CN109083175A - The cushion cap foundation pit and its construction method for having continuous drainage function - Google Patents

The cushion cap foundation pit and its construction method for having continuous drainage function Download PDF

Info

Publication number
CN109083175A
CN109083175A CN201810966687.2A CN201810966687A CN109083175A CN 109083175 A CN109083175 A CN 109083175A CN 201810966687 A CN201810966687 A CN 201810966687A CN 109083175 A CN109083175 A CN 109083175A
Authority
CN
China
Prior art keywords
cushion cap
pit
outlet pipe
cap foundation
foundation pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810966687.2A
Other languages
Chinese (zh)
Inventor
王侨
罗利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN201810966687.2A priority Critical patent/CN109083175A/en
Publication of CN109083175A publication Critical patent/CN109083175A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/20Restraining of underground water by damming or interrupting the passage of underground water by displacing the water, e.g. by compressed air

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention discloses a kind of cushion cap foundation pit for having continuous drainage function and its construction methods, the bottom of cushion cap foundation pit is provided with catch pit, catch pit is connect by outlet pipe with the draining pump outside cushion cap foundation pit, and outlet pipe is embedded in cushion cap pouring layer and water resistant plate pouring layer;Internal layer filtering screen is provided in the catch pit, the water inlet end of the outlet pipe is located inside internal layer filtering screen.The function of realizing the draining of cushion cap foundation pit overall process, effectively reduces construction cost, and improve construction efficiency, this arrangement and method for construction is small by natural environment influence, and construction quality also more preferably controls.

Description

The cushion cap foundation pit and its construction method for having continuous drainage function
Technical field
The invention belongs to technical field of building construction, in particular to a kind of cushion cap foundation pit for having continuous drainage function and its Construction method.
Background technique
Cushion cap pit water accumulation be always room build in class basement construction need in face of the problem of, for cushion cap foundation pit Yield rainfall relation, Traditional approach be drained using immersible pump, but the fitness that immersible pump changes operating condition is poor, once encounter rainy, cushion cap Foundation pit can continuous ponding, it is therefore desirable to which continuous pump drainage, labour's consumption is big, and cost is also very high, and to cushion cap subsequent construction shadow Sound is larger, if processing is bad, or even influences whether waterproof effect.How by effective measures, construction quality both can guarantee, Cost can be reduced again, is accelerated construction progress, it appears very urgent.
Summary of the invention
It is an object of the invention to: in view of the above-mentioned problems of the prior art, providing one kind has continuous drainage function The cushion cap foundation pit and its construction method of energy, realize the effect of cushion cap foundation pit overall process drains, effectively reduce construction cost, and Improve construction efficiency.
The technical solution of the technology of the present invention is achieved in that a kind of cushion cap foundation pit for having continuous drainage function, is holding The bottom in stylobate hole is provided with catch pit, and catch pit is connect by outlet pipe with the draining pump outside cushion cap foundation pit, and outlet pipe It is embedded in cushion cap pouring layer and water resistant plate pouring layer;Internal layer filtering screen is provided in the catch pit, the outlet pipe Water inlet end is located inside internal layer filtering screen;The fitros bed of material is filled between the internal layer filtering screen and catch pit inner wall.
The cushion cap foundation pit of the present invention for having continuous drainage function, internal layer filtering screen bottom to catch pit bottom The distance in portion is the 1/3 of catch pit height, and the top of internal layer filtering screen is located under catch pit edge, the top of the fitros bed of material It is flushed with the edge of catch pit.
The cushion cap foundation pit of the present invention for having continuous drainage function is stamped one layer of isolation steel at the top of catch pit Plate, isolation steel plate are provided with the through-hole passed through for outlet pipe.
The cushion cap foundation pit of the present invention for having continuous drainage function, the crater wall for being close to catch pit are also equipped with outer layer mistake Screen cover, to stop sedendary soil, the fitros bed of material is between internal layer filtering screen and outer filter mesh enclosure.
The cushion cap foundation pit of the present invention for having continuous drainage function, the outlet pipe are pvc material, stretch out foundation pit Outer top is connected with elbow, and elbow water outlet picks out extension tube and connect with draining pump.
Have the cushion cap foundation ditch construction method of continuous drainage function, described method includes following steps:
S1: complete cushion cap foundation pit original hole is excavated;
S2: a catch pit is excavated again in the bottom Yuan Keng of cushion cap foundation pit;
S3: installing internal layer filtering screen in catch pit, and outlet pipe water inlet end is inserted into the internal layer filter screen in catch pit In cover, the water outlet of outlet pipe is picked out outside cushion cap foundation pit, and the filling between internal layer filtering screen and catch pit crater wall The fitros bed of material;
S4: starting lasting ponding outlet, after stylobate of entertaining hole is dry, the carry out waterproof protective layer construction of sequence, and foundation pit Steel mesh and water resistant plate bar frame facility work, and outlet pipe is fixed on steel mesh;
S5: one-piece casting foundation pit and water resistant plate, and carry out the maintenance of concrete.
The cushion cap foundation ditch construction method of the present invention for having continuous drainage function completes supporting for concrete in step S5 After protecting and reaching corresponding design strength, reversed slip casting is carried out to outlet pipe using cement mortar, so that cement mortar filling is full The gap of fitros material and outlet pipe, cement mortar and fitros material form permanent water-tight concrete, and outlet conduit permanently stays in In suspended deck structure.
The cushion cap foundation ditch construction method of the present invention for having continuous drainage function, in step s3, the outlet pipe It is installed perpendicular to horizontal plane, and is provided with stability of one or more the vertical vertical bar to reinforce outlet pipe.
The cushion cap foundation ditch construction method of the present invention for having continuous drainage function, in step s3, in installation internal layer Before filter screen, the crater wall for being first close to catch pit installs outer filter mesh enclosure, and fitros material is filled in internal layer filter screen and outer layer mistake Between strainer.
The cushion cap foundation ditch construction method of the present invention for having continuous drainage function, in step s3, the fitros bed of material It is flushed at the top of top and catch pit, stone layer filling to be filtered finishes, and covers one layer of isolation steel plate at the top of catch pit.
The invention has the benefit that realizing the function of cushion cap foundation pit overall process draining, construction cost is effectively reduced, And construction efficiency is improved, this arrangement and method for construction is small by natural environment influence, and construction quality also more preferably controls.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of cushion cap foundation pit of the present invention;
Fig. 2 is the isolation steel plate structure schematic diagram of cushion cap foundation pit of the present invention;
Fig. 3 is the top view of catch pit of the present invention.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to the accompanying drawings and embodiments, right The technology of the present invention is further elaborated.It should be appreciated that specific embodiment described herein is only used to explain this hair It is bright, it is not intended to limit the present invention.
As shown, having the cushion cap foundation pit of continuous drainage function, the bottom of cushion cap foundation pit 1 is provided with catch pit 2, collects Puddle 2 is connect by outlet pipe 4 with the draining pump 5 outside cushion cap foundation pit 1, and outlet pipe 4 can be embedded in cushion cap pouring layer and resist In water plate pouring layer.
Specifically, being provided with internal layer filtering screen 21 in the catch pit 2, the water inlet end of the outlet pipe 4 is located at internal layer Inside filtering screen 21;The fitros bed of material 22 is filled between 2 inner wall of the internal layer filtering screen 21 and catch pit.The fitros material The fitros material of layer 22 is the diameter that uniformly-graded, partial size 10-15mm, and the eyelet of internal layer filtering screen 21 are less than fitros.
The distance of 21 bottom of internal layer filtering screen to 2 bottom of catch pit is the 1/3 of 2 height of catch pit, internal layer filtering The top of mesh enclosure 21 is located under 2 edge of catch pit, and the top of the fitros bed of material 22 is flushed with the edge of catch pit 2.
It is stamped one layer of isolation steel plate 23 at the top of catch pit 2, isolation steel plate 23 is provided with the through-hole passed through for outlet pipe 4 231, it can be fallen into the fitros bed of material 22 to avoid sedendary soil from top, so that the gap between fitros material is blocked.
The crater wall for being close to catch pit 2 is also equipped with outer filter mesh enclosure 24, to stop sedendary soil, the fitros bed of material 22 Between internal layer filtering screen 21 and outer filter mesh enclosure 24.Outer filter mesh enclosure 24 can effectively keep the structure of catch pit Stablize, and further plays the purpose of filtering sedendary soil.Further, internal layer filtering screen 21 and outer filter mesh enclosure 24 It is cylinder, maximum hoop rigidity can be kept in this way, avoids being collapsed.
The outlet pipe 4 is installed perpendicular to horizontal plane, and the vertical vertical bar (not shown) for being provided with one or more is used To reinforce the stability of outlet pipe 4.Before cushion cap foundation pit 1 pours, the tube bottom of outlet pipe 4 has from 21 bottom of internal layer filtering screen To the freedom of movement at top.Requirement herein is, when between outlet pipe 4 and vertical vertical bar and subsequent laying steel mesh Connection, be not be fixed, and can guarantee outlet pipe 4 bottom nozzle can the bottom and top of internal layer filtering screen 21 it Between freely move up and down, in this way can according to operating condition needs, adjust height, to take the ponding at different depth away, until complete At pouring for armored concrete, and it must assure that the bottom of outlet pipe 4 is located at the center of internal layer filtering screen 21 when pouring.
The outlet pipe 4 is PVC material, and the top stretched out outside cushion cap foundation pit 1 is connected with elbow 41,41 water outlet of elbow It picks out extension tube 42 to connect with draining pump 5, the setting of elbow 41, can be convenient the connection of pipeline, and work as and reversely pour in the later period When note, it is also more convenient to disassemble remaining pipeline.
The construction method of the above-mentioned cushion cap foundation pit for having continuous drainage function includes the following steps:
S1: complete cushion cap foundation pit 1 is excavated;
S2: a catch pit 2 is excavated again in the bottom of cushion cap foundation pit 1;
S3: installing internal layer filtering screen 21 in catch pit 2, and 4 water inlet end of outlet pipe is inserted into the internal layer mistake in catch pit In screen cover 21, the water outlet of outlet pipe 4 is picked out outside cushion cap foundation pit, and is connect with draining pump 3, in internal layer filtering screen 21 The fitros bed of material 22 is packed between 2 crater wall of catch pit;
S4: starting lasting ponding outlet, after stylobate of entertaining hole 1 is dry, the carry out waterproof protective layer construction of sequence, and foundation pit Steel mesh and water resistant plate bar frame facility work, and outlet pipe 4 is fixed on steel mesh;
S5: one-piece casting cushion cap foundation pit 1 and water resistant plate 3, and carry out the maintenance of concrete.
After completing the maintenance of concrete in step S5 and reaching corresponding design strength, using cement mortar to outlet pipe 4 Reversed slip casting is carried out, the gap of water pipe 4 and the fitros bed of material 22 so that cement mortar filling is overfilled, cement mortar is formed with fitros material Permanent water-tight concrete, outlet pipe 4 permanently stay in suspended deck structure.
In step s3, the outlet pipe 4 is installed perpendicular to horizontal plane, and is provided with one or more vertical vertical bar (figure In be not shown) to reinforce the stability of outlet pipe.
In step s3, before installing internal layer filter screen 21, the crater wall for being first close to catch pit 2 installs outer filter mesh enclosure 24, fitros material is filled between internal layer filter screen 21 and outer filter net 24.
In step s3, the top of the fitros bed of material 22 is flushed with the top of catch pit 2, and the filling of stone layer 22 to be filtered finishes, One layer of isolation steel plate 23 is covered at the top of catch pit 2.
The cement mortar of reversed slip casting is impervious, cement mortar, component condition are as follows:
Additive: high performance water reducing agent of polyocarboxy acid, volume 1.5%;DX cement expansive material, volume 10%;
Cement: P.O42.5R;
Fine aggregate: Machine-made Sand, fineness modulus: 2.6;
Admixture: II grade of flyash;Fiber is split in SY-A resistance.
Match ratio is specially following table:
Fitros material can be uniformly-graded pellet, can also be non-homogeneous gradation pellet.When for non-homogeneous gradation pellet, Specification is 5-25mm;Gradation composition see the table below:
Serial number Square hole sieve size (mm) It is accumulative to tail over (%) (in mass)
1 4.75 90~100
2 9.50 70~90
3 16.0 50~70
4 19.0 25~40
5 25.5 0~5
The pressure of reversed slip casting: 0.5~1.5MPa;Outlet pipe is pvc pipe, while being also reversed Grouting Pipe, and caliber is 50-60mm。
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Made any modifications, equivalent replacements, and improvements etc., should all be included in the protection scope of the present invention within mind and principle.

Claims (10)

1. a kind of cushion cap foundation pit for having continuous drainage function, it is characterised in that: the bottom of cushion cap foundation pit is provided with catch pit, Catch pit is connect by outlet pipe with the draining pump outside cushion cap foundation pit, and outlet pipe is embedded in cushion cap pouring layer and water resistant plate pours It builds in layer;Internal layer filtering screen is provided in the catch pit, the water inlet end of the outlet pipe is located inside internal layer filtering screen; The fitros bed of material is filled between the internal layer filtering screen and catch pit inner wall.
2. the cushion cap foundation pit according to claim 1 for having continuous drainage function, it is characterised in that: the internal layer filter screen Cover bottom to catch pit bottom distance be catch pit height 1/3, the top of internal layer filtering screen be located at catch pit edge it Under, the top of the fitros bed of material is flushed with the edge of catch pit.
3. the cushion cap foundation pit according to claim 2 for having continuous drainage function, it is characterised in that: at the top of catch pit It is stamped one layer of isolation steel plate, isolation steel plate is provided with the through-hole passed through for outlet pipe.
4. the cushion cap foundation pit according to claim 2 for having continuous drainage function, it is characterised in that: be close to the hole of catch pit Wall is also equipped with outer filter mesh enclosure, and to stop sedendary soil, the fitros bed of material is located at internal layer filtering screen and outer filter net Between cover.
5. the cushion cap foundation pit according to claim 1 for having continuous drainage function, it is characterised in that: the outlet pipe is Pvc material, the top stretched out outside foundation pit are connected with elbow, and elbow water outlet picks out extension tube and connect with draining pump.
6. a kind of cushion cap foundation ditch construction method for having continuous drainage function, which is characterized in that described method includes following steps:
S1: complete cushion cap foundation pit original hole is excavated;
S2: a catch pit is excavated again in the bottom Yuan Keng of cushion cap foundation pit;
S3: installing internal layer filtering screen in catch pit, and outlet pipe water inlet end is inserted into the internal layer filtering screen in catch pit, The water outlet of outlet pipe picks out outside cushion cap foundation pit, and the filling fitros material between internal layer filtering screen and catch pit crater wall Layer;
S4: start lasting ponding outlet, after stylobate of entertaining hole is dry, the carry out waterproof protective layer construction of sequence is foundation pit reinforced Net and water resistant plate bar frame facility work, and outlet pipe is fixed on steel mesh;
S5: one-piece casting foundation pit and water resistant plate, and carry out the maintenance of concrete.
7. the cushion cap foundation ditch construction method according to claim 7 for having continuous drainage function, it is characterised in that: step S5 The middle maintenance for completing concrete and after reaching corresponding design strength, carries out reversed slip casting to outlet pipe using cement mortar, makes Gap and outlet pipe that cement mortar fills full fitros material are obtained, cement mortar and fitros material form permanent water-tight concrete, out Waterpipe permanently stays in suspended deck structure.
8. the cushion cap foundation ditch construction method according to claim 7 for having continuous drainage function, it is characterised in that: in step In S3, the outlet pipe is installed perpendicular to horizontal plane, and is provided with one or more vertical vertical bar to reinforce the steady of outlet pipe Fixed degree.
9. the cushion cap foundation ditch construction method according to claim 7 for having continuous drainage function, it is characterised in that: in step In S3, before installing internal layer filter screen, the crater wall for being first close to catch pit installs outer filter mesh enclosure, and fitros material is filled in internal layer Between filter screen and outer filter net.
10. the cushion cap foundation ditch construction method according to claim 7 for having continuous drainage function, it is characterised in that: in step It in rapid S3, is flushed at the top of the top of the fitros bed of material and catch pit, stone layer filling to be filtered finishes, and covers at the top of catch pit One layer of isolation steel plate.
CN201810966687.2A 2018-08-23 2018-08-23 The cushion cap foundation pit and its construction method for having continuous drainage function Pending CN109083175A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810966687.2A CN109083175A (en) 2018-08-23 2018-08-23 The cushion cap foundation pit and its construction method for having continuous drainage function

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810966687.2A CN109083175A (en) 2018-08-23 2018-08-23 The cushion cap foundation pit and its construction method for having continuous drainage function

Publications (1)

Publication Number Publication Date
CN109083175A true CN109083175A (en) 2018-12-25

Family

ID=64794301

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810966687.2A Pending CN109083175A (en) 2018-08-23 2018-08-23 The cushion cap foundation pit and its construction method for having continuous drainage function

Country Status (1)

Country Link
CN (1) CN109083175A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114718098A (en) * 2022-04-08 2022-07-08 中铁建电气化局集团第三工程有限公司 Drainage and water isolation structure and drainage and water isolation method in foundation pit

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08135005A (en) * 1994-11-15 1996-05-28 Fujita Corp Drain pit
CN104179189A (en) * 2014-08-29 2014-12-03 上海建工七建集团有限公司 Dewatering and drainage structure of foundation pit deep drop area and construction method thereof
CN104452786A (en) * 2014-11-14 2015-03-25 武汉一冶建筑安装工程有限责任公司 Deep foundation pit elevator shaft sump dewatering construction method
CN104711994A (en) * 2015-01-27 2015-06-17 江苏省华建建设股份有限公司 Foundation pit deep well rainfall and plugging construction method
CN106223351A (en) * 2016-07-26 2016-12-14 中国二十二冶集团有限公司 Self priming pump reduces local groundwater level construction method
CN208844591U (en) * 2018-08-23 2019-05-10 中国五冶集团有限公司 It is a kind of can continuous drainage cushion cap foundation pit

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08135005A (en) * 1994-11-15 1996-05-28 Fujita Corp Drain pit
CN104179189A (en) * 2014-08-29 2014-12-03 上海建工七建集团有限公司 Dewatering and drainage structure of foundation pit deep drop area and construction method thereof
CN104452786A (en) * 2014-11-14 2015-03-25 武汉一冶建筑安装工程有限责任公司 Deep foundation pit elevator shaft sump dewatering construction method
CN104711994A (en) * 2015-01-27 2015-06-17 江苏省华建建设股份有限公司 Foundation pit deep well rainfall and plugging construction method
CN106223351A (en) * 2016-07-26 2016-12-14 中国二十二冶集团有限公司 Self priming pump reduces local groundwater level construction method
CN208844591U (en) * 2018-08-23 2019-05-10 中国五冶集团有限公司 It is a kind of can continuous drainage cushion cap foundation pit

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114718098A (en) * 2022-04-08 2022-07-08 中铁建电气化局集团第三工程有限公司 Drainage and water isolation structure and drainage and water isolation method in foundation pit
CN114718098B (en) * 2022-04-08 2024-04-19 中铁建电气化局集团第三工程有限公司 Drainage and water-isolation structure in foundation pit and drainage and water-isolation method

Similar Documents

Publication Publication Date Title
CN103046565B (en) Draining method for ultra-deep batholith deep foundation pit
CN106320353B (en) A kind of construction method of basement construction Yield rainfall relation device
CN103437379B (en) Post-cast strip construction and drainage method for base plate of basement
CN208844591U (en) It is a kind of can continuous drainage cushion cap foundation pit
CN109083175A (en) The cushion cap foundation pit and its construction method for having continuous drainage function
CN209066465U (en) A kind of deep basal pit structure with ejectment side wall water burst
CN113373963A (en) Drainage structure for water collection pit and elevator foundation pit and construction method
CN109025899A (en) A kind of well-sealing device
CN210002331U (en) protection architecture of hydraulic and hydroelectric engineering side slope
CN107542059B (en) A method of it repairing base soil flow and loses buttress
CN104421169B (en) The vertical pump for mine that can be embedded under sandstone
CN207331699U (en) Pit-in-pit reinforced concrete retaining wall composite supporting structure
CN110424496A (en) A kind of change off land deep water water-fetching head structure structure and its construction method
CN109083176A (en) A kind of design has the local Yield rainfall relation system of auxiliary slip casting function
CN205895309U (en) Prevention of seepage water system for pitshaft driving
CN114703878A (en) Plugging and draining device for dewatering well and construction method
CN210621879U (en) Steel construction vestibule drainage structures system
CN211816267U (en) Deep foundation pit support structure
CN107299649A (en) A kind of post-cast strip advance water stop construction method for plentiful level of ground water
KR101245334B1 (en) caisson foundation concrete curing method using temperature maintaining sea water membrane
CN207538058U (en) A kind of soft rock base cut-pff wall cell bottom structure
CN105113617B (en) A kind of device for drainage at same layer and its construction method
CN104264656A (en) Method of reinforcing soft soil foundations through downward drainage during vacuum preloading
CN104863168A (en) Hydrophobic device on lower part of basic baseplate and usage method of same
CN207032328U (en) A kind of reset processing system after open trench tunnel structure floating

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181225