CN109116141A - A kind of POE interchanger restarts the test method of power supply reliability - Google Patents

A kind of POE interchanger restarts the test method of power supply reliability Download PDF

Info

Publication number
CN109116141A
CN109116141A CN201810784211.7A CN201810784211A CN109116141A CN 109116141 A CN109116141 A CN 109116141A CN 201810784211 A CN201810784211 A CN 201810784211A CN 109116141 A CN109116141 A CN 109116141A
Authority
CN
China
Prior art keywords
time
poe
power supply
power
access controller
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810784211.7A
Other languages
Chinese (zh)
Other versions
CN109116141B (en
Inventor
李玲玲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHENZHEN JIXIANG TENDA TECHNOLOGY Co Ltd
Original Assignee
SHENZHEN JIXIANG TENDA TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHENZHEN JIXIANG TENDA TECHNOLOGY Co Ltd filed Critical SHENZHEN JIXIANG TENDA TECHNOLOGY Co Ltd
Priority to CN201810784211.7A priority Critical patent/CN109116141B/en
Publication of CN109116141A publication Critical patent/CN109116141A/en
Application granted granted Critical
Publication of CN109116141B publication Critical patent/CN109116141B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/003Environmental or reliability tests

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Power Sources (AREA)

Abstract

The present invention is suitable for POE interchanger field, provide the test method that a kind of POE interchanger restarts power supply reliability, including AC access controller, connect the POE interchanger of the AC access controller, connect the AP of the POE interchanger, connect the PC machine of the AC access controller or the POE interchanger, it is electrically connected the on-off electric equipment of the AC access controller and the POE interchanger, and it is electrically connected the on-off electric equipment, the power supply of the AP and the PC machine, power-on time and power-off time can be set in the on-off electric equipment, solve interchanger restart after power whether normal technical problem.

Description

A kind of POE interchanger restarts the test method of power supply reliability
Technical field
The invention belongs to the test sides that power supply reliability is restarted in POE interchanger field more particularly to a kind of POE interchanger Method.
Background technique
Current test method is manually to restart interchanger after interchanger accesses PD, and rear power supply for exchange is restarted in observation It is whether normal.The defect of this test mode: after a manpower power on/off must be expended, observe whether each port powers to PD Success and power-on time, the testing time is long, low efficiency.And can not accurate geo-statistic PD power-on time, if desired thousands of times Restart test, manual testing is difficult to realize.
Summary of the invention
The purpose of the present invention is to provide the test methods that a kind of POE interchanger restarts power supply reliability, it is intended to solve to hand over Change planes power after restarting whether normal technical problem.
The invention is realized in this way a kind of POE interchanger restarts the test method of power supply reliability, including AC access control Device processed connects the POE interchanger of the AC access controller, connects the AP of the POE interchanger, connects the AC access control The PC machine of device or the POE interchanger is electrically connected the on-off electric equipment of the AC access controller and the POE interchanger, And it is electrically connected the power supply of the on-off electric equipment, the AP and the PC machine, when power supply can be set in the on-off electric equipment Between and power-off time, the test method the following steps are included:
Step S1: judging whether AC access controller can manage to all AP connected, if so, then by the IP of PC machine network interface card The management IP address of address and AC access controller is set as same network segment, carries out next step operation, sets if not, being attached Set inspection and handle, until AC access controller can manage to all AP connected, and by the IP address of PC machine network interface card with The management IP address of AC access controller is set as same network segment, then carries out next step operation;
Step S2: P1, nominative testing time are denoted as by the AP quantity and nominative testing number of PC machine setting management, and by AP quantity Number scale is NUM, starts to be tested;
Step S3: POE power supply for exchange test report will be tested out when testing, and POE power supply for exchange is tested and is reported Result is accused to be saved;
Step S4: when testing time is the power-on time report that the NUM time test will obtain each AP, and by the power supply of each AP Time report result is saved;
Step S5: being completed, and exports POE power supply for exchange test report and the power-on time report of each AP.
A further technical solution of the present invention is: the step S3 is further comprising the steps of:
Step S31: judging whether it is and test for the first time, if so, then reading the IP address of all AP, save as IP.txt file, The IP address for carrying out all AP of Ping, saves as Ping log, in the AP quantity for reading the management of AC access controller, is denoted as P2; If not, no longer reading the IP address of all AP, the IP address of all AP of Ping is directly carried out, Ping log is saved as, read The AP quantity of AC access controller management, is denoted as P2;
Step S:32: judging whether AP quantity P1 is equal to P2, if so, then POE power supply for exchange is normal, normal number of powering adds One, if not, POE power supply for exchange is abnormal, abnormal electrical power supply number adds one, records POE power supply for exchange test result, and save In POE power supply for exchange test report.
A further technical solution of the present invention is: the step S4 is further comprising the steps of:
Step S41: judge whether it is the NUM times test, if so, then reading all Ping logs, and determined with Ping log Institute's having time that AP starting works normally after POE interchanger is powered down to POE interchanger during entire circulation power on/off, is used Institute's having time is individually subtracted POE interchanger power-off time and obtains POE interchanger to the power-on time of each AP, records each AP's Power-on time finds out maximum/minimum/average value of the power-on time of each AP, and is stored in the power-on time report of each AP In announcement, next step operation is carried out;If not, continuing to test.
The beneficial effects of the present invention are: can accurately count interchanger by such method, whether function is powered successfully, And it can also obtain specific power-on time, not need manually to be restarted if you need to repeatedly be restarted test, and be not required to The too long of testing time is spent, and then improves testing efficiency.
Detailed description of the invention
Fig. 1 is the step of a kind of POE interchanger provided in an embodiment of the present invention restarts the test method of power supply reliability stream Cheng Tu.
Specific embodiment
Fig. 1 shows the test method that a kind of POE interchanger provided by the invention restarts power supply reliability, including AC access Controller connects the POE interchanger of the AC access controller, connects the AP of the POE interchanger, connects the AC access control The PC machine of device processed or the POE interchanger, the power on/off for being electrically connected the AC access controller and the POE interchanger are set It is standby, and it is electrically connected the power supply of the on-off electric equipment, the AP and the PC machine, power supply can be set in the on-off electric equipment Time and power-off time, the test method the following steps are included:
Step S1: judging whether AC access controller can manage to all AP connected, if so, then by the IP of PC machine network interface card The management IP address of address and AC access controller is set as same network segment, carries out next step operation, sets if not, being attached Set inspection and handle, until AC access controller can manage to all AP connected, and by the IP address of PC machine network interface card with The management IP address of AC access controller is set as same network segment, then carries out next step operation;
Step S2: P1, nominative testing time are denoted as by the AP quantity and nominative testing number of PC machine setting management, and by AP quantity Number scale is NUM, starts to be tested;
Step S3: POE power supply for exchange test report will be tested out when testing, and POE power supply for exchange is tested and is reported Result is accused to be saved;
Step S31: judging whether it is and test for the first time, if so, then reading the IP address of all AP, save as IP.txt file, The IP address for carrying out all AP of Ping, saves as Ping log, in the AP quantity for reading the management of AC access controller, is denoted as P2; If not, no longer reading the IP address of all AP, the IP address of all AP of Ping is directly carried out, Ping log is saved as, read The AP quantity of AC access controller management, is denoted as P2;
Step S:32: judging whether AP quantity P1 is equal to P2, if so, then POE power supply for exchange is normal, normal number of powering adds One, if not, POE power supply for exchange is abnormal, abnormal electrical power supply number adds one, records POE power supply for exchange test result, and save In POE power supply for exchange test report.
Step S4: testing when testing time for the NUM times will show that the power-on time of each AP is reported, and by each AP's Power-on time report result is saved;
Step S41: judge whether it is the NUM times test, if so, then reading all Ping logs, and determined with Ping log Institute's having time that AP starting works normally after POE interchanger is powered down to POE interchanger during entire circulation power on/off, is used Institute's having time is individually subtracted POE interchanger power-off time and obtains POE interchanger to the power-on time of each AP, records each AP's Power-on time finds out maximum/minimum/average value of the power-on time of each AP, and is stored in the power-on time report of each AP In announcement, next step operation is carried out;If not, continuing to test.
Step S5: being completed, and exports POE power supply for exchange test report and the power-on time report of each AP.
Interchanger can accurately be counted by such method, and whether function is powered successfully, and can also be obtained specific Power-on time does not need manually to be restarted, and does not need to spend the too long of testing time if you need to repeatedly be restarted test, And then improve testing efficiency.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Made any modifications, equivalent replacements, and improvements etc., should all be included in the protection scope of the present invention within mind and principle.

Claims (3)

1. a kind of POE interchanger restarts the test method of power supply reliability, including AC access controller, the AC access control is connected The POE interchanger of device processed connects the AP of the POE interchanger, connects the PC of the AC access controller or the POE interchanger Machine is electrically connected the on-off electric equipment of the AC access controller and the POE interchanger, and is electrically connected the power on/off and sets Power-on time and power-off time can be set in the power supply of standby, the described AP and the PC machine, the on-off electric equipment, and feature exists In, the test method the following steps are included:
Step S1: judging whether AC access controller can manage to all AP connected, if so, then by the IP of PC machine network interface card The management IP address of address and AC access controller is set as same network segment, carries out next step operation, sets if not, being attached Set inspection and handle, until AC access controller can manage to all AP connected, and by the IP address of PC machine network interface card with The management IP address of AC access controller is set as same network segment, then carries out next step operation;
Step S2: P1, nominative testing time are denoted as by the AP quantity and nominative testing number of PC machine setting management, and by AP quantity Number scale is NUM, starts to be tested;
Step S3: POE power supply for exchange test report will be tested out when testing, and POE power supply for exchange is tested and is reported Result is accused to be saved;
Step S4: when testing time is the power-on time report that the NUM time test will obtain each AP, and by the power supply of each AP Time report result is saved;
Step S5: being completed, and exports POE power supply for exchange test report and the power-on time report of each AP.
2. test method according to claim 1, which is characterized in that the step S3 is further comprising the steps of:
Step S31: judging whether it is and test for the first time, if so, then reading the IP address of all AP, save as IP.txt file, The IP address for carrying out all AP of Ping, saves as Ping log, in the AP quantity for reading the management of AC access controller, is denoted as P2; If not, no longer reading the IP address of all AP, the IP address of all AP of Ping is directly carried out, Ping log is saved as, read The AP quantity of AC access controller management, is denoted as P2;
Step S:32: judging whether AP quantity P1 is equal to P2, if so, then POE power supply for exchange is normal, normal number of powering adds One, if not, POE power supply for exchange is abnormal, abnormal electrical power supply number adds one, records POE power supply for exchange test result, and save In POE power supply for exchange test report.
3. test method according to claim 1, which is characterized in that the step S4 is further comprising the steps of:
Step S41: judge whether it is the NUM times test, if so, then reading all Ping logs, and determined with Ping log Institute's having time that AP starting works normally after POE interchanger is powered down to POE interchanger during entire circulation power on/off, is used Institute's having time is individually subtracted POE interchanger power-off time and obtains POE interchanger to the power-on time of each AP, records each AP's Power-on time finds out maximum/minimum/average value of the power-on time of each AP, and is stored in the power-on time report of each AP In announcement, next step operation is carried out;If not, continuing to test.
CN201810784211.7A 2018-07-17 2018-07-17 Method for testing power supply reliability of POE switch restart Expired - Fee Related CN109116141B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810784211.7A CN109116141B (en) 2018-07-17 2018-07-17 Method for testing power supply reliability of POE switch restart

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810784211.7A CN109116141B (en) 2018-07-17 2018-07-17 Method for testing power supply reliability of POE switch restart

Publications (2)

Publication Number Publication Date
CN109116141A true CN109116141A (en) 2019-01-01
CN109116141B CN109116141B (en) 2020-12-15

Family

ID=64862800

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810784211.7A Expired - Fee Related CN109116141B (en) 2018-07-17 2018-07-17 Method for testing power supply reliability of POE switch restart

Country Status (1)

Country Link
CN (1) CN109116141B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115208807A (en) * 2022-09-14 2022-10-18 中兴系统技术有限公司 POE switch test system and method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012142710A (en) * 2010-12-28 2012-07-26 Hitachi Systems Ltd System and method of lan i/f switchover control, and program
CN103095505A (en) * 2013-02-05 2013-05-08 北京傲天动联技术股份有限公司 Method and system for controlling power supply of power over Ethernet (POE) exchanger port
CN105337795A (en) * 2015-09-24 2016-02-17 上海斐讯数据通信技术有限公司 POE switch testing device and detection method thereof
CN105807155A (en) * 2016-03-04 2016-07-27 太仓市同维电子有限公司 Testing device and method for power cut and starting of electric devices
US20170195179A1 (en) * 2013-09-05 2017-07-06 Pismo Labs Technology Limited Methods and systems for managing a device through a manual information input module

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012142710A (en) * 2010-12-28 2012-07-26 Hitachi Systems Ltd System and method of lan i/f switchover control, and program
CN103095505A (en) * 2013-02-05 2013-05-08 北京傲天动联技术股份有限公司 Method and system for controlling power supply of power over Ethernet (POE) exchanger port
US20170195179A1 (en) * 2013-09-05 2017-07-06 Pismo Labs Technology Limited Methods and systems for managing a device through a manual information input module
CN105337795A (en) * 2015-09-24 2016-02-17 上海斐讯数据通信技术有限公司 POE switch testing device and detection method thereof
CN105807155A (en) * 2016-03-04 2016-07-27 太仓市同维电子有限公司 Testing device and method for power cut and starting of electric devices

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
HAIMENG WU 等: ""50W Power Device (PD) power in Power over Ethernet (PoE) system with input current balance in four-pair architecture with two DC/DC converters"", 《2010 TWENTY-FIFTH ANNUAL IEEE APPLIED POWER ELECTRONICS CONFERENCE AND EXPOSITION (APEC)》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115208807A (en) * 2022-09-14 2022-10-18 中兴系统技术有限公司 POE switch test system and method
CN115208807B (en) * 2022-09-14 2022-12-30 中兴系统技术有限公司 POE switch test system and method

Also Published As

Publication number Publication date
CN109116141B (en) 2020-12-15

Similar Documents

Publication Publication Date Title
EP2977770A1 (en) Leakage current detection method and device
CN111585841B (en) Automatic test method and related device
CN110008070A (en) A kind of AEP memory AC test method powered off at random based on power supervisor
CN109240865A (en) A kind of AC test method, device, terminal and the storage medium of AEP memory
CN105743707A (en) Method for testing BMC log analysis function based on Redhat system
CN107273258A (en) Method of testing and system are restarted in the automation of interchanger built in a kind of blade server
CN109116141A (en) A kind of POE interchanger restarts the test method of power supply reliability
CN110767259A (en) Power failure pressure test method for flash memory device
CN110489287B (en) Method, system and storage medium for testing hot plug through Ipomitool
CN113590401B (en) CPE equipment multifunctional test method, CPE equipment multifunctional test device, computer equipment and storage medium
CN109412819A (en) Method and device for warning device power down
CN108599377A (en) A kind of monitoring method of 230M power load controls communication base station
CN113687992B (en) Method for electrifying and electrifying test of airborne equipment
CN102654845B (en) Power detecting system and method
CN110658478A (en) Testing method and device based on power supply balance signal stability and storage medium
CN208257508U (en) A kind of monitoring device of 230M power load control communication base station
CN115437865A (en) Method, device, equipment and medium for testing abnormal power failure of hard disk
CN213585156U (en) Self-power-off circuit after display screen test
CN113589092A (en) Fatigue machine, equipment power-on and power-off test system and power-on and power-off test method
CN210155240U (en) System for testing high-low temperature power-off restart of Internet of things gateway
CN113687993A (en) Onboard equipment power-on and power-off test system
CN107907762B (en) Test method and system for detecting influence of BBU on stability of whole cabinet
CN105515918A (en) Network awakening test method under SUSE Linux system
CN106257305B (en) One kind obtaining source list automated detection method based on GNSS receiver hardware module
CN112904105A (en) Method, device and system for testing initialization function of transformer substation relay protection device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201215