CN109208586A - A kind of slope protection pile construction method - Google Patents
A kind of slope protection pile construction method Download PDFInfo
- Publication number
- CN109208586A CN109208586A CN201811222180.2A CN201811222180A CN109208586A CN 109208586 A CN109208586 A CN 109208586A CN 201811222180 A CN201811222180 A CN 201811222180A CN 109208586 A CN109208586 A CN 109208586A
- Authority
- CN
- China
- Prior art keywords
- construction
- steel reinforcement
- reinforcement cage
- drilling
- drilling machine
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/36—Concrete or concrete-like piles cast in position ; Apparatus for making same making without use of mouldpipes or other moulds
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
- E02D17/207—Securing of slopes or inclines with means incorporating sheet piles or piles
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
The invention discloses a kind of slope protection pile construction method, specific steps are as follows: the preparation before carrying out drilling machine construction first;Secondly drilling machine drilling and forming hole;Then guncreting;Finally, fabrication of reinforcing cage and vibration are put, specific steps are as follows: fabrication of reinforcing cage should construct by design drawing, and be able to satisfy requirement;The steel reinforcement cage made is placed on smooth location, convenient for hanging construction;Steel reinforcement cage, vibrating conduit, vibration hammer are assembled in advance, are lifted to aperture together, starting vibration hammer is slowly by steel reinforcement cage vibration decentralization to requiring absolute altitude after the completion of contraposition.Beneficial effects of the present invention: the present invention using the dry pore-forming of long-spiral drilling machine, guncreting, fall plug in cage by the way of construct, this form of construction work had both reduced a large amount of discharges of live mud, construction speed is improved again, while also maintaining the civilization of site operation clean and tidy;This method has the advantages that design is reasonable, construction procedure is simple, while ensure that the accuracy and construction quality of construction.
Description
Technical field
The present invention relates to technical field of building construction, it particularly relates to a kind of slope protection pile construction method.
Background technique
With the fast development of construction industry, the construction of skyscraper and the utilization of the underground space have stimulated deep-foundation pit engineering
The development of excavation and support technology.Wherein, for major comonomer silo building, single pile foundation construction with regard to product coal slot storehouse just has
Three types: i.e. foundation pile, slope protection pile, friction pile etc., common construction method are to use percussive drill, but there are one for impact drill
Fixed disadvantage is exactly that mud capacity is big, and construction efficiency is low, and construction precision is poor, therefore has been unable to meet the demand in market.
Summary of the invention
For above-mentioned technical problem in the related technology, the present invention proposes a kind of slope protection pile construction method, can overcome existing
There is the above-mentioned deficiency of technology.
To realize the above-mentioned technical purpose, the technical scheme of the present invention is realized as follows:
A kind of slope protection pile construction method, comprising the following steps:
S1: the preparation before carrying out drilling machine construction;
S2: drilling machine drilling and forming hole;
S3: guncreting;
S4: fabrication of reinforcing cage and vibration are put, specific steps are as follows:
S4.1: fabrication of reinforcing cage should construct by design drawing, and be able to satisfy requirement;
S4.2: the steel reinforcement cage made is placed on smooth location, convenient for hanging construction;
S4.3: on-the-spot record personnel will select steel reinforcement cage by design requirement according to pile No., and make a record;
S4.4: in advance assembling steel reinforcement cage, vibrating conduit, vibration hammer, is lifted to aperture together, starting vibration after the completion of contraposition
Hammer is slowly by steel reinforcement cage vibration decentralization to requiring absolute altitude.
Further, in step sl, the described preparation carried out before drilling machine construction specifically includes the following steps:
S1.1: carrying out construction site smooth, and to guarantee drilling machine smooth running, positioning stablity, pile body is vertical;
S1.2: it discharges stake position and applies for checking and examination;
S1.3: reserved Construction traffic access roads guarantee that its traveling is unobstructed;
S1.4: examining steel reinforcement cage, prepares stand-by;
S1.5: drilling machine utilizes theodolite to examine drilling rod verticality before spudding in good hole location, and pile body is in straight line after guaranteeing pile
On.
Further, in step s 2, the specific steps of the drilling machine drilling and forming hole include:
S2.1: drilling machine is ready, connects concrete pump pipe, debugs ground pump running parameter, using mortar lubrication piping, examines and hangs down
After straight degree, can spud in pore-forming;
S2.2: drilling parameter should be selected and be adjusted according to strata condition;
S2.3: when drilling construction, in time being cleared boring mud using crowd shovel, guarantees place neat and tidy;
S2.4: drilling stops boring after reaching requirement hole depth.
Further, in step s3, the specific steps of the guncreting include:
S3.1: according to the plan of needs concrete amount of drilling;
S3.2: the concrete for reaching scene is checked;
S3.3: qualified concrete is examined to carry out pressure filling.
Further, in step S4.1, the fabrication of reinforcing cage should construct by design drawing, and be able to satisfy requirement
Refer to that main reinforcement spacing tolerance ± 10mm, stirrup spacing or spiral bar spacing tolerance ± 20mm, steel reinforcement cage diameter allow
Deviation ± 10mm, length of reinforcing cage tolerance ± 50mm.
Further, start vibration hammer in step S4.4, after the completion of the contraposition and steel reinforcement cage is slowly vibrated into decentralization
To requiring absolute altitude to be in steel reinforcement cage decentralization using level elevation control, error is no more than ± 5cm, and steel reinforcement cage is placed in hole
It is intermediate.
Beneficial effects of the present invention: the present invention using the dry pore-forming of long-spiral drilling machine, guncreting, fall plug in cage by the way of
It constructs, this form of construction work had not only reduced a large amount of discharges of live mud, but also improved construction speed, while also maintaining existing
The civilization of field construction is clean and tidy;This method has the advantages that design is reasonable, construction procedure is simple, while ensure that the accuracy of construction
And construction quality.
Detailed description of the invention
It in order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, below will be to institute in embodiment
Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the invention
Example, for those of ordinary skill in the art, without creative efforts, can also obtain according to these attached drawings
Obtain other attached drawings.
Fig. 1 is a kind of flow chart of the slope protection pile construction method described according to embodiments of the present invention.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, those of ordinary skill in the art's every other embodiment obtained belong to what the present invention protected
Range.
As shown in Figure 1, a kind of slope protection pile construction method described according to embodiments of the present invention, comprising the following steps:
S1: the preparation before carrying out drilling machine construction;
S2: drilling machine drilling and forming hole;
S3: guncreting;
S4: fabrication of reinforcing cage and vibration are put, specific steps are as follows:
S4.1: fabrication of reinforcing cage should construct by design drawing, and be able to satisfy requirement;
S4.2: the steel reinforcement cage made is placed on smooth location, convenient for hanging construction;
S4.3: on-the-spot record personnel will select steel reinforcement cage by design requirement according to pile No., and make a record;
S4.4: in advance assembling steel reinforcement cage, vibrating conduit, vibration hammer, is lifted to aperture together, starting vibration after the completion of contraposition
Hammer is slowly by steel reinforcement cage vibration decentralization to requiring absolute altitude.
In one embodiment, in step sl, the described preparation carried out before drilling machine construction specifically includes following step
It is rapid:
S1.1: carrying out construction site smooth, and to guarantee drilling machine smooth running, positioning stablity, pile body is vertical;
S1.2: it discharges stake position and applies for checking and examination;
S1.3: reserved Construction traffic access roads guarantee that its traveling is unobstructed;
S1.4: examining steel reinforcement cage, prepares stand-by;
S1.5: drilling machine utilizes theodolite to examine drilling rod verticality before spudding in good hole location, and pile body is in straight line after guaranteeing pile
On.
In one embodiment, in step s 2, the specific steps of the drilling machine drilling and forming hole include:
S2.1: drilling machine is ready, connects concrete pump pipe, debugs ground pump running parameter, using mortar lubrication piping, examines and hangs down
After straight degree, can spud in pore-forming;
S2.2: drilling parameter should be selected and be adjusted according to strata condition;
S2.3: when drilling construction, in time being cleared boring mud using crowd shovel, guarantees place neat and tidy;
S2.4: drilling stops boring after reaching requirement hole depth.
In one embodiment, in step s3, the specific steps of the guncreting include:
S3.1: according to the plan of needs concrete amount of drilling;
S3.2: the concrete for reaching scene is checked;
S3.3: qualified concrete is examined to carry out pressure filling.
In one embodiment, in step S4.1, the fabrication of reinforcing cage should construct by design drawing, and energy
It meets the requirements and refers to main reinforcement spacing tolerance ± 10mm, stirrup spacing or spiral bar spacing tolerance ± 20mm, steel reinforcement cage
Diameter tolerance ± 10mm, length of reinforcing cage tolerance ± 50mm.
In one embodiment, start vibration hammer in step S4.4, after the completion of the contraposition slowly by steel reinforcement cage
Vibration decentralization is in steel reinforcement cage decentralization using level elevation control to absolute altitude is required, and error is no more than ± 5cm, and steel reinforcement cage
It is placed among hole.
In order to facilitate understanding above-mentioned technical proposal of the invention, below by way of in specifically used mode to of the invention above-mentioned
Technical solution is described in detail.
When specifically used, present invention brill carries out the preparation before drilling machine construction first;Specifically: first to construction site into
Row is smooth, and to guarantee drilling machine smooth running, positioning stablity, pile body is vertical;Then it discharges stake position and applies for checking and examination;Secondly, reserved construction
Vehicles while passing road guarantees that its traveling is unobstructed, then examines steel reinforcement cage, prepares stand-by;Finally, drilling machine is to good hole location, before spudding in
Drilling rod verticality is examined using theodolite, point-blank, stake position error is not more than 100mm to pile body, vertically after guaranteeing pile
It spends error and is not more than 1%.
Secondly, drilling machine drilling and forming hole;After drilling machine is ready, concrete pump pipe is connected, debugs ground pump running parameter, benefit
With mortar lubrication piping, after examining verticality, can spud in pore-forming;The drilling parameter of drilling machine should be selected according to strata condition
And adjusting, for example when entering layer of sand and boulder bed, should suitably slow down penetration rate, guarantee that hole wall is stablized;In drilling construction,
Boring mud is cleared in time using crowd shovel, guarantees place neat and tidy, is conducive to construct in next step;Drilling is stopped after reaching requirement hole depth
It bores.
Again, guncreting;The first step, plan concrete amount: according to the concrete condition of drilling such as features as poor geologic condition, collapse or
There is underpass etc., plan concrete side can expand fullness coefficient when measuring, to meet the casting designed elevation requirement of pile body concrete;Second step,
Concrete inspection: having to conscientiously check to live concrete, and rule of thumb, whether the concrete for checking scene has good workability,
Whether slump meets the requirements (180~220mm), and whether concrete isolates, and whether there is or not agglomerate, large-particle-size aggregate etc., nonconforming
Never allow to be poured;Third step, concrete pressure fill: examine qualified concrete to pass through in drilling rod press-in hole using ground pump through pump line,
Brill is mentioned in guncreting, until concrete surface reaches design height, in sand bed when guncreting, should suitably be slowed down and be mentioned
Drilling speed degree prevents from forming undergauge in sand bed;Concrete pouring should be more than 50~80cm of designed elevation, in order to guarantee stake top concrete
Label meets design requirement;Flexibly processing according to field condition thus;4th step, concrete test block production: each casting machine-team must not
Less than 1 group, every group 3.
Finally, fabrication of reinforcing cage and vibration are put;Fabrication of reinforcing cage should construct by design drawing, and be able to satisfy corresponding specification and want
It asks, ± 10 mm of main reinforcement spacing tolerance, ± 20 mm of stirrup spacing or spiral bar spacing tolerance, steel reinforcement cage diameter allows
± 10 mm of deviation, ± 50 mm of length of reinforcing cage tolerance, the steel reinforcement cage made should put a smooth location near the scene, just
It constructs in hanging;Fabrication of reinforcing cage should be first carried out before boring drill is marched into the arena, and guarantee to examine qualification at least 10 at the scene
Steel reinforcement cage is spare;On-the-spot record personnel will select steel reinforcement cage by design requirement according to pile No., and make a record;Before lifting by crane steel reinforcement cage
It should be by the steel reinforcement cage of quality inspection (never allowing not to be put into hole by what is checked);The jail of suspension centre should be first checked for when lifting
Gu the adjunct on degree and cage;Hoistman should be noted that the instruction of commander's hand, gently lift by crane;Steel reinforcement cage, vibration are led in advance
Pipe, vibration hammer assemble, and are lifted to aperture together, steel reinforcement cage is slowly vibrated decentralization to requirement by starting vibration hammer after the completion for contraposition
Absolute altitude;Level elevation control is utilized when steel reinforcement cage is transferred, error is no more than ± 5cm, and steel reinforcement cage is placed among hole.
In conclusion the present invention using the dry pore-forming of long-spiral drilling machine, guncreting, fall plug in cage by the way of apply
Work, this form of construction work had not only reduced a large amount of discharges of live mud, but also improved construction speed, while also maintaining site operation
Civilization it is clean and tidy;This method has the advantages that design is reasonable, construction procedure is simple, while ensure that the accuracy and construction of construction
Quality.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention
Within mind and principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.
Claims (6)
1. a kind of slope protection pile construction method, which comprises the following steps:
S1: the preparation before carrying out drilling machine construction;
S2: drilling machine drilling and forming hole;
S3: guncreting;
S4: fabrication of reinforcing cage and vibration are put, specific steps are as follows:
S4.1: fabrication of reinforcing cage should construct by design drawing, and be able to satisfy requirement;
S4.2: the steel reinforcement cage made is placed on smooth location, convenient for hanging construction;
S4.3: on-the-spot record personnel will select steel reinforcement cage by design requirement according to pile No., and make a record;
S4.4: in advance assembling steel reinforcement cage, vibrating conduit, vibration hammer, is lifted to aperture together, starting vibration after the completion of contraposition
Hammer is slowly by steel reinforcement cage vibration decentralization to requiring absolute altitude.
2. a kind of slope protection pile construction method according to claim 1, which is characterized in that in step sl, described carries out
Preparation before drilling machine construction specifically includes the following steps:
S1.1: carrying out construction site smooth, and to guarantee drilling machine smooth running, positioning stablity, pile body is vertical;
S1.2: it discharges stake position and applies for checking and examination;
S1.3: reserved Construction traffic access roads guarantee that its traveling is unobstructed;
S1.4: examining steel reinforcement cage, prepares stand-by;
S1.5: drilling machine utilizes theodolite to examine drilling rod verticality before spudding in good hole location, and pile body is in straight line after guaranteeing pile
On.
3. a kind of slope protection pile construction method according to claim 1, which is characterized in that in step s 2, the drilling machine
The specific steps of drilling and forming hole include:
S2.1: drilling machine is ready, connects concrete pump pipe, debugs ground pump running parameter, using mortar lubrication piping, examines and hangs down
After straight degree, can spud in pore-forming;
S2.2: drilling parameter should be selected and be adjusted according to strata condition;
S2.3: when drilling construction, in time being cleared boring mud using crowd shovel, guarantees place neat and tidy;
S2.4: drilling stops boring after reaching requirement hole depth.
4. a kind of slope protection pile construction method according to claim 1, which is characterized in that in step s3, the pressure fills
The specific steps of concrete include:
S3.1: according to the plan of needs concrete amount of drilling;
S3.2: the concrete for reaching scene is checked;
S3.3: qualified concrete is examined to carry out pressure filling.
5. a kind of slope protection pile construction method according to claim 1, which is characterized in that described in step S4.1
Fabrication of reinforcing cage should construct by design drawing, and be able to satisfy requirement and refer to main reinforcement spacing tolerance ± 10mm, stirrup spacing or
Spiral bar spacing tolerance ± 20mm, steel reinforcement cage diameter tolerance ± 10mm, length of reinforcing cage tolerance ± 50mm.
6. a kind of slope protection pile construction method according to claim 1, which is characterized in that described in step S4.4
Steel reinforcement cage vibration decentralization is slowly that level is utilized when steel reinforcement cage is transferred to absolute altitude is required by starting vibration hammer after the completion of contraposition
Elevation control, error is no more than ± 5cm, and steel reinforcement cage is placed among hole.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811222180.2A CN109208586A (en) | 2018-10-19 | 2018-10-19 | A kind of slope protection pile construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811222180.2A CN109208586A (en) | 2018-10-19 | 2018-10-19 | A kind of slope protection pile construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109208586A true CN109208586A (en) | 2019-01-15 |
Family
ID=64981430
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811222180.2A Pending CN109208586A (en) | 2018-10-19 | 2018-10-19 | A kind of slope protection pile construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109208586A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109914430A (en) * | 2019-04-03 | 2019-06-21 | 杭州萌友服饰有限公司 | A kind of anti-collapse supporting construction in heavy construction deep basal pit side |
CN111926821A (en) * | 2020-07-13 | 2020-11-13 | 北京城建勘测设计研究院有限责任公司 | Construction method of novel slope protection pile |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108612087A (en) * | 2018-05-10 | 2018-10-02 | 江苏地基工程有限公司 | A kind of novel long screw auger pore pressure fills the construction technology of support pile |
-
2018
- 2018-10-19 CN CN201811222180.2A patent/CN109208586A/en active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108612087A (en) * | 2018-05-10 | 2018-10-02 | 江苏地基工程有限公司 | A kind of novel long screw auger pore pressure fills the construction technology of support pile |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109914430A (en) * | 2019-04-03 | 2019-06-21 | 杭州萌友服饰有限公司 | A kind of anti-collapse supporting construction in heavy construction deep basal pit side |
CN111926821A (en) * | 2020-07-13 | 2020-11-13 | 北京城建勘测设计研究院有限责任公司 | Construction method of novel slope protection pile |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107524142A (en) | A kind of holing with slurry wall protection cast-in-place pile construction method | |
CN102691294B (en) | Construction method of underground continuous wall | |
CN106400782B (en) | A kind of construction method for going along with sb. to guard him hole-drilling interlocking pile using rotary drilling rig construction foundation pit | |
CN105178288A (en) | Construction method of underground continuous wall below viaduct | |
CN104532813B (en) | A kind of aquatic building operation platform and erection method, using method | |
CN103195058B (en) | Be convenient to solution cavity and grow the method that regional bridge pier adopts many casings to construct | |
CN103088814A (en) | Rotary drilling rig coordinated with percussion drill hole-forming construction method | |
CN110185844A (en) | Shallow earthing pipe-jacking with large diameter construction method | |
CN110331992A (en) | A kind of hole daguanpeng construction method | |
CN109555116A (en) | A kind of high density karst intense development area fully-sleeved filled pile construction method | |
CN105275381A (en) | Drilling construction method for water-rich cobble stratum by utilizing impact drill | |
CN107246007B (en) | A kind of CFG of construction method | |
CN104264663A (en) | Hard cutting construction technology for secant piles | |
CN103741963A (en) | Industrial plant foundation strengthening method | |
CN104164881A (en) | Piling wall overlapping cantilever foundation pit support construction method and structure | |
CN204174625U (en) | The superimposed cantilever foundation pit supporting construction of a kind of piling wall | |
CN106988305A (en) | A kind of pile-column pier construction method of underground integrated molding | |
CN104264708A (en) | Sequential construction technology for underground diaphragm wall of highline rotational-flow pond | |
CN109208586A (en) | A kind of slope protection pile construction method | |
CN106284311B (en) | A kind of dry efficient construction technology of pore-forming cast-in-place concrete pile of rotary drilling rig | |
CN110258512A (en) | It constructs in a kind of basement rock the method for diaphram wall | |
CN110331715A (en) | A kind of construction method of underground continuous wall in urban construction | |
CN110725163B (en) | Composite roadbed device based on existing rail transit roadbed and pile construction method | |
CN204040021U (en) | Large diameter pile construction equipment system in city underground engineering tunneling pilot tunnel | |
CN110924401A (en) | Construction foundation pit supporting mode for combined arching and bearing of mixing piles and cast-in-place piles |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190115 |