CN109235903A - Steel structure modularization construction method - Google Patents

Steel structure modularization construction method Download PDF

Info

Publication number
CN109235903A
CN109235903A CN201811217605.0A CN201811217605A CN109235903A CN 109235903 A CN109235903 A CN 109235903A CN 201811217605 A CN201811217605 A CN 201811217605A CN 109235903 A CN109235903 A CN 109235903A
Authority
CN
China
Prior art keywords
component
modularization
installation
construction method
steel structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811217605.0A
Other languages
Chinese (zh)
Inventor
尹彭霞
陈彦
汪晓波
任红臣
崔相超
王磊
张莹
张涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Chemical Engineering Sixth Construction Co Ltd
Original Assignee
China National Chemical Engineering Sixth Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Chemical Engineering Sixth Construction Co Ltd filed Critical China National Chemical Engineering Sixth Construction Co Ltd
Priority to CN201811217605.0A priority Critical patent/CN109235903A/en
Publication of CN109235903A publication Critical patent/CN109235903A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of steel structure modularization construction methods.1) construction method is the following steps are included: handle basis, and foundation bolt is buried and is positioned at basis and carries out first time measurement, concreting is carried out after meeting installation requirement, pour it is firm after carry out second of measurement again, meet and parallels be installed on the foundation bolt after installation requirement;2) base plate is installed on the foundation bolt by the parallels;3) it takes using module centers line as component position baseline, component assembly is become into modularization installation unit;4) temporary support structure is arranged on lifting device, modularization installation unit lifting is installed on by the base plate using lifting device, and be fixedly mounted after verticality and levelness leveling and adjusting;5) the modularization installation unit arrange and be welded and fixed, complete structural module construction.Work efficiency is high for the construction method, installation accuracy is good and construction cost is low.

Description

Steel structure modularization construction method
Technical field
The present invention relates to Installation Technique of Steel Structure fields.It is more particularly related to which steel structure modularization is applied Work method.
Background technique
In recent years, with the development of social economy and productivity, steel building few, overall cost with its occupied area Low, many advantages, such as speed of application is fast, quality easily guarantees, is environmentally protective, is rapidly developed, and is widely used in workshop, large size is built It builds.Traditional Construction of Steel Structure method is: first in processing factory by steel column, girder used in steel construction, various beams of platform etc. Component completion of processing waits and all components is transported to erecting bed after civil constructions, and carries out structure one by one using lifting device Part group is to installation.But traditional Construction of Steel Structure method has following deficiency: 1. amount of high-altitude operation are big, and time-consuming for work progress, Working efficiency is low and safety cost is high;2. high altitude operation difficulty is high, frame structure and installation accuracy are not easy to control, installation accuracy Difference;3. the equipments usage amount such as Large-scale Hoisting tool is big, construction cost is high.Therefore, traditional Construction of Steel Structure method is not suitable for The frame installation of super large, superelevation formed steel construction.
Summary of the invention
The object of the present invention is to provide a kind of steel structure modularizations that work efficiency is high, installation accuracy is good and construction cost is low Construction method.
In order to realize these purposes and other advantages according to the present invention, a kind of steel structure modularization construction party is provided Method, comprising the following steps:
1) basis is handled, and foundation bolt is buried and is positioned at basis and carries out first time measurement, meet installation Concreting is carried out after it is required that, pour it is firm after carry out second of measurement again, meet and parallels be installed on institute after installation requirement State foundation bolt;
2) base plate is installed on the foundation bolt by the parallels;
3) it takes using module centers line as component position baseline, component assembly is become into modularization installation unit, In, the reinforcement member in the modularization installation unit is spliced by high-strength bolt and rotary table shearing-resistant member, the modularization installation Left and right component in unit is connected by steel member;
4) temporary support structure is arranged on lifting device, the modularization installation unit is lifted using lifting device and is pacified It is fixedly mounted loaded on the base plate, and after verticality and levelness leveling and adjusting;
5) the modularization installation unit arrange and be welded and fixed, complete structural module construction.
The step 3) specifically includes following process in one of the embodiments: making assembled moulding bed;Component inspection; Using module centers line as component position baseline, component assembly is become into modularization installation unit, wherein reinforcement member passes through High-strength bolt and rotary table shearing-resistant member splice, and the left and right component in the modularization installation unit is connected by steel member;Contraposition connects Dimensional gaughing, welding, reinforcing at mouthful.
The assembled moulding bed in the step 3) is by perpendicular to the component and being horizontally arranged in one of the embodiments, It is made in the H profile steel on ground.
It further include using with virtual route planning technology to described in one of the embodiments, in the step 3) The step of installation path of component is planned.
Described use is advised with installation path of the virtual route planning technology to component in one of the embodiments, The step of drawing specifically includes: determining the initial moving direction of the component;By comparing the initial moving direction of the component and described Modularization installation unit obtains component translational movement in the projection split on direction vector;It repeats the above process, until the component Reach designated position, then the component paths traversed is the installation path of component.
The step 4) in one of the embodiments, further include: Force Calculation is carried out to wirerope;It selects and check is hung Holding tool;Select and check lifting handling machinery;Lifting device is installed in place.
Lifting device described in the step 4) is lifted using 4 lift-on/lift-off systems in one of the embodiments,.
CO is used in the step 5) in one of the embodiments,2Gas shielded arc welding is welded and fixed.
Further include the steps that mounting platform, ladder and pull rod in the step 5) in one of the embodiments,.
The temporary support structure is support fashioned iron in one of the embodiments,.
The present invention is include at least the following beneficial effects:
A large amount of high-altitude vertical space operation is changed into ground or low latitude operation by construction method disclosed by the invention, is improved Construction safety assurance coefficient, and the degree-of-difficulty factor of construction is reduced, and then effectively reduce construction cost;And multiple constructions Face can construct simultaneously, and operation side increases, and effectively shorten the duration, it is easy for installation effectively, and then improve construction effect Rate.In addition, the construction method is used using module centers line as component position baseline, component assembly is installed as modularization Unit will build error diffusion on a direction, and the matching performance of all directions is more preferable.Meanwhile pacifying inside it after module construction It installs standby, can be improved accuracy when module abutting joint, and then effectively increase installation accuracy.
Construction method in the embodiment of the present invention increases the stability in hoisting process by using 4 lift-on/lift-off systems, It is easy to operate, rapidly and efficiently.
The vertical operation in a large amount of high-altitude can be changed into ground by the construction method in the embodiment of the present invention or low latitude level is made Industry, and by using CO2Gas shielded arc welding is welded and fixed, and construction personnel is easy to operate, and welding and installation quality are effectively mentioned Height, welding first-time qualification rate can control 98% or more.It can reduce construction quality omission factor simultaneously, it is blind that no quality inspection may be implemented Area, inspection rate reach 100%.
Construction method in the embodiment of the present invention is by using virtual route planning technology to the installation path of interlayer equipment It is planned, effectively reduces the resource consumption of equipment installation project.
Further advantage, target and feature of the invention will be partially reflected by the following instructions, and part will also be by this The research and practice of invention and be understood by the person skilled in the art.
Detailed description of the invention
Fig. 1 is the construction process schematic diagram of steel structure modularization construction method according to an embodiment of the invention.
Specific embodiment
Present invention will be described in further detail below with reference to the accompanying drawings, to enable those skilled in the art referring to specification text Word can be implemented accordingly.
It should be noted that experimental method described in following embodiments is unless otherwise specified conventional method, institute Reagent and material are stated, unless otherwise specified, is commercially obtained;In the description of the present invention, term " transverse direction ", " vertical To ", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", the instructions such as "outside" side Position or positional relationship are to be based on the orientation or positional relationship shown in the drawings, and are merely for convenience of description of the present invention and simplification of the description, It is not that the device of indication or suggestion meaning or element must have a particular orientation, be constructed and operated in a specific orientation, because This is not considered as limiting the invention.
As shown in Figure 1, the present invention provides a kind of steel structure modularization construction method, comprising the following steps:
S11: handling basis, and foundation bolt is buried and is positioned at basis and carries out first time measurement, meets peace Concreting is carried out after reload request, pour it is firm after carry out second of measurement again, parallels is installed on after meeting installation requirement The foundation bolt.
In bolt embedment technology, the most important is the determination to the position of pre-embedded anchoring bolts, it is necessary to assure this The accuracy of position, there will be larger difficulty when otherwise carrying out steel column installation, while the quality installed also it is difficult to ensure that.Therefore, When pre-embedded anchoring bolts position is constructed, need to carry out stringent control to basic axis and absolute altitude datum mark, when necessary It needs to carry out repetition measurement twice, be measured after burying positioning first, secondly the progress repetition measurement after concreting time is firm, two Secondary measurement all must assure that displacement cannot go beyond the scope.
The connection on equipment and basis, which refers to, is securely fixed in equipment in Equipment Foundations, in order to avoid generate displacement or topple, Equipment can be made to keep necessary installation accuracy for a long time simultaneously, guarantee the normal operation of equipment.Equipment in modularization structural steelwork Mainly foundation bolt is used to connect with the connection method on basis and pass through parallels for equipment to just levelling, then fixes equipment On deck or steel construction.In addition to this, also some equipment are directly weldingly fixed on deck or steel construction.
Foundation bolt in the present embodiment include be not limited to fixed foundation bolt, movable foundation bolt, expanded anchor bolt and It is bonded foundation bolt.Specifically, movable foundation bolt, also known as long foundation bolt are a kind of dismountable foundation bolts, for solid There is the heavy duty equipment of sharp pounding or impact when working surely.This foundation bolt is long, mainly there is the double of double thread The T-shaped T-type formula of hair style and threaded one end one end.Fixed foundation bolt, also known as short foundation bolt are usually cast in one with basis It rises.Equipment for fixing no sharp pounding and impact, length are generally 100-1000mm, and head is made into jag shape, ring Shape, hook-type is to prevent spin-ended turn and extracts.Swollen anchorage foot bolt is mainly used in the operating condition that armored concrete is contacted with equipment.Bonding It is that very high or ordinary foundation bolt is difficult in the case where meeting the requirements that foundation bolt, which is primarily adapted for use in intensity requirement not,.
S12: base plate is installed on the foundation bolt by parallels.
The main function of parallels is the weight transmitting of equipment to basis in the present embodiment, at the same time it can also by adjusting The thickness of parallels realizes that equipment is levelling.Specifically, the type of parallels include be not limited to plain cushion iron, inclined sizing block, aperture parallels, Be open parallels, the pairs of inclined sizing block of gib head, adjustment parallels, adjusting screw etc..Wherein, adjustment parallels has bolt adjustment parallels and spherical surface Two kinds of parallels of adjustment.Bolt adjustment parallels is divided to two blocks of adjustment parallels and three blocks of adjustment parallels again, and two blocks of adjustment parallels are by base, tune Whole bolt, adjustment block form, and increase elevator on respect to two pieces adjustment cushion block structures of three pieces of adjustment cushion blocks.Spherical surface adjusts cushion block It is made of parallels pedestal, adjustment wedge, bolt, nut, spheric washer etc., is mainly used for the higher mechanical equipment peace of required precision In dress.Inclined sizing block is divided into A type and two kinds of Type B, and plain cushion iron is c-type, and surface generally without finishing, is mainly used in machinery Levelling, centering in installation.Gib head thickness in the pairs of inclined sizing block of gib head is generally 15mm, is highly generally 10mm is generally used for not needing on the accurate mechanical equipment of comparison of equipment anchor bolt.Be open parallels and aperture parallels, opens Hole, the size of opening are 2-5mm bigger than the diameter of foundation bolt, and width is more slightly wider than foundation bolt, and length is generally longer than equipment lower margin 20-40mm is mainly used in the lesser equipment of the bearing area such as equipment support.
S13: taking using module centers line as component position baseline, and component assembly is become modularization installation unit, Wherein, the reinforcement member in modularization installation unit is spliced by high-strength bolt and rotary table shearing-resistant member, in modularization installation unit Left and right component pass through steel member connect.
In one embodiment, live component assembly becomes the technical process of modularization installation unit are as follows: makes assembled tire Frame;Component inspection;Using module centers line as component position baseline, component assembly is become into modularization installation unit, wherein Reinforcement member is spliced by high-strength bolt and rotary table shearing-resistant member, and the left and right component in the modularization installation unit passes through steel member Connection;Align interface dimensional gaughing, welding, reinforcing, the process for completing segmented assembly.
Optionally, live component assembly at the process of modularization installation unit is completed on an assembly moulding bed.It is existing It is illustrated by taking Steel for Large Steel Column on-site consolidation as an example, assembled moulding bed perpendicular to component and is placed horizontally at the H on ground by one group Fashioned iron is constituted.
It in one embodiment, further include using to plan with installation path of the virtual route planning technology to component The step of.
Specifically, largely there is big and long cylinder, cone and frame class equipment in large-scale steel structure, and with higher Space utilization rate, the installation of large scale equipment is usually also required to the auxiliary of special fixture and type frame in steel construction.Equipment is in practical peace During dress assembly space is reserved not enough, assemble sequence is different or assembly tool prepare it is improper etc. due to and be likely to occur nothing The case where method is installed, the particularity of equipment and the complexity of installation process determine that the installation of large scale equipment in steel construction must adopt With the process program for being different from general device installation.Virtual route planning is one of key technology of Virtual assemble, it is being assembled On the basis of modeling and assembly sequence-planning, makes full use of assembly information to carry out path analysis and solution, judge and generate one Reasonable assembly path, to can reach the effect of optimization design.The concrete operation step of virtual route planning technology are as follows:
(1) the initial moving direction of equipment
In order to determine the movement routine of equipment, it must be determined that the initial moving direction of equipment.Here in order to reduce algorithm Operand determines the initial moving direction of equipment with the following method: firstly, extracting geometrical constraint direction and arranging direction Table, and taking first direction in table is w principal direction, secondly, second direction in table is taken to carry out Projective decomposition to w, is taken perpendicular to the main side of w To projecting direction be u direction, then, take w, u vector product be the direction v, then successively take other directions to u, v and w carry out Projection determines that it is equipment moving direction if nothing finally, judging whether there is constraint along+w ,+u ,+v ,-w ,-u, the direction-v.
This method is likely to be obtained multiple moving directions, needs to further determine that in subsequent step or final feasible It is optimized in path to obtain equipment optimal path of movement.
(2) equipment translational movement
Structure is obtained in the projection split on direction vector by comparing the initial moving direction of component and modularization installation unit Part translational movement.For a unit equipment moving direction, if phasor coordinate collection { F1、F2、....、FnRepresent required mobile component Vertex, { S1、S2、....、SnRepresent the vertex of modularization installation unit.
Enable Smax=max { (u × Si) l i=1,2 ..., m
Fmin=min { (u × Fi) l i=1,2 ..., n
It can obtain, the mobile translational movement M=(S of equipmentmax-Fmin)。
It repeats the above process, until equipment reaches designated position, then equipment paths traversed is the shifting of equipment installation Dynamic path.Certainly, it due to the spatial dimension between component and modularization installation unit (equipment) and does not know, the equipment peace of acquisition Filling path or equipment moving direction, there are number of ways, this just needs to consider that the mobile specific environment of equipment carries out in summation optimal Scheme Choice.
S14: temporary support structure is arranged on lifting device, the modularization installation unit is lifted using lifting device It is installed on the base plate, and is fixedly mounted after verticality and levelness leveling and adjusting.
Wherein, for the modularization installation unit of geometry and rigidity bi-directional symmetrical, lifting point is arranged in modularization On the flooring girder steel of installation unit;Modularization installation unit asymmetric for geometry and rigidity lifted to reduce The deflection of modularization installation unit in journey can increase temperature pier facility according to deformation when lifting.Optionally, described to hang Holding tool uses 4 lift-on/lift-off systems.
Specifically, the lifting transport of large scale equipment is a technical special work post operation strong, danger level is big, is needed more The mutual cooperation of work post personnel is coordinated mutually.It must be to the environment of operation field, heavy equipment handling route and handling before lifting It designated position and plays weight weight, center of gravity, level point and a lifting point and whether balances etc. and carry out analytical calculation, formulate optimal Lifting scheme achievees the purpose that equipment safety is in place.Modularization steel construction is since equipment is numerous, and single device figure is big, quality The features such as weight, installation space is narrow, need to work out special Hoisting Program.It constructs and is first spelled according to steel construction waypoint ground early period It fills weight and selectes large-scale hoisting machinery, lifting accounting is being carried out according to actual field pack weight before lifting, it is determined whether meet Lifting condition, checks whether splice point welding meets loose hook condition after lifting.
(1) hoisting appliance requirement
All hoist cables must have inspection certificate.Hoisting operation person should check rigging before lifting, and must not have damaged, disconnected Situations such as stock, fracture of wire.
(2) site requirements is lifted
The place of crane track route should be sufficiently flat, and barrier on scene and lane is removed to clean, guarantee shoe Band crane etc. smooth operations in the course of travel.It cannot be across cable duct and other danger zones on driving channel;Before construction, answer The scaffold or structural member that have an impact to lifting are removed, it is necessary to assure equipment is from slinging predetermined installation site, on route There cannot be any shelter to obstruct the view or influence operation.
(3) lifting is meteorological requires
Tranquil weather should be selected when lifting, the precision that the weather such as wind, rain, snow all will affect lifting work even results in Slinger is difficult to carry out.Common, wind-force is not greater than six grades (10.8m/s) during lifting work.
(4) other requirements are lifted
The technical data such as facility installation drawing, equipment assembling figure, the installation manual for equipments of hanging device are complete errorless and are most New edition;When carrying out lifting operation, there cannot be any barrier within the scope of the radius of turn of crane;It is common, lifting operation area The normal operation to guarantee the large spans object such as hoisting machine tool rotating arm must be isolated;In addition, lifting work will be arranged in Daytime carries out.During installation and shipping, all flange faces must all cover and avoid directly contacting with steel construction;Large scale equipment It should pause 1 minute or so when being transferred from ground or pad pier 300mm or so, band hoisting technology personnel confirm hoist cable, snap ring and loop wheel machine It can continue lifting operation after state is without exception.
In addition to this, for large equipment, should shift to an earlier date and place some sleepers on transport vehicle, sleeper put range by Equipment size and transport vehicle size determine;Then according to scene and equipment situation, select crane will be on equipment hoisting to transport vehicle. Technical staff review and validate band hanging device and its attachment it is intact after, select crane by equipment hoisting to flat bed transport vehicle Upper rope fixation, and it is steady to drive a vehicle, and reduces vibration to the greatest extent.Traffic route is established according to the position of equipment in the module.
It includes two large divisions that large scale equipment, which lifts force analysis and calculates, first is that hoisting machine tool, rigging;Second is that by equipment is hung Itself.By the diagram of lifting force analysis or number solution, each portion's maximum weighted value is determined, to select lifting equipment, rigging.Together When, according to worst operating condition, strength and stability check carried out to main equipment (referring generally to mast), in necessary situation, Monolithic stability can be carried out to equipment and local stable nucleus is calculated.
(1) Force Calculation of wirerope
Wirerope is widely used in various lifting equipments, and in lifting operation, wirerope also serves as fine cable (cable wind rope), set Rope (jack line) and drawstring etc..According to the actual needs that hoisting and hanging works, following several wirerope: 6X19 are generally selected in lifting Wirerope --- it is used as cable wind rope and drag-line, i.e., rope is for not by bending or the place that may be worn;6X37 steel wire Rope --- in tackle pulley, i.e., rope to bear to use when bending, as passing around tackle pulley hoisting line etc.;6X61 wirerope --- Component etc. is sling for tackle pulley and production hoist cable (jack line) and binding.Furthermore it is mainly used for heavy-duty lifting machine.
(2) lifting device is selected and is checked
The selection and check of snap ring: snap ring is mainly used for the connection between hoist cable and hoist cable or hoist cable and component, by bending ring It is formed with pin two parts.
(3) selection and check of handling machinery are lifted
The selection of lifting handling machinery should comprehensively consider following factor: crane performance data, and such as rated load weight is hung Vehicle lifting performance, crane overall dimensions, length of boom, operating radius, counterweight etc.;Equipment and technology data, as device structure size, Main material, equipment hoisting weight, equipment monolithic stability type, shackle structure and position etc.;Environment is lifted, such as equipment Plane Installation Plan-position, equipment installed height mark before position and equipment lifting, space at Standing position of a crane, underground installation are (underground pipe network, buried Cable etc.) and earth bearing strength, crane installation counterweight needed for space etc.;Safety specifications, requirement such as related with hoisting, Requirement related with device structure, requirement related with crane performance, particular/special requirement related with construction site etc.;Crane is practical Crane capacity subtracts gib head (including rigging more than gib head) weight according to theoretical value in crane capacity table in crane handbook to examine Consider.When selecting suspender, practical hoist is needed comprising 1.05 times of safety factor and 1.1 times of dynamic amplification coefficient.Loop wheel machine exists Peak load utilization rate must be met in working radius, be not required to recalculate in working radius, but suggest that operative radius is working Within 2/3rds of radius.
(4) installation in place of equipment
After flat car crane is in place, carried out hanging appearance adjustment according to the installation requirement of equipment.After, revolving crane principal arm, Equipment is adjusted to above predetermined installation site, while the equipment such as chain block auxiliary can be used to be accurately positioned, equipment is transferred, It must be steady during lower section;After in place, it is connected and fixed by facility installation drawing;If live scaffold is more than this height, influence to set Standby lifting, the scaffold of dismountable superelevation part;After the installation is completed, the levelness and verticality of equipment should be checked and adjust, with Installation to next batch.After equipment is installed, lifting lug is cut away in installation check hole, then installs other attachmentes.
In addition, equipment hoisting is needed to vacate afterwards in place construction space or carried out next time by large-scale handling equipment Equipment handling needs to be arranged equipment temporary support structure before equipment hoisting is preliminary in place to guarantee that equipment meets adjustment requirement and anti- Only steel construction intentional deformation realizes normal mounting.Temporary support structure in large-scale steel structure engineering has support stress effect Greatly, the features such as bearing height is high is the important construction installation in structural steelwork.Conventional temporary support structure utilizes tower crane lifting For the tower body standard component of machine as supporting member, it is fast to set up speed, has versatility, reuse it is high-efficient, it can be achieved that promoted and Support function is applied in large-scale steel structure engineering.In addition to this, it can be mounted so as to need to be arranged various face according to equipment When support construction.After the completion of construction, temporary support will be removed and be polished smooth, and when removal cannot damage base material, in temporary support Position need to carry out magnetic powder and penetrating inspection.
Large-scale steel structure figure is different, and temporary support when equipment is installed is also many kinds of, the temporary support knot Structure includes to be not limited to interim drag-line, diagonal brace, pillar or other fit structures.Specifically, again may be used according to the structure of temporary support It is divided into bearing supporting frame, supports fashioned iron, support plate and very heavy top support etc..The position according to set by temporary support, temporarily Support can be divided into compression bar support (including support fashioned iron etc.) again, beam support and frame support (including deck plate support etc.).
S15: carrying out arrangement to the modularization installation unit and be welded and fixed, and completes structural module construction.
The major influence factors of welding have the selection of welding parameter, the type of welding wire and welding arc voltage and electric current.Its In, welding current will be selected according to the thickness of workpiece, welding position and gage of wire, and the selection of arc voltage will match with electric current It closes;Different location selects different welding manners.Optionally, which uses CO2Gas shielded arc welding.
Specifically, to guarantee welding quality, welding deformation is accurately predicted, to solve structure steel fabrication mounting structure safety Property difficult point, this technique uses following methods: welding stress when reasonable reinforcement measure 1) being taken to obstruct welding reduces welding and receives Contracting amount, is controlled within the allowable range;2) reasonable welding procedure is formulated, avoids welding part or certain point, welding as far as possible When should symmetrically be uniformly distributed, branch after first main body, preferably balanced welding, control welding current preferably it is small less, be rapidly completed;3) it controls Component groups reduce weld shrinkage to gap;4) it takes heat straightening and gagging to handle deformation element, is heated and carried out using flame Correction, mechanical correction, which can also be used, can reach the purpose of correction.
Further include the steps that mounting platform, ladder and pull rod in the step S15 in one of the embodiments,.Pass through Mounting platform, ladder and pull rod are convenient for subsequent use and maintenance conditions.
The present invention is include at least the following beneficial effects:
A large amount of high-altitude vertical space job task is changed into ground or low latitude and made by the construction method in present invention implementation Industry improves construction safety assurance coefficient and incites somebody to action, and reduces the degree-of-difficulty factor of construction, effectively reduces construction cost;And it is more A construction surface can construct simultaneously, and operation side increases, and simplify construction, shorten the construction period, easy for installation effective, into And improve construction efficiency.In addition, the construction method is used using module centers line as component position baseline, by component assembly As modularization installation unit, error diffusion can be built on a direction, the matching performance of all directions is more more preferably to just levelling It is good.Meanwhile equipment being installed inside it after module construction, working link can be reduced, and equipment can be effectively improved in module Accuracy when docking, and then effectively increase installation accuracy.
Construction method in the embodiment of the present invention increases the stability in hoisting process by using 4 lift-on/lift-off systems, It is easy to operate, rapidly and efficiently.
The vertical operation in a large amount of high-altitude can be changed into ground by the construction method in the embodiment of the present invention or low latitude level is made Industry, and by using CO2Gas shielded arc welding is welded and fixed, and construction personnel is easy to operate, and welding and installation quality are effectively mentioned Height, welding first-time qualification rate can control 98% or more.It can reduce construction quality omission factor simultaneously, no quality inspection may be implemented Blind area, inspection rate reach 100%.
Construction method in the embodiment of the present invention is by using virtual route planning technology to the installation path of interlayer equipment It is planned, effectively reduces the resource consumption of equipment installation project.
Although the embodiments of the present invention have been disclosed as above, but its is not only in the description and the implementation listed With it can be fully applied to various fields suitable for the present invention, for those skilled in the art, can be easily Realize other modification, therefore without departing from the general concept defined in the claims and the equivalent scope, the present invention is simultaneously unlimited In specific details and legend shown and described herein.

Claims (10)

1. a kind of steel structure modularization construction method, which comprises the following steps:
1) foundation bolt is buried and is positioned at basis and carries out first time measurement, carry out concreting after meeting installation requirement, Pour it is firm after carry out second of measurement again, meet and parallels be installed on the foundation bolt after installation requirement;
2) base plate is installed on the foundation bolt by the parallels;
3) it takes using module centers line as component position baseline, component assembly is become into modularization installation unit, wherein institute The reinforcement member stated in modularization installation unit is spliced by high-strength bolt and rotary table shearing-resistant member, in the modularization installation unit Left and right component pass through steel member connect;
4) temporary support structure is set on lifting device, is installed on modularization installation unit lifting using lifting device The base plate, and be fixedly mounted after verticality and levelness leveling and adjusting;
5) the modularization installation unit arrange and be welded and fixed, complete structural module construction.
2. steel structure modularization construction method according to claim 1, which is characterized in that the step 3) specifically include with Lower process: assembled moulding bed is made;Component inspection;Using module centers line as component position baseline, component assembly is become into mould Block installation unit, wherein reinforcement member is spliced by high-strength bolt and rotary table shearing-resistant member, in the modularization installation unit Left and right component is connected by steel member;Align interface dimensional gaughing, welding, reinforcing.
3. steel structure modularization construction method according to claim 2, which is characterized in that the assembled tire in the step 3) Frame is by perpendicular to the component and being placed horizontally at the H profile steel on ground and being made.
4. steel structure modularization construction method according to claim 1, which is characterized in that in the step 3), further include Using the step of being planned with installation path of the virtual route planning technology to the component.
5. steel structure modularization construction method according to claim 4, which is characterized in that described using with virtual route The step of planning technology plans the installation path of component specifically includes: determining the initial moving direction of the component;Pass through Comparing the initial moving direction of the component and the modularization installation unit, to obtain component flat splitting the projection on direction vector Shifting amount;It repeats the above process, until the component reaches designated position, then the component paths traversed is the peace of component Fill path.
6. steel structure modularization construction method according to claim 1, which is characterized in that the step 4) further include: right Wirerope carries out Force Calculation;Select and check lifting device;Select and check lifting handling machinery;Lifting device is in place Installation.
7. steel structure modularization construction method according to claim 1, which is characterized in that lifted described in the step 4) Tool is lifted using 4 lift-on/lift-off systems.
8. steel structure modularization construction method according to claim 1, which is characterized in that use CO in the step 5)2 Gas shielded arc welding is welded and fixed.
9. steel structure modularization construction method according to claim 1, which is characterized in that further include peace in the step 5) The step of assembling platform, ladder and pull rod.
10. -9 described in any item steel structure modularization construction methods according to claim 1, which is characterized in that the interim branch Support structure is support fashioned iron.
CN201811217605.0A 2018-10-18 2018-10-18 Steel structure modularization construction method Pending CN109235903A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811217605.0A CN109235903A (en) 2018-10-18 2018-10-18 Steel structure modularization construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811217605.0A CN109235903A (en) 2018-10-18 2018-10-18 Steel structure modularization construction method

Publications (1)

Publication Number Publication Date
CN109235903A true CN109235903A (en) 2019-01-18

Family

ID=65053930

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811217605.0A Pending CN109235903A (en) 2018-10-18 2018-10-18 Steel structure modularization construction method

Country Status (1)

Country Link
CN (1) CN109235903A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109797643A (en) * 2019-04-01 2019-05-24 滕州市建筑安装工程集团公司 A kind of installation method of annular overline bridge steel box-girder entirety
CN111143915A (en) * 2019-11-18 2020-05-12 中国化学工程第六建设有限公司 Steel structure modular installation method based on Tekla software platform
CN111395848A (en) * 2020-03-24 2020-07-10 中铁建设集团南方工程有限公司 Mast type steel structure and inhaul cable installation construction method
CN113738122A (en) * 2021-08-27 2021-12-03 中国二十冶集团有限公司 Mounting method of circular silo steel structure
CN114837428A (en) * 2022-03-25 2022-08-02 长江精工钢结构(集团)股份有限公司 Steel structure industrial building modular installation method
CN114941264A (en) * 2022-05-31 2022-08-26 中国二十二冶集团有限公司 Method for installing track and basic embedded plate

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101451397A (en) * 2007-12-05 2009-06-10 中冶天工建设有限公司 Steel structure modularization construction process
CN101871265A (en) * 2010-07-02 2010-10-27 中国十七冶集团有限公司 Flat shim plate-adjustable grouting installation method
CN102359185A (en) * 2011-08-08 2012-02-22 中国舰船研究设计中心 Connecting structure of large steel structural member and concrete member and construction method
CN105421792A (en) * 2015-12-15 2016-03-23 安徽伟宏钢结构集团股份有限公司 Lifting construction process of modular steel structural components
CN106121257A (en) * 2016-08-16 2016-11-16 郑州暖树实业有限公司 Component Intelligent transport method and system for assembled architecture

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101451397A (en) * 2007-12-05 2009-06-10 中冶天工建设有限公司 Steel structure modularization construction process
CN101871265A (en) * 2010-07-02 2010-10-27 中国十七冶集团有限公司 Flat shim plate-adjustable grouting installation method
CN102359185A (en) * 2011-08-08 2012-02-22 中国舰船研究设计中心 Connecting structure of large steel structural member and concrete member and construction method
CN105421792A (en) * 2015-12-15 2016-03-23 安徽伟宏钢结构集团股份有限公司 Lifting construction process of modular steel structural components
CN106121257A (en) * 2016-08-16 2016-11-16 郑州暖树实业有限公司 Component Intelligent transport method and system for assembled architecture

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109797643A (en) * 2019-04-01 2019-05-24 滕州市建筑安装工程集团公司 A kind of installation method of annular overline bridge steel box-girder entirety
CN111143915A (en) * 2019-11-18 2020-05-12 中国化学工程第六建设有限公司 Steel structure modular installation method based on Tekla software platform
CN111395848A (en) * 2020-03-24 2020-07-10 中铁建设集团南方工程有限公司 Mast type steel structure and inhaul cable installation construction method
CN111395848B (en) * 2020-03-24 2021-07-23 中铁建设集团南方工程有限公司 Mast type steel structure and inhaul cable installation construction method
CN113738122A (en) * 2021-08-27 2021-12-03 中国二十冶集团有限公司 Mounting method of circular silo steel structure
CN113738122B (en) * 2021-08-27 2022-10-11 中国二十冶集团有限公司 Mounting method of circular silo steel structure
CN114837428A (en) * 2022-03-25 2022-08-02 长江精工钢结构(集团)股份有限公司 Steel structure industrial building modular installation method
CN114941264A (en) * 2022-05-31 2022-08-26 中国二十二冶集团有限公司 Method for installing track and basic embedded plate

Similar Documents

Publication Publication Date Title
CN109235903A (en) Steel structure modularization construction method
CN103291076B (en) Multilayer steel truss fragmented reverse hoisting construction method in arc-shaped frame
CN110259145A (en) A kind of arch tubular truss rapid constructing method
CN106703416B (en) Steel roof truss dead man hanging method in small space
CN102797226A (en) Integral erection construction method of 60m steel box girder
CN112554345A (en) Ground splicing and integral lifting construction method for large-span welding ball net rack
CN113982280A (en) Construction method of complex space truss integral hoisting system
CN111794119B (en) Temporary supporting system and hoisting method for basket type steel box tie bar arch
CN105649334A (en) Concrete shear wall tower crane wall-attachment construction method and device thereof
CN110528390A (en) It closes on both wired narrow spaces and sets up T beam construction method
CN113047447B (en) Split-level steel structure building semi-reverse construction method
CN113356597A (en) Lifting process of large-span net rack and truss combined roof
CN111561175B (en) Prestress underpinning static force cutting and column pulling construction process
CN104727226A (en) Construction method for steel-concrete composite girder
CN114541652A (en) V-shaped steel column and construction method thereof
CN108842954A (en) Installation and construction method of huge different-section honeycomb beam structure system of wing-shaped roof
CN111622125A (en) Method for mounting through-type inverted triangular comb-shaped steel pipe arch rib
CN208932821U (en) A kind of erecting beam construction height leg gantry crane
CN106400675A (en) Steel anchor box and mounting method thereof
CN113982281A (en) Super-tonnage space truss lifting and reinforcing structure and construction method thereof
CN113338333A (en) Quick mounting method for steel beam plate under cover-excavation top-down condition
CN102777044A (en) Hoisting method of steel-structured spraying layer of urea prilling tower
CN111119493A (en) Construction method for integrally and synchronously lifting light steel keel
CN106245531B (en) Steel structural bridge installation method is hung under bilateral derrick type
CN110485386A (en) A kind of lifting operation method of ultra-large type gates of segmental shape installation in flood discharging tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190118