CN109113364A - Super-high storied building installs the overhung construction and construction method of two floor plates additional - Google Patents
Super-high storied building installs the overhung construction and construction method of two floor plates additional Download PDFInfo
- Publication number
- CN109113364A CN109113364A CN201811028810.2A CN201811028810A CN109113364A CN 109113364 A CN109113364 A CN 109113364A CN 201811028810 A CN201811028810 A CN 201811028810A CN 109113364 A CN109113364 A CN 109113364A
- Authority
- CN
- China
- Prior art keywords
- fixed
- port
- platform sling
- plate
- super
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0266—Enlarging
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Chemical & Material Sciences (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Electrochemistry (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Floor Finish (AREA)
Abstract
Super-high storied building installs the overhung construction and construction method of two floor plates additional.Its composition of the invention includes: house, the house has the left wall and right wall of length direction, the left wall is provided with one group of left socket being parallel to each other, the right wall is provided with one group of right socket being parallel to each other, cross girders is inserted between the left socket and the right socket, the first from left port and the second from left port are provided on the left of the cross girders, the first from left port connect left lifting sub-assembly with the second from left port, the left lifting sub-assembly is fixed on the left wall by one group of expansion bolt, a right port and right two ports are provided on the right side of the cross girders, one port of the right side connect right lifting sub-assembly with two port of the right side, the right lifting sub-assembly is fixed on the right wall by one group of expansion bolt.The present invention installs two floor plates additional for super-high storied building.
Description
Technical field:
The present invention relates to overhung constructions and construction method that a kind of super-high storied building installs two floor plates additional.
Background technique:
It is all above normal level now with the height of house of many buildings, highly generally at 4.5 meters or more, if this
Sample is using will cause certain waste, if installing two layer height floors additional needs to be laid with one layer of joist or supporting plate, the support of installation
Perhaps to be supported existing method be supported in the bottom of joist or supporting plate to supporting plate needs to beam, such support meeting
The globality in house is destroyed, and reduces usable floor area.
Summary of the invention:
It does not need to support in bottom the object of the present invention is to provide one kind, installs two floor plate safety additional, using effect is good
Super-high storied building installs the overhung construction and construction method of two floor plates additional.
Above-mentioned purpose is realized by following technical scheme:
A kind of super-high storied building installs the overhung construction of two floor plates additional, and composition includes: house, and the house has length
The left wall and right wall in direction, the left wall are provided with one group of left socket being parallel to each other, and the right wall is provided with one
The right socket that group is parallel to each other is inserted into cross girders, a left side for the cross girders between the left socket and the right socket
Side is provided with the first from left port and the second from left port, and the first from left port connect left lifting sub-assembly with the second from left port, described
Left lifting sub-assembly be fixed on by one group of expansion bolt on the left wall, the right side one is provided on the right side of the cross girders
Port and right two ports, one port of the right side connect right lifting sub-assembly, the right lifting group with two port of the right side
Component is fixed on the right wall by one group of expansion bolt.
The super-high storied building installs the overhung construction of two floor plates additional, and the left lifting sub-assembly includes left platform sling, institute
The left platform sling stated is attached on the left wall and is fixed by expansion bolt, the bottom insertion of the left platform sling left side
One port, the left platform sling are vertically fixedly connected with left supporting plate, and the left supporting plate is vertically fixedly connected with left plate, the left side
Plate is vertically fixedly connected with left flexible fastening plate, and the right side of the second from left port connects left hugging, the left plate insertion
In the second from left port, it is fixed in the left flexible fastening plate insertion left hugging and by screw, it is described
Left supporting plate be attached to the bottom between the first from left port and the second from left port and be fixed by screw.
The super-high storied building installs the overhung construction of two floor plates additional, and the right lifting sub-assembly includes right platform sling, institute
The right platform sling stated is attached on the right wall and is fixed by expansion bolt, the bottom insertion of the right platform sling right side
One port, the right platform sling are vertically fixedly connected with right supporting plate, and the right supporting plate is vertically fixedly connected with right plate, the right side
Plate is vertically fixedly connected with right flexible fastening plate, and the right side of two port of the right side connects right hugging, the right plate insertion
In two port of the right side, it is fixed in the right flexible fastening plate insertion right hugging and by screw, it is described
Right supporting plate be attached to the bottom between one port of the right side and two port of the right side and be fixed by screw.
The super-high storied building installs the overhung construction of two floor plates additional, the corresponding right socket of the left socket, simultaneously
And be parallel to each other, the left side insertion left socket of the cross girders is simultaneously fixed, the right side of the cross girders with cement slurry
The insertion right socket in side is simultaneously fixed with cement slurry.
The super-high storied building installs the overhung construction of two floor plates additional, and the bottom of cross girders is bonded magnetic sheet, the magnetic sheet
With left supporting plate and right supporting plate in same plane, the magnetic sheet is fixed magnetic sheet, and the fixation magnetic sheet is bonded in decorative panel
Top.
The super-high storied building installs the overhung construction of two floor plates, the suitable position connection in the top of the cross girders additional
Platform sling leads to overpenetrated bolt and fixes between the cross girders and the platform sling, the platform sling welds sunpender, described
Sunpender welding top fixed plate, the top fixed plate are attached on the ceiling in house and are fixed by expansion bolt.
The super-high storied building installs the overhung construction of two floor plates additional, and the sunpender is cased with plastic sheath or the sunpender
Magnetic sheet set, the plastic sheath connection decoration floral leaf or the decoration leaf of bamboo are connected, the magnetic sheet set is attracted decoration magnetic sheet, described
Decoration magnetic sheet is bonded in the inside of decoration partition panel.
The super-high storied building installs the overhung construction of two floor plates additional, and the left platform sling is bonded left magnetic patch, the left side
In same plane, the left magnetic patch is attracted left fixation for the outer end of the expansion bolt of magnetic patch and the fixed left platform sling
Magnetic sheet, the left fixed magnetic sheet are bonded in the inside of left decorative panel.
The super-high storied building installs the overhung construction of two floor plates additional, and the right platform sling is bonded right magnetic patch, the right side
In same plane, the right magnetic patch is attracted right fixation for the outer end of the expansion bolt of magnetic patch and the fixed right platform sling
Magnetic sheet, the right fixed magnetic sheet are bonded in the inside of right decorative panel.
A kind of super-high storied building installs the construction method of the overhung construction of two floor plates additional, this construction method includes seven steps, and first
Left wall is outputed left socket by step, right wall outputs right socket, and cross girders is inserted into left socket and right socket by second step, and uses water
Mud is fixed, and left lifting sub-assembly is assembled on the first from left port and the second from left port and is fixed by third step, right lifting combination
Part is assembled on a right port and right two ports and is fixed, and left platform sling is fixed on left wall by the 4th step, and right platform sling is solid
It is scheduled on right wall, the 5th step is chosen the position of platform sling as needed and is fixed, and the 6th step is fixed on top for fixed plate is pushed up
On canopy, the 7th step assembles decorative panel, left decorative panel, right decorative panel, plastic sheath or magnetic sheet set.
The utility model has the advantages that
1. speed is fast when present invention assembling, construction, secured after assembling, use is very safe, and decorative parts are also square
Just it assembles, it is beautiful, beautiful after assembling.
2. left platform sling of the invention is fixed on left wall, right platform sling is fixed on and is fully able to undertake cross girders on right wall
And the weight of the article on the floor, placement being laid on cross girders, human body up, use is very safe.
3. the present invention does not need to be supported in the bottom of cross girders, it is not take up the space of Stall, makes the globality of Stall
It is very good, increase usable floor area.
4. decorative parts of the invention are attached by magnetic, assembling, speed of application are all fast, need to replace decoration
It is all convenient when plate and ornament.
Detailed description of the invention:
Attached drawing 1 is the structural schematic diagram of this product.
Attached drawing 2 is structural schematic diagram of this product equipped with decoration floral leaf.
Attached drawing 3 is the structural schematic diagram of cross girders in attached drawing 2 and attached drawing 1.
Specific embodiment:
Embodiment 1:
A kind of super-high storied building installs the overhung construction of two floor plates additional, and composition includes: house, and the house has length
The left wall 1 and right wall 2 in direction, the left wall are provided with one group of left socket 3 being parallel to each other, and the right wall is provided with
One group of right socket 4 being parallel to each other is inserted into cross girders 5, the cross girders between the left socket and the right socket
Left side be provided with the first from left port 6 and the second from left port 7, the first from left port is combined with the left lifting of the second from left port connection
Part, the left lifting sub-assembly are fixed on the left wall by one group of expansion bolt 8, the right side of the cross girders
One port 9 of the right side and right two ports 10 are provided with, one port of the right side connect right lifting sub-assembly with two port of the right side, described
Right lifting sub-assembly be fixed on by one group of expansion bolt on the right wall.
Left socket and right socket not only play the role of connection to cross girders, additionally it is possible to play the role of lifting, pass through
After cement slurry is fixed, it can guarantee that the connection between cross girders and left wall and right wall is stronger, using more
Safety.
Embodiment 2:
Super-high storied building described in embodiment 1 installs the overhung construction of two floor plates additional, and the left lifting sub-assembly includes a left side
Platform sling 11, the left platform sling are attached on the left wall and are fixed by expansion bolt, and the bottom of the left platform sling is inserted
Enter the first from left port, the left platform sling is vertically fixedly connected with left supporting plate 12, and the left supporting plate is vertically fixedly connected with a left side
Plate 13, the left plate are vertically fixedly connected with left flexible fastening plate 14, and the right side of the second from left port connects left hugging
15, the left plate is inserted into the second from left port, in the left flexible fastening plate insertion left hugging and is led to
It crosses screw to be fixed, the left supporting plate is attached to the bottom between the first from left port and the second from left port and leads to
Screw is crossed to be fixed.
Left platform sling, left supporting plate, left plate, left flexible fastening plate are structure as a whole, between the first from left port, the second from left port
Connection is very secured, and stronger after assembling, the left side of the cross girders of lifting is very secured, and use is very safe.
Embodiment 3:
Super-high storied building described in embodiment 1 installs the overhung construction of two floor plates additional, and the right lifting sub-assembly includes the right side
Platform sling 16, the right platform sling are attached on the right wall and are fixed by expansion bolt, and the bottom of the right platform sling is inserted
Enter one port of the right side, the right platform sling is vertically fixedly connected with right supporting plate 17, and the right supporting plate is vertically fixedly connected with the right side
Plate 18, the right plate are vertically fixedly connected with right flexible fastening plate 19, and the right side of two port of the right side connects right hugging
20, the right plate is inserted into two port of the right side, in the right flexible fastening plate insertion right hugging and is led to
It crosses screw to be fixed, the right supporting plate is attached to the bottom between one port of the right side and two port of the right side and leads to
Screw is crossed to be fixed.
Right platform sling, right supporting plate, right plate, right flexible fastening plate are structure as a whole, between a right port, right two ports
Connection is very secured, and stronger after assembling, the right side of the cross girders of lifting is very secured, and use is very safe.
Embodiment 4:
Super-high storied building described in embodiment 1 installs the overhung construction of two floor plates, the corresponding right side of the left socket additional
It socket and is parallel to each other, the left socket that the left side insertion of the cross girders is described is simultaneously fixed, the cross with cement slurry
The right side insertion right socket of joist is simultaneously fixed with cement slurry.
The supporting power of cross girders is good, and use is safe, effect is good.
Embodiment 5:
Super-high storied building described in embodiment 1 installs the overhung construction of two floor plates additional, and the bottom of cross girders is bonded magnetic sheet 21, institute
In same plane, the magnetic sheet is fixed magnetic sheet 22 for the magnetic sheet and left supporting plate stated and right supporting plate, and the fixation magnetic sheet is viscous
It connects at the top of decorative panel 23.Decorative panel installation speed is fast, convenient when installation.
Embodiment 6:
Super-high storied building described in embodiment 1 installs the overhung construction of two floor plates additional, and the top of the cross girders is suitable
Position connects platform sling 24, and overpenetrated bolt is led between the cross girders and the platform sling and is fixed, the platform sling welding
Sunpender 25, the sunpender welding top fixed plate 26, the top fixed plate are attached on the ceiling 27 in house and pass through expanding screw
Bolt is fixed.
The position of platform sling can be chosen as needed, and platform sling, sunpender, top fixed plate, expansion bolt can be further
Cross girders is lifted, uses cross girders safer.
Embodiment 7:
Super-high storied building described in embodiment 6 installs the overhung construction of two floor plates additional, and the sunpender is cased with plastic sheath 28, institute
The plastic sheath connection decoration floral leaf 29 stated or the decoration leaf of bamboo.
It is not only simple but also beautiful to decorate floral leaf or decorative bamboo acanthus sunpender, assembling speed is also fast.
Embodiment 8:
Super-high storied building as described in example 2 installs the overhung construction of two floor plates additional, and the left platform sling is bonded left magnetic patch 30,
In same plane, the left magnetic patch is inhaled for the outer end of the expansion bolt of the left magnetic patch and the fixed left platform sling
Left fixed magnetic sheet 31 is closed, the left fixed magnetic sheet is bonded in the inside of left decorative panel 32.
Left decorative panel is attracted left fixed magnetic sheet by left magnetic patch and is fixed, and fixed is i.e. securely and stable.
Embodiment 9:
Super-high storied building described in embodiment 3 installs the overhung construction of two floor plates additional, and the right platform sling is bonded right magnetic patch 33,
In same plane, the right magnetic patch is inhaled for the outer end of the expansion bolt of the right magnetic patch and the fixed right platform sling
Right fixed magnetic sheet 34 is closed, the right fixed magnetic sheet is bonded in the inside of right decorative panel 35.
Right decorative panel is attracted right fixed magnetic sheet by right magnetic patch and is fixed, and fixed is i.e. securely and stable.
Embodiment 10:
A kind of super-high storied building installs the construction method of the overhung construction of two floor plates additional, this construction method includes seven steps, and first
Left wall is outputed left socket by step, right wall outputs right socket, and cross girders is inserted into left socket and right socket by second step, and uses water
Mud is fixed, and left lifting sub-assembly is assembled on the first from left port and the second from left port and is fixed by third step, right lifting combination
Part is assembled on a right port and right two ports and is fixed, and left platform sling is fixed on left wall by the 4th step, and right platform sling is solid
It is scheduled on right wall, the 5th step is chosen the position of platform sling as needed and is fixed, and the 6th step is fixed on top for fixed plate is pushed up
On canopy, the 7th step assembles decorative panel, left decorative panel, right decorative panel, plastic sheath or magnetic sheet set.
Embodiment 11:
Super-high storied building described in above-described embodiment installs the overhung construction and construction method of two floor plates additional, wherein one group 2
Stair are connected between cross girders.
Embodiment 12:
Super-high storied building described in embodiment 7 installs the overhung construction of two floor plates additional, and the sunpender connects magnetic sheet set, described
Magnetic sheet set be attracted decoration magnetic sheet, the decoration magnetic sheet be bonded in decorate partition panel inside.
Decoration partition panel can clamp sunpender and be installed, and can be wrapped in sunpender between 2 decoration partition panels, very
Beauty, and assembling speed is fast.
Laying floor 36 on cross girders are parallel to each other between cross girders, bearing beam 37 are lined between cross girders and floor.
Claims (10)
1. a kind of super-high storied building installs the overhung construction of two floor plates additional, composition includes: house, it is characterized in that: the house
Left wall and right wall with length direction, the left wall are provided with one group of left socket being parallel to each other, the right wall
Body is provided with one group of right socket being parallel to each other, and cross girders, the cross are inserted between the left socket and the right socket
The first from left port and the second from left port are provided on the left of joist, the first from left port is combined with the left lifting of the second from left port connection
Part, the left lifting sub-assembly are fixed on the left wall by one group of expansion bolt, the right side of the cross girders
It is provided with a right port and right two ports, one port of the right side connect right lifting sub-assembly with two port of the right side, described
Right lifting sub-assembly is fixed on the right wall by one group of expansion bolt.
2. super-high storied building according to claim 1 installs the overhung construction of two floor plates additional, it is characterized in that: the left lifting
Sub-assembly includes left platform sling, and the left platform sling is attached on the left wall and is fixed by expansion bolt, and the left side is hung
The bottom insertion of plate the first from left port, the left platform sling are vertically fixedly connected with left supporting plate, and the left supporting plate is vertically solid
Surely left plate is connected, the left plate is vertically fixedly connected with left flexible fastening plate, and the right side of the second from left port connects left
Hugging, the left plate are inserted into the second from left port, in the left flexible fastening plate insertion left hugging, simultaneously
It is fixed by screw, the left supporting plate is attached to bottom between the first from left port and the second from left port, simultaneously
It is fixed by screw.
3. super-high storied building according to claim 1 installs the overhung construction of two floor plates additional, it is characterized in that: the right lifting
Sub-assembly includes right platform sling, and the right platform sling is attached on the right wall and is fixed by expansion bolt, and the right side is hung
The bottom insertion of plate one port of the right side, the right platform sling are vertically fixedly connected with right supporting plate, and the right supporting plate is vertically solid
Surely right plate is connected, the right plate is vertically fixedly connected with right flexible fastening plate, and the right side of two port of the right side connects right
Hugging, the right plate are inserted into two port of the right side, in the right flexible fastening plate insertion right hugging, simultaneously
It is fixed by screw, the right supporting plate is attached to bottom between one port of the right side and two port of the right side, simultaneously
It is fixed by screw.
4. super-high storied building according to claim 1 installs the overhung construction of two floor plates additional, it is characterized in that: the left socket
It corresponds to the right socket and is parallel to each other, the left socket that the left side insertion of the cross girders is described is simultaneously solid with cement slurry
Fixed, the right side insertion right socket of the cross girders is simultaneously fixed with cement slurry.
5. super-high storied building according to claim 1 installs the overhung construction of two floor plates additional, it is characterized in that: the bottom of cross girders
Magnetic sheet, the magnetic sheet and left supporting plate and right supporting plate are bonded in same plane, the magnetic sheet is fixed magnetic sheet, and described consolidates
Determine the top that magnetic sheet is bonded in decorative panel.
6. super-high storied building according to claim 1 installs the overhung construction of two floor plates additional, it is characterized in that: the cross girders
The suitable position in top connect platform sling, overpenetrated bolt is led between the cross girders and the platform sling and is fixed, it is described
Platform sling weld sunpender, described sunpender welding top fixed plate, the top fixed plate is attached on the ceiling in house and passes through swollen
Swollen bolt is fixed.
7. super-high storied building according to claim 6 installs the overhung construction of two floor plates additional, it is characterized in that: the sunpender set
There are plastic sheath or sunpender connection magnetic sheet set, the plastic sheath connection decoration floral leaf or the decoration leaf of bamboo, the magnetic sheet
Set is attracted decoration magnetic sheet, and the decoration magnetic sheet is bonded in the inside of decoration partition panel.
8. super-high storied building according to claim 2 installs the overhung construction of two floor plates additional, it is characterized in that: the left platform sling
It is bonded left magnetic patch, the outer end of the expansion bolt of the left magnetic patch left platform sling described with fixation is in same plane, institute
The left magnetic patch stated is attracted left fixed magnetic sheet, and the left fixed magnetic sheet is bonded in the inside of left decorative panel.
9. super-high storied building according to claim 3 installs the overhung construction of two floor plates additional, it is characterized in that: the right platform sling
It is bonded right magnetic patch, the outer end of the expansion bolt of the right magnetic patch right platform sling described with fixation is in same plane, institute
The right magnetic patch stated is attracted right fixed magnetic sheet, and the right fixed magnetic sheet is bonded in the inside of right decorative panel.
10. a kind of super-high storied building installs the construction method of the overhung construction of two floor plates additional, it is characterized in that: this construction method includes seven
Step, left wall is outputed left socket by the first step, right wall outputs right socket, and cross girders is inserted into left socket and inserted with the right side by second step
Mouthful, and fixed with cement slurry, left lifting sub-assembly is assembled on the first from left port and the second from left port and is fixed by third step, right
Lifting sub-assembly is assembled on a right port and right two ports and is fixed, and left platform sling is fixed on left wall by the 4th step,
Right platform sling is fixed on right wall, and the 5th step is chosen the position of platform sling as needed and is fixed, and the 6th step will push up fixed plate
It is fixed on ceiling, the 7th step assembles decorative panel, left decorative panel, right decorative panel, plastic sheath or magnetic sheet set.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811028810.2A CN109113364B (en) | 2018-08-28 | 2018-08-28 | Suspension structure for additionally installing two floors on ultrahigh floor and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811028810.2A CN109113364B (en) | 2018-08-28 | 2018-08-28 | Suspension structure for additionally installing two floors on ultrahigh floor and construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109113364A true CN109113364A (en) | 2019-01-01 |
CN109113364B CN109113364B (en) | 2020-12-15 |
Family
ID=64858056
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811028810.2A Expired - Fee Related CN109113364B (en) | 2018-08-28 | 2018-08-28 | Suspension structure for additionally installing two floors on ultrahigh floor and construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109113364B (en) |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN86102326A (en) * | 1986-04-23 | 1987-03-11 | 夏英湖 | The storey-plus extension project in the old room of low layer, greening |
CN1131975A (en) * | 1993-08-10 | 1996-09-25 | 詹姆斯·W·富兰克林 | Concrete building frame construction method |
CN2246143Y (en) * | 1995-10-11 | 1997-01-29 | 浙江省海宁市狮岭电梯装饰厂 | Magnetic elevator box decorative board |
GB0314911D0 (en) * | 2003-06-26 | 2003-07-30 | Harvey Peter R | Improvements in or relating to a principal roof truss for loft conversion |
CN1470720A (en) * | 2003-06-23 | 2004-01-28 | 上海建科建筑设计院 | Suspension type steel concrete residence structure |
CN101892706A (en) * | 2010-07-09 | 2010-11-24 | 浙江大学 | Current building renovation external energy-saving balcony structure system |
CN102051983A (en) * | 2010-12-01 | 2011-05-11 | 西安建筑科技大学 | Method of reconstructing steel rolling workshop into teaching building |
CN202416577U (en) * | 2012-02-27 | 2012-09-05 | 山东同圆设计集团有限公司 | Suspended type equipment layer |
CN203066343U (en) * | 2013-03-06 | 2013-07-17 | 四川东大板业有限公司 | Steel edge frame heat insulation light board/wall board/roof board/LOFT interlayer floor slab |
CN206467871U (en) * | 2017-01-18 | 2017-09-05 | 北京东方国兴建筑设计院有限公司 | A kind of novel metal draws in the net ceiling decoration structure |
CN107761946A (en) * | 2017-12-01 | 2018-03-06 | 贵州精正检测有限公司 | Steel construction assembled architecture |
-
2018
- 2018-08-28 CN CN201811028810.2A patent/CN109113364B/en not_active Expired - Fee Related
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN86102326A (en) * | 1986-04-23 | 1987-03-11 | 夏英湖 | The storey-plus extension project in the old room of low layer, greening |
CN1131975A (en) * | 1993-08-10 | 1996-09-25 | 詹姆斯·W·富兰克林 | Concrete building frame construction method |
CN2246143Y (en) * | 1995-10-11 | 1997-01-29 | 浙江省海宁市狮岭电梯装饰厂 | Magnetic elevator box decorative board |
CN1470720A (en) * | 2003-06-23 | 2004-01-28 | 上海建科建筑设计院 | Suspension type steel concrete residence structure |
GB0314911D0 (en) * | 2003-06-26 | 2003-07-30 | Harvey Peter R | Improvements in or relating to a principal roof truss for loft conversion |
CN101892706A (en) * | 2010-07-09 | 2010-11-24 | 浙江大学 | Current building renovation external energy-saving balcony structure system |
CN102051983A (en) * | 2010-12-01 | 2011-05-11 | 西安建筑科技大学 | Method of reconstructing steel rolling workshop into teaching building |
CN202416577U (en) * | 2012-02-27 | 2012-09-05 | 山东同圆设计集团有限公司 | Suspended type equipment layer |
CN203066343U (en) * | 2013-03-06 | 2013-07-17 | 四川东大板业有限公司 | Steel edge frame heat insulation light board/wall board/roof board/LOFT interlayer floor slab |
CN206467871U (en) * | 2017-01-18 | 2017-09-05 | 北京东方国兴建筑设计院有限公司 | A kind of novel metal draws in the net ceiling decoration structure |
CN107761946A (en) * | 2017-12-01 | 2018-03-06 | 贵州精正检测有限公司 | Steel construction assembled architecture |
Also Published As
Publication number | Publication date |
---|---|
CN109113364B (en) | 2020-12-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
RU2634132C2 (en) | Method and system for building construction | |
US8402706B2 (en) | Pillar part for modular construction | |
DK2617913T3 (en) | Prefabricated PANEL TO A BUILDING | |
US20160040443A1 (en) | Modular Building System | |
US20130305629A1 (en) | Modular Building System | |
CN106400966B (en) | A kind of assembling method of prefabricated integral assembling formula movable plank house | |
AU2013201852A1 (en) | Modular Building | |
WO2015071821A1 (en) | Modular prefabricated panel for buildings, in particular for houses | |
CN102561513A (en) | Unit cabin type building system | |
US4586299A (en) | Building system of interconnected block elements | |
AU2013332012B2 (en) | Building system, particularly a residential building | |
US10240334B2 (en) | Z-arch building system | |
CN205134527U (en) | Three -dimensional building module | |
CN204781575U (en) | Structure keeps warm and decorates outer wall hanging plate of large -scale prefabrication of integration | |
CN211774828U (en) | Multifunctional light steel keel and partition wall | |
CN105040815A (en) | Three-dimensional building module and factory building and on-site installing method thereof | |
CN106193540B (en) | A kind of GRC components | |
CN209260911U (en) | Foldable modular building | |
CN109113364A (en) | Super-high storied building installs the overhung construction and construction method of two floor plates additional | |
CN207277542U (en) | A kind of Novel steel-wooden frame structure | |
CN216195894U (en) | Light trough structure and suspended ceiling | |
CN209538396U (en) | It is foldable now to fill modular building | |
CN201962894U (en) | Suspension structure for building wall | |
CN101070723A (en) | Large unit assembled sandwich decoration board | |
CN214461603U (en) | Independent back-hanging stone curtain wall structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20201215 Termination date: 20210828 |
|