CN101818493A - Construction method of compound ground base - Google Patents

Construction method of compound ground base Download PDF

Info

Publication number
CN101818493A
CN101818493A CN 201010135858 CN201010135858A CN101818493A CN 101818493 A CN101818493 A CN 101818493A CN 201010135858 CN201010135858 CN 201010135858 CN 201010135858 A CN201010135858 A CN 201010135858A CN 101818493 A CN101818493 A CN 101818493A
Authority
CN
China
Prior art keywords
stake
weight portions
pile
cfg
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201010135858
Other languages
Chinese (zh)
Inventor
沈宝林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANTONG HONGHUA CONSTRUCTION INSTALLATION CO Ltd
Original Assignee
NANTONG HONGHUA CONSTRUCTION INSTALLATION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANTONG HONGHUA CONSTRUCTION INSTALLATION CO Ltd filed Critical NANTONG HONGHUA CONSTRUCTION INSTALLATION CO Ltd
Priority to CN 201010135858 priority Critical patent/CN101818493A/en
Publication of CN101818493A publication Critical patent/CN101818493A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a construction method of a compound ground base, comprising the following steps of enabling a drilling machine to be in position; drilling a hole to the designed elevation; pre-stirring a mixed material; lifting a pipe and simultaneously pumping the mixed material to the designed elevation; protecting pile length, clearing soil, cutting off piles, paving a cushion layer and the like. The construction method has the advantages of high construction efficiency, low noise, strong pore-forming penetration capability, easy control of quality, lower construction cost and the like, and can be widely applied to processing ground bases of high-rise buildings.

Description

The job practices of composite foundation
Technical field:
The present invention relates to a kind of job practices of ground.
Background technology:
Existing foundation construction method is a lot, but all has different defectives, and construction is complicated, the cost height, and quality is wayward.
Summary of the invention:
The object of the present invention is to provide the high and low noise of a kind of efficiency of construction, the quality job practices of the composite foundation of control easily.
Technical solution of the present invention is:
A kind of job practices of composite foundation is characterized in that: comprise the following steps:
(1) rig is in place, holes to design elevation;
(2) mix material in advance: CFG pile material and match ratio:
CFG stake pile strength grade C15 adopts 42.5 Portland cements, sand, particle diameter 5~10mm rubble, II level flyash and pumping admixture, the compound slump 18~20cm; Concrete stirs and requires every biscuit mixing time to be no less than 60S, and the compound slump is controlled at 18~20cm; CFG stake Mixture Ratio is: cement 300 weight portions, sand 195 weight portions, sand 714 weight portions, rubble 1149 weight portions, flyash 50 weight portions, pumping admixture 11 weight portions, water 195 weight portions;
(3) carry pipe simultaneous pumping compound to design elevation, with concrete pump and long-spiral drilling machine matching operation, rig promotion speed is controlled at 2~3m/min when construction, in long-spiral drilling machine unit head elbow outlet valve is set, and guarantees that the air in the drilling rod can be discharged;
(4) the protection stake is long: construction back stake top mark height exceeds the high 500mm of design stake top mark, and push up with grave on top;
(5) clear soil and section stake:
The CFG pile driving construction adopts machinery to cut the earth after 7 days and indwelling is no less than the thick soil body of 700mm, adopts the hand excavation; Reject one by one to design elevation along the circumferential stake of a stake heart with drill rod when rejecting pile crown, after pile crown was handled, inter-pile soil and pile crown were at same absolute altitude;
(6) mattress layer is laid
Mattress layer is laid on and carries out after the pile crown processing finishes, and the mattress layer material uses 5~10mm rubble, and the static(al) compacting is adopted in back, empty shop, rams degree of filling out and is not more than 0.9.
Advantages such as the present invention has the high and low noise of efficiency of construction, the pore-forming penetration capacity is strong, quality is controlled easily, cost is lower can be widely used in the Ground Treatment of High-rise Buildings.Composite foundation of the present invention can be good at solving the highrise building Question of Ground Bearing Capacity.Ground is handled the back characteristic load bearing capacity and is improved 2~3 times; Pile composite foundation of the present invention has made full use of the bearing capacity of inter-pile soil, compares with adopting pile foundation, and its cost and duration only are about 1/3 of pile foundation, and overall economic efficiency is obvious; Adopt its efficiency of construction height of pump pressure CFG pile constructing process in the long spiral pore-forming, pore-forming penetration capacity strong.
The invention will be further described below in conjunction with embodiment.
The specific embodiment:
A kind of job practices of composite foundation comprises the following steps:
(1) rig is in place, holes to design elevation;
(2) mix material in advance: CFG pile material and match ratio:
CFG stake pile strength grade C15 adopts 42.5 Portland cements, sand, particle diameter 5~10mm rubble, II level flyash and pumping admixture, the compound slump 18~20cm; Concrete stirs and requires every biscuit mixing time to be no less than 60S, and the compound slump is controlled at 18~20cm; CFG stake Mixture Ratio is: cement 300 weight portions, sand 195 weight portions, sand 714 weight portions, rubble 1149 weight portions, flyash 50 weight portions, conventional commercially available pumping admixture 11 weight portions, water 195 weight portions;
(3) carry pipe simultaneous pumping compound to design elevation, with concrete pump and long-spiral drilling machine matching operation, rig promotion speed is controlled at 2~3m/min when construction, in long-spiral drilling machine unit head elbow outlet valve is set, and guarantees that the air in the drilling rod can be discharged;
(4) the protection stake is long: construction back stake top mark height exceeds the high 500mm of design stake top mark, and push up with grave on top;
(5) clear soil and section stake:
The CFG pile driving construction adopts machinery to cut the earth after 7 days and indwelling is no less than the thick soil body of 700mm, adopts the hand excavation; Reject one by one to design elevation along the circumferential stake of a stake heart with drill rod when rejecting pile crown, after pile crown was handled, inter-pile soil and pile crown were at same absolute altitude;
(6) mattress layer is laid
Mattress layer is laid on and carries out after the pile crown processing finishes, and the mattress layer material uses 5~10mm rubble, and the static(al) compacting is adopted in back, empty shop, rams degree of filling out and is not more than 0.9.

Claims (1)

1. the job practices of a composite foundation is characterized in that: comprise the following steps:
(1) rig is in place, holes to design elevation;
(2) mix material in advance: CFG pile material and match ratio:
CFG stake pile strength grade C15 adopts 42.5 Portland cements, sand, particle diameter 5~10mm rubble, II level flyash and pumping admixture, the compound slump 18~20cm; Concrete stirs and requires every biscuit mixing time to be no less than 60S, and the compound slump is controlled at 18~20cm; CFG stake Mixture Ratio is: cement 300 weight portions, sand 195 weight portions, sand 714 weight portions, rubble 1149 weight portions, flyash 50 weight portions, pumping admixture 11 weight portions, water 195 weight portions;
(3) carry pipe simultaneous pumping compound to design elevation, with concrete pump and long-spiral drilling machine matching operation, rig promotion speed is controlled at 2~3m/min when construction, in long-spiral drilling machine unit head elbow outlet valve is set, and guarantees that the air in the drilling rod can be discharged;
(4) the protection stake is long: construction back stake top mark height exceeds the high 500mm of design stake top mark, and push up with grave on top;
(5) clear soil and section stake:
The CFG pile driving construction adopts machinery to cut the earth after 7 days and indwelling is no less than the thick soil body of 700mm, adopts the hand excavation; Reject one by one to design elevation along the circumferential stake of a stake heart with drill rod when rejecting pile crown, after pile crown was handled, inter-pile soil and pile crown were at same absolute altitude;
(6) mattress layer is laid
Mattress layer is laid on and carries out after the pile crown processing finishes, and the mattress layer material uses 5~10mm rubble, and the static(al) compacting is adopted in back, empty shop, rams degree of filling out and is not more than 0.9.
CN 201010135858 2010-03-23 2010-03-23 Construction method of compound ground base Pending CN101818493A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010135858 CN101818493A (en) 2010-03-23 2010-03-23 Construction method of compound ground base

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010135858 CN101818493A (en) 2010-03-23 2010-03-23 Construction method of compound ground base

Publications (1)

Publication Number Publication Date
CN101818493A true CN101818493A (en) 2010-09-01

Family

ID=42653750

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010135858 Pending CN101818493A (en) 2010-03-23 2010-03-23 Construction method of compound ground base

Country Status (1)

Country Link
CN (1) CN101818493A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102617080A (en) * 2012-04-01 2012-08-01 中铁二院工程集团有限责任公司 Pozzolan, cement and gravel pile for reinforcing soft foundation
CN102677661A (en) * 2012-05-07 2012-09-19 中铁上海工程局有限公司 Reinforcement method for foundation of silt soft-based cast-in-place box girder support
CN102912808A (en) * 2012-11-06 2013-02-06 山东兴华建设集团有限公司 Spiral CFG pile and cement stirring pile combined composite foundation construction method
CN102966097A (en) * 2012-11-30 2013-03-13 华侨大学 Novel composite foundation with vertical bearing piles
WO2017185817A1 (en) * 2016-04-27 2017-11-02 王继忠 Construction method for on-site mixing cement-soil pile overground
CN108570979A (en) * 2018-04-17 2018-09-25 中国水利水电第九工程局有限公司 A kind of construction method for building antiseepage composite foundation on dolomite stratigraph
CN109537616A (en) * 2018-11-26 2019-03-29 广西万科企业管理有限公司 A kind of the CFG stake device and its construction method of spiral-digging pore

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1370893A (en) * 2002-04-04 2002-09-25 中国建筑科学研究院 Pile end mortar pre-pressing construction method and apparatus for long screw auger drilling deposited pile and CFG pile
CN1542234A (en) * 2003-11-07 2004-11-03 东南大学 Pile forming technology for nail-shaped pile
CN1641112A (en) * 2004-12-28 2005-07-20 王继忠 Composite foundation construction method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1370893A (en) * 2002-04-04 2002-09-25 中国建筑科学研究院 Pile end mortar pre-pressing construction method and apparatus for long screw auger drilling deposited pile and CFG pile
CN1542234A (en) * 2003-11-07 2004-11-03 东南大学 Pile forming technology for nail-shaped pile
CN1641112A (en) * 2004-12-28 2005-07-20 王继忠 Composite foundation construction method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
《吉林地质》 20090615 王宪忠等 浅谈长螺旋钻管内泵压CFG桩施工工艺 79-82 1 第28卷, 第2期 *
《建材与装饰》 20080711 韦盛胡 对长螺旋钻管内泵压CFG桩在复杂地基处理施工探讨 77-78 1 , *
《石家庄铁路职业技术学院学报》 20100315 田达 临近既有线施工路基CFG桩工艺研究 29-32 1 第9卷, 第1期 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102617080A (en) * 2012-04-01 2012-08-01 中铁二院工程集团有限责任公司 Pozzolan, cement and gravel pile for reinforcing soft foundation
CN102677661A (en) * 2012-05-07 2012-09-19 中铁上海工程局有限公司 Reinforcement method for foundation of silt soft-based cast-in-place box girder support
CN102912808A (en) * 2012-11-06 2013-02-06 山东兴华建设集团有限公司 Spiral CFG pile and cement stirring pile combined composite foundation construction method
CN102966097A (en) * 2012-11-30 2013-03-13 华侨大学 Novel composite foundation with vertical bearing piles
WO2017185817A1 (en) * 2016-04-27 2017-11-02 王继忠 Construction method for on-site mixing cement-soil pile overground
CN108570979A (en) * 2018-04-17 2018-09-25 中国水利水电第九工程局有限公司 A kind of construction method for building antiseepage composite foundation on dolomite stratigraph
CN109537616A (en) * 2018-11-26 2019-03-29 广西万科企业管理有限公司 A kind of the CFG stake device and its construction method of spiral-digging pore

Similar Documents

Publication Publication Date Title
CN101818493A (en) Construction method of compound ground base
CN101429766B (en) Ground strengthened high pressure rotary spraying pile construction technique
CN108517877B (en) Supporting construction method combining consolidation grouting of hybrid filling ultra-deep foundation pit with double-row steel pipe piles
CN100501011C (en) Hole drilling mudjack pile construction method
CN106368214B (en) A kind of casing formula cement mixing method at pile operation method
CN104929114A (en) High pressure jet grouting pile waterproof curtain construction device and method
CN102011399B (en) PHC pile-based multiple high jet pedestal pile construction method
CN103233473B (en) Many ribs of high polymer stake grouting method
CN1487150A (en) Combined grouting construction process of reinforcing foundation
CN106996105A (en) Down-the-hole impacts jet mixing pile constructing process and equipment
CN107653889B (en) Construction method of section steel pressure-grouting cement soil curtain support pile
CN105155550A (en) Construction method for digging deep foundation pit in large-thickness highly weathered sandstone stratum in combined supporting mode
CN101775814A (en) Anti-slip cement soil pile soil blocking structure and construction method thereof
JP2015183364A (en) Method for preventing soil structure from sliding at slope surface layer with geocell fixing operation auxiliary means
CN106320331A (en) Construction method for penetrating block stone layer of pore-forming system of high-pressure jet grouting pile
CN106284295A (en) Multichannel high-pressure vibro-grouting jet groutinl construction method
CN107587502B (en) Construction method for rotary drilling hole-forming pressure-grouting cement soil occlusion curtain pile
CN102979091B (en) Method for constructing cement jet grouting pile with fine aggregate concrete core
CN108149682A (en) A kind of slip casting casing device and the pile foundation drilling construction method using the casing device
CN207862925U (en) A kind of slip casting casing device
CN116427396A (en) Stirring pile construction method and composite pile construction method thereof
CN207260138U (en) Drill rod of high-pressure jet grouting stirring bearing pile and device with drill rod
CN101649614A (en) Variable-diameter multi-direction anchor pile
CN107447754A (en) The new plant stake technique of prefabricated tubular pile and the pile body formed
CN104005416A (en) Method for processing major-diameter hole pile collapsed holes under high and steep slope plain fill back-pressing condition

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20100901