CN109137827B - Underwater rapid plugging method for large hole - Google Patents

Underwater rapid plugging method for large hole Download PDF

Info

Publication number
CN109137827B
CN109137827B CN201811048045.0A CN201811048045A CN109137827B CN 109137827 B CN109137827 B CN 109137827B CN 201811048045 A CN201811048045 A CN 201811048045A CN 109137827 B CN109137827 B CN 109137827B
Authority
CN
China
Prior art keywords
plugging
brick wall
building
underwater
concrete precast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811048045.0A
Other languages
Chinese (zh)
Other versions
CN109137827A (en
Inventor
李永山
梁勇
陈猛
于庆
齐磊
杨彪
王芹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 5 Co Ltd
Original Assignee
Sinohydro Bureau 5 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 5 Co Ltd filed Critical Sinohydro Bureau 5 Co Ltd
Priority to CN201811048045.0A priority Critical patent/CN109137827B/en
Publication of CN109137827A publication Critical patent/CN109137827A/en
Application granted granted Critical
Publication of CN109137827B publication Critical patent/CN109137827B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/16Sealings or joints

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention discloses a method for quickly plugging large holes underwater, which comprises the following steps of 1: determining an underwater plugging position; step 2: determining an underwater plugging construction channel and path, and setting an underwater operation platform; and step 3: calculating the length of the plugging body; and 4, step 4: building a first brick wall, and reducing the water flow speed in the hole and the scouring of the water flow to the plugging body; and 5: a flat pressing communicating pipe is arranged in the middle of the first brick wall; step 6: when the first brick wall is constructed to the required height, building a concrete precast block on the back of the first brick wall, and embedding a flat-pressing communicating pipe; and 7: filling and plugging the flat-pressing communicating pipe by building blocks, and cutting off the water flow of the hole; and 8: and building a second brick wall on the back of the concrete precast block, plastering and caulking by using special waterproof mortar after the building is finished, and building a back supporting platform on the back of the second brick wall. The method ensures the stability of the plugging body and improves the construction efficiency.

Description

Underwater rapid plugging method for large hole
Technical Field
The invention relates to the field of underwater plugging construction of large holes, in particular to an underwater rapid plugging method for large holes, which ensures that the large holes can be safely and efficiently plugged.
Background
In large-scale hydraulic and hydroelectric engineering, the large-scale hole under water overflows frequently, and the large-scale hole under water needs to be plugged after the task of overflowing is completed, so that the construction difficulty is high when plugging is performed under water. The existing underwater plugging construction has the following problems: 1. the underwater situation is complex, and when the underwater plugging position is far away from the outside, the plugging material is inconvenient to transport; 2. the plugging body has a complex structure and high construction difficulty; 3. the plugging material has high cost and high plugging construction cost; 4. the plugging is affected by water pressure, and the stability of the plugging body is difficult to ensure when the construction is too fast. Due to the problems, the underwater plugging construction difficulty is high, the construction period is long, and a large amount of manpower and material resources are consumed.
Disclosure of Invention
The invention aims to solve the technical problem of providing an underwater rapid plugging method for large holes, ensuring the stability of a plugging body and improving the construction efficiency.
In order to solve the technical problems, the invention adopts the technical scheme that:
an underwater rapid plugging method for large holes comprises the following steps:
step 1: determining an underwater plugging position according to the topographic condition and the hydrological condition of the engineering area and in combination with the arrangement type of a hydraulic building;
step 2: determining an underwater plugging construction channel and path, and setting an underwater operation platform;
and step 3: calculating the length of the plugging body according to the size, the water level difference and the plugging diameter of the hole;
and 4, step 4: building a first brick wall, and reducing the water flow speed in the hole and the scouring of the water flow to the plugging body;
and 5: a flat pressing communicating pipe is arranged in the middle of the first brick wall to ensure that the water pressure on two sides is balanced;
step 6: when the first brick wall is constructed to the required height, building a concrete precast block on the back of the first brick wall, and embedding a flat-pressing communicating pipe;
and 7: after the concrete precast block is completely constructed and reaches the expected strength, the flat-pressing communicating pipe is filled with the building blocks and plugged, and the water flow of the holes is cut off;
and 8: and building a second brick wall on the back of the concrete precast block, plastering and caulking by using professional waterproof mortar after the building is finished, and building a back supporting platform on the back of the second brick wall to finally form a plugging body sequentially consisting of the first brick wall, the concrete precast block, the second brick wall and the back supporting platform.
Further, in step 6, the concrete precast block is constructed layer by using a step method by using special waterproof mortar.
Further, the method also comprises the step 9: and after the plugging body is built, arranging a displacement meter at the tail end of the plugging body.
Further, the method also comprises the step 10: and (5) carrying out accumulated water pumping and draining.
Compared with the prior art, the invention has the beneficial effects that: 1) the plugging material related by the invention has low cost and is convenient to transport. 2) The plugging body is simple in structure and low in construction difficulty. 3) The invention adopts the brick wall combined with the concrete precast block to build the plugging body, thereby greatly improving the construction speed. 4) The invention adopts the embedded flat-pressing communicating pipe, reduces the water pressure difference and ensures the stability of the plugging body during rapid construction.
Drawings
FIG. 1 is a schematic plan view of a plugging body of the underwater rapid plugging method for large holes.
FIG. 2 is a cross-sectional view of a plugging body of the underwater rapid plugging method for large holes.
In the figure: 1-a first brick wall; 2-flat pressing communicating pipe; 3-precast concrete block; 4-a second brick wall; 5-back support platform.
Detailed Description
The underwater rapid plugging method for the large hole is further described in detail by combining the attached drawings and the specific embodiment, and the specific embodiment comprises the following steps:
firstly, determining an underwater plugging position according to the topographic condition and the hydrological condition of an engineering area and in combination with the arrangement type of a hydraulic building, and completing field construction preparation, including site cleaning, plugging material preparation, water and electricity supply and the like;
secondly, performing underwater exploration investigation: professional underwater operation personnel submerge the plugging material to perform investigation, determine an optimal underwater plugging construction channel and path, and arrange an underwater operation platform to facilitate temporary storage and transportation of plugging materials;
thirdly, before underwater plugging construction, calculating the length of a plugging body according to parameters such as the size of a hole, the water level difference and the plugging diameter;
fourthly, in order to be convenient and rapid in construction, a professional underwater operator firstly builds the first brick wall 1, the wall thickness is 48cm, the material is common sintered bricks, the engineering quantity is small, and the construction can be rapidly carried out to the design elevation, so that the water flow speed in the hole and the scouring of the water flow to the plugging body are reduced;
fifthly, a flat pressing communicating pipe 2 is arranged in the middle of the wall body of the first brick wall 1, so that water pressure balance on two sides is guaranteed, the size of the flat pressing communicating pipe 2 is determined according to specific conditions, water flows on two sides of the plugging body are communicated in the construction process, the water pressure difference on two sides is adjusted, and the stability of the plugging body in the construction process is guaranteed;
sixthly, when the first brick wall 1 is constructed to the plugging height 1/3, building a concrete precast block 3 (with a self-defined size, mainly convenient to move and capable of improving overall stability) on the back of the first brick wall 1 and embedding a flat pressing communicating pipe 2, wherein the concrete precast block 3 is built in a layered mode by adopting special waterproof mortar and a step method, so that the stability of a plugging body in the construction process is guaranteed, and the length of the plugging body is determined according to calculation;
seventhly, after the concrete precast block 3 is completely constructed and the strength is waited for 7 days, the flat pressing communicating pipe 2 is filled with the building blocks and plugged, the water flow of the holes is cut off, and the water flow in the holes is plugged;
eighthly, completing the building of the second brick wall 4 by professional underwater operators, wherein the wall thickness is 48cm, the second brick wall is made of common sintered bricks, and after the building is completed, plastering and caulking are performed by professional waterproof mortar, so that the main function of the second brick wall is to increase the anti-seepage effect of the plugging body; building a back supporting platform 5 on the back of the second brick wall 4; according to the requirements, accumulated water pumping and draining are carried out, and a displacement meter is arranged at the tail end of the plugging body for displacement monitoring.
In general, a first brick wall 1 with the thickness of 48cm is built by an underwater professional in a large hole, a flat pressing communicating pipe 2 is embedded, and the flat pressing communicating pipe 2 is embedded in a concrete precast block 3; plugging the flat pressing communicating pipe 2; then building the concrete precast block 3 and building a second brick wall 4 with the thickness of 48cm to play a role of seepage prevention; and building a back supporting platform 5 on the back to finish the plugging of the large holes.
The castration meets with the flood that exceeds standard for the avionic hub engineering, and right bank ship lock foundation pit intakes, and the flood pours into left bank power generation factory building into from right bank grout corridor, leads to the power generation factory building foundation ditch to be flooded. In order to restore the construction production of the power generation plant on the left bank as early as possible in time, the grouting gallery is blocked underwater, namely the traffic gallery communicated with the grouting gallery from the 9# machine set section of the power generation plant is blocked underwater in the submerged area of the foundation pit.

Claims (1)

1. An underwater rapid plugging method for large holes is characterized by comprising the following steps:
step 1: determining an underwater plugging position according to the topographic condition and the hydrological condition of the engineering area and in combination with the arrangement type of a hydraulic building;
step 2: determining an underwater plugging construction channel and path, and setting an underwater operation platform;
and step 3: calculating the length of the plugging body according to the size, the water level difference and the plugging diameter of the hole;
and 4, step 4: a first brick wall (1) is built, so that the water flow speed in the hole and the scouring of the water flow to the plugging body are reduced;
and 5: a flat pressing communicating pipe (2) is arranged in the middle of the first brick wall (1) to ensure that the water pressure at two sides is balanced;
step 6: when the first brick wall (1) is constructed to a required height, building a concrete precast block (3) on the back of the first brick wall (1) and embedding a flat-pressing communicating pipe (2);
and 7: after the concrete precast block (3) is completely constructed and reaches the expected strength, the flat pressing communicating pipe (2) is filled and blocked by building blocks, and the water flow of the hole is cut off;
and 8: building a second brick wall (4) on the back of the concrete precast block (3), plastering and caulking by using special waterproof mortar after building, building a back supporting platform (5) on the back of the second brick wall (4), and finally forming a plugging body consisting of the first brick wall (1), the concrete precast block (3), the second brick wall (4) and the back supporting platform (5) in sequence;
in the step 6, the concrete precast block (3) is built layer by a step method by adopting special waterproof mortar;
further comprising step 9: after the construction of the plugging body is finished, arranging a displacement meter at the tail end of the plugging body;
further comprising the step 10: and (5) carrying out accumulated water pumping and draining.
CN201811048045.0A 2018-09-10 2018-09-10 Underwater rapid plugging method for large hole Active CN109137827B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811048045.0A CN109137827B (en) 2018-09-10 2018-09-10 Underwater rapid plugging method for large hole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811048045.0A CN109137827B (en) 2018-09-10 2018-09-10 Underwater rapid plugging method for large hole

Publications (2)

Publication Number Publication Date
CN109137827A CN109137827A (en) 2019-01-04
CN109137827B true CN109137827B (en) 2021-05-28

Family

ID=64824220

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811048045.0A Active CN109137827B (en) 2018-09-10 2018-09-10 Underwater rapid plugging method for large hole

Country Status (1)

Country Link
CN (1) CN109137827B (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN207537993U (en) * 2017-10-31 2018-06-26 广东水电二局股份有限公司 A kind of diversion tunnel concrete plug

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN207537993U (en) * 2017-10-31 2018-06-26 广东水电二局股份有限公司 A kind of diversion tunnel concrete plug

Also Published As

Publication number Publication date
CN109137827A (en) 2019-01-04

Similar Documents

Publication Publication Date Title
CN103835283B (en) Full wet joint prefabricated prestressed underground continuous wall and construction method thereof
CN101096852B (en) Method for anti-floating of underground building
CN103343543A (en) Foundation pit dewatering well pressure-reduction-type plugging method
CN104389318B (en) Reinforced concrete-steel structure hybrid gravity foundation for offshore wind power and construction method thereof
CN103422510B (en) Steel pipe frame type cofferdam structure and construction method
CN100510281C (en) Semi-reverse construction method for ultra-large-diameter and ultra-buried depth storage tank
CN203891087U (en) Gravity-type retaining wall reinforcement structure
CN208219694U (en) A kind of prefabricated barricade
CN104652371A (en) Overflow cemented rock-fill dam established based on old dam and construction method thereof
CN104179156A (en) Cylindrical foundation water gate structure and construction method for closure of cofferdam
CN106638486B (en) High-tech zones cut-pff wall and gallery stage construction method
CN103122642B (en) Construction method of vertical post support change
CN109137827B (en) Underwater rapid plugging method for large hole
CN204080750U (en) Box-type suction foundation sluice structure
CN204212168U (en) A kind of dam water-retaining structure utilizing solution cavity to combine to build a dam
CN107152034A (en) A kind of pipe gallery and its construction method
CN110512571B (en) Roller compacted concrete dam containing rock-fill concrete core wall and construction method thereof
CN211547830U (en) Structure for preventing ground from being wetted
CN213952130U (en) Concrete face rockfill dam partition filling isolation retaining device
CN204139190U (en) A kind of Liftable preformed bricks fetal membrane
CN104047273A (en) Energy dissipation anti-flushing wall for hydropower station and construction method thereof
CN207143843U (en) A kind of explosion-proof earth embankment of precast splice type
CN204780777U (en) Geogrid concrete structure
CN216515690U (en) Novel sump pit is used to underground structures
CN105625435A (en) Fast forming method for multi-section and multi-layer special-shaped equipment deep foundation pit of marine accumulation island

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant