CN109146422A - Project packet generation method, device and storage medium - Google Patents

Project packet generation method, device and storage medium Download PDF

Info

Publication number
CN109146422A
CN109146422A CN201810944001.XA CN201810944001A CN109146422A CN 109146422 A CN109146422 A CN 109146422A CN 201810944001 A CN201810944001 A CN 201810944001A CN 109146422 A CN109146422 A CN 109146422A
Authority
CN
China
Prior art keywords
project
information
artificial
budget
selection page
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810944001.XA
Other languages
Chinese (zh)
Other versions
CN109146422B (en
Inventor
叶少江
叶广伟
聂金新
王彦聪
吴鸿爵
郭巧丽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Jiangyida Technology Co Ltd
Original Assignee
Shenzhen Jiangyida Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Jiangyida Technology Co Ltd filed Critical Shenzhen Jiangyida Technology Co Ltd
Priority to CN201810944001.XA priority Critical patent/CN109146422B/en
Publication of CN109146422A publication Critical patent/CN109146422A/en
Application granted granted Critical
Publication of CN109146422B publication Critical patent/CN109146422B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Engineering & Computer Science (AREA)
  • General Business, Economics & Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Data Mining & Analysis (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The embodiment of the invention provides a kind of project packet generation method, device and storage mediums, are related to engineering cost analysis technical field.Method selectes the item argument of at least one project in engineering by determining, the item argument includes feature description and the item characteristic information for obtaining the feature description, it is based on the item characteristic information again, automatically generate the mode of corresponding material and the artificial selection page, and then obtaining the item characteristic information, material information, artificial information and the mechanical facility that user selects on the material and the artificial selection page, the project quota of generation wraps.It is easy to operate, to be further simplified engineering cost analysis.

Description

Project packet generation method, device and storage medium
Technical field
The present invention relates to engineering cost analysis technical field, in particular to a kind of project packet generation method, device and Storage medium.
Background technique
For architectural ornament enterprise, main business is building decoration engineering construction, the more single i.e. contract budget of income Income.But since construction enterprises are usually two-level management, so cost structure is complex.It can divide substantially are as follows: company's pipe Reason expense, company are directly used in a certain purpose expense, the administration fee of project itself, the direct cost for engineering project.With It is divided into again in the direct cost of engineering project: first, it is directly used in the consumption of engineering entity, including: material consumption, medium and small The consumption of type machinery, manpower consumption.Second, it is indirectly for the consumption of engineering entity, including: the consumption of big machinery and other Consumption.
It is the administration fee of project itself and for the direct cost of engineering project for a controllable cost of project management department, Other are that corporate manager considers the problems of.Direct cost institute for this controllable departmental cost, for decorative engineering project Accounting example is maximum, is also most difficult to control.Wherein, project quota packet refers to element of the enterprise for project cost budget analysis.At present Project quota packet generation method is more complex.
Summary of the invention
The purpose of the present invention is to provide a kind of project packet generation method, device and storage mediums, to improve the above problem. To achieve the goals above, the technical solution adopted by the present invention is as follows:
In a first aspect, the embodiment of the invention provides a kind of project packet generation method, method is comprised determining that in selected engineering The item argument of at least one project, the item argument include feature description;Obtain the item characteristic letter of the feature description Breath;Based on the item characteristic information, corresponding material and the artificial selection page are automatically generated;Obtain the item characteristic letter It is fixed to generate project for material information, artificial information and the mechanical facility that breath, user select on the material and the artificial selection page Volume packet.
Second aspect, the embodiment of the invention provides a kind of project packet generating means, described device comprise determining that unit, Characteristic acquisition unit, selection interface generation unit and project packet generation unit.Determination unit, for determining in selected engineering The item argument of at least one project, the item argument include feature description.Characteristic acquisition unit, it is described for obtaining The item characteristic information of feature description.Selection interface generation unit automatically generates corresponding for being based on the item characteristic information Material and the artificial selection page.Project packet generation unit, for obtain the item characteristic information, user in the material and Material information, artificial information and the mechanical facility selected on the artificial selection page, the project quota of generation wrap.
The third aspect, the embodiment of the invention provides a kind of storage medium, the storage medium is stored with program code, institute Program code is stated when being read out by the processor and running, executes above-mentioned method.
The embodiment of the invention provides a kind of project packet generation method, device and storage medium, method is selected by determining The item argument of at least one project in engineering, the item argument include feature description and the project for obtaining the feature description Characteristic information, then it is based on the item characteristic information, the mode of corresponding material and the artificial selection page is automatically generated, and then obtain Material information, artificial information and the machine for taking the item characteristic information, user to select on the material and the artificial selection page Tool facility, the project quota of generation wrap.It is easy to operate, to be further simplified engineering cost analysis.
Other features and advantages of the present invention will be illustrated in subsequent specification, also, partly be become from specification It is clear that by implementing understanding of the embodiment of the present invention.The objectives and other advantages of the invention can be by written theory Specifically noted structure is achieved and obtained in bright book, claims and attached drawing.
Detailed description of the invention
In order to illustrate the technical solution of the embodiments of the present invention more clearly, below will be to needed in the embodiment attached Figure is briefly described, it should be understood that the following drawings illustrates only certain embodiments of the present invention, therefore is not construed as pair The restriction of range for those of ordinary skill in the art without creative efforts, can also be according to this A little attached drawings obtain other relevant attached drawings.
Fig. 1 is the structural block diagram that can be applied to electronic equipment provided in an embodiment of the present invention;
Fig. 2 is a kind of flow chart of project packet generation method provided in an embodiment of the present invention;
Fig. 3 is specific example project quota packet schematic diagram in a kind of project packet generation method provided in an embodiment of the present invention;
Fig. 4 is 1 schematic diagram of material and the artificial selection page in a kind of project packet generation method provided in an embodiment of the present invention;
Fig. 5 is definition frame in a kind of project packet generation method provided in an embodiment of the present invention;
Fig. 6 is store page schematic diagram on a kind of project packet generation method middle line provided in an embodiment of the present invention;
Fig. 7 is enterprise's material depot schematic diagram in a kind of project packet generation method provided in an embodiment of the present invention;
Fig. 8 is 2 schematic diagram of material and the artificial selection page in a kind of project packet generation method provided in an embodiment of the present invention;
Fig. 9 is the flow chart of another project packet generation method provided in an embodiment of the present invention;
Figure 10 is the text of Su Weier project valuation inventory in another project packet generation method provided in an embodiment of the present invention Part partial schematic diagram;
Figure 11 is parsing Su Weier project valuation inventory in another project packet generation method provided in an embodiment of the present invention And the project list schematic diagram obtained;
Figure 12 is analysis process schematic diagram in another project packet generation method provided in an embodiment of the present invention;
Figure 13 is that estimated cost analyzes overview page in cost analysis page of data methods of exhibiting provided in an embodiment of the present invention Face schematic diagram;
Figure 14 is that the estimated cost page 1 is illustrated in cost analysis page of data methods of exhibiting provided in an embodiment of the present invention Figure;
Figure 15 is that the cost analysis page can be performed in cost analysis page of data methods of exhibiting provided in an embodiment of the present invention Schematic diagram;
Figure 16 is that the estimated cost page 2 is illustrated in cost analysis page of data methods of exhibiting provided in an embodiment of the present invention Figure;
Figure 17 is procurement inquiry schematic diagram in cost analysis page of data methods of exhibiting provided in an embodiment of the present invention;
Figure 18 is that the estimated cost page 3 is illustrated in cost analysis page of data methods of exhibiting provided in an embodiment of the present invention Figure;
Figure 19 is that the estimated cost page 4 is illustrated in cost analysis page of data methods of exhibiting provided in an embodiment of the present invention Figure;
Figure 20 is that the estimated cost page 5 is illustrated in cost analysis page of data methods of exhibiting provided in an embodiment of the present invention Figure;
Figure 21 is material query page schematic diagram in cost analysis page of data methods of exhibiting provided in an embodiment of the present invention;
Figure 22 is the structural block diagram of project packet generating means provided in an embodiment of the present invention.
Specific embodiment
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is A part of the embodiment of the present invention, instead of all the embodiments.The present invention being usually described and illustrated herein in the accompanying drawings is implemented The component of example can be arranged and be designed with a variety of different configurations.Therefore, below to the reality of the invention provided in the accompanying drawings The detailed description for applying example is not intended to limit the range of claimed invention, but is merely representative of selected implementation of the invention Example.Based on the embodiments of the present invention, obtained by those of ordinary skill in the art without making creative efforts Every other embodiment, shall fall within the protection scope of the present invention.
It should also be noted that similar label and letter indicate similar terms in following attached drawing, therefore, once a certain Xiang Yi It is defined in a attached drawing, does not then need that it is further defined and explained in subsequent attached drawing.Meanwhile of the invention In description, term " first ", " second " etc. are only used for distinguishing description, are not understood to indicate or imply relative importance.
Fig. 1 shows a kind of structural block diagram of electronic equipment 100 that can be applied in the embodiment of the present invention.As shown in Figure 1, Electronic equipment 100 may include memory 102, storage control 104, one or more (one is only shown in Fig. 1) processors 106, Peripheral Interface 108, input/output module 110, audio-frequency module 112, display module 114, radio-frequency module 116 and project Bao Sheng At device.
Memory 102, storage control 104, processor 106, Peripheral Interface 108, input/output module 110, audio mould Block 112, display module 114 are directly or indirectly electrically connected between each element of radio-frequency module 116, with realize data transmission or Interaction.For example, can realize electrical connection by one or more communication bus or signal bus between these elements.Project Bao Sheng At least one software that can be stored in the form of software or firmware (firmware) in memory 102 is respectively included at method Functional module, such as software function module or computer program that the project packet generating means include.
Memory 102 can store various software programs and module, and such as project packet provided by the embodiments of the present application generates Corresponding program instruction/the module of method and device.Processor 106 by operation storage software program in the memory 102 with And module, thereby executing various function application and data processing, i.e. project packet generation method in realization the embodiment of the present application.
Memory 102 can include but is not limited to random access memory (Random Access Memory, RAM), only It reads memory (Read Only Memory, ROM), programmable read only memory (Programmable Read-Only Memory, PROM), erasable read-only memory (Erasable Programmable Read-Only Memory, EPROM), Electricallyerasable ROM (EEROM) (Electric Erasable Programmable Read-Only Memory, EEPROM) etc..
Processor 106 can be a kind of IC chip, have signal handling capacity.Above-mentioned processor can be general Processor, including central processing unit (Central Processing Unit, abbreviation CPU), network processing unit (Network Processor, abbreviation NP) etc.;It can also be digital signal processor (DSP), specific integrated circuit (ASIC), field-programmable Gate array (FPGA) either other programmable logic device, discrete gate or transistor logic, discrete hardware components.It can To realize or execute disclosed each method, step and the logic diagram in the embodiment of the present application.General processor can be micro- Processor or the processor are also possible to any conventional processor etc..
Various input/output devices are couple processor 106 and memory 102 by the Peripheral Interface 108.Some In embodiment, Peripheral Interface 108, processor 106 and storage control 104 can be realized in one single chip.Other one In a little examples, they can be realized by independent chip respectively.
Input/output module 110 is used to be supplied to the interaction that user input data realizes user and electronic equipment 100.It is described Input/output module 110 may be, but not limited to, mouse and keyboard etc..
Audio-frequency module 112 provides a user audio interface, may include one or more microphones, one or more raises Sound device and voicefrequency circuit.
Display module 114 provides an interactive interface (such as user interface) between electronic equipment 100 and user Or it is referred to for display image data to user.In the present embodiment, the display module 114 can be liquid crystal display or touching Control display.It can be the touching of the capacitance type touch control screen or resistance-type of support single-point and multi-point touch operation if touch control display Control screen etc..Single-point and multi-point touch operation is supported to refer to that touch control display can sense on the touch control display one or more The touch control operation generated simultaneously at a position, and the touch control operation that this is sensed transfers to processor 106 to be calculated and handled.
Radio-frequency module 116 is used to receive and transmit electromagnetic wave, realizes the mutual conversion of electromagnetic wave and electric signal, thus with Communication network or other equipment are communicated.
It is appreciated that structure shown in FIG. 1 is only to illustrate, electronic equipment 100 may also include it is more than shown in Fig. 1 or Less component, or with the configuration different from shown in Fig. 1.Each component shown in Fig. 1 can using hardware, software or its Combination is realized.
In the embodiment of the present invention, electronic equipment 100 can for PC (personal computer) computer, tablet computer, The equipment such as mobile phone, laptop, smart television, set-top box, car-mounted terminal.
Referring to Fig. 2, the embodiment of the invention provides a kind of project packet generation methods, which comprises step S200, Step S210, step S220 and step S230.
Step S200: the item argument of at least one project in selected engineering is determined, the item argument includes that feature is retouched It states;
Step S210: the item characteristic information of the feature description is obtained.
Step S220: it is based on the item characteristic information, automatically generates corresponding material and the artificial selection page.
Step S230: the item characteristic information is obtained, the material that user selects on the material and the artificial selection page Expect information, artificial information and mechanical facility, the project quota of generation wraps.
Further, after step S230, the method also includes:
Show that the project quota wraps in a manner of patterned.
As shown in figure 3, the project packet quota that the quota store serial number for illustrating certain selected engineering is 1 generation wraps, feature description Item characteristic information be stone decoration line (straight line) white cement cream paste width 50mm within (master defend wash platform facade: snowflake Bai Shicai lines 30*30mm).Correspondingly, material as shown in Figure 4 and the artificial selection page are selected for user, and user selects material Expect title, supplier, dosage, unit, specification/model etc., obtains material budget;Similarly, user select process title, work post, Work post rank etc. obtains labor budget, and then the project quota of generation wraps, and the quota store unit price of the project quota packet is equal to material Budget adds labor budget.So that project quota package informatin is very clear.
As an implementation, step S230 may include:
The retrieval store instruction that user selects on the material and the artificial selection page is received, quotient on corresponding line is returned The city page, the store page includes a variety of real-time material information on the line;
It is selected and is input in the material and the artificial selection page from a variety of real-time material information based on user The first material information, obtain the first material budget;
Based on the artificial information that user selects on the material and the artificial selection page, labor budget is obtained;
Based on the mechanical facility that user selects on the material and the artificial selection page, mechanical facility budget is obtained;
The item characteristic information, first material budget, the labor budget and the mechanical facility budget are obtained, Generation project quota wraps.
Incorporated by reference to shown in Fig. 5 and Fig. 6, project quota store refers to artificial, material of the enterprise for project cost budget analysis The combination of expense.Using the group packet of material cost and cost of labor, the project packet quota store of enterprise is formed, wherein material information Store and enterprise's material depot on butted line are convenient for real-time reference store price and historical purchase price, it is honest and clean to select object favorable rates Material.Store may include dress easily up to store on the decoration material stockline of independent research operation on line.Enterprise's material depot includes enterprise Used Historical Materials information summarizes.Skilled worker's talent bank: unified labour standard, management and screening resources of human talents.As shown in Figure 6 Line on the store page, a variety of real-time material information such as low cabinet, shoe chest, for user select.Real-time Knowing material price dynamic, branch Hold multiple material reference pair ratios, it is excellent in select it is excellent.User can directly easily place an order up to buying store from dress and buy ornament materials.
As another embodiment, step S230 may include:
Receive the retrieval material instruction that user selects on the material and the artificial selection page, automatic butt to enterprise's material Expect library, enterprise's material depot includes that the material that uses of history summarizes;
Summarize middle selection from the material that the history uses based on user and is input to the material and the artificial selection page In the second material information, obtain the second material budget;
Based on the artificial information that user selects on the material and the artificial selection page, labor budget is obtained;
Based on the mechanical facility that user selects on the material and the artificial selection page, mechanical facility budget is obtained;
The item characteristic information, second material budget, the labor budget and the mechanical facility budget are obtained, Generation project quota wraps.
Enterprise's material depot as shown in Figure 7, enterprise's material depot summarize the material information that history uses, and material information includes The information such as price, the supplier of material.It is advantageous in that with reference to Historical Materials information, when being saved for user again selection with inquiry Between.
Further, the artificial information selected on the material and the artificial selection page based on user is obtained artificial pre- It calculates, comprising:
Process title, work post, work post rank, dosage and the list selected based on user in the material and the artificial selection page Position determines corresponding artificial conjunction valence;
Add up multiple artificial conjunction valences, obtains labor budget.
Wherein, the artificial information is stored in preset skilled worker's talent bank.Unified diligent standard, solution are diligent different Problem.
Material and the artificial selection page as shown in Figure 8, user can be selected different with corresponding selection material and artificial information Process title, work post, work post rank be such as primary, dosage and unit, corresponding different artificial conjunction valence, add up multiple artificial conjunctions Valence obtains labor budget.
Further, after step S230, the method also includes:
When detecting that the material information on the material and the artificial selection page, artificial information and mechanical facility are modified, The estimated cost data of the quota packet of project described in synchronized update.
In the present embodiment, estimated cost data=material budget+labor budget+mechanical facility of project quota packet is pre- It calculates.Project quota packet estimated cost data according to material information, artificial information and the modification of mechanical facility budget it is synchronous more Newly, realize quota data quickly, accurately.
The value of project quota packet is, forms project data packet according to engineering project parameter, passes through the side of aspect ratio pair Method is matched with engineering project, estimated cost analysis is participated in, referring to Fig. 9, the method is also wrapped after step S230 It includes: step S240, step S250, step S260 and step S270.
Step S240: multiple project quotas are obtained and are wrapped, storage is used as preset project quota store.
Step S250: the original valuation inventory of engineering to be analyzed is obtained.
Step S260: the parsing original valuation inventory obtains project list, the project list includes described to be analyzed At least one project and at least one corresponding engineering parameter of at least one described project in engineering.
In the present embodiment, original valuation inventory can be Excel file format.For example, importing the projects such as popular software The Excel file of original valuation inventory, therefrom to parse the engineering parameter of engineering project.As shown in Figure 10, engineering to be analyzed is Certain Beijing hotel engineering quotation-installing engineering building external decoration engineering, including project code are 020210001001 He 020210001002 two projects obtain project list, as shown in figure 11, project list includes multiple by system analysis The engineering parameters such as sub- engineering, the project name of every a sub- engineering, feature description.
Step S270: at least one described engineering parameter is matched with preset project quota store, if successful match, Generate the master budget bill of costs of the engineering to be analyzed.
In the present embodiment, engineering parameter is matched with preset project quota store, if being matched to as this is to be analyzed Engineering selects the highest project quota of compatible degree to wrap, and surface matching success, automatic Perform Project Financial Aanalysis cost solves Decoration Enterprise cost The problem of calculating low efficiency, heavy workload, intelligent Matching analysis process is as shown in figure 12.
Further, at least one described engineering parameter includes project name and feature description, and step S270 may include: Sub-step S271 and sub-step S272.
Sub-step S271: carrying out characteristic matching with the project quota store for the project name and feature description, If equal successful match, the project quota for generating the project is wrapped.
Sub-step S271 may include:
By the project name and the project quota store carry out minimum particle size characteristic matching and by feature description with The project quota store carries out maximum particle size characteristic matching, if equal successful match, the project quota for generating the project is wrapped.
Sub-step S272: it is wrapped based on the project quota, obtains the project budget bill of costs of the project, and then generating should The master budget bill of costs of engineering to be analyzed, the master budget bill of costs include that at least one described project budget cost is clear It is single.
Sub-step S272 may include:
Obtain material budget, labor budget, mechanical facility budget and the project amount in the project quota packet;
The sum of the material budget, the labor budget and mechanical facility budget is calculated, and by this and as the project Project quota packet budget;
The product of the budget of project quota packet and the project amount is calculated, and the product is pre- as the project of the project It is counted as this, and then after the project budget cost for each project that adds up, obtains the master budget cost of the engineering to be analyzed;
Generate the master budget bill of costs of the engineering to be analyzed, the master budget bill of costs include the master budget at Sheet, project list cost analysis summary table, material cost analysis summary table, analysis of labor costs's summary table, mechanical facility cost analysis are total Table and other fees cost analysis summary table.
That is, in the present embodiment, engineering cost computation rule are as follows: project quota packet budget=material budget+artificial pre- Calculation+mechanical facility budget;Project budget cost=project quota packet budget × project amount;All items estimated cost summation=total Estimated cost.
Further, the master budget bill of costs further includes gross profit, the gross profit be get in advance should be to The difference of the total cost of analysis project and the master budget cost.
That is, in the present embodiment, gross profit=total cost-master budget.
Further, the project quota store is Enterprise Project packet quota store, and the matching quota store is platform project packet Quota store;Or the project quota store is platform project packet quota store, the matching quota store is Enterprise Project packet quota store.
I.e. the matching of quota store includes two channels, first is that Enterprise Project packet quota store, second is that platform project packet quota store. Platform project packet quota store easily reaches system platform typing and management by filling, and provides opening function.
Further, by the project name and the feature description with the project quota store carry out characteristic matching it Afterwards, if in equal successful match, before the project quota packet for generating the project, the method can also include:
If it fails to match, output matching quota store selects prompt information;
Obtain the matching quota store of user's selection;
The project name or feature description and the matching quota store of user selection that it fails to match are carried out Characteristic matching.
In the present embodiment, preferential to retrieve Enterprise Project quota store in intelligent Matching, if matching is less than quota store System can prompt whether searching platform project packet quota store, by user independently select match channel.
Illustrate concrete application scene of the invention below by a specific embodiment.Figure 13-Figure 21 is please referred to, can be used Terminal device is implemented, and the detailed process of method includes:
One, user easily reaches system by terminal device logs dress, and terminal device receives the cost analysis instruction that user issues, It generates estimated cost and analyzes the overview page, the estimated cost analysis overview page includes that multiple channels of selected engineering are respective The analysis progress of cost analysis and each cost analysis, it is specific as shown in figure 13, administrative staff such as chief inspector can in real time with Track and check job schedule, estimated cost is measured in comparison.
Two, terminal device generates multiple channels when the analysis progress for detecting each cost analysis is to be completed Respective cost analysis information;
Three, user compares the multiple respective cost analysis information in channel, determines that estimated cost is believed according to comparing result Breath;
Four, the estimated cost information that terminal device is determined according to user in the estimated cost analysis overview page, generates budget The cost page, the estimated cost page include that project list cost analysis summary table, the material cost analysis of sub-category displaying are total Table, analysis of labor costs's summary table, mechanical facility cost analysis summary table and other fees cost analysis summary table.Specifically such as Figure 14 institute Show.Wherein, specific cost analysis process includes: that the projects such as the original valuation inventory such as popular software that user imports engineering are original The Excel file of valuation inventory to terminal device, terminal device executes: parsing original valuation inventory, obtains project list, project Inventory includes at least one project and at least one corresponding engineering parameter of at least one described project of engineering;It will be described At least one engineering parameter is matched with preset project quota store, if successful match, generates the master budget bill of costs, total pre- Calculating the bill of costs includes that master budget cost, project list cost analysis summary table, material cost analysis summary table, analysis of labor costs are total Table, mechanical facility cost analysis summary table and other fees cost analysis summary table.Project quota store is stored with multiple pre-generated Project quota wraps.Specifically as shown in figs. 10-11.
If five, the user is chief inspector, the multiple channel includes chief inspector's analysis channel, and user selects the chief inspector generated analysis The cost analysis information in channel, terminal device, which generates chief inspector, can be performed the cost analysis page, and as shown in figure 15, user can in chief inspector Executory cost, which is analyzed to click on the page, assigns project manager's button, selects to implement project manager accordingly.
Six, after user clicks the total table button of material cost analysis on the estimated cost page, terminal device shows project material Material list quotation analysis summary and project material shopping list summarize, as shown in figure 16.Wherein, user such as procurement staff can be pre- Procurement inquiry is first carried out, as shown in figure 17, procurement staff is logged in by computer and submits inquiry result to filling easily up to system, is generated Material purchases are inquired the price summary table, and with this, multiple material purchases inquiry summary tables are incorporated into during project material shopping list summarizes.
Seven, after user clicks the total table button of analysis of labor costs on the estimated cost page, terminal device shows project people The artificial diligent invoice summary of work list quotation analysis summary and project, it is specific as shown in figure 18.
Eight, user is clicked on the estimated cost page after engineering summarizes button, described in terminal device is shown in a tabular form The project cost and estimated cost of selected engineering, personnel's overview and with patterned form show engineering cost analysis summary figure and Multiple engineering informations of completion have been analyzed in display, specific as shown in figure 19.
Nine, user such as project manager click Xiang Mingda on the estimated cost page and summarize button, and input change request is extremely Dress easily reaches system, to submit to chief inspector's examination & approval;It is easy up to system, synchronized update project list cost to filling that chief inspector inputs approval results Analyze summary table, material cost analysis summary table, analysis of labor costs's summary table, mechanical facility cost analysis summary table and other fees cost Summary table is analyzed, as shown in figure 20.
Ten, after the bill of materials button that the estimated cost page clicks under selection warehouse, terminal is set by user such as storekeeper personnel It is standby to return to corresponding material query page, user in material query page in the corresponding Text Entry of title material input to Such as military ceramic tile clay of query material, then after clicking the inquiry button in material query page, terminal device shows corresponding material Inventory information, bill of materials information include the material outbound of material to be checked, storage, are returned goods etc. using consuming, retract and use. Specifically as shown in figs 20 and 21.
Thus cost analysis data are visually illustrated by diversified forms.
The embodiment of the invention provides a kind of project packet generation method, method is by determining at least one in selected engineering Purpose item argument, the item argument includes feature description and the item characteristic information for obtaining the feature description, then is based on The item characteristic information automatically generates the mode of corresponding material and the artificial selection page, and then obtains the item characteristic Material information, artificial information and the mechanical facility that information, user select on the material and the artificial selection page generate project Quota wraps.It is easy to operate, to be further simplified engineering cost analysis.
Figure 22 is please referred to, the embodiment of the invention provides a kind of project packet generating means 400, described device 400 includes true Order member 410, characteristic acquisition unit 420, selection interface generation unit 430 and project packet generation unit 440.
Determination unit 410, for the item argument of at least one project in determining selected engineering, the item argument includes Feature description.
Characteristic acquisition unit 420, for obtaining the item characteristic information of the feature description.
Selection interface generation unit 430 automatically generates corresponding material and artificial for being based on the item characteristic information Select the page.
Project packet generation unit 440, for obtaining the item characteristic information, user in the material and artificial selection page Material information, artificial information and the mechanical facility selected on face, the project quota of generation wrap.The artificial information is stored in preset In skilled worker's talent bank.
As an implementation, project packet generation unit 440, is used for: receiving user in the material and artificial selection The retrieval store instruction selected on the page, returns to the store page on corresponding line, and the store page includes a variety of real-time on the line Material information;It is selected and is input in the material and the artificial selection page from a variety of real-time material information based on user The first material information, obtain the first material budget;It is selected on the material and the artificial selection page based on user artificial Information obtains labor budget;Based on the mechanical facility that user selects on the material and the artificial selection page, obtains machinery and set Apply budget;The item characteristic information, first material budget, the labor budget and mechanical facility budget are obtained, is generated Project quota wraps.
As an implementation, project packet generation unit 440, is used for: receiving user in the material and artificial selection The retrieval material instruction selected on the page, automatic butt to enterprise's material depot, enterprise's material depot includes the material that history uses Material summarizes;Summarize middle selection from the material that the history uses based on user and is input in the material and the artificial selection page The second material information, obtain the second material budget;It is selected on the material and the artificial selection page based on user artificial Information obtains labor budget;Based on the mechanical facility that user selects on the material and the artificial selection page, obtains machinery and set Apply budget;The item characteristic information, second material budget, the labor budget and mechanical facility budget are obtained, is generated Project quota wraps.
Project packet generation unit 440, is used for: the process name selected based on user in the material and the artificial selection page Title, work post, work post rank, dosage and unit determine corresponding artificial conjunction valence;Add up multiple artificial conjunction valences, obtains labor budget.
Project packet generation unit 440, is also used to: when detect the material information on the material and the artificial selection page, When artificial information and mechanical facility are modified, the estimated cost data of project quota packet described in synchronized update.
Project packet generation unit 440, is also used to: showing that the project quota wraps in a manner of patterned.
Project packet generation unit 440, is also used to: obtaining multiple project quotas and wraps, storage is fixed as preset project E Ku;Obtain the original valuation inventory of engineering to be analyzed;The original valuation inventory is parsed, project list, the project are obtained Inventory includes at least one project and at least one corresponding work of at least one described project in the engineering to be analyzed Journey parameter;At least one described engineering parameter is matched with preset project quota store, if successful match, generating should be wait divide Analyse the master budget bill of costs of engineering.
The above each unit can be by software code realization, at this point, above-mentioned each unit can be stored in memory 102. The above each unit can equally be realized by hardware such as IC chip.
The technical effect of project packet generating means 400 provided in an embodiment of the present invention, realization principle and generation and aforementioned Embodiment of the method is identical, and to briefly describe, Installation practice part does not refer to place, can refer to corresponding in preceding method embodiment Content.
The embodiment of the invention provides a kind of storage medium, the storage medium is stored with program code, described program generation Code executes above-mentioned method when being read out by the processor and running.
In several embodiments provided herein, it should be understood that disclosed device and method can also pass through Other modes are realized.The apparatus embodiments described above are merely exemplary, for example, flow chart and block diagram in attached drawing Show the device of multiple embodiments according to the present invention, the architectural framework in the cards of method and computer program product, Function and operation.In this regard, each box in flowchart or block diagram can represent the one of a module, section or code Part, a part of the module, section or code, which includes that one or more is for implementing the specified logical function, to be held Row instruction.It should also be noted that function marked in the box can also be to be different from some implementations as replacement The sequence marked in attached drawing occurs.For example, two continuous boxes can actually be basically executed in parallel, they are sometimes It can execute in the opposite order, this depends on the function involved.It is also noted that every in block diagram and or flow chart The combination of box in a box and block diagram and or flow chart can use the dedicated base for executing defined function or movement It realizes, or can realize using a combination of dedicated hardware and computer instructions in the system of hardware.
In addition, each functional module in each embodiment of the present invention can integrate one independent portion of formation together Point, it is also possible to modules individualism, an independent part can also be integrated to form with two or more modules.
It, can be with if the function is realized and when sold or used as an independent product in the form of software function module It is stored in a computer readable storage medium.Based on this understanding, technical solution of the present invention is substantially in other words The part of the part that contributes to existing technology or the technical solution can be embodied in the form of software products, the meter Calculation machine software product is stored in a storage medium, including some instructions are used so that a computer equipment (can be a People's computer, server or network equipment etc.) it performs all or part of the steps of the method described in the various embodiments of the present invention. And storage medium above-mentioned includes: that USB flash disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), arbitrary access are deposited The various media that can store program code such as reservoir (RAM, Random Access Memory), magnetic or disk.It needs Illustrate, herein, relational terms such as first and second and the like be used merely to by an entity or operation with Another entity or operation distinguish, and without necessarily requiring or implying between these entities or operation, there are any this realities The relationship or sequence on border.Moreover, the terms "include", "comprise" or its any other variant are intended to the packet of nonexcludability Contain, so that the process, method, article or equipment for including a series of elements not only includes those elements, but also including Other elements that are not explicitly listed, or further include for elements inherent to such a process, method, article, or device. In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that including the element Process, method, article or equipment in there is also other identical elements.
The foregoing is only a preferred embodiment of the present invention, is not intended to restrict the invention, for the skill of this field For art personnel, the invention may be variously modified and varied.All within the spirits and principles of the present invention, made any to repair Change, equivalent replacement, improvement etc., should all be included in the protection scope of the present invention.
The above description is merely a specific embodiment, but scope of protection of the present invention is not limited thereto, any Those familiar with the art in the technical scope disclosed by the present invention, can easily think of the change or the replacement, and should all contain Lid is within protection scope of the present invention.Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.

Claims (10)

1. a kind of project packet generation method, which is characterized in that the described method includes:
Determine that the item argument of at least one project in selected engineering, the item argument include feature description;
Obtain the item characteristic information of the feature description;
Based on the item characteristic information, corresponding material and the artificial selection page are automatically generated;
Obtain the item characteristic information, the material information that user selects on the material and the artificial selection page, artificial letter Breath and mechanical facility, the project quota of generation wrap.
2. the method according to claim 1, wherein obtaining the item characteristic information, user in the material With material information, artificial information and the mechanical facility selected on the artificial selection page, the project quota of generation is wrapped, comprising:
The retrieval store instruction that user selects on the material and the artificial selection page is received, store page on corresponding line is returned Face, the store page includes a variety of real-time material information on the line;
Selected from a variety of real-time material information based on user and be input in the material and the artificial selection page One material information obtains the first material budget;
Based on the artificial information that user selects on the material and the artificial selection page, labor budget is obtained;
Based on the mechanical facility that user selects on the material and the artificial selection page, mechanical facility budget is obtained;
The item characteristic information, first material budget, the labor budget and the mechanical facility budget are obtained, is generated Project quota wraps.
3. the method according to claim 1, wherein obtaining the item characteristic information, user in the material With material information, artificial information and the mechanical facility selected on the artificial selection page, the project quota of generation is wrapped, comprising:
Receive the retrieval material instruction that user selects on the material and the artificial selection page, automatic butt to enterprise's material Library, enterprise's material depot include that the material that uses of history summarizes;
Summarize middle selection from the material that the history uses based on user and is input in the material and the artificial selection page Second material information obtains the second material budget;
Based on the artificial information that user selects on the material and the artificial selection page, labor budget is obtained;
Based on the mechanical facility that user selects on the material and the artificial selection page, mechanical facility budget is obtained;
The item characteristic information, second material budget, the labor budget and mechanical facility budget are obtained, project is generated Quota wraps.
4. according to the method in claim 2 or 3, which is characterized in that based on user in the material and the artificial selection page The artificial information of upper selection obtains labor budget, comprising:
Based on process title, work post, work post rank, dosage and unit that user selects in the material and the artificial selection page, Determine corresponding artificial conjunction valence;
Add up multiple artificial conjunction valences, obtains labor budget.
5. the method according to claim 1, wherein obtaining the item characteristic information, user in the material Material information, artificial information and the mechanical facility selected on material and the artificial selection page, after the project quota of generation wraps, the side Method further include:
It is synchronous when detecting that the material information on the material and the artificial selection page, artificial information and mechanical facility are modified Update the estimated cost data of the project quota packet.
6. the method according to claim 1, wherein obtaining the item characteristic information, user in the material Material information, artificial information and the mechanical facility selected on material and the artificial selection page, after the project quota of generation wraps, the side Method further include:
Show that the project quota wraps in a manner of patterned.
7. the method according to claim 1, wherein the artificial information is stored in preset skilled worker's talent bank In.
8. method according to claim 1-7, which is characterized in that obtaining the item characteristic information, user Material information, artificial information and the mechanical facility selected on the material and the artificial selection page, generation project quota wrap it Afterwards, the method also includes:
It obtains multiple project quotas to wrap, storage is used as preset project quota store;
Obtain the original valuation inventory of engineering to be analyzed;
Parse the original valuation inventory, obtain project list, the project list include in the engineering to be analyzed at least One project and at least one corresponding engineering parameter of at least one described project;
At least one described engineering parameter is matched with preset project quota store, if successful match, it is to be analyzed to generate this The master budget bill of costs of engineering.
9. a kind of project packet generating means, which is characterized in that described device includes:
Determination unit, for determining the item argument of at least one project in selected engineering, the item argument includes that feature is retouched It states;
Characteristic acquisition unit, for obtaining the item characteristic information of the feature description;
Selection interface generation unit automatically generates corresponding material and artificial selection page for being based on the item characteristic information Face;
Project packet generation unit is selected on the material and the artificial selection page for obtaining the item characteristic information, user Material information, artificial information and the mechanical facility selected, the project quota of generation wrap.
10. a kind of storage medium, which is characterized in that the storage medium is stored with program code, and said program code is being located When reason device reads and runs, the method as described in any claim of claim 1-8 is executed.
CN201810944001.XA 2018-08-18 2018-08-18 Project package generation method and device and storage medium Active CN109146422B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810944001.XA CN109146422B (en) 2018-08-18 2018-08-18 Project package generation method and device and storage medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810944001.XA CN109146422B (en) 2018-08-18 2018-08-18 Project package generation method and device and storage medium

Publications (2)

Publication Number Publication Date
CN109146422A true CN109146422A (en) 2019-01-04
CN109146422B CN109146422B (en) 2021-07-13

Family

ID=64790047

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810944001.XA Active CN109146422B (en) 2018-08-18 2018-08-18 Project package generation method and device and storage medium

Country Status (1)

Country Link
CN (1) CN109146422B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110674540A (en) * 2019-09-06 2020-01-10 北京创艺汇文化传播有限公司 Restaurant design scheme quotation method and system
CN111737306A (en) * 2020-06-19 2020-10-02 广联达科技股份有限公司 Engineering index determination method and device, computer equipment and storage medium
CN111738486A (en) * 2020-05-09 2020-10-02 北京兴中海建工程造价咨询有限公司 Comprehensive management method and system for construction project cost, bid inviting and consultation

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106934527A (en) * 2017-02-22 2017-07-07 广东华联软件科技有限公司 A kind of enterprise model system system and method
CN107220808A (en) * 2017-05-26 2017-09-29 李扬球 A kind of bill of quantities visualization method
CN107807980A (en) * 2017-10-27 2018-03-16 巧夺天宫(深圳)科技有限公司 Report automatic generatioin system and its generation method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106934527A (en) * 2017-02-22 2017-07-07 广东华联软件科技有限公司 A kind of enterprise model system system and method
CN107220808A (en) * 2017-05-26 2017-09-29 李扬球 A kind of bill of quantities visualization method
CN107807980A (en) * 2017-10-27 2018-03-16 巧夺天宫(深圳)科技有限公司 Report automatic generatioin system and its generation method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110674540A (en) * 2019-09-06 2020-01-10 北京创艺汇文化传播有限公司 Restaurant design scheme quotation method and system
CN111738486A (en) * 2020-05-09 2020-10-02 北京兴中海建工程造价咨询有限公司 Comprehensive management method and system for construction project cost, bid inviting and consultation
CN111738486B (en) * 2020-05-09 2024-03-01 北京兴中海建工程造价咨询有限公司 Comprehensive management method and system for construction project cost, bid-inviting and consultation
CN111737306A (en) * 2020-06-19 2020-10-02 广联达科技股份有限公司 Engineering index determination method and device, computer equipment and storage medium

Also Published As

Publication number Publication date
CN109146422B (en) 2021-07-13

Similar Documents

Publication Publication Date Title
Han et al. Artificial intelligence in business-to-business marketing: a bibliometric analysis of current research status, development and future directions
CN107734059B (en) Industrial Internet cloud platform
Ibem et al. Survey of digital technologies in procurement of construction projects
CN109087150A (en) Cost intelligent analysis method and device
Ru et al. Consignment contracting: who should control inventory in the supply chain?
CN102523247A (en) Cloud service recommendation method and device based on multi-attribute matching
US20120260201A1 (en) Collection and analysis of service, product and enterprise soft data
CN109146422A (en) Project packet generation method, device and storage medium
Shin et al. Application of information technology for mass customization in the housing construction industry in Korea
CN110348921B (en) Method and device for selecting store articles
CN109615459A (en) A kind of digital intelligent house ornamentation method and system
CN109961299A (en) The method and apparatus of data analysis
TW201828200A (en) Data processing method and apparatus increasing the overall display efficiency of the object display environment and decreasing the waste of display resources of each object display environment
Yu et al. The role of big data analysis in new product development
CN109886790A (en) A kind of textile fabric management transaction system
Ercolani Cloud computing services potential analysis. An integrated model for evaluating software as a service
Ahmad et al. Challenges and practices identification via a systematic literature review in the adoption of green cloud computing: client’s side approach
Lin et al. Manufacturing process analysis with support of workflow modelling and simulation
KR102270645B1 (en) Methods and systems for delivering business services that enable manufacturing collaboration
Chen et al. Establishing an order allocation decision support system via learning curve model for apparel logistics
CN109146421A (en) Cost analysis page of data methods of exhibiting and device
Hu et al. Modeling and simulating a smart information-based real estate online platform
Syuntyurenko The evolutionary factors, management, and efficiency of information support
CN112069780A (en) Control method and device for custom billboard data display in third-party platform
Zhou Inventory management of multi-item systems with order size constraint

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant