CN109113364A - Super-high storied building installs the overhung construction and construction method of two floor plates additional - Google Patents

Super-high storied building installs the overhung construction and construction method of two floor plates additional Download PDF

Info

Publication number
CN109113364A
CN109113364A CN201811028810.2A CN201811028810A CN109113364A CN 109113364 A CN109113364 A CN 109113364A CN 201811028810 A CN201811028810 A CN 201811028810A CN 109113364 A CN109113364 A CN 109113364A
Authority
CN
China
Prior art keywords
fixed
port
platform sling
plate
super
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811028810.2A
Other languages
Chinese (zh)
Other versions
CN109113364B (en
Inventor
周仲景
马春香
张艳红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Heilongjiang College of Construction
Original Assignee
Heilongjiang College of Construction
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Heilongjiang College of Construction filed Critical Heilongjiang College of Construction
Priority to CN201811028810.2A priority Critical patent/CN109113364B/en
Publication of CN109113364A publication Critical patent/CN109113364A/en
Application granted granted Critical
Publication of CN109113364B publication Critical patent/CN109113364B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0266Enlarging

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Floor Finish (AREA)

Abstract

Super-high storied building installs the overhung construction and construction method of two floor plates additional.Its composition of the invention includes: house, the house has the left wall and right wall of length direction, the left wall is provided with one group of left socket being parallel to each other, the right wall is provided with one group of right socket being parallel to each other, cross girders is inserted between the left socket and the right socket, the first from left port and the second from left port are provided on the left of the cross girders, the first from left port connect left lifting sub-assembly with the second from left port, the left lifting sub-assembly is fixed on the left wall by one group of expansion bolt, a right port and right two ports are provided on the right side of the cross girders, one port of the right side connect right lifting sub-assembly with two port of the right side, the right lifting sub-assembly is fixed on the right wall by one group of expansion bolt.The present invention installs two floor plates additional for super-high storied building.

Description

Super-high storied building installs the overhung construction and construction method of two floor plates additional
Technical field:
The present invention relates to overhung constructions and construction method that a kind of super-high storied building installs two floor plates additional.
Background technique:
It is all above normal level now with the height of house of many buildings, highly generally at 4.5 meters or more, if this Sample is using will cause certain waste, if installing two layer height floors additional needs to be laid with one layer of joist or supporting plate, the support of installation Perhaps to be supported existing method be supported in the bottom of joist or supporting plate to supporting plate needs to beam, such support meeting The globality in house is destroyed, and reduces usable floor area.
Summary of the invention:
It does not need to support in bottom the object of the present invention is to provide one kind, installs two floor plate safety additional, using effect is good Super-high storied building installs the overhung construction and construction method of two floor plates additional.
Above-mentioned purpose is realized by following technical scheme:
A kind of super-high storied building installs the overhung construction of two floor plates additional, and composition includes: house, and the house has length The left wall and right wall in direction, the left wall are provided with one group of left socket being parallel to each other, and the right wall is provided with one The right socket that group is parallel to each other is inserted into cross girders, a left side for the cross girders between the left socket and the right socket Side is provided with the first from left port and the second from left port, and the first from left port connect left lifting sub-assembly with the second from left port, described Left lifting sub-assembly be fixed on by one group of expansion bolt on the left wall, the right side one is provided on the right side of the cross girders Port and right two ports, one port of the right side connect right lifting sub-assembly, the right lifting group with two port of the right side Component is fixed on the right wall by one group of expansion bolt.
The super-high storied building installs the overhung construction of two floor plates additional, and the left lifting sub-assembly includes left platform sling, institute The left platform sling stated is attached on the left wall and is fixed by expansion bolt, the bottom insertion of the left platform sling left side One port, the left platform sling are vertically fixedly connected with left supporting plate, and the left supporting plate is vertically fixedly connected with left plate, the left side Plate is vertically fixedly connected with left flexible fastening plate, and the right side of the second from left port connects left hugging, the left plate insertion In the second from left port, it is fixed in the left flexible fastening plate insertion left hugging and by screw, it is described Left supporting plate be attached to the bottom between the first from left port and the second from left port and be fixed by screw.
The super-high storied building installs the overhung construction of two floor plates additional, and the right lifting sub-assembly includes right platform sling, institute The right platform sling stated is attached on the right wall and is fixed by expansion bolt, the bottom insertion of the right platform sling right side One port, the right platform sling are vertically fixedly connected with right supporting plate, and the right supporting plate is vertically fixedly connected with right plate, the right side Plate is vertically fixedly connected with right flexible fastening plate, and the right side of two port of the right side connects right hugging, the right plate insertion In two port of the right side, it is fixed in the right flexible fastening plate insertion right hugging and by screw, it is described Right supporting plate be attached to the bottom between one port of the right side and two port of the right side and be fixed by screw.
The super-high storied building installs the overhung construction of two floor plates additional, the corresponding right socket of the left socket, simultaneously And be parallel to each other, the left side insertion left socket of the cross girders is simultaneously fixed, the right side of the cross girders with cement slurry The insertion right socket in side is simultaneously fixed with cement slurry.
The super-high storied building installs the overhung construction of two floor plates additional, and the bottom of cross girders is bonded magnetic sheet, the magnetic sheet With left supporting plate and right supporting plate in same plane, the magnetic sheet is fixed magnetic sheet, and the fixation magnetic sheet is bonded in decorative panel Top.
The super-high storied building installs the overhung construction of two floor plates, the suitable position connection in the top of the cross girders additional Platform sling leads to overpenetrated bolt and fixes between the cross girders and the platform sling, the platform sling welds sunpender, described Sunpender welding top fixed plate, the top fixed plate are attached on the ceiling in house and are fixed by expansion bolt.
The super-high storied building installs the overhung construction of two floor plates additional, and the sunpender is cased with plastic sheath or the sunpender Magnetic sheet set, the plastic sheath connection decoration floral leaf or the decoration leaf of bamboo are connected, the magnetic sheet set is attracted decoration magnetic sheet, described Decoration magnetic sheet is bonded in the inside of decoration partition panel.
The super-high storied building installs the overhung construction of two floor plates additional, and the left platform sling is bonded left magnetic patch, the left side In same plane, the left magnetic patch is attracted left fixation for the outer end of the expansion bolt of magnetic patch and the fixed left platform sling Magnetic sheet, the left fixed magnetic sheet are bonded in the inside of left decorative panel.
The super-high storied building installs the overhung construction of two floor plates additional, and the right platform sling is bonded right magnetic patch, the right side In same plane, the right magnetic patch is attracted right fixation for the outer end of the expansion bolt of magnetic patch and the fixed right platform sling Magnetic sheet, the right fixed magnetic sheet are bonded in the inside of right decorative panel.
A kind of super-high storied building installs the construction method of the overhung construction of two floor plates additional, this construction method includes seven steps, and first Left wall is outputed left socket by step, right wall outputs right socket, and cross girders is inserted into left socket and right socket by second step, and uses water Mud is fixed, and left lifting sub-assembly is assembled on the first from left port and the second from left port and is fixed by third step, right lifting combination Part is assembled on a right port and right two ports and is fixed, and left platform sling is fixed on left wall by the 4th step, and right platform sling is solid It is scheduled on right wall, the 5th step is chosen the position of platform sling as needed and is fixed, and the 6th step is fixed on top for fixed plate is pushed up On canopy, the 7th step assembles decorative panel, left decorative panel, right decorative panel, plastic sheath or magnetic sheet set.
The utility model has the advantages that
1. speed is fast when present invention assembling, construction, secured after assembling, use is very safe, and decorative parts are also square Just it assembles, it is beautiful, beautiful after assembling.
2. left platform sling of the invention is fixed on left wall, right platform sling is fixed on and is fully able to undertake cross girders on right wall And the weight of the article on the floor, placement being laid on cross girders, human body up, use is very safe.
3. the present invention does not need to be supported in the bottom of cross girders, it is not take up the space of Stall, makes the globality of Stall It is very good, increase usable floor area.
4. decorative parts of the invention are attached by magnetic, assembling, speed of application are all fast, need to replace decoration It is all convenient when plate and ornament.
Detailed description of the invention:
Attached drawing 1 is the structural schematic diagram of this product.
Attached drawing 2 is structural schematic diagram of this product equipped with decoration floral leaf.
Attached drawing 3 is the structural schematic diagram of cross girders in attached drawing 2 and attached drawing 1.
Specific embodiment:
Embodiment 1:
A kind of super-high storied building installs the overhung construction of two floor plates additional, and composition includes: house, and the house has length The left wall 1 and right wall 2 in direction, the left wall are provided with one group of left socket 3 being parallel to each other, and the right wall is provided with One group of right socket 4 being parallel to each other is inserted into cross girders 5, the cross girders between the left socket and the right socket Left side be provided with the first from left port 6 and the second from left port 7, the first from left port is combined with the left lifting of the second from left port connection Part, the left lifting sub-assembly are fixed on the left wall by one group of expansion bolt 8, the right side of the cross girders One port 9 of the right side and right two ports 10 are provided with, one port of the right side connect right lifting sub-assembly with two port of the right side, described Right lifting sub-assembly be fixed on by one group of expansion bolt on the right wall.
Left socket and right socket not only play the role of connection to cross girders, additionally it is possible to play the role of lifting, pass through After cement slurry is fixed, it can guarantee that the connection between cross girders and left wall and right wall is stronger, using more Safety.
Embodiment 2:
Super-high storied building described in embodiment 1 installs the overhung construction of two floor plates additional, and the left lifting sub-assembly includes a left side Platform sling 11, the left platform sling are attached on the left wall and are fixed by expansion bolt, and the bottom of the left platform sling is inserted Enter the first from left port, the left platform sling is vertically fixedly connected with left supporting plate 12, and the left supporting plate is vertically fixedly connected with a left side Plate 13, the left plate are vertically fixedly connected with left flexible fastening plate 14, and the right side of the second from left port connects left hugging 15, the left plate is inserted into the second from left port, in the left flexible fastening plate insertion left hugging and is led to It crosses screw to be fixed, the left supporting plate is attached to the bottom between the first from left port and the second from left port and leads to Screw is crossed to be fixed.
Left platform sling, left supporting plate, left plate, left flexible fastening plate are structure as a whole, between the first from left port, the second from left port Connection is very secured, and stronger after assembling, the left side of the cross girders of lifting is very secured, and use is very safe.
Embodiment 3:
Super-high storied building described in embodiment 1 installs the overhung construction of two floor plates additional, and the right lifting sub-assembly includes the right side Platform sling 16, the right platform sling are attached on the right wall and are fixed by expansion bolt, and the bottom of the right platform sling is inserted Enter one port of the right side, the right platform sling is vertically fixedly connected with right supporting plate 17, and the right supporting plate is vertically fixedly connected with the right side Plate 18, the right plate are vertically fixedly connected with right flexible fastening plate 19, and the right side of two port of the right side connects right hugging 20, the right plate is inserted into two port of the right side, in the right flexible fastening plate insertion right hugging and is led to It crosses screw to be fixed, the right supporting plate is attached to the bottom between one port of the right side and two port of the right side and leads to Screw is crossed to be fixed.
Right platform sling, right supporting plate, right plate, right flexible fastening plate are structure as a whole, between a right port, right two ports Connection is very secured, and stronger after assembling, the right side of the cross girders of lifting is very secured, and use is very safe.
Embodiment 4:
Super-high storied building described in embodiment 1 installs the overhung construction of two floor plates, the corresponding right side of the left socket additional It socket and is parallel to each other, the left socket that the left side insertion of the cross girders is described is simultaneously fixed, the cross with cement slurry The right side insertion right socket of joist is simultaneously fixed with cement slurry.
The supporting power of cross girders is good, and use is safe, effect is good.
Embodiment 5:
Super-high storied building described in embodiment 1 installs the overhung construction of two floor plates additional, and the bottom of cross girders is bonded magnetic sheet 21, institute In same plane, the magnetic sheet is fixed magnetic sheet 22 for the magnetic sheet and left supporting plate stated and right supporting plate, and the fixation magnetic sheet is viscous It connects at the top of decorative panel 23.Decorative panel installation speed is fast, convenient when installation.
Embodiment 6:
Super-high storied building described in embodiment 1 installs the overhung construction of two floor plates additional, and the top of the cross girders is suitable Position connects platform sling 24, and overpenetrated bolt is led between the cross girders and the platform sling and is fixed, the platform sling welding Sunpender 25, the sunpender welding top fixed plate 26, the top fixed plate are attached on the ceiling 27 in house and pass through expanding screw Bolt is fixed.
The position of platform sling can be chosen as needed, and platform sling, sunpender, top fixed plate, expansion bolt can be further Cross girders is lifted, uses cross girders safer.
Embodiment 7:
Super-high storied building described in embodiment 6 installs the overhung construction of two floor plates additional, and the sunpender is cased with plastic sheath 28, institute The plastic sheath connection decoration floral leaf 29 stated or the decoration leaf of bamboo.
It is not only simple but also beautiful to decorate floral leaf or decorative bamboo acanthus sunpender, assembling speed is also fast.
Embodiment 8:
Super-high storied building as described in example 2 installs the overhung construction of two floor plates additional, and the left platform sling is bonded left magnetic patch 30, In same plane, the left magnetic patch is inhaled for the outer end of the expansion bolt of the left magnetic patch and the fixed left platform sling Left fixed magnetic sheet 31 is closed, the left fixed magnetic sheet is bonded in the inside of left decorative panel 32.
Left decorative panel is attracted left fixed magnetic sheet by left magnetic patch and is fixed, and fixed is i.e. securely and stable.
Embodiment 9:
Super-high storied building described in embodiment 3 installs the overhung construction of two floor plates additional, and the right platform sling is bonded right magnetic patch 33, In same plane, the right magnetic patch is inhaled for the outer end of the expansion bolt of the right magnetic patch and the fixed right platform sling Right fixed magnetic sheet 34 is closed, the right fixed magnetic sheet is bonded in the inside of right decorative panel 35.
Right decorative panel is attracted right fixed magnetic sheet by right magnetic patch and is fixed, and fixed is i.e. securely and stable.
Embodiment 10:
A kind of super-high storied building installs the construction method of the overhung construction of two floor plates additional, this construction method includes seven steps, and first Left wall is outputed left socket by step, right wall outputs right socket, and cross girders is inserted into left socket and right socket by second step, and uses water Mud is fixed, and left lifting sub-assembly is assembled on the first from left port and the second from left port and is fixed by third step, right lifting combination Part is assembled on a right port and right two ports and is fixed, and left platform sling is fixed on left wall by the 4th step, and right platform sling is solid It is scheduled on right wall, the 5th step is chosen the position of platform sling as needed and is fixed, and the 6th step is fixed on top for fixed plate is pushed up On canopy, the 7th step assembles decorative panel, left decorative panel, right decorative panel, plastic sheath or magnetic sheet set.
Embodiment 11:
Super-high storied building described in above-described embodiment installs the overhung construction and construction method of two floor plates additional, wherein one group 2 Stair are connected between cross girders.
Embodiment 12:
Super-high storied building described in embodiment 7 installs the overhung construction of two floor plates additional, and the sunpender connects magnetic sheet set, described Magnetic sheet set be attracted decoration magnetic sheet, the decoration magnetic sheet be bonded in decorate partition panel inside.
Decoration partition panel can clamp sunpender and be installed, and can be wrapped in sunpender between 2 decoration partition panels, very Beauty, and assembling speed is fast.
Laying floor 36 on cross girders are parallel to each other between cross girders, bearing beam 37 are lined between cross girders and floor.

Claims (10)

1. a kind of super-high storied building installs the overhung construction of two floor plates additional, composition includes: house, it is characterized in that: the house Left wall and right wall with length direction, the left wall are provided with one group of left socket being parallel to each other, the right wall Body is provided with one group of right socket being parallel to each other, and cross girders, the cross are inserted between the left socket and the right socket The first from left port and the second from left port are provided on the left of joist, the first from left port is combined with the left lifting of the second from left port connection Part, the left lifting sub-assembly are fixed on the left wall by one group of expansion bolt, the right side of the cross girders It is provided with a right port and right two ports, one port of the right side connect right lifting sub-assembly with two port of the right side, described Right lifting sub-assembly is fixed on the right wall by one group of expansion bolt.
2. super-high storied building according to claim 1 installs the overhung construction of two floor plates additional, it is characterized in that: the left lifting Sub-assembly includes left platform sling, and the left platform sling is attached on the left wall and is fixed by expansion bolt, and the left side is hung The bottom insertion of plate the first from left port, the left platform sling are vertically fixedly connected with left supporting plate, and the left supporting plate is vertically solid Surely left plate is connected, the left plate is vertically fixedly connected with left flexible fastening plate, and the right side of the second from left port connects left Hugging, the left plate are inserted into the second from left port, in the left flexible fastening plate insertion left hugging, simultaneously It is fixed by screw, the left supporting plate is attached to bottom between the first from left port and the second from left port, simultaneously It is fixed by screw.
3. super-high storied building according to claim 1 installs the overhung construction of two floor plates additional, it is characterized in that: the right lifting Sub-assembly includes right platform sling, and the right platform sling is attached on the right wall and is fixed by expansion bolt, and the right side is hung The bottom insertion of plate one port of the right side, the right platform sling are vertically fixedly connected with right supporting plate, and the right supporting plate is vertically solid Surely right plate is connected, the right plate is vertically fixedly connected with right flexible fastening plate, and the right side of two port of the right side connects right Hugging, the right plate are inserted into two port of the right side, in the right flexible fastening plate insertion right hugging, simultaneously It is fixed by screw, the right supporting plate is attached to bottom between one port of the right side and two port of the right side, simultaneously It is fixed by screw.
4. super-high storied building according to claim 1 installs the overhung construction of two floor plates additional, it is characterized in that: the left socket It corresponds to the right socket and is parallel to each other, the left socket that the left side insertion of the cross girders is described is simultaneously solid with cement slurry Fixed, the right side insertion right socket of the cross girders is simultaneously fixed with cement slurry.
5. super-high storied building according to claim 1 installs the overhung construction of two floor plates additional, it is characterized in that: the bottom of cross girders Magnetic sheet, the magnetic sheet and left supporting plate and right supporting plate are bonded in same plane, the magnetic sheet is fixed magnetic sheet, and described consolidates Determine the top that magnetic sheet is bonded in decorative panel.
6. super-high storied building according to claim 1 installs the overhung construction of two floor plates additional, it is characterized in that: the cross girders The suitable position in top connect platform sling, overpenetrated bolt is led between the cross girders and the platform sling and is fixed, it is described Platform sling weld sunpender, described sunpender welding top fixed plate, the top fixed plate is attached on the ceiling in house and passes through swollen Swollen bolt is fixed.
7. super-high storied building according to claim 6 installs the overhung construction of two floor plates additional, it is characterized in that: the sunpender set There are plastic sheath or sunpender connection magnetic sheet set, the plastic sheath connection decoration floral leaf or the decoration leaf of bamboo, the magnetic sheet Set is attracted decoration magnetic sheet, and the decoration magnetic sheet is bonded in the inside of decoration partition panel.
8. super-high storied building according to claim 2 installs the overhung construction of two floor plates additional, it is characterized in that: the left platform sling It is bonded left magnetic patch, the outer end of the expansion bolt of the left magnetic patch left platform sling described with fixation is in same plane, institute The left magnetic patch stated is attracted left fixed magnetic sheet, and the left fixed magnetic sheet is bonded in the inside of left decorative panel.
9. super-high storied building according to claim 3 installs the overhung construction of two floor plates additional, it is characterized in that: the right platform sling It is bonded right magnetic patch, the outer end of the expansion bolt of the right magnetic patch right platform sling described with fixation is in same plane, institute The right magnetic patch stated is attracted right fixed magnetic sheet, and the right fixed magnetic sheet is bonded in the inside of right decorative panel.
10. a kind of super-high storied building installs the construction method of the overhung construction of two floor plates additional, it is characterized in that: this construction method includes seven Step, left wall is outputed left socket by the first step, right wall outputs right socket, and cross girders is inserted into left socket and inserted with the right side by second step Mouthful, and fixed with cement slurry, left lifting sub-assembly is assembled on the first from left port and the second from left port and is fixed by third step, right Lifting sub-assembly is assembled on a right port and right two ports and is fixed, and left platform sling is fixed on left wall by the 4th step, Right platform sling is fixed on right wall, and the 5th step is chosen the position of platform sling as needed and is fixed, and the 6th step will push up fixed plate It is fixed on ceiling, the 7th step assembles decorative panel, left decorative panel, right decorative panel, plastic sheath or magnetic sheet set.
CN201811028810.2A 2018-08-28 2018-08-28 Suspension structure for additionally installing two floors on ultrahigh floor and construction method Expired - Fee Related CN109113364B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811028810.2A CN109113364B (en) 2018-08-28 2018-08-28 Suspension structure for additionally installing two floors on ultrahigh floor and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811028810.2A CN109113364B (en) 2018-08-28 2018-08-28 Suspension structure for additionally installing two floors on ultrahigh floor and construction method

Publications (2)

Publication Number Publication Date
CN109113364A true CN109113364A (en) 2019-01-01
CN109113364B CN109113364B (en) 2020-12-15

Family

ID=64858056

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811028810.2A Expired - Fee Related CN109113364B (en) 2018-08-28 2018-08-28 Suspension structure for additionally installing two floors on ultrahigh floor and construction method

Country Status (1)

Country Link
CN (1) CN109113364B (en)

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN86102326A (en) * 1986-04-23 1987-03-11 夏英湖 The storey-plus extension project in the old room of low layer, greening
CN1131975A (en) * 1993-08-10 1996-09-25 詹姆斯·W·富兰克林 Concrete building frame construction method
CN2246143Y (en) * 1995-10-11 1997-01-29 浙江省海宁市狮岭电梯装饰厂 Magnetic elevator box decorative board
GB0314911D0 (en) * 2003-06-26 2003-07-30 Harvey Peter R Improvements in or relating to a principal roof truss for loft conversion
CN1470720A (en) * 2003-06-23 2004-01-28 上海建科建筑设计院 Suspension type steel concrete residence structure
CN101892706A (en) * 2010-07-09 2010-11-24 浙江大学 Current building renovation external energy-saving balcony structure system
CN102051983A (en) * 2010-12-01 2011-05-11 西安建筑科技大学 Method of reconstructing steel rolling workshop into teaching building
CN202416577U (en) * 2012-02-27 2012-09-05 山东同圆设计集团有限公司 Suspended type equipment layer
CN203066343U (en) * 2013-03-06 2013-07-17 四川东大板业有限公司 Steel edge frame heat insulation light board/wall board/roof board/LOFT interlayer floor slab
CN206467871U (en) * 2017-01-18 2017-09-05 北京东方国兴建筑设计院有限公司 A kind of novel metal draws in the net ceiling decoration structure
CN107761946A (en) * 2017-12-01 2018-03-06 贵州精正检测有限公司 Steel construction assembled architecture

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN86102326A (en) * 1986-04-23 1987-03-11 夏英湖 The storey-plus extension project in the old room of low layer, greening
CN1131975A (en) * 1993-08-10 1996-09-25 詹姆斯·W·富兰克林 Concrete building frame construction method
CN2246143Y (en) * 1995-10-11 1997-01-29 浙江省海宁市狮岭电梯装饰厂 Magnetic elevator box decorative board
CN1470720A (en) * 2003-06-23 2004-01-28 上海建科建筑设计院 Suspension type steel concrete residence structure
GB0314911D0 (en) * 2003-06-26 2003-07-30 Harvey Peter R Improvements in or relating to a principal roof truss for loft conversion
CN101892706A (en) * 2010-07-09 2010-11-24 浙江大学 Current building renovation external energy-saving balcony structure system
CN102051983A (en) * 2010-12-01 2011-05-11 西安建筑科技大学 Method of reconstructing steel rolling workshop into teaching building
CN202416577U (en) * 2012-02-27 2012-09-05 山东同圆设计集团有限公司 Suspended type equipment layer
CN203066343U (en) * 2013-03-06 2013-07-17 四川东大板业有限公司 Steel edge frame heat insulation light board/wall board/roof board/LOFT interlayer floor slab
CN206467871U (en) * 2017-01-18 2017-09-05 北京东方国兴建筑设计院有限公司 A kind of novel metal draws in the net ceiling decoration structure
CN107761946A (en) * 2017-12-01 2018-03-06 贵州精正检测有限公司 Steel construction assembled architecture

Also Published As

Publication number Publication date
CN109113364B (en) 2020-12-15

Similar Documents

Publication Publication Date Title
RU2634132C2 (en) Method and system for building construction
US8402706B2 (en) Pillar part for modular construction
DK2617913T3 (en) Prefabricated PANEL TO A BUILDING
US20160040443A1 (en) Modular Building System
US20130305629A1 (en) Modular Building System
CN106400966B (en) A kind of assembling method of prefabricated integral assembling formula movable plank house
AU2013201852A1 (en) Modular Building
WO2015071821A1 (en) Modular prefabricated panel for buildings, in particular for houses
CN102561513A (en) Unit cabin type building system
US4586299A (en) Building system of interconnected block elements
AU2013332012B2 (en) Building system, particularly a residential building
US10240334B2 (en) Z-arch building system
CN205134527U (en) Three -dimensional building module
CN204781575U (en) Structure keeps warm and decorates outer wall hanging plate of large -scale prefabrication of integration
CN211774828U (en) Multifunctional light steel keel and partition wall
CN105040815A (en) Three-dimensional building module and factory building and on-site installing method thereof
CN106193540B (en) A kind of GRC components
CN209260911U (en) Foldable modular building
CN109113364A (en) Super-high storied building installs the overhung construction and construction method of two floor plates additional
CN207277542U (en) A kind of Novel steel-wooden frame structure
CN216195894U (en) Light trough structure and suspended ceiling
CN209538396U (en) It is foldable now to fill modular building
CN201962894U (en) Suspension structure for building wall
CN101070723A (en) Large unit assembled sandwich decoration board
CN214461603U (en) Independent back-hanging stone curtain wall structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201215

Termination date: 20210828

CF01 Termination of patent right due to non-payment of annual fee