecting curtain |
-
2018
- 2018-04-17 CN CN201810344159.3A patent/CN108570979A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1761876A1 (en) * | 1989-07-26 | 1992-09-15 | Среднеазиатский Филиал Научно-Исследовательского, Проектно-Изыскательского, Конструкторско-Технологического Института Оснований И Подземных Сооружений Им.Н.М.Герсеванова | Earthquake-proof foundation of building |
CN101818493A (en) * | 2010-03-23 | 2010-09-01 | 南通宏华建筑安装有限公司 | Construction method of compound ground base |
CN103276716A (en) * | 2013-05-23 | 2013-09-04 | 汇通路桥建设集团有限公司 | Method for stabilization and construction of transition section CFG and mattress cushion layer composite foundation |
CN107740434A (en) * | 2017-10-23 | 2018-02-27 | 中国水利水电第九工程局有限公司 | It is a kind of to be used for sandy gravel, the construction method of dolomite crushed zone dam foundation ditch water protecting curtain |
Non-Patent Citations (3)
Title |
---|
肖金媛、魏瞿霖: "《建筑施工技术》", 28 February 2010, 北京理工大学出版社 * |
马永峰 等: "岩溶地区CFG桩复合地基现场试验研究", 《人民长江》 * |
高恩策、李晶晶: "高速公路水泥粉煤灰碎石桩应用关键技术研究", 《内江科技》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112982427A (en) * | 2021-03-22 | 2021-06-18 | 云南建投第一勘察设计有限公司 | Reinforcement construction method for foundation pit dangerous case in soft soil area |
CN115463944A (en) * | 2022-08-16 | 2022-12-13 | 北京建材地质工程有限公司 | Protective pile head processing method and device, terminal equipment and medium |
CN115463944B (en) * | 2022-08-16 | 2024-04-02 | 北京建材地质工程有限公司 | Protection pile head processing method, device, terminal equipment and medium |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106759473B (en) | The constructing structure and its construction method of underground pipe gallery and road | |
CN107503257B (en) | One kind being close to mountain high-filled subgrade stabilization and Deformation control structure and construction method | |
CN105672348A (en) | Construction method for cropping bridge pile foundation at sandy gravel stratum of abyssal region | |
CN103981876B (en) | For deep soft foundation river course be close to combined member and the construction method that river embankment is built together | |
CN110344400A (en) | The hard rock pore-forming construction technology of churning driven opportunity | |
Bell | Methods of treatment of unstable ground | |
CN207109475U (en) | It is close to mountain high-filled subgrade stabilization and Deformation control structure | |
CN104963346A (en) | Support construction method for deep foundation pit in complex geological condition | |
CN110219359A (en) | A kind of Submersed type inspection well and its construction method | |
CN103074882A (en) | Construction method for reinforcing island-type perennial frozen-soil foundation by adopting gravel piles | |
CN109281330A (en) | A kind of osmotic control method | |
CN108571000A (en) | The construction method of underground water cutting when wearing existing railway under a kind of road of location along the river | |
Abdrabbo et al. | Challenges and uncertainties relating to open caissons | |
CN106812149A (en) | A kind of construction method of pile foundation | |
CN107740434A (en) | It is a kind of to be used for sandy gravel, the construction method of dolomite crushed zone dam foundation ditch water protecting curtain | |
CN104329020A (en) | Reinforced long-screw rock-socketed construction equipment and process thereof | |
CN105714748A (en) | Excavating construction method for surge shaft in gravel and sandy soil layer | |
CN204252164U (en) | A kind of Submersed type active well | |
CN108570979A (en) | A kind of construction method for building antiseepage composite foundation on dolomite stratigraph | |
CN207032212U (en) | A kind of stabilization by drainage structure of new and old roadbed in the firm splicing of watersplash | |
Raju | Ground improvement-applications and quality control | |
CN102425179B (en) | Reinforced soil infiltration ditch structure supported by miniature steel pipe cast-in-place pile | |
CN106049467A (en) | Method for treating slurry leakage of bored pile through percussion drill under complex geology | |
CN208266895U (en) | Cofferdam is built in returning for seabed tunnel point storehouse construction | |
CN111042144A (en) | Excavation method for foundation pit of underground beam under condition of continuous flow of riverway in cold region |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180925 |
|
RJ01 | Rejection of invention patent application after publication |