CN109179121A CN201811167618.1A CN201811167618A CN109179121A CN 109179121 A CN109179121 A CN 109179121A CN 201811167618 A CN201811167618 A CN 201811167618A CN 109179121 A CN109179121 A CN 109179121A
Authority
CN
China
Prior art keywords
guide rail
cage
rail pipe
debugging apparatus
parallel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811167618.1A
Other languages
Chinese (zh)
Other versions
CN109179121B (en
Inventor
陈智龙
邹小平
沙晓鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhangjiagang Rongda Construction Machinery Manufacturing Co Ltd
Original Assignee
Zhangjiagang Rongda Construction Machinery Manufacturing Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhangjiagang Rongda Construction Machinery Manufacturing Co Ltd filed Critical Zhangjiagang Rongda Construction Machinery Manufacturing Co Ltd
Priority to CN201811167618.1A priority Critical patent/CN109179121B/en
Publication of CN109179121A publication Critical patent/CN109179121A/en
Application granted granted Critical
Publication of CN109179121B publication Critical patent/CN109179121B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B5/00Applications of checking, fault-correcting, or safety devices in elevators

Landscapes

  • Types And Forms Of Lifts (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

The invention discloses a kind of debugging apparatus for construction elevator cage, it is liftable to be set between two cage girders, the guide rail pipe for the outside circumference for contradicting idler wheel being parallel to each other including two, the connecting rod being connected between two guide rail pipes, the connection pin shaft for being used to connect guide rail pipe and cage girder for being arranged in guide rail pipe top, the inside set on two cage girders is supported on the top of two guide rail pipes respectively;Debugging apparatus further includes along the adjustable adjusting bolt between guide rail pipe and corresponding cage girder inside set on guide rail pipe lower part of length extending direction, dismountable rack gear for engaging with output gear in connecting rod for making guide rail pipe be parallel to the locating support of cage girder, fixation for be cooperatively connected pin shaft and adjusting bolt set on guide rail pipe lower part.A kind of debugging apparatus for construction elevator cage of the present invention, can idler wheel to cage and output gear debug, the cage after debugging can be used directly.

Description

A kind of debugging apparatus for construction elevator cage
Technical field
The present invention relates to building machinery field, in particular to a kind of debugging apparatus for construction elevator cage.
Background technique
Building hoist is the dual-purpose construction machinery of people's goods for being commonly used in construction site, primarily serves and vertical transports people The effect of member and material, is mainly made of guide rail bracket, cage, driving mechanism.Guide rail bracket along the vertical direction on rack gear is installed, Driving mechanism is connected with cage and cage is driven to run up and down along guide rail bracket, and cage is filled as the delivery of transport personnel and material It sets, is equipped with the safety devices such as guide roller, anti-falling safe protection mechanism and the control protection of other electromechanical interlocks.
Main component of the cage as building hoist will usually be installed in use site to guide rail bracket, when leaving the factory, Cage idler wheel and fall protection equipment are unable to adjust required precision when using, and technical staff is needed to adjust at the scene. Work on the spot large labor intensity, it is inconvenient for operation, two people's co-ordinations are needed, time-consuming, seriously affects the progress of construction site.
Summary of the invention
The object of the present invention is to provide a kind of debugging apparatus for construction elevator cage, can adjust scroll wheel positions extremely Required precision when use;And the back lash of output gear wheel and rack is adjusted to meeting the requirements.
In order to achieve the above objectives, the technical solution adopted by the present invention is that:
A kind of debugging apparatus for construction elevator cage, cage include two cage girders being parallel to each other, set on described Idler wheel on the inside of cage girder, the fall arrest protection mechanism on the cage girder, the fall arrest protection mechanism include Output gear, the debugging apparatus is liftable to be set between two cage girders;The debugging apparatus includes two phases Mutually parallel guide rail pipe, be connected between two guide rail pipes connecting rod, be arranged in the guide rail pipe top for connecting Connect the connection pin shaft of the guide rail pipe and the cage girder, the top of two guide rail pipes is supported respectively set on hanging described in two The inside of cage girder;
The debugging apparatus further includes adjustable described set on being located at for the guide rail pipe lower part along length extending direction Adjustings bolt between on the inside of guide rail pipe and the corresponding cage girder is removably set to being used for for the guide rail pipe lower part Cooperate the connection pin shaft and the locating support for adjusting bolt and the guide rail pipe being made to be parallel to the cage girder;
The guide rail pipe is used to be contradicted by the outside circumference of the idler wheel;
The debugging apparatus further includes the fixed rack gear for engaging with the output gear being set in the connecting rod.
Preferably, the guide rail pipe is equipped with the mounting hole for being passed through by the connection pin shaft, the connection pin shaft Direction of axis line is parallel to the orientation of two guide rail pipes.
It is highly preferred that the locating support includes for preventing the lower end of the guide rail pipe around connecting pin axial direction side First countercheck rod of rotation, the second blocking for preventing the lower end of the guide rail pipe from rotating around the connecting pin axial direction other side Bar, the connector being connected between first countercheck rod and second countercheck rod.
It is further preferred that first countercheck rod and second countercheck rod are parallel to each other, and both ends are separately connected On two cage girders.
Preferably, the length extending direction of the rack gear is parallel to the length extending direction of the guide rail pipe.
Preferably, the direction of axis line for adjusting bolt is parallel to the orientation of two guide rail pipes.
Preferably, the connecting rod has a plurality of, and is parallel to each other, and the length extending direction of the connecting rod is parallel to two The orientation of the guide rail pipe.
It is highly preferred that the debugging apparatus further includes the support rod being connected between two adjacent connecting rods.
Due to the application of the above technical scheme, compared with the prior art, the invention has the following advantages: a kind of use of the present invention In the debugging apparatus of construction elevator cage, required precision when scroll wheel positions to use can be adjusted by setting guide rail pipe, The back lash of output gear wheel and rack can be adjusted to meeting the requirements by the way that rack gear is arranged;After so that cage is entered construction site, It can directly lift into a guide rail bracket, can be connected with driving mechanism and can put into operation without debugging.
Detailed description of the invention
Attached drawing 1 is that apparatus of the present invention are fitted into the structural schematic diagram in cage.
Wherein: 1, cage girder;2, idler wheel;3, fall arrest protection mechanism;4, output gear;5, guide rail pipe;6, connecting rod; 7, pin shaft is connected;8, bolt is adjusted;9, locating support;91, the first countercheck rod;92, the second countercheck rod;93, connector;10, tooth Item;11, support rod.
Specific embodiment
The technical solution of the present invention will be further described below with reference to the accompanying drawings.
Shown in Figure 1, a kind of above-mentioned debugging apparatus for construction elevator cage, cage includes two and is parallel to each other Cage girder 1, the idler wheel 2, anti-fall on cage girder 1 that is respectively arranged on 1 inside upper part of cage girder and lower inside Protection mechanism 3 is fallen, which includes output gear 4.
A kind of above-mentioned debugging apparatus for construction elevator cage is liftable to be set between two cage girders 1, energy It enough lowers between two cage girders 1 or rises and extracted out between two cage girders 1.
A kind of above-mentioned debugging apparatus for construction elevator cage includes two being parallel to each other and for by idler wheel 2 The guide rail pipe 5 of outside circumference conflict, is arranged in being used for for 5 top of guide rail pipe at the connecting rod 6 being connected between two guide rail pipes 5 The connection pin shaft 7 of guide rail pipe 5 and cage girder 1 is connected, the top of two guide rail pipes 5 is supported respectively set on two cage girders 1 Inside.In the present embodiment, connection pin shaft 7 is set on cage girder 1, is then equipped with for being worn by the connection pin shaft 7 in guide rail pipe 5 The direction of axis line of the mounting hole crossed, connection pin shaft 7 is parallel to the orientation of two guide rail pipes 5.In the present embodiment, it connects Bar 6 has a plurality of, and is parallel to each other, the length extending direction of connecting rod 6 is parallel to the orientation of two guide rail pipes 5;Above-mentioned one Debugging apparatus of the kind for construction elevator cage further includes the support rod 11 being connected between two adjacent connecting rods 6.
A kind of above-mentioned debugging apparatus for construction elevator cage further includes adjustable along length extending direction Set on 5 lower part of guide rail pipe the adjusting bolt 8 being located between guide rail pipe 5 and the inside of corresponding cage girder 1, be removably set to The locating support 9 for making guide rail pipe 5 be parallel to cage girder 1 for be cooperatively connected pin shaft 7 and adjusting bolt 8 of 5 lower part of guide rail pipe. In the present embodiment, the direction of axis line for adjusting bolt 8 is parallel to the orientation of two guide rail pipes 5, adjusts spiral shell by setting Bolt 8 can guarantee 5 lower part of guide rail pipe to the distance between corresponding cage girder 1 and another 5 lower part of guide rail pipe to right The distance between the cage girder 1 answered is identical, keeps the center line of two cage girders 1 and the center line of two guide rail pipes 5 mutual It is overlapped.
Guide rail pipe 5 is whole in order to prevent rotates around the connection pin shaft 7, and above-mentioned locating support 9 includes for preventing guide rail pipe 5 Lower end around connection pin shaft 7 rotate to side the first countercheck rod 91, for prevent the lower end of guide rail pipe 5 around connect pin shaft 7 to Second countercheck rod 92 of other side rotation, the connector 93 being connected between the first countercheck rod 91 and the second countercheck rod 92.At this In embodiment, the first countercheck rod 91 and the second countercheck rod 92 are parallel to each other, and both ends are connected on two cage girders 1, Orientation of the length extending direction of first countercheck rod 91 and the second countercheck rod 92 each parallel to two guide rail pipes 5.By setting Locating support 9 is set, the length extending direction for adjusting bolt 8 and connection two guide rail pipes 5 of guarantee of pin shaft 7 can be cooperated to hang with two The length extending direction of cage girder 1 is identical, extends along the vertical direction.Make to meet cage between cage and debugging apparatus and work When and guide rail bracket between positional relationship.
A kind of above-mentioned debugging apparatus for construction elevator cage further include it is fixed be set in connecting rod 6 for The rack gear 10 that output gear 4 engages, the length extending direction of rack gear 10 are parallel to the length extending direction of guide rail pipe 5, i.e., along perpendicular Histogram is to extension.
Adjust bolt 8 makes two guide rail pipes 5 in left and right directions (with reference to Fig. 1, the side of two guide rail pipes 5 arrangement for adjusting To as left and right directions) and two centers having the same of cage girder 1, and locating support 9 then makes for the pin shaft 7 that is cooperatively connected Two guide rail pipes 5 are in front-rear direction not run-off the straight.Adjusting bolt 8, locating support 9, connection 7 three of pin shaft mutual cooperation make to lead Rail pipe 5 is parallel to cage girder 1.
The course of work of lower the present embodiment is illustrated in detail below:
Guide rail pipe 5 is sling with shop traveller to bottom and is higher than 1 top of cage girder, alignment 1 middle position of cage girder will be led Rail pipe 5 is filled between cage girder 1, so that the outer circumference surface of guide rail pipe 5 is directed at the concave surface of upper roller 2, is decreased until leads always The concave surface of the outer circumference surface of rail pipe 5 aligned with lower idler wheel 2 again;Then the connection pin shaft 7 on cage girder 1 will be set to and pass through installation Hole, and be adjusted by two adjustment bolts, make two guide rail pipes 5 and two center lines having the same of cage girder 1;Again Installation locating support 9 is simultaneously locked, and extends guide rail pipe 5 along the vertical direction, and opposite cage girder 1 is fixed.
Then the required precision that opposite rail pipe 5 adjusts upper bottom roller 2 when its position being made to meet use;And adjust anti-fall plate The back lash between output gear 4 and rack gear 10 is set to meet the requirements.
Locating support 9 is removed after the completion of adjustment, and extracts connection pin shaft 7 out, and guide rail pipe 5 is sling and disengages it from cage girder 1。
The above embodiments merely illustrate the technical concept and features of the present invention, and its object is to allow person skilled in the art Scholar cans understand the content of the present invention and implement it accordingly, and it is not intended to limit the scope of the present invention.It is all according to the present invention Equivalent change or modification made by Spirit Essence, should be covered by the protection scope of the present invention.

Claims (8)

1. a kind of debugging apparatus for construction elevator cage, cage includes two cage girders being parallel to each other, is set to institute State the idler wheel on the inside of cage girder, the fall arrest protection mechanism on the cage girder, the fall arrest protection mechanism packet Include output gear, it is characterised in that: the debugging apparatus is liftable to be set between two cage girders;The debugging dress It sets including two guide rail pipes being parallel to each other, the connecting rod being connected between two guide rail pipes, be arranged in the guide rail pipe The connection pin shaft for being used to connect the guide rail pipe and the cage girder on top, the top of two guide rail pipes is supported respectively to be set In the inside of two cage girders;
The debugging apparatus further includes adjustable described set on being located at for the guide rail pipe lower part along length extending direction Adjustings bolt between on the inside of guide rail pipe and the corresponding cage girder is removably set to being used for for the guide rail pipe lower part Cooperate the connection pin shaft and the locating support for adjusting bolt and the guide rail pipe being made to be parallel to the cage girder;
The guide rail pipe is used to be contradicted by the outside circumference of the idler wheel;
The debugging apparatus further includes the fixed rack gear for engaging with the output gear being set in the connecting rod.
2. a kind of debugging apparatus for construction elevator cage according to claim 1, it is characterised in that: the guide rail Pipe is equipped with the mounting hole for being passed through by the connection pin shaft, and the direction of axis line of the connection pin shaft is parallel to described in two The orientation of guide rail pipe.
3. a kind of debugging apparatus for construction elevator cage according to claim 2, it is characterised in that: the positioning Bracket includes the first countercheck rod for preventing the lower end of the guide rail pipe from rotating around connecting pin axial direction side, for preventing The second countercheck rod that the lower end of the guide rail pipe is rotated around the connecting pin axial direction other side, be connected to first countercheck rod and Connector between second countercheck rod.
4. a kind of debugging apparatus for construction elevator cage according to claim 3, it is characterised in that: described first Countercheck rod and second countercheck rod are parallel to each other, and both ends are connected on two cage girders.
5. a kind of debugging apparatus for construction elevator cage according to claim 1, it is characterised in that: the rack gear Length extending direction be parallel to the length extending direction of the guide rail pipe.
6. a kind of debugging apparatus for construction elevator cage according to claim 1, it is characterised in that: the adjusting The direction of axis line of bolt is parallel to the orientation of two guide rail pipes.
7. a kind of debugging apparatus for construction elevator cage according to claim 1, it is characterised in that: the connection Bar has a plurality of, and is parallel to each other, the length extending direction of the connecting rod is parallel to the orientation of two guide rail pipes.
8. a kind of debugging apparatus for construction elevator cage according to claim 7, it is characterised in that: the debugging Device further includes the support rod being connected between two adjacent connecting rods.
CN201811167618.1A 2018-10-08 2018-10-08 Debugging device for construction elevator cage Active CN109179121B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811167618.1A CN109179121B (en) 2018-10-08 2018-10-08 Debugging device for construction elevator cage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811167618.1A CN109179121B (en) 2018-10-08 2018-10-08 Debugging device for construction elevator cage

Publications (2)

Publication Number Publication Date
CN109179121A true CN109179121A (en) 2019-01-11
CN109179121B CN109179121B (en) 2024-03-12

Family

ID=64946702

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811167618.1A Active CN109179121B (en) 2018-10-08 2018-10-08 Debugging device for construction elevator cage

Country Status (1)

Country Link
CN (1) CN109179121B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109592562A (en) * 2019-02-12 2019-04-09 法兰泰克重工股份有限公司 A kind of loop wheel machine
CN109761133A (en) * 2019-03-26 2019-05-17 济南工程职业技术学院 A kind of knapsack type elevator
CN114368664A (en) * 2021-12-30 2022-04-19 江苏省送变电有限公司 Inclined construction elevator cage
CN109592562B (en) * 2019-02-12 2024-06-04 法兰泰克重工股份有限公司 Crane

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE9419648U1 (en) * 1994-12-08 1996-04-11 Dechentreiter Maschf Josef Overload protection for a construction elevator
JP2005343691A (en) * 2004-06-05 2005-12-15 Sadao Suzuki Elevator with self-advancing device
US20080190706A1 (en) * 2004-01-20 2008-08-14 Franklin Samuel H Elevator Climbing System
CN202030408U (en) * 2011-04-15 2011-11-09 江苏中原建设集团有限公司 Falling resistant safety device of building construction lifter
CN202956983U (en) * 2012-12-24 2013-05-29 中联重科股份有限公司 Debugging and demonstrating device for driving body of construction elevator
CN202996160U (en) * 2012-12-24 2013-06-12 中联重科股份有限公司 Construction elevator cage debugging demonstration device
KR101470517B1 (en) * 2014-08-01 2014-12-12 주식회사 경신산기 Gondola for tower working
CN204022221U (en) * 2014-08-26 2014-12-17 陈德 Building hoist separate-box type driving device
CN204938665U (en) * 2015-09-30 2016-01-06 广州市特威工程机械有限公司 A kind of construction elevator cage structure
CN205873585U (en) * 2016-08-02 2017-01-11 东莞市毅新庆江机械制造有限公司 Gyro wheel system of debugging exempts from after building hoist lifting cage installation
JP2018052683A (en) * 2016-09-29 2018-04-05 フジテック株式会社 elevator
CN208948611U (en) * 2018-10-08 2019-06-07 张家港市荣达建筑机械制造有限公司 A kind of debugging apparatus for construction elevator cage

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE9419648U1 (en) * 1994-12-08 1996-04-11 Dechentreiter Maschf Josef Overload protection for a construction elevator
US20080190706A1 (en) * 2004-01-20 2008-08-14 Franklin Samuel H Elevator Climbing System
JP2005343691A (en) * 2004-06-05 2005-12-15 Sadao Suzuki Elevator with self-advancing device
CN202030408U (en) * 2011-04-15 2011-11-09 江苏中原建设集团有限公司 Falling resistant safety device of building construction lifter
CN202956983U (en) * 2012-12-24 2013-05-29 中联重科股份有限公司 Debugging and demonstrating device for driving body of construction elevator
CN202996160U (en) * 2012-12-24 2013-06-12 中联重科股份有限公司 Construction elevator cage debugging demonstration device
KR101470517B1 (en) * 2014-08-01 2014-12-12 주식회사 경신산기 Gondola for tower working
CN204022221U (en) * 2014-08-26 2014-12-17 陈德 Building hoist separate-box type driving device
CN204938665U (en) * 2015-09-30 2016-01-06 广州市特威工程机械有限公司 A kind of construction elevator cage structure
CN205873585U (en) * 2016-08-02 2017-01-11 东莞市毅新庆江机械制造有限公司 Gyro wheel system of debugging exempts from after building hoist lifting cage installation
JP2018052683A (en) * 2016-09-29 2018-04-05 フジテック株式会社 elevator
CN208948611U (en) * 2018-10-08 2019-06-07 张家港市荣达建筑机械制造有限公司 A kind of debugging apparatus for construction elevator cage

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109592562A (en) * 2019-02-12 2019-04-09 法兰泰克重工股份有限公司 A kind of loop wheel machine
CN109592562B (en) * 2019-02-12 2024-06-04 法兰泰克重工股份有限公司 Crane
CN109761133A (en) * 2019-03-26 2019-05-17 济南工程职业技术学院 A kind of knapsack type elevator
CN114368664A (en) * 2021-12-30 2022-04-19 江苏省送变电有限公司 Inclined construction elevator cage
CN114368664B (en) * 2021-12-30 2024-04-26 江苏省送变电有限公司 Inclined construction elevator cage

Also Published As

Publication number Publication date
CN109179121B (en) 2024-03-12

Similar Documents

Publication Publication Date Title
US10801220B2 (en) Gondola apparatus
CN102155089A (en) Self-jacking construction platform integrating vertical transportation equipment and mold base
CN202000646U (en) Self-lifting construction platform integrating vertical transportation device and mould frame
CN109179121A (en) A kind of debugging apparatus for construction elevator cage
CN208122264U (en) A kind of external wall finishing hanging basket
CN107975384A (en) A kind of anchor bar of waterproof plate in tunnels and geotextiles synthetic assembly trolley
CN101537965B (en) Step chain installation device and method thereof
CN208948611U (en) A kind of debugging apparatus for construction elevator cage
CN104153586B (en) A kind of suspension cable hangs the construction method of mounting purlines
CN107869315A (en) One kind automation workover rig
CN104110123B (en) A kind of elevating scaffold electric hoisting mechanism
CN107217993B (en) Pylon
CN107190991A (en) The special-shaped curtain wall vertical lifting system of glass plate
CN109853924A (en) A kind of architectural engineering Multifunctional lift scaffold
CN107816209A (en) The large-scale Roof Truss construction technology of installation is lifted across outer both sides
CN111851982A (en) Scaffold frame liftable prevents weighing down safety device
CN214995818U (en) Climbing type construction operation platform outside building
CN106836109B (en) Suspended platform device for protecting, repairing and processing bottom of suspended building
CN204111122U (en) Optimize the composition component without scaffold lift-mounting
CN206784303U (en) A kind of hanging building foot guard repairing treatment suspension platform device
CN214739727U (en) Safe building construction platform
CN104847283A (en) Drilling module drill pipe ramp for offshore cluster wells
CN110593582A (en) High-rise curtain wall installation auxiliary assembly with safety facility
CN104549834A (en) Dual-cantilever basket assembly for automatically spraying inner wall of oil tank
CN203795885U (en) Tower-type large-height-building demolition machine

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant