CN107299649A - A kind of post-cast strip advance water stop construction method for plentiful level of ground water - Google Patents
A kind of post-cast strip advance water stop construction method for plentiful level of ground water Download PDFInfo
- Publication number
- CN107299649A CN107299649A CN201710462595.6A CN201710462595A CN107299649A CN 107299649 A CN107299649 A CN 107299649A CN 201710462595 A CN201710462595 A CN 201710462595A CN 107299649 A CN107299649 A CN 107299649A
- Authority
- CN
- China
- Prior art keywords
- post
- cast strip
- construction
- water
- wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/16—Arrangement or construction of joints in foundation structures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2450/00—Gaskets
- E02D2450/10—Membranes
- E02D2450/105—Membranes impermeable
- E02D2450/106—Membranes impermeable for liquids
Abstract
The invention discloses a kind of post-cast strip advance water stop construction method for plentiful level of ground water, construction, poured band of outer wall of basement construction, the construction of outer wall of basement construction of guide wall seam available for sole plate post-poured strip, without the construction of waterproof requirement after-pouring band beam-slab.The post-cast strip advance water stop construction method for being used for plentiful level of ground water can greatly shorten the duration of whole engineering, avoid underground water from leaking into inside basement, cause quality and potential safety hazard and the work holdup, process not to overlap, economic benefit is lacked and social harmful effect.
Description
Technical field
The invention belongs to construction engineering technical field, specifically a kind of post-cast strip advanced water-stopping for plentiful level of ground water
Construction method.
Background technology
Because the regional level of ground water of project construction is higher, particularly in the wet season, water level is away from ground surface only 2m or so, relatively
In building absolute altitude be -2.8 meters, and a height of -5.12 meters of this engineering design raft plate top mark.Water so inside foundation ditch just very may be used
It can leak into inside basement, cause certain from the gap of reinforced mesh at the vertical or horizontal post-cast strip of basement
The hidden danger of quality and secure context.And the construction at general post-cast strip position will be waited to post-cast strip both sides Equalsettlement certain time
The processing that could be closed afterwards, thus influences whether applying for whole waterproofing work, backfill engineering and some fine engineerings
The time that process is overlapped before and after work, serious influence is generated to the duration of whole engineering, it is impossible to meet the contracted worker of Construction Party
Phase demand etc., it is thus determined that by the construction of advanced water-stopping pattern, can so greatly shorten the duration of whole engineering, it is to avoid underground
Water is leaked into inside basement, cause quality and potential safety hazard and the work holdup, process not to overlap, economic benefit missing and society not
Good influence etc..
The content of the invention
In order to solve the above-mentioned technical problem, the present invention provides a kind of post-cast strip advanced water-stopping for plentiful level of ground water and applied
Work method.
The technical solution adopted by the present invention is respectively:A kind of post-cast strip advanced water-stopping construction party for plentiful level of ground water
Method, construction for sole plate post-poured strip, poured band of outer wall of basement construction, the construction of outer wall of basement construction of guide wall seam,
Without the construction of waterproof requirement after-pouring band beam-slab.
First, the construction of sole plate post-poured strip, comprises the following steps:
(1)After the formwork erection of sole plate post-poured strip, pour band and add steel plate water stopper;
(2)The construction of basement raft board post poured band uses the pattern of advanced water-stopping;
(3)Post-cast strip Side shuttering is fixed on soldered ladder muscle using steel wire, and with making reliable in baseplate reinforcing bar
Connection, ladder muscle and post-cast strip side are installed using fast easy-to-closing in net stencil, and wherein steel wire is 10 mesh steel wires, if necessary may be used
Clad steel silk screen is used, ladder muscle uses the reinforcing bars of Φ 14, and bottom plate is beam, wall, plate.
2nd, poured band of outer wall of basement is constructed, and is comprised the following steps:
(1)Wall adds steel plate water stopper at post-cast strip;
(2)Side form is installed and is cast in after the formwork erection of sole plate post-poured strip, is poured band and is added steel plate water stopper;
(3)The construction of basement raft board post poured band uses the pattern of advanced water-stopping;
(4)Post-cast strip Side shuttering is fixed on soldered ladder muscle using steel wire, and with making reliable in baseplate reinforcing bar
Connection, ladder muscle and post-cast strip side are installed using fast easy-to-closing in net stencil, and wherein steel wire is 10 mesh steel wires, or using double
Layer steel wire, ladder muscle uses the reinforcing bars of Φ 14, and bottom plate is beam, wall, plate.
3rd, the construction of outer wall of basement construction of guide wall seam, comprises the following steps:
(1)Because step 2-3 is poured, to smash the difference time longer, many debris and dust fine sand is retained on surface, if cleaning is not clean
As separation layer, as penetrating passage, therefore it must be rinsed well before pouring with water;
(2)40 thick 1:Concrete is poured in 1 cement mortar.
4th, without waterproof requirement after-pouring band beam-slab, comprise the following steps:
(1)Fast-easy closing-up net is used for template without waterproof requirement post-cast strip beam;
(2)Post-cast strip is supported post-cast strip top plate position in top plate position shuttering supporting using double bowl buckle frame.
Beneficial effects of the present invention:Using post-cast strip advance water stop construction method, economic benefit harvest is obvious, and to whole
The influence that duration is brought compares, and can save the duration 25 days or so, and construction costs can reduce by 950,000, and with to personnel's work holdup
Influence compares, and the enthusiasm of workman's work can be improved, beneficial to the stabilization of personnel.
Brief description of the drawings
Fig. 1 is post-cast strip steel plate water-stopping belt construction schematic diagram;
Fig. 2 is advanced water-stopping construction schematic diagram;
Post-cast strip handles schematic diagram based on Fig. 3;
Fig. 4 is ladder muscle and steel wire machining sketch chart;
Fig. 5 is post-cast strip raft plate, side form steel wire reinforces signal at top plate;
Fig. 6 is that basement wall post-cast strip handles schematic diagram;
Fig. 7 is that outer wall of basement construction of guide wall stitches schematic diagram;
Fig. 8 is beam post-cast strip schematic diagram;
Fig. 9 is roof plate template support top schematic diagram at post-cast strip;
Wherein, 1, steel plate water stopper, 2, advanced water-stopping basis, 3, steel wire, 4, ladder muscle, 5, concrete, 6, fast-easy closing-up net, 7, after
Pour template at band, 8, bowl buckle frame.
Embodiment
In order to deepen the understanding of the present invention, below in conjunction with embodiment and accompanying drawing, the invention will be further described.
As shown in figs 1-9, a kind of post-cast strip advance water stop construction method for plentiful level of ground water, for sole plate
The construction of post-cast strip, poured band of outer wall of basement construction, the construction of outer wall of basement construction of guide wall seam, without waterproof requirement post-cast strip
Beam-Slab Construction.
First, the construction of sole plate post-poured strip, comprises the following steps:
(1)After the formwork erection of sole plate post-poured strip, the steel plate water-stopping 1 that band adds 3*350 is poured;
(2)The construction of basement raft board post poured band uses the pattern of advanced water-stopping;
(3)Post-cast strip Side shuttering is fixed on the ladder muscle 4 of the soldered reinforcing bars of Φ 14 using 10 mesh steel wires 3, and with
It is reliably connected in baseplate reinforcing bar, ladder muscle 4 and post-cast strip side are installed using fast easy-to-closing in net stencil 6, can use if necessary double
Layer steel wire 3, bottom plate can be beam, wall, plate.
2nd, poured band of outer wall of basement is constructed, and is comprised the following steps:
(1)Steel plate water stopper 1 is added at wall post-cast strip;
(2)Side form is installed and is cast in after the formwork erection of sole plate post-poured strip, is poured band and is added steel plate water stopper 1;
(2)The construction of basement raft board post poured band uses the pattern of advanced water-stopping;
(3)Post-cast strip Side shuttering is fixed on soldered ladder muscle 4 using steel wire 3, and can with work in baseplate reinforcing bar
By connection, ladder muscle 4 and post-cast strip side are installed using fast easy-to-closing in net stencil 6, and wherein steel wire 3 is 10 mesh steel wires 3, or
Using clad steel silk screen 3, ladder muscle 4 uses the reinforcing bars of Φ 14, and bottom plate is beam, wall, plate.
3rd, the construction of outer wall of basement construction of guide wall seam, comprises the following steps:
(1)Because step 2-3 is poured, to smash the difference time longer, many debris and dust fine sand is retained on surface, if cleaning is not clean
As separation layer, as penetrating passage, therefore it must be rinsed well before pouring with water;
(2)40 thick 1:Concrete 5 is poured in 1 cement mortar.
4th, without waterproof requirement after-pouring band beam-slab, comprise the following steps:
(1)Fast-easy closing-up net 6 is used for template without waterproof requirement post-cast strip beam;
(2)Post-cast strip is supported post-cast strip top plate position in top plate position shuttering supporting using double bowl buckle frame 8.
Claims (5)
1. a kind of post-cast strip advance water stop construction method for plentiful level of ground water, it is characterised in that after sole plate
Pour band construction, poured band of outer wall of basement construction, outer wall of basement construction of guide wall seam construction, without waterproof requirement post-cast strip beam
Plate is constructed.
2. after the post-cast strip advance water stop construction method according to claim 1 for plentiful level of ground water, sole plate
Pour the construction of band, it is characterised in that:Comprise the following steps:
(1)After the formwork erection of sole plate post-poured strip, pour band and add steel plate water stopper;
(2)The construction of basement raft board post poured band uses the pattern of advanced water-stopping;
(3)Post-cast strip Side shuttering is fixed on soldered ladder muscle using steel wire, and with making reliable in baseplate reinforcing bar
Connection, ladder muscle and post-cast strip side are installed using fast easy-to-closing in net stencil, and wherein steel wire is 10 mesh steel wires, or using double
Layer steel wire, ladder muscle uses the reinforcing bars of Φ 14, and bottom plate is beam, wall, plate.
3. the post-cast strip advance water stop construction method according to claim 1 for plentiful level of ground water, outer wall of basement
Post empiricism, it is characterised in that:Comprise the following steps:
(1)Wall adds steel plate water stopper at post-cast strip;
(2)Side form is installed and is cast in after the formwork erection of sole plate post-poured strip, is poured band and is added steel plate water stopper;
(3)The construction of basement raft board post poured band uses the pattern of advanced water-stopping;
(4)Post-cast strip Side shuttering is fixed on soldered ladder muscle using steel wire, and with making reliable in baseplate reinforcing bar
Connection, ladder muscle and post-cast strip side are installed using fast easy-to-closing in net stencil, and wherein steel wire is 10 mesh steel wires, or using double
Layer steel wire, ladder muscle uses the reinforcing bars of Φ 14, and bottom plate is beam, wall, plate.
4. the post-cast strip advance water stop construction method according to claim 1 for plentiful level of ground water, outer wall of basement
The construction of construction of guide wall seam, it is characterised in that:Comprise the following steps:
(1)Rinsed well before pouring with water;
(2)40 thick 1:Concrete is poured in 1 cement mortar.
5. the post-cast strip advance water stop construction method according to claim 1 for plentiful level of ground water, no waterproof requirement
After-pouring band beam-slab, it is characterised in that:Comprise the following steps:
(1)Fast-easy closing-up net is used for template without waterproof requirement post-cast strip beam;
(2)Post-cast strip is supported post-cast strip top plate position in top plate position shuttering supporting using double bowl buckle frame.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710462595.6A CN107299649A (en) | 2017-06-19 | 2017-06-19 | A kind of post-cast strip advance water stop construction method for plentiful level of ground water |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710462595.6A CN107299649A (en) | 2017-06-19 | 2017-06-19 | A kind of post-cast strip advance water stop construction method for plentiful level of ground water |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107299649A true CN107299649A (en) | 2017-10-27 |
Family
ID=60135850
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710462595.6A Pending CN107299649A (en) | 2017-06-19 | 2017-06-19 | A kind of post-cast strip advance water stop construction method for plentiful level of ground water |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107299649A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108396761A (en) * | 2018-04-03 | 2018-08-14 | 江苏南通三建集团股份有限公司 | The non-fully pile foundation cushion cap and production method under precipitation state inside a kind of foundation pit |
CN115126003A (en) * | 2022-06-29 | 2022-09-30 | 华北水利水电大学 | Post-cast strip pre-sealing structure and pre-sealing construction method |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201598645U (en) * | 2009-12-11 | 2010-10-06 | 江苏双楼建设集团有限公司 | Advanced water stop post-pouring belt for base soleplate |
CN202324012U (en) * | 2011-11-17 | 2012-07-11 | 辽宁省建筑设计研究院 | Basement waterproof construction post-pouring strip structural member |
CN202689046U (en) * | 2012-05-18 | 2013-01-23 | 中建一局集团第三建筑有限公司 | Closed advanced water sealing post-cast strip |
CN104594387A (en) * | 2013-11-04 | 2015-05-06 | 永升建设集团有限公司 | Improved post-pouring strip advanced water-stopping construction method |
-
2017
- 2017-06-19 CN CN201710462595.6A patent/CN107299649A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201598645U (en) * | 2009-12-11 | 2010-10-06 | 江苏双楼建设集团有限公司 | Advanced water stop post-pouring belt for base soleplate |
CN202324012U (en) * | 2011-11-17 | 2012-07-11 | 辽宁省建筑设计研究院 | Basement waterproof construction post-pouring strip structural member |
CN202689046U (en) * | 2012-05-18 | 2013-01-23 | 中建一局集团第三建筑有限公司 | Closed advanced water sealing post-cast strip |
CN104594387A (en) * | 2013-11-04 | 2015-05-06 | 永升建设集团有限公司 | Improved post-pouring strip advanced water-stopping construction method |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108396761A (en) * | 2018-04-03 | 2018-08-14 | 江苏南通三建集团股份有限公司 | The non-fully pile foundation cushion cap and production method under precipitation state inside a kind of foundation pit |
CN115126003A (en) * | 2022-06-29 | 2022-09-30 | 华北水利水电大学 | Post-cast strip pre-sealing structure and pre-sealing construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105951848B (en) | Ultra-deep foundation pit supports Non-intermittent combined type transformational structure and construction method | |
CN107059903A (en) | Bottom plate plugging dewatering well construction method is worn in foundation ditch | |
CN104060629B (en) | The superimposed wall construction method in covered back-digging subway station and portable side wall formwork jumbo | |
CN204000956U (en) | A kind of basement bottom plate rear pouring tape structure | |
CN110761322B (en) | Cast-in-place pipe gallery side wall horizontal construction joint reinforcing structure and construction method thereof | |
CN204343339U (en) | A kind of temporary support columns waterproof base plate | |
CN107574842A (en) | Basement post-pouring zone advance water stop construction method | |
CN109183825A (en) | The construction method of raft board post poured band side form | |
CN109235493A (en) | Basement beam slab is backbreak and short formwork construction method in a kind of contrary sequence method | |
CN106930277A (en) | A kind of construction of manual-excavation cast-in-place pile method | |
CN108678000A (en) | A kind of U-shaped retaining structure of roadbed Xia Chuan highways and its construction method | |
CN1307348C (en) | Construction method for underground structure through half reverse course of action of inverting connection | |
CN203924116U (en) | Portable side wall formwork jumbo | |
CN104358275B (en) | Darker elevator shaft or collecting well construction method | |
CN201943086U (en) | Underground building wall body | |
CN107806114A (en) | Basement roof closes late poured band structure and construction method in advance | |
CN105002927A (en) | Construction method for excavation slope retaining wall reversed filter layer | |
CN205576955U (en) | Raft foundation's reinforced structure is displaced into to strip footing | |
CN110004991A (en) | Underground structure anti-floating system and construction method based on raised type tangs plate | |
CN109706952A (en) | Large-scale well-sinking construction method | |
CN107299649A (en) | A kind of post-cast strip advance water stop construction method for plentiful level of ground water | |
CN109610473A (en) | A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration | |
CN108396761A (en) | The non-fully pile foundation cushion cap and production method under precipitation state inside a kind of foundation pit | |
CN106193120A (en) | Basement is encorbelmented, and base plate is inverse makees structure and construction method | |
CN110273435A (en) | A kind of construction of city open trench tunnel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |