CN109235604A CN201811157997.6A CN201811157997A CN109235604A CN 109235604 A CN109235604 A CN 109235604A CN 201811157997 A CN201811157997 A CN 201811157997A CN 109235604 A CN109235604 A CN 109235604A
Authority
CN
China
Prior art keywords
pipeline
deposit
pump group
control valve
forebay
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811157997.6A
Other languages
Chinese (zh)
Inventor
张欣
董磊
陈昱霖
陶贤成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN201811157997.6A priority Critical patent/CN109235604A/en
Publication of CN109235604A publication Critical patent/CN109235604A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F1/00Methods, systems, or installations for draining-off sewage or storm water
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F1/00Methods, systems, or installations for draining-off sewage or storm water
    • E03F1/001Methods, systems, or installations for draining-off sewage or storm water into a body of water
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/02Arrangement of sewer pipe-lines or pipe-line systems
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/22Adaptations of pumping plants for lifting sewage
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F9/00Arrangements or fixed installations methods or devices for cleaning or clearing sewer pipes, e.g. by flushing
    • E03F9/007Devices providing a flushing surge
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F2201/00Details, devices or methods not otherwise provided for
    • E03F2201/20Measuring flow in sewer systems

Abstract

The automatic method for removing pipeline deposit is responsible for suitable for multichannel the invention discloses a kind of, when thickness of deposits reaches setting value in pipeline, deposit monitoring system in access well transmits signals to control system, open washing control valve door, close the second control valve, third control valve door is closed, rainwater pump group is opened;It opens and cuts dirty pump group, continue Forebay of Pumping Station middle and high concentration sewage transport to urban sewage system;After water pollutant concentration is reduced and tended towards stability when pump group forebay, pipe flushing system can be terminated;Method of the invention reduces pumping plant by way of cutting down pipeline deposit and puts river, solves the problems, such as that river is black smelly from the root.With strong points present invention could apply to the drainage system of various systems, flexible operation, construction investment is few, can realize effective control that river pollution is put to pumping plant in a short time.

Description

A method of automatic removing pipeline deposit is responsible for suitable for multichannel
Technical field
The invention belongs to black-odor riverway Treatment process fields, are related to a kind of automatic method and device for removing pipeline deposit, The automatic method for removing pipeline deposit is responsible for suitable for multichannel more particularly to a kind of.
Background technique
As rapid urban and the density of population are continuously increased, river water environmental problems are increasingly highlighted, most cities Black-odor riverway is developed into river.Black-odor riverway problem seriously affects nearby residents quality of life, city image generation.River The black smelly origin cause of formation is other than leading to river channel ecology system destruction due to urban construction, and most importantly pollutant directly enters river and causes External source pollution.
In existing black-odor riverway Treatment process, sewage interception along river, bed mud dredging, restoration of the ecosystem, the technologies such as clean water diversion It is widely used, but since each technological means is there are respective limitation, is difficult to solve the problems, such as that river is black smelly in a short time.
Sewage interception along river, which refers to, lays wastewater interception pipe along river two sides, by it is originally in line enter river sewage access cut dirty pipe Road, and it is delivered to sewage treatment plant, mitigate the in line impact to river water quality of sewage.But interception project implement engineering cost compared with Height, implementation cycle are longer.After the completion of interception project, since the sewage of rain dirt hybrid junction accumulation is in rain in combined sewage and municipal pipeline It can put river by pumping plant driving and enter river, influence river quality of water environment again.
Bed mud dredging is to blow the mud for depositing river bed using mechanical equipment to stir into the watery of muddiness, and transport extraction.Clearly Deposit technique can reduce the endogenous pollution in river, but improper for the sludge handling of extraction be easy to cause secondary pollution.
River corridor restoration refers in river land-based area control line, is meeting the rivers basic training such as flood control, water drainage and diversion On the basis of energy, urban river water ecosystem restoration is promoted by artificial reclamation activities, constructs healthy, complete, stable urban river water The activity of the ecosystem.But the technology to black-odor riverway renovating effect there are limitation, rainfall day put river with pumping plant, pollute Object can destroy river channel ecology system back into river.
Clean water diversion is to introduce polluted river channel upstream or neighbouring cleaning by the regulation of water conservancy projects (such as gate, pumping plant) Water source enhances the diffusion, purification and output of water pollutant to improve the hydrodynamic conditions in river, being capable of rapid recovery water body It is black smelly, but can not achieve the improvement steady in a long-term of black-odor riverway water quality.
For the black-odor riverway Treatment process applied at this stage there are long construction period, investment is big, and the limitation such as can not take effect in short term Property.In addition, often river as before, it is clear long to cannot achieve Changzhi again multiple " black " after heavy rain.Tracing it to its cause is pollutant warp Over long distances, it deposits to form mud in tube bottom after low flow velocity conveying, when catchment occurs, pumping plant rainwater pump group is opened, pipeline Interior deposit is washed into water body.For combined flow system, when pipe diameter determing, considers that (pipeline is set for 2 ~ 5 times of interception ratio The flow of meter is 3 ~ 6 times of dry flow sewage amount), flow velocity is lower in pipeline when dry days sewage transport, and dirty water pollutant can be in pipe It is deposited in road.For separate flow system, the problems such as due to rain dirt hybrid junction, dry flow sewage enters storm sewer, and sewage passes through rainwater The dirty pump that cuts of pumping plant is delivered to sewerage;Many drainage systems are in high water level operational mode, and rain pipe caliber is pressed 3 ~ 5 years Return period designs (i.e. pipe design conveying capacity is tens times of dry flow sewage amount or more), and caliber is larger, and dry flow sewage is in rain Flow velocity is lower in waterpipe, and polluter is deposited in tube bottom.Since system high water level is run, tradition connects the water that interim water pipe rinses Stream impulse force has been consumed in 1m at the pipeline access, and mud is difficult to be washed, even if the deposit that origin or beginning is taken up by instantaneous flow It can be deposited again in subsequent main pipe;It is only 100m that external high-pressure water pipeline flushing device maximum, which rinses range, and Chinese large-sized Sewerage system main pipe length generally drains conveying main pipe longest up to 55km more than 1km, such as Shanghai City large size.Therefore, it opens Sending out one kind automatic method and device for removing pipeline deposit and reduction pumping plant is put river and polluted has positive meaning, is that realization is black Smelly river regulation Changzhi is necessary means clearly long.
Summary of the invention
It is responsible for the automatic method for removing pipeline deposit suitable for multichannel it is an object of the invention to provide a kind of, by cutting Subtract the deposit in municipal pipeline, the reduction rainy day puts the total amount of pollutant that river enters river by pumping plant, river is solved from source The black smelly problem in road, the effect for maintaining black-odor riverway to administer realize that Changzhi is clear long.
In order to achieve the above object, technical scheme is as follows: one kind being suitable for the automatic removing pipeline of multichannel supervisor The method of deposit, municipal drainage pumping plant include Forebay of Pumping Station, cut dirty pump group, rainwater pump group, and Forebay of Pumping Station and multiple drainings are The general pipeline that unites is connected, and Forebay of Pumping Station is respectively connected to cut a dirt pump group and rainwater pump group by pipeline, Forebay of Pumping Station and rainwater pump group it Between be additionally provided with withdrawal of currency from circulation water pipe;The one access well of setting on each drainage system general pipeline, the access well is by adding row pressure hydraulic piping It is connect with water pipe is steam again;Washing control valve door, the withdrawal of currency from circulation water pipe and pump are equipped between described plus row pressure hydraulic piping and access well It stands and is equipped with the second control valve between forebay, third control valve door is equipped between the rainwater pump group and river;
The automatic removing pipeline deposit method comprises the following steps:
Step 1, when thickness of deposits reaches setting value in drainage system general pipeline, the deposit in access well monitors system Control system is transmitted signals to, washing control valve door is opened, closes the second control valve, closes third control valve door, is opened 1 or more rainwater pumps in rainwater pump group;
Step 2, it cuts dirty pump group and opens normal operation, continue Forebay of Pumping Station middle and high concentration sewage transport to urban sewage system;
Step 3, after Forebay of Pumping Station water quality is gradually decreased and tended towards stability, water quality monitoring system transmits signals to pumping plant control System closes the rainwater pump of rainwater pump group, and closing control valve, terminates to rinse.
Further, described plus row pressure hydraulic piping is pumped using closed steel pipe, ductile iron pipe, plastic tube etc. according to rainwater Length, caliber and the buried depth of the parameter adjustment pipeline of group water pump.Pumping plant high for configuration pump head, flow is big, adds row pressure Hydraulic piping length is long, caliber is relatively large;For configuring pump head is small, flow is small pumping plant, add row pressure hydraulic piping length it is shorter, Caliber is relatively small;Buried depth of pipeline can be according to adding discharge pipe performance to be adjusted.
Further, it accesses toxic and harmful gas when setting deodorization device prevents the circulatory system from running in well and dissipates and overflow.
Further, it accesses in well and the refluence that anti-water recovery apparatus avoids circulating flushing wash water is set, guarantee flushing water for silt Mud deposit is washed away.
For according to drainage system actual conditions, multiple access wells are set in the different location of drainage system general pipeline, and set Setting multichannel adds row pressure hydraulic piping to realize to drainage system general pipeline while or dividing by the control of valve to the multiple access well When flushing, cut down pipeline in deposit.
Further, when drainage system general pipeline caliber is larger, submersible agitator is installed in the inspection shaft of drainage system general pipeline, Promote deposit to wash away, accelerates circulation flushing process.Various ways, including vertical installation, opposite peace can be used in blender installation Be filled with and misorientation installation etc..
It is total to simulate drainage system when river is put in rainy day driving in dry days for the method for automatic removing pipeline deposit of the invention High flow rate scour process in managing, tube bottom deposit are washed reductions in dry days, and greatly reducing rainy day pumping plant and driving to put river causes Pollute the risk into river.Described plus discharge pipe length, caliber can be according to drainage system general pipeline caliber and rainwater pump group device parameters It is designed.The circle irrigation system can flexibly be run according to deposition in pipeline, save operating cost.
The method that reduction pipeline deposit provided by the invention realizes that pumping plant puts pollution river reduction has the advantage that
(1) efficiently using existing facility, engineering measure is few, and investment for trnasforming urban land is small.
(2) operating method is simple, convenient for management.
(3) removal of pipeline deposit is obvious, and it is good to put river contamination control effect to pumping plant, quick.
(4) different system drainage systems, method wide application be can adapt to.
Detailed description of the invention
Fig. 1 is the process flow chart of the method and device of automatic removing pipeline deposit of the invention.
Fig. 2 circulation flushing operational mode schematic diagram.
Specific embodiment
A specific embodiment of the invention is further described below in conjunction with attached drawing.
Of the invention realizes that pumping plant puts the pipe flushing formed in the method for polluting river reduction by cutting down pipeline deposit System, as shown in Figure 1, the system includes:
Forebay of Pumping Station 11, section dirty pump group 12 in municipal drainage pumping plant 1, rainwater pump group 13, the withdrawal of currency from circulation water pipe 14, intelligence control system With the access well 61(62 ... 6n of the additional row pressure hydraulic piping 51(52 ... 5n of pumping plant), reconstruction) and drainage system general pipeline 21(22 ... 2n);Increase control valve 15 and control valve 16 after the withdrawal of currency from circulation water pipe 14 is engineered;Described plus row pressure hydraulic piping 51 (52 ... 5n) be connected to steam again water pipe 14, and access drainage system general pipeline 21(22 ... 2n) on access well 6(62 ... 6n);The city 1 control room of political affairs drainage pumping plant increases intelligence control system, accesses well 6(62 ... 6n) in installation deposit monitor system, before pumping plant Water quality monitoring system is installed in pond 11.
Washing control valve door 15 and the second control valve 16 for switching rainfall pumping station test run mode, pumping plant puts river mode and Pipe flushing mode.The washing control valve door 15 is closed, when the second control valve 16 is opened and third control valve door 17 is closed, Enter the test run mode of pumping plant daily maintenance when rainwater 13 turn on pump of pump group;Washing control valve door 15 is closed, the second control valve 16 It closes, third control valve door 17 enters rainy day pumping plant when opening and puts river mode;Washing control valve door 15 is opened, the second control valve 16 close, and third control valve door 17 enters pipe flushing mode when closing.
Add row pressure hydraulic piping 51,52,5n quoted from steaming again water pipe 14 in municipal drainage pumping plant 1, and adds row pressure hydraulic piping 51, switch valve 52, is installed respectively on 5n;Described plus row pressure hydraulic piping 51(52 ... 5n) it connects and steams again water pipe 14 and drainage system General pipeline 21(22 ... 2n) on access well 61(62 ... 6n);The access well 61(62 ... 6n) it is drainage system general pipeline 21(22 ... Inspection shaft on 2n) accesses after engineered and adds row pressure hydraulic piping 51(52 ... 5n), access well 61(62 ... 6n) according to deodorizing facility Prevent foul smell during circulation flushing scattered excessive.
Rainwater, combined sewage, hybrid junction sewage in plot and branch pipe import drainage system general pipeline 21(22 ... 2n), and convey To the Forebay of Pumping Station 11 of municipal drainage pumping plant 1.The siltation in pipeline forms pipeline deposition to pollutant in water during transportation Object, the wastewater pollutants concentration for reaching Forebay of Pumping Station 11 is lower, cuts dirty pump group 12 and sewage of low concentration is only delivered to sewerage. When municipal drainage pumping plant 1, which opens rainy day pumping plant, puts river mode, deposit can enter river with current scour in pipeline;
After pipe flushing mode starts, rainwater pump group 13 extracts the water in Forebay of Pumping Station 11, by steaming again water pipe 14 and adding row pressure Hydraulic piping 51(52 ... 5n), be delivered to drainage system general pipeline 21(22 ... 2n) on access well 61(62 ... 6n), connect to be promoted Enter well 61(62 ... 6n) flow velocity into the pipeline of 11 drainage system general pipeline 21(22 ... 2n of Forebay of Pumping Station), to tube bottom deposit into Row washes away, and pollutant concentration quickly increases in pipeline, and pollutant flows through Forebay of Pumping Station → withdrawal of currency from circulation water pipe → plus row pressure power with water flow Pipeline → drainage system general pipeline circulation;It cuts dirty pump group 12 and keeps continuous service, high-concentration sewage is delivered to municipal sewage system System;Access well 61(62 ... 6n) sewage of low concentration of upstream is supplemented into circle irrigation system and continues to wash away.
It can realize and drainage system general pipeline 21,22 ... 2n are rinsed simultaneously by the switching of control valve, it can also be with Drainage system general pipeline 21,22 ... 2n are rinsed in realization stage by stage.
It is comprised the following steps using the method that reduction pipeline deposit of the invention realizes that pumping plant puts pollution river reduction:
Step 1, when thickness of deposits reaches the 20% of duct height in pipeline (ratio can be adjusted according to system actual conditions), Intelligence control system starts flushing process, opening controlling valve door 15, closing control valve 16, closing control valve 17, unlatching rain 1 ~ 2,13 moderate rain water pump of water pump group.
Step 2, it cuts dirty pump group 12 and opens normal operation, continue Forebay of Pumping Station middle and high concentration sewage transport to municipal sewage System.
Step 3, it after 11 water quality of Forebay of Pumping Station is gradually decreased and tended towards stability, can be selected according to deposit situation in pipeline The rainwater pump for closing rainwater pump group 13, terminates to rinse;Cutting dirty pump group can choose whether to continue to run according to water level in system.
Drainage system general pipeline 21,22 ... 2n can be rinsed simultaneously by the switching of control valve, it can also be to row Water system general pipeline 21,22 ... 2n are rinsed stage by stage, are realized the synchronous developing be responsible for drainage system multichannel and are alternately rinsed.
In the present invention, the Municipal pumping stations rainwater pump group, section dirty pump group, Forebay of Pumping Station are that general Municipal pumping stations are set substantially It applies, can be applied to pipeline hydraulic rinse-system without transformation.
It is described to steam again the basic facilities that water pipe is general pumping plant, it is debugged for pumping plant, pumping plant does not use generally after building up.Through It is applied to pipeline hydraulic rinse-system after transformation, improves project benefit.The withdrawal of currency from circulation water pipe adds the at access Forebay of Pumping Station Two control valves, and increase bypass and add row pressure hydraulic piping for connecting.The multichannel add row pressure hydraulic piping from pumping plant lay to Access well on each road general pipeline of drainage system;Buried depth of pipeline, Guan Weike are freely adjusted according to the actual situation.The access well is row Inspection shaft on water system general pipeline, selection are transformed with pumping plant distance, the suitable inspection shaft of transformation difficulty, access plus row pressure power Pipeline, and in well indoor location deodorizing facility, foul smell dissipates excessive when preventing rinse-system from running.
Rainwater pump of different sizes is set, and small pump lift is big, flow is small, opens small pump impulse and washes the lesser system master of caliber It is longer to rinse distance for pipe;Big pump lift is small, flow is big, to rinse the biggish system manifold of caliber, rinses distance relatively It is short.
The intelligence control system includes deposit monitoring, Forebay of Pumping Station water quality monitoring system etc. in pipeline.The intelligence The system of can control can automatically turn on according to pipeline deposition, terminate flushing process.
Carrying out pipe flushing in dry days is to carry out pipe flushing using idle rainwater pump group in non-rainfall day;The rainwater Pump group configuration rainwater pump can be steam again on water pipe and newly-built pressure pipeline access general pipeline from drawing water and passing through in Forebay of Pumping Station Inspection shaft realizes the flushing to deposit in access well to Forebay of Pumping Station segment pipe;The rainwater pump conveying energy of the rainwater pump group Power is strong, can increase pipe flow speed in drainage system general pipeline, is conducive to washing away for deposit in pipeline.
Circulation flushing refers to that deposit can uniformly mix after washing away in pipeline in pipeline, and defeated via drainage system general pipeline It send to Forebay of Pumping Station;Water in the Forebay of Pumping Station is taken by rainwater pump group rainwater pumping, defeated via withdrawal of currency from circulation water pipe and pressure pipeline It send to access well.It moves in circles through this, Forebay of Pumping Station water pollutant concentration increases;Described section of dirty pump group continuous service, will be high Concentration sewage transport is to urban sewage system, and low concentration of water enters back into the circulatory system before accessing well;By long-play, follow Concentration of wastewater gradually reduces in ring rinse-system;Pipeline deposit is washed completely substantially in system manifold after access well.
After Forebay of Pumping Station water quality tends towards stability, i.e., deposit can stop recycling after washing away completely in pipeline after access well System operation, energy saving;If long-time Municipal pumping stations rainwater pump group does not drive to put river, intelligent control after circulation flushing System will restart flushing process.
Pipeline deposition fraction is lower when opening rinse-system, and the open frequency of automated development is higher, and deposit cuts down effect Fruit is more preferable, but energy consumption is higher;Pipeline deposition fraction is higher when opening rinse-system, and the open frequency of automated development is lower, energy Consumption is lower, but deposit reduction effect is weaker.
Described plus row pressure hydraulic piping is laid to the access well on each road general pipeline of drainage system, can be with by valve transfer It realizes that multiloop loop system general pipeline is rinsed simultaneously, each road supervisor also may be implemented and alternately rinse.
Described plus row pressure hydraulic piping length can be responsible for caliber difference according to multiloop loop system, be configured, supervisor is managed The small general pipeline of diameter, corresponding plus row pressure hydraulic piping length are long;The general pipeline big for supervisor's caliber, corresponding plus row pressure hydraulic piping length phase To shorter.
The pipe flushing system is adapted to separate sewage system and combined drainage system.For drainage system System, flow is in early evening peak (morning peak is about 7:00 ~ 9:00, and evening peak is about 17:00 ~ 20:00) flow in system main pipe Higher, concentration of wastewater is lower, and intelligence control system reduces circle irrigation system and rinse according to the dry velocity in pipes of system, concentration of wastewater Intensity, energy saving restore backwash rate after flow velocity in pipeline reduces;For separate flow system, the initial stage of 3 ~ 8mm before rainfall The pollutant that rainwater generates can enter storm sewer, and (general 60 ~ 75% rainfall is light rain) end rainfall pumping station is not opened when light rain It pumps, the pollutant in initial rainwater can deposit in system main pipe, can increase circulating flushing by intelligence control system after the rain Intensity is washed, deposit is effectively washed away;In addition it can pass through facility scale and the facility rear end of shutting off in amplification rainfall pumping station Pipe capacity (processing capacity etc. including sewage treatment facility) accelerates the speed that forebay water quality tends towards stability, and reduces The time of flushing process reduces energy consumption.
The present invention by cut down pipeline deposit realize pumping plant put river pollute reduced method maximum possible be utilized it is built Urban operating mechanism, avoid tearing open greatly build in large scale under the premise of, strive with smaller project inputs, realize in a short time and river dirt is put to pumping plant Dye control effectively.For caliber DN3600, the system manifold that about 1.6 kilometers of length was rushed by 10 hours or so pipelines Wash, can cut down wash away in range 80% or more pipeline deposit.
It is discussed in detail although the contents of the present invention have passed through above preferred embodiment, but it should be appreciated that above-mentioned Description is not considered as limitation of the present invention.After those skilled in the art have read above content, for of the invention A variety of modifications and substitutions all will be apparent.Therefore, protection scope of the present invention should be limited to the appended claims.

Claims (7)

1. a kind of be responsible for the automatic method for removing pipeline deposit suitable for multichannel, municipal drainage pumping plant includes Forebay of Pumping Station, cuts Dirty pump group, rainwater pump group, Forebay of Pumping Station are connected with multiple drainage system general pipeline, and Forebay of Pumping Station is respectively connected to cut dirt by pipeline Pump group and rainwater pump group, are additionally provided with withdrawal of currency from circulation water pipe between Forebay of Pumping Station and rainwater pump group;It is arranged on each drainage system general pipeline One access well, the access well are connect by adding row pressure hydraulic piping with water pipe is steam again;Described plus row pressure hydraulic piping and access well it Between be equipped with washing control valve door, between withdrawals of currency from circulation water pipe and the Forebay of Pumping Station be equipped with the second control valve, the rainwater pump group with Third control valve door is equipped between river;
The automatic removing pipeline deposit method comprises the following steps:
Step 1, when thickness of deposits reaches setting value in drainage system general pipeline, the deposit in access well monitors system Control system is transmitted signals to, washing control valve door is opened, closes the second control valve, closes third control valve door, is opened 1 or more rainwater pumps in rainwater pump group;
Step 2, it cuts dirty pump group and opens normal operation, continue Forebay of Pumping Station middle and high concentration sewage transport to urban sewage system;
Step 3, after Forebay of Pumping Station water quality is gradually decreased and tended towards stability, water quality monitoring system transmits signals to pumping plant control System closes the rainwater pump of rainwater pump group, and closing control valve, terminates to rinse.
2. the automatic method for removing pipeline deposit as described in claim 1, which is characterized in that described plus row pressure hydraulic piping is adopted With steel pipe, ductile iron pipe, plastic tube etc..
3. the automatic method for removing pipeline deposit as described in claim 1, which is characterized in that setting deodorization fills in access well It sets toxic and harmful gas when preventing the circulatory system from running and dissipates and overflow.
4. the as described in claim 1 automatic method for removing pipeline deposit, which is characterized in that drainage system general pipeline not Multiple access wells are set with position, and multichannel is set and adds row pressure hydraulic piping to the multiple access well, it is real by the control of valve Now to drainage system general pipeline simultaneously or timesharing flushing, cut down pipeline in deposit.
5. the as described in claim 1 automatic method for removing pipeline deposit, which is characterized in that drainage system general pipeline caliber compared with When big, submersible agitator is installed in the inspection shaft of drainage system general pipeline, deposit is promoted to wash away, accelerates circulation flushing process.
6. the automatic method for removing pipeline deposit as described in claim 1, which is characterized in that special according to Municipal pumping stations water pump Property, be arranged different length and caliber plus row pressure hydraulic piping.
7. the automatic method for removing pipeline deposit as described in claim 1, which is characterized in that the peace in drainage system general pipeline The flow monitoring device of dress, according to the operating condition that rainfall pumping station, section dirt pump in flow velocity adjustment pumping plant in pipeline.
CN201811157997.6A 2018-09-30 2018-09-30 A method of automatic removing pipeline deposit is responsible for suitable for multichannel Pending CN109235604A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811157997.6A CN109235604A (en) 2018-09-30 2018-09-30 A method of automatic removing pipeline deposit is responsible for suitable for multichannel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811157997.6A CN109235604A (en) 2018-09-30 2018-09-30 A method of automatic removing pipeline deposit is responsible for suitable for multichannel

Publications (1)

Publication Number Publication Date
CN109235604A true CN109235604A (en) 2019-01-18

Family

ID=65054233

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811157997.6A Pending CN109235604A (en) 2018-09-30 2018-09-30 A method of automatic removing pipeline deposit is responsible for suitable for multichannel

Country Status (1)

Country Link
CN (1) CN109235604A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112726734A (en) * 2020-12-28 2021-04-30 湖南省园景生态园林有限公司 Environment-friendly garden landscape rainwater collection and circulation control system and method
CN113522895A (en) * 2021-07-20 2021-10-22 西安交通大学 Pipeline flushing method and device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112726734A (en) * 2020-12-28 2021-04-30 湖南省园景生态园林有限公司 Environment-friendly garden landscape rainwater collection and circulation control system and method
CN113522895A (en) * 2021-07-20 2021-10-22 西安交通大学 Pipeline flushing method and device

Similar Documents

Publication Publication Date Title
CN109235602A (en) A kind of pipeline deposit automatic clearing apparatus steaming again water pipe by pumping plant
CN106759073B (en) Single river channel Overspill type water environment treatment system and method
CN206859397U (en) The flushing desilting system of gravity stream sewage pipe in pipe gallery
CN104196118B (en) A kind of pond automatic vacuum rinses Accrete clearing device and method
CN109629657A (en) A kind of multiple-effect multiplication storage pond
CN111932403A (en) Urban sewage pipe network and water environment quality-improving and efficiency-increasing technology integration method
CN203684373U (en) Equipment for improving urban waterlogging prevention standard and controlling water pollution
CN106988401A (en) A kind of face groundwater pollution control for combined flow system pipe network system
CN109235604A (en) A method of automatic removing pipeline deposit is responsible for suitable for multichannel
CN106958227A (en) The governing system and method for a kind of tidal black-odor riverway of bilateral
CN103669547A (en) Method and equipment for raising urban water-logging prevention standard and controlling water pollution
CN106545069A (en) A kind of series connection of improvement city black and odorous water cuts dirt and receives pipe method
CN210086451U (en) Multiple-effect multiplication regulation and storage tank
CN105178425B (en) Cities and towns water drainage, moisturizing, water-change pump station hinge
CN106223455A (en) A kind of drainage pipeline automatic dash turnover panel dams flusher
CN109235603A (en) A method of water pipe is steam again by pumping plant and realizes automatic removing pipeline deposit
CN109235605A (en) It is a kind of to be responsible for the automatic device for removing pipeline deposit suitable for multichannel
CN206245390U (en) A kind of culvert pipe water channeling type pumping plant
CN211172272U (en) System for flushing and shunting municipal sewage pipe
CN109629656A (en) A method of realizing that municipal drainage pumping plant puts river contamination control using storage pond
CN209523268U (en) It is a kind of to be responsible for the automatic device for removing pipeline deposit suitable for multichannel
CN209523269U (en) A kind of pipeline deposit automatic clearing apparatus steaming again water pipe by pumping plant
CN114045915B (en) System that dams that has function of washing to rain sewage deposit in pipe network
CN209620224U (en) It is a kind of to cut dirty box culvert-type Vatch basin for city river
CN106592748A (en) Storage and utilization system for underwater initial rainwater

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination