CN109208586A - A kind of slope protection pile construction method - Google Patents

A kind of slope protection pile construction method Download PDF

Info

Publication number
CN109208586A
CN109208586A CN201811222180.2A CN201811222180A CN109208586A CN 109208586 A CN109208586 A CN 109208586A CN 201811222180 A CN201811222180 A CN 201811222180A CN 109208586 A CN109208586 A CN 109208586A
Authority
CN
China
Prior art keywords
construction
steel reinforcement
reinforcement cage
drilling
drilling machine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811222180.2A
Other languages
Chinese (zh)
Inventor
陈宏伟
丁明辉
吕静
黄明亮
徐恒雷
吴浩
高亚飞
姜龙
徐飞
胡文超
王鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA NATIONAL GOLD GROUP CONSTRUCTION Co Ltd
Original Assignee
CHINA NATIONAL GOLD GROUP CONSTRUCTION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA NATIONAL GOLD GROUP CONSTRUCTION Co Ltd filed Critical CHINA NATIONAL GOLD GROUP CONSTRUCTION Co Ltd
Priority to CN201811222180.2A priority Critical patent/CN109208586A/en
Publication of CN109208586A publication Critical patent/CN109208586A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/36Concrete or concrete-like piles cast in position ; Apparatus for making same making without use of mouldpipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/207Securing of slopes or inclines with means incorporating sheet piles or piles

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a kind of slope protection pile construction method, specific steps are as follows: the preparation before carrying out drilling machine construction first;Secondly drilling machine drilling and forming hole;Then guncreting;Finally, fabrication of reinforcing cage and vibration are put, specific steps are as follows: fabrication of reinforcing cage should construct by design drawing, and be able to satisfy requirement;The steel reinforcement cage made is placed on smooth location, convenient for hanging construction;Steel reinforcement cage, vibrating conduit, vibration hammer are assembled in advance, are lifted to aperture together, starting vibration hammer is slowly by steel reinforcement cage vibration decentralization to requiring absolute altitude after the completion of contraposition.Beneficial effects of the present invention: the present invention using the dry pore-forming of long-spiral drilling machine, guncreting, fall plug in cage by the way of construct, this form of construction work had both reduced a large amount of discharges of live mud, construction speed is improved again, while also maintaining the civilization of site operation clean and tidy;This method has the advantages that design is reasonable, construction procedure is simple, while ensure that the accuracy and construction quality of construction.

Description

A kind of slope protection pile construction method
Technical field
The present invention relates to technical field of building construction, it particularly relates to a kind of slope protection pile construction method.
Background technique
With the fast development of construction industry, the construction of skyscraper and the utilization of the underground space have stimulated deep-foundation pit engineering The development of excavation and support technology.Wherein, for major comonomer silo building, single pile foundation construction with regard to product coal slot storehouse just has Three types: i.e. foundation pile, slope protection pile, friction pile etc., common construction method are to use percussive drill, but there are one for impact drill Fixed disadvantage is exactly that mud capacity is big, and construction efficiency is low, and construction precision is poor, therefore has been unable to meet the demand in market.
Summary of the invention
For above-mentioned technical problem in the related technology, the present invention proposes a kind of slope protection pile construction method, can overcome existing There is the above-mentioned deficiency of technology.
To realize the above-mentioned technical purpose, the technical scheme of the present invention is realized as follows:
A kind of slope protection pile construction method, comprising the following steps:
S1: the preparation before carrying out drilling machine construction;
S2: drilling machine drilling and forming hole;
S3: guncreting;
S4: fabrication of reinforcing cage and vibration are put, specific steps are as follows:
S4.1: fabrication of reinforcing cage should construct by design drawing, and be able to satisfy requirement;
S4.2: the steel reinforcement cage made is placed on smooth location, convenient for hanging construction;
S4.3: on-the-spot record personnel will select steel reinforcement cage by design requirement according to pile No., and make a record;
S4.4: in advance assembling steel reinforcement cage, vibrating conduit, vibration hammer, is lifted to aperture together, starting vibration after the completion of contraposition Hammer is slowly by steel reinforcement cage vibration decentralization to requiring absolute altitude.
Further, in step sl, the described preparation carried out before drilling machine construction specifically includes the following steps:
S1.1: carrying out construction site smooth, and to guarantee drilling machine smooth running, positioning stablity, pile body is vertical;
S1.2: it discharges stake position and applies for checking and examination;
S1.3: reserved Construction traffic access roads guarantee that its traveling is unobstructed;
S1.4: examining steel reinforcement cage, prepares stand-by;
S1.5: drilling machine utilizes theodolite to examine drilling rod verticality before spudding in good hole location, and pile body is in straight line after guaranteeing pile On.
Further, in step s 2, the specific steps of the drilling machine drilling and forming hole include:
S2.1: drilling machine is ready, connects concrete pump pipe, debugs ground pump running parameter, using mortar lubrication piping, examines and hangs down After straight degree, can spud in pore-forming;
S2.2: drilling parameter should be selected and be adjusted according to strata condition;
S2.3: when drilling construction, in time being cleared boring mud using crowd shovel, guarantees place neat and tidy;
S2.4: drilling stops boring after reaching requirement hole depth.
Further, in step s3, the specific steps of the guncreting include:
S3.1: according to the plan of needs concrete amount of drilling;
S3.2: the concrete for reaching scene is checked;
S3.3: qualified concrete is examined to carry out pressure filling.
Further, in step S4.1, the fabrication of reinforcing cage should construct by design drawing, and be able to satisfy requirement Refer to that main reinforcement spacing tolerance ± 10mm, stirrup spacing or spiral bar spacing tolerance ± 20mm, steel reinforcement cage diameter allow Deviation ± 10mm, length of reinforcing cage tolerance ± 50mm.
Further, start vibration hammer in step S4.4, after the completion of the contraposition and steel reinforcement cage is slowly vibrated into decentralization To requiring absolute altitude to be in steel reinforcement cage decentralization using level elevation control, error is no more than ± 5cm, and steel reinforcement cage is placed in hole It is intermediate.
Beneficial effects of the present invention: the present invention using the dry pore-forming of long-spiral drilling machine, guncreting, fall plug in cage by the way of It constructs, this form of construction work had not only reduced a large amount of discharges of live mud, but also improved construction speed, while also maintaining existing The civilization of field construction is clean and tidy;This method has the advantages that design is reasonable, construction procedure is simple, while ensure that the accuracy of construction And construction quality.
Detailed description of the invention
It in order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, below will be to institute in embodiment Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the invention Example, for those of ordinary skill in the art, without creative efforts, can also obtain according to these attached drawings Obtain other attached drawings.
Fig. 1 is a kind of flow chart of the slope protection pile construction method described according to embodiments of the present invention.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art's every other embodiment obtained belong to what the present invention protected Range.
As shown in Figure 1, a kind of slope protection pile construction method described according to embodiments of the present invention, comprising the following steps:
S1: the preparation before carrying out drilling machine construction;
S2: drilling machine drilling and forming hole;
S3: guncreting;
S4: fabrication of reinforcing cage and vibration are put, specific steps are as follows:
S4.1: fabrication of reinforcing cage should construct by design drawing, and be able to satisfy requirement;
S4.2: the steel reinforcement cage made is placed on smooth location, convenient for hanging construction;
S4.3: on-the-spot record personnel will select steel reinforcement cage by design requirement according to pile No., and make a record;
S4.4: in advance assembling steel reinforcement cage, vibrating conduit, vibration hammer, is lifted to aperture together, starting vibration after the completion of contraposition Hammer is slowly by steel reinforcement cage vibration decentralization to requiring absolute altitude.
In one embodiment, in step sl, the described preparation carried out before drilling machine construction specifically includes following step It is rapid:
S1.1: carrying out construction site smooth, and to guarantee drilling machine smooth running, positioning stablity, pile body is vertical;
S1.2: it discharges stake position and applies for checking and examination;
S1.3: reserved Construction traffic access roads guarantee that its traveling is unobstructed;
S1.4: examining steel reinforcement cage, prepares stand-by;
S1.5: drilling machine utilizes theodolite to examine drilling rod verticality before spudding in good hole location, and pile body is in straight line after guaranteeing pile On.
In one embodiment, in step s 2, the specific steps of the drilling machine drilling and forming hole include:
S2.1: drilling machine is ready, connects concrete pump pipe, debugs ground pump running parameter, using mortar lubrication piping, examines and hangs down After straight degree, can spud in pore-forming;
S2.2: drilling parameter should be selected and be adjusted according to strata condition;
S2.3: when drilling construction, in time being cleared boring mud using crowd shovel, guarantees place neat and tidy;
S2.4: drilling stops boring after reaching requirement hole depth.
In one embodiment, in step s3, the specific steps of the guncreting include:
S3.1: according to the plan of needs concrete amount of drilling;
S3.2: the concrete for reaching scene is checked;
S3.3: qualified concrete is examined to carry out pressure filling.
In one embodiment, in step S4.1, the fabrication of reinforcing cage should construct by design drawing, and energy It meets the requirements and refers to main reinforcement spacing tolerance ± 10mm, stirrup spacing or spiral bar spacing tolerance ± 20mm, steel reinforcement cage Diameter tolerance ± 10mm, length of reinforcing cage tolerance ± 50mm.
In one embodiment, start vibration hammer in step S4.4, after the completion of the contraposition slowly by steel reinforcement cage Vibration decentralization is in steel reinforcement cage decentralization using level elevation control to absolute altitude is required, and error is no more than ± 5cm, and steel reinforcement cage It is placed among hole.
In order to facilitate understanding above-mentioned technical proposal of the invention, below by way of in specifically used mode to of the invention above-mentioned Technical solution is described in detail.
When specifically used, present invention brill carries out the preparation before drilling machine construction first;Specifically: first to construction site into Row is smooth, and to guarantee drilling machine smooth running, positioning stablity, pile body is vertical;Then it discharges stake position and applies for checking and examination;Secondly, reserved construction Vehicles while passing road guarantees that its traveling is unobstructed, then examines steel reinforcement cage, prepares stand-by;Finally, drilling machine is to good hole location, before spudding in Drilling rod verticality is examined using theodolite, point-blank, stake position error is not more than 100mm to pile body, vertically after guaranteeing pile It spends error and is not more than 1%.
Secondly, drilling machine drilling and forming hole;After drilling machine is ready, concrete pump pipe is connected, debugs ground pump running parameter, benefit With mortar lubrication piping, after examining verticality, can spud in pore-forming;The drilling parameter of drilling machine should be selected according to strata condition And adjusting, for example when entering layer of sand and boulder bed, should suitably slow down penetration rate, guarantee that hole wall is stablized;In drilling construction, Boring mud is cleared in time using crowd shovel, guarantees place neat and tidy, is conducive to construct in next step;Drilling is stopped after reaching requirement hole depth It bores.
Again, guncreting;The first step, plan concrete amount: according to the concrete condition of drilling such as features as poor geologic condition, collapse or There is underpass etc., plan concrete side can expand fullness coefficient when measuring, to meet the casting designed elevation requirement of pile body concrete;Second step, Concrete inspection: having to conscientiously check to live concrete, and rule of thumb, whether the concrete for checking scene has good workability, Whether slump meets the requirements (180~220mm), and whether concrete isolates, and whether there is or not agglomerate, large-particle-size aggregate etc., nonconforming Never allow to be poured;Third step, concrete pressure fill: examine qualified concrete to pass through in drilling rod press-in hole using ground pump through pump line, Brill is mentioned in guncreting, until concrete surface reaches design height, in sand bed when guncreting, should suitably be slowed down and be mentioned Drilling speed degree prevents from forming undergauge in sand bed;Concrete pouring should be more than 50~80cm of designed elevation, in order to guarantee stake top concrete Label meets design requirement;Flexibly processing according to field condition thus;4th step, concrete test block production: each casting machine-team must not Less than 1 group, every group 3.
Finally, fabrication of reinforcing cage and vibration are put;Fabrication of reinforcing cage should construct by design drawing, and be able to satisfy corresponding specification and want It asks, ± 10 mm of main reinforcement spacing tolerance, ± 20 mm of stirrup spacing or spiral bar spacing tolerance, steel reinforcement cage diameter allows ± 10 mm of deviation, ± 50 mm of length of reinforcing cage tolerance, the steel reinforcement cage made should put a smooth location near the scene, just It constructs in hanging;Fabrication of reinforcing cage should be first carried out before boring drill is marched into the arena, and guarantee to examine qualification at least 10 at the scene Steel reinforcement cage is spare;On-the-spot record personnel will select steel reinforcement cage by design requirement according to pile No., and make a record;Before lifting by crane steel reinforcement cage It should be by the steel reinforcement cage of quality inspection (never allowing not to be put into hole by what is checked);The jail of suspension centre should be first checked for when lifting Gu the adjunct on degree and cage;Hoistman should be noted that the instruction of commander's hand, gently lift by crane;Steel reinforcement cage, vibration are led in advance Pipe, vibration hammer assemble, and are lifted to aperture together, steel reinforcement cage is slowly vibrated decentralization to requirement by starting vibration hammer after the completion for contraposition Absolute altitude;Level elevation control is utilized when steel reinforcement cage is transferred, error is no more than ± 5cm, and steel reinforcement cage is placed among hole.
In conclusion the present invention using the dry pore-forming of long-spiral drilling machine, guncreting, fall plug in cage by the way of apply Work, this form of construction work had not only reduced a large amount of discharges of live mud, but also improved construction speed, while also maintaining site operation Civilization it is clean and tidy;This method has the advantages that design is reasonable, construction procedure is simple, while ensure that the accuracy and construction of construction Quality.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Within mind and principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.

Claims (6)

1. a kind of slope protection pile construction method, which comprises the following steps:
S1: the preparation before carrying out drilling machine construction;
S2: drilling machine drilling and forming hole;
S3: guncreting;
S4: fabrication of reinforcing cage and vibration are put, specific steps are as follows:
S4.1: fabrication of reinforcing cage should construct by design drawing, and be able to satisfy requirement;
S4.2: the steel reinforcement cage made is placed on smooth location, convenient for hanging construction;
S4.3: on-the-spot record personnel will select steel reinforcement cage by design requirement according to pile No., and make a record;
S4.4: in advance assembling steel reinforcement cage, vibrating conduit, vibration hammer, is lifted to aperture together, starting vibration after the completion of contraposition Hammer is slowly by steel reinforcement cage vibration decentralization to requiring absolute altitude.
2. a kind of slope protection pile construction method according to claim 1, which is characterized in that in step sl, described carries out Preparation before drilling machine construction specifically includes the following steps:
S1.1: carrying out construction site smooth, and to guarantee drilling machine smooth running, positioning stablity, pile body is vertical;
S1.2: it discharges stake position and applies for checking and examination;
S1.3: reserved Construction traffic access roads guarantee that its traveling is unobstructed;
S1.4: examining steel reinforcement cage, prepares stand-by;
S1.5: drilling machine utilizes theodolite to examine drilling rod verticality before spudding in good hole location, and pile body is in straight line after guaranteeing pile On.
3. a kind of slope protection pile construction method according to claim 1, which is characterized in that in step s 2, the drilling machine The specific steps of drilling and forming hole include:
S2.1: drilling machine is ready, connects concrete pump pipe, debugs ground pump running parameter, using mortar lubrication piping, examines and hangs down After straight degree, can spud in pore-forming;
S2.2: drilling parameter should be selected and be adjusted according to strata condition;
S2.3: when drilling construction, in time being cleared boring mud using crowd shovel, guarantees place neat and tidy;
S2.4: drilling stops boring after reaching requirement hole depth.
4. a kind of slope protection pile construction method according to claim 1, which is characterized in that in step s3, the pressure fills The specific steps of concrete include:
S3.1: according to the plan of needs concrete amount of drilling;
S3.2: the concrete for reaching scene is checked;
S3.3: qualified concrete is examined to carry out pressure filling.
5. a kind of slope protection pile construction method according to claim 1, which is characterized in that described in step S4.1 Fabrication of reinforcing cage should construct by design drawing, and be able to satisfy requirement and refer to main reinforcement spacing tolerance ± 10mm, stirrup spacing or Spiral bar spacing tolerance ± 20mm, steel reinforcement cage diameter tolerance ± 10mm, length of reinforcing cage tolerance ± 50mm.
6. a kind of slope protection pile construction method according to claim 1, which is characterized in that described in step S4.4 Steel reinforcement cage vibration decentralization is slowly that level is utilized when steel reinforcement cage is transferred to absolute altitude is required by starting vibration hammer after the completion of contraposition Elevation control, error is no more than ± 5cm, and steel reinforcement cage is placed among hole.
CN201811222180.2A 2018-10-19 2018-10-19 A kind of slope protection pile construction method Pending CN109208586A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811222180.2A CN109208586A (en) 2018-10-19 2018-10-19 A kind of slope protection pile construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811222180.2A CN109208586A (en) 2018-10-19 2018-10-19 A kind of slope protection pile construction method

Publications (1)

Publication Number Publication Date
CN109208586A true CN109208586A (en) 2019-01-15

Family

ID=64981430

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811222180.2A Pending CN109208586A (en) 2018-10-19 2018-10-19 A kind of slope protection pile construction method

Country Status (1)

Country Link
CN (1) CN109208586A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109914430A (en) * 2019-04-03 2019-06-21 杭州萌友服饰有限公司 A kind of anti-collapse supporting construction in heavy construction deep basal pit side
CN111926821A (en) * 2020-07-13 2020-11-13 北京城建勘测设计研究院有限责任公司 Construction method of novel slope protection pile

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108612087A (en) * 2018-05-10 2018-10-02 江苏地基工程有限公司 A kind of novel long screw auger pore pressure fills the construction technology of support pile

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108612087A (en) * 2018-05-10 2018-10-02 江苏地基工程有限公司 A kind of novel long screw auger pore pressure fills the construction technology of support pile

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109914430A (en) * 2019-04-03 2019-06-21 杭州萌友服饰有限公司 A kind of anti-collapse supporting construction in heavy construction deep basal pit side
CN111926821A (en) * 2020-07-13 2020-11-13 北京城建勘测设计研究院有限责任公司 Construction method of novel slope protection pile

Similar Documents

Publication Publication Date Title
CN107524142A (en) A kind of holing with slurry wall protection cast-in-place pile construction method
CN102691294B (en) Construction method of underground continuous wall
CN106400782B (en) A kind of construction method for going along with sb. to guard him hole-drilling interlocking pile using rotary drilling rig construction foundation pit
CN105178288A (en) Construction method of underground continuous wall below viaduct
CN104532813B (en) A kind of aquatic building operation platform and erection method, using method
CN103195058B (en) Be convenient to solution cavity and grow the method that regional bridge pier adopts many casings to construct
CN103088814A (en) Rotary drilling rig coordinated with percussion drill hole-forming construction method
CN110185844A (en) Shallow earthing pipe-jacking with large diameter construction method
CN110331992A (en) A kind of hole daguanpeng construction method
CN109555116A (en) A kind of high density karst intense development area fully-sleeved filled pile construction method
CN105275381A (en) Drilling construction method for water-rich cobble stratum by utilizing impact drill
CN107246007B (en) A kind of CFG of construction method
CN104264663A (en) Hard cutting construction technology for secant piles
CN103741963A (en) Industrial plant foundation strengthening method
CN104164881A (en) Piling wall overlapping cantilever foundation pit support construction method and structure
CN204174625U (en) The superimposed cantilever foundation pit supporting construction of a kind of piling wall
CN106988305A (en) A kind of pile-column pier construction method of underground integrated molding
CN104264708A (en) Sequential construction technology for underground diaphragm wall of highline rotational-flow pond
CN109208586A (en) A kind of slope protection pile construction method
CN106284311B (en) A kind of dry efficient construction technology of pore-forming cast-in-place concrete pile of rotary drilling rig
CN110258512A (en) It constructs in a kind of basement rock the method for diaphram wall
CN110331715A (en) A kind of construction method of underground continuous wall in urban construction
CN110725163B (en) Composite roadbed device based on existing rail transit roadbed and pile construction method
CN204040021U (en) Large diameter pile construction equipment system in city underground engineering tunneling pilot tunnel
CN110924401A (en) Construction foundation pit supporting mode for combined arching and bearing of mixing piles and cast-in-place piles

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190115