CN109083009B - Construction method for transferring bridge deck slab by using multi-hoisting-point cable crane in mountainous area with limited site - Google Patents

Construction method for transferring bridge deck slab by using multi-hoisting-point cable crane in mountainous area with limited site Download PDF

Info

Publication number
CN109083009B
CN109083009B CN201810666804.3A CN201810666804A CN109083009B CN 109083009 B CN109083009 B CN 109083009B CN 201810666804 A CN201810666804 A CN 201810666804A CN 109083009 B CN109083009 B CN 109083009B
Authority
CN
China
Prior art keywords
hoisting
bridge deck
cable
truss girder
steel truss
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201810666804.3A
Other languages
Chinese (zh)
Other versions
CN109083009A (en
Inventor
胡洪俊
赵晓光
李清培
陈刚
强永林
周咏凯
龚进
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SICHUAN LUQIAO HUADONG BUILDING CO Ltd
Sichuan Road and Bridge Group Co Ltd
Original Assignee
SICHUAN LUQIAO HUADONG BUILDING CO Ltd
Sichuan Road and Bridge Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SICHUAN LUQIAO HUADONG BUILDING CO Ltd, Sichuan Road and Bridge Group Co Ltd filed Critical SICHUAN LUQIAO HUADONG BUILDING CO Ltd
Priority to CN201810666804.3A priority Critical patent/CN109083009B/en
Publication of CN109083009A publication Critical patent/CN109083009A/en
Application granted granted Critical
Publication of CN109083009B publication Critical patent/CN109083009B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Abstract

The invention provides a construction method for transferring a bridge deck by using a multi-hoisting-point cable crane in a limited mountain area; the invention constructs a multi-hoisting point cable hoisting system on the basis of the existing cable hoisting system, the system is provided with a set of bearing cable, and three sets of traction and hoisting systems are arranged on the bearing cable, wherein 1 set of the system in front of each tower on two banks is used as a bridge deck plate transfer system for transfer construction of an approach bridge deck plate, and the operation range of the system is 100m in front of the tower; a set of main hoisting points is arranged in the span and used for mounting the steel truss girder, and the steel truss girder can run in the full span range; when the main hoisting point of the cable hoisting system is in midspan construction operation, the bridge deck is transported by using the bridge deck transporting system; the method is mainly used for solving the problem of transportation when the bridge approach is used for assembling the orthotropic steel bridge deck in the construction process of the suspension bridge in the limited mountainous area.

Description

Construction method for transferring bridge deck slab by using multi-hoisting-point cable crane in mountainous area with limited site
Technical Field
The invention relates to a construction method of a transfer bridge deck, in particular to a construction method for hoisting a transfer bridge deck by using a multi-hoisting-point cable in a mountainous area with limited site.
Background
In the construction process of the suspension bridge in the limited mountainous area, an assembling field is usually arranged for assembling the steel truss girder and the bridge deck. For the area with steep terrain, the assembly field is difficult to set, the cost is high, the area of the assembly field is limited by the field and is small, and the assembly requirements of the steel trussed beams and the bridge deck can not be met at the same time, so the steel trussed beam assembly field is usually arranged at a bearing platform, the bridge deck is directly assembled by using a bridge approach bridge deck, the bridge deck is required to be transferred to the steel trussed beam assembly field after being assembled, and the bridge deck is lifted together with the steel trussed beams after being assembled. The following methods are currently generally used for the transfer of bridge decks:
firstly, directly utilize cable hoist system main hoisting point to carry out the transportation of decking, but cable hoist system only has a set of hoisting point, therefore must wait that a section of installation is accomplished and return the back, and the decking is transported and follow-up a series of construction operation can be carried out to the side, because steel longeron installation is longer with pulling the walking time, consequently there is a large amount of idle time midway in this mode, leads to the waste of mechanical equipment and manpower resources, construction cycle length.
Secondly, a set of working antenna system is independently arranged for transferring the bridge deck slab, but the orthotropic steel bridge deck slab is heavier after being assembled, and the arrangement span of the working antenna bearing cables is large, so that the system needs to consume a large amount of equipment and materials, and the construction cost is very high.
Thirdly, the installed main cable is used as a bearing cable, the bridge deck is transported only by means of independently setting the hoisting cable, the main cable is easily damaged by the aid of the method, the bridge deck can be transported to a designed position only by means of askew pulling after hoisting is completed, and construction is extremely irregular and safe risks exist.
Disclosure of Invention
Therefore, in order to solve the above-mentioned disadvantages, the present invention provides a construction method for transferring a bridge deck by using a multi-hoisting point cable crane in a limited mountainous area; the method is mainly used for solving the problem of transportation when the bridge approach is used for assembling the orthotropic steel bridge deck in the construction process of the suspension bridge in the limited mountainous area.
The invention is realized in this way, and the construction method for constructing the transfer bridge deck by using the multi-hoisting point cable crane in the mountainous area with limited site is characterized in that:
the multi-hoisting-point cable hoisting system is constructed on the basis of the existing cable hoisting system, the system is provided with a set of bearing cable, and three sets of traction and hoisting systems are arranged on the bearing cable, wherein 1 set of the system in front of each tower on two banks is used as a bridge deck plate transfer system for transfer construction of bridge deck plates of an approach bridge, and the operation range of the system is 100m in front of the tower; a set of main hoisting points is arranged in the span and used for mounting the steel truss girder, and the steel truss girder can run in the full span range; when the main hoisting point of the cable hoisting system is in midspan construction operation, the bridge deck is transported by using the bridge deck transporting system; the concrete construction steps are as follows:
the method comprises the following steps: arranging a steel truss girder assembling field and an approach bridge deck assembling field at a bearing platform, installing a multi-hoisting-point cable hoisting system, and arranging a bridge deck transferring system in front of the two-shore towers;
step two: installing front end beams of the two-bank towers by using main hoisting points and installing permanent slings, so that the bridge approach deck and the front end beams of the towers jointly form a bridge deck assembly field, and directly transporting subsequent bridge decks to the front end beam area of the towers for vertical hoisting;
step three: hoisting the first section of steel truss girder by using the cable hoisting system and dragging towards midspan, starting the bridge deck transfer system to transfer the bridge deck to a designed position on the steel truss girder assembly field after a main hoisting point of the cable hoisting system is dragged away from the steel truss girder assembly field, and returning the system to a tower front area for waiting after the bridge deck is transferred in place;
step four: assembling the steel truss girder and the bridge deck according to design requirements;
step five: after the first section of steel truss girder is installed, the main hoisting point returns to the steel truss girder assembling field for hoisting the next section;
step six: and repeating the third step to the fifth step until the installation of the steel truss girder is completed.
The invention has the following advantages: the invention provides a construction method for transferring a bridge deck by using a multi-hoisting-point cable crane in a limited mountain area; the method is mainly used for solving the transportation problem when the orthotropic steel bridge deck is assembled by using the approach bridge in the construction process of the suspension bridge in the limited mountainous area; when the patent is implemented according to the mode, the following advantages are achieved:
the existing cable hoisting system is directly utilized, the structural characteristic of small bearing tension in hoisting in front of the tower is fully utilized, a bearing main cable does not need to be arranged independently, the using amount of the bearing cable is greatly reduced, and the construction cost is low;
2, the installation of the system can be carried out while the installation of the cable hoisting system is carried out, the construction is convenient, and the construction period is short;
3, the bridge deck is lifted by utilizing multiple lifting points, the on-site flow operation is realized, the construction efficiency is high, and the utilization rate of equipment and personnel is high;
4, the device does not conflict with the permanent structure of the suspension bridge.
Drawings
Fig. 1-2 are schematic views of the construction method of the present invention.
Detailed Description
The present invention will be described in detail with reference to fig. 1-2, and the technical solutions in the embodiments of the present invention will be clearly and completely described, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The invention provides a construction method for transferring bridge deck slab by using multi-hoisting point cable crane in a limited mountain area through improvement; the method is mainly used for solving the problem of transportation when the bridge approach is used for assembling the orthotropic steel bridge deck in the construction process of the suspension bridge in the limited mountainous area.
When the system is implemented, a multi-hoisting-point cable hoisting system is constructed on the basis of the existing cable hoisting system, the system is provided with a set of bearing cables, and three sets of traction and hoisting systems are arranged on the bearing cables, wherein 1 set of the system in front of each tower on two banks is used as a bridge deck plate transfer system for transfer construction of an approach bridge deck plate, and the operation range of the system is 100m in front of the tower; a set of main hoisting points is arranged in the span and used for installing the steel truss girder, and the steel truss girder can operate in the full span range. When the main hoisting point of the cable hoisting system is in midspan construction operation, the bridge deck is transported by the bridge deck transporting system. The concrete construction steps are as follows:
the method comprises the following steps: arranging a steel truss girder assembling field and an approach bridge deck assembling field at a bearing platform, installing a multi-hoisting-point cable hoisting system, and arranging a bridge deck transferring system in front of the two-shore towers;
step two: the front end beams of the two-bank tower are installed by using the main hoisting points, and the permanent sling is installed, so that the bridge approach deck and the front end beams of the tower jointly form a bridge deck assembly field, and the subsequent bridge decks are directly transported to the front end beam area of the tower to be vertically hoisted.
Step three: and hoisting the first section of steel truss girder by using the cable hoisting system and dragging towards midspan, starting the bridge deck transfer system to transfer the bridge deck to a designed position on the steel truss girder assembly field after a main hoisting point of the cable hoisting system is dragged away from the steel truss girder assembly field, and returning the system to a tower front area for waiting after the bridge deck is transferred in place.
Step four: and assembling the steel truss girder and the bridge deck according to design requirements.
Step five: after the first section of steel truss girder is installed, the main hoisting point returns to the steel truss girder assembling field for hoisting the next section;
step six: and repeating the third step to the fifth step until the installation of the steel truss girder is completed.
When the patent is implemented according to the mode, the following advantages are achieved:
(1) the existing cable hoisting system is directly utilized, the structural characteristic of small bearing tension when the tower is hoisted in front of the tower is fully utilized, a bearing main cable does not need to be arranged independently, the using amount of the bearing cable is greatly reduced, and the construction cost is low;
(2) the installation of the system can be carried out while the installation of the cable hoisting system is carried out, the construction is convenient, and the construction period is short;
(3) the bridge deck is lifted by utilizing multiple lifting points, the on-site line production is realized, the construction efficiency is high, and the utilization rate of equipment and personnel is high;
(4) without interfering with the suspension bridge permanent structure.
The previous description of the disclosed embodiments is provided to enable any person skilled in the art to make or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the invention. Thus, the present invention is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims (1)

1. A construction method for transferring bridge decks by using multi-hoisting-point cable cranes in mountainous areas with limited sites is characterized by comprising the following steps: the multi-hoisting-point cable hoisting system is constructed on the basis of the existing cable hoisting system, the system is provided with a set of bearing cable, and three sets of traction and hoisting systems are arranged on the bearing cable, wherein 1 set of the system in front of each tower on two banks is used as a bridge deck plate transfer system for transfer construction of bridge deck plates of an approach bridge, and the operation range of the system is 100m in front of the tower; a set of main hoisting points is arranged in the span and used for mounting the steel truss girder, and the steel truss girder can run in the full span range; when the main hoisting point of the cable hoisting system is in midspan construction operation, the bridge deck is transported by using the bridge deck transporting system; the concrete construction steps are as follows:
the method comprises the following steps: arranging a steel truss girder assembling field and an approach bridge deck assembling field at a bearing platform, installing a multi-hoisting-point cable hoisting system, and arranging a bridge deck transferring system in front of the two-shore towers;
step two: installing front end beams of the two-bank towers by using main hoisting points and installing permanent slings, so that the bridge approach deck and the front end beams of the towers jointly form a bridge deck assembly field, and directly transporting subsequent bridge decks to the front end beam area of the towers for vertical hoisting;
step three: hoisting the first section of steel truss girder by using the cable hoisting system and dragging towards midspan, starting the bridge deck transfer system to transfer the bridge deck to a designed position on the steel truss girder assembly field after a main hoisting point of the cable hoisting system is dragged away from the steel truss girder assembly field, and returning the system to a tower front area for waiting after the bridge deck is transferred in place;
step four: assembling the steel truss girder and the bridge deck according to design requirements;
step five: after the first section of steel truss girder is installed, the main hoisting point returns to the steel truss girder assembling field for hoisting the next section;
step six: and repeating the third step to the fifth step until the installation of the steel truss girder is completed.
CN201810666804.3A 2018-06-26 2018-06-26 Construction method for transferring bridge deck slab by using multi-hoisting-point cable crane in mountainous area with limited site Active CN109083009B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810666804.3A CN109083009B (en) 2018-06-26 2018-06-26 Construction method for transferring bridge deck slab by using multi-hoisting-point cable crane in mountainous area with limited site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810666804.3A CN109083009B (en) 2018-06-26 2018-06-26 Construction method for transferring bridge deck slab by using multi-hoisting-point cable crane in mountainous area with limited site

Publications (2)

Publication Number Publication Date
CN109083009A CN109083009A (en) 2018-12-25
CN109083009B true CN109083009B (en) 2020-03-24

Family

ID=64839713

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810666804.3A Active CN109083009B (en) 2018-06-26 2018-06-26 Construction method for transferring bridge deck slab by using multi-hoisting-point cable crane in mountainous area with limited site

Country Status (1)

Country Link
CN (1) CN109083009B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109914223B (en) * 2019-04-26 2024-01-23 四川路桥华东建设有限责任公司 Hoisting system suitable for suspension bridge steel structure bridge deck system and operation method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006214113A (en) * 2005-02-02 2006-08-17 Jfe Koken Corp Demolition method and erection method for bridge
CN101224856A (en) * 2007-12-20 2008-07-23 中铁大桥局股份有限公司 Long-span load-carrying cable lifting machine and mounting method therefor
CN101684639A (en) * 2009-08-28 2010-03-31 中国第一冶金建设有限责任公司 Process method for construction of steel-structured suspension bridge and light type cable carrying crane specially used in same
CN104674668A (en) * 2015-01-19 2015-06-03 中铁大桥局集团有限公司 Method for hoisting construction girder sections through cables
CN108118622A (en) * 2018-02-06 2018-06-05 中交二公局第二工程有限公司 A kind of steel-concrete composite beam cable-stayed bridge main cable and girder construction cable crane system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006214113A (en) * 2005-02-02 2006-08-17 Jfe Koken Corp Demolition method and erection method for bridge
CN101224856A (en) * 2007-12-20 2008-07-23 中铁大桥局股份有限公司 Long-span load-carrying cable lifting machine and mounting method therefor
CN101684639A (en) * 2009-08-28 2010-03-31 中国第一冶金建设有限责任公司 Process method for construction of steel-structured suspension bridge and light type cable carrying crane specially used in same
CN104674668A (en) * 2015-01-19 2015-06-03 中铁大桥局集团有限公司 Method for hoisting construction girder sections through cables
CN108118622A (en) * 2018-02-06 2018-06-05 中交二公局第二工程有限公司 A kind of steel-concrete composite beam cable-stayed bridge main cable and girder construction cable crane system

Also Published As

Publication number Publication date
CN109083009A (en) 2018-12-25

Similar Documents

Publication Publication Date Title
CN104480862B (en) A kind of erection method of cable stayed bridge end bay steel truss girder
CN201943007U (en) Constant amplitude frame beam crane capable of being used in combination with movable support frame
CN105421249A (en) Novel dragging- hoisting combined type hanging basket structure and construction method
CN205223872U (en) Drag and hang novel string of basket structure of convolution
CN103911956A (en) Long-span cable stayed bridge steel truss girder mounting method
CN103882812A (en) Construction method for midspan main beams of cable-stayed bridge
CN109083009B (en) Construction method for transferring bridge deck slab by using multi-hoisting-point cable crane in mountainous area with limited site
CN109680616B (en) Construction method for hoisting main beam by using cable crane and reverse lifting equipment
CN103696569B (en) Overhead steel-beam platform dismounting device and method
CN105836640A (en) Self-climbing fixing device and method for climbing tower crane
CN205241086U (en) Template hoist and mount and ann gun carriage of disassembling and using
CN108374351B (en) Simple hoisting device and method for dismantling box girder bailey pieces
CN107795133B (en) Integral protective frame platform and construction method thereof
CN107988909B (en) Railway is just roof beam rapid transit erects and uses trailer
CN108625275A (en) A kind of stiffening girder of suspension bridge section installation method
CN203640290U (en) High-altitude erected steel beam platform dismounting device
CN204982628U (en) Horizontal drawing cable bridge
CN204940130U (en) A kind of integral lifting device of Wavelike steel webplate parts
CN201952736U (en) Auxiliary pier movable bracket for assisting invariable-amplitude beam erecting crane in erecting steel box girder
CN202358822U (en) Hoisting structure for oil field skid block
CN201980890U (en) Herringbone hoisting mast for hoisting under special situation of high altitude
CN208294101U (en) A kind of large-span steel girder mounting slip and promote coupling apparatus
CN201686458U (en) Movable operating platform used for quickly processing welding seam at end opening of steel box girder
CN215717067U (en) Construction platform suitable for concrete composite shear wall structure
CN202936088U (en) T-shaped beam steel lifting bracket

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Hu Hongjun

Inventor after: Zhao Xiaoguang

Inventor after: Li Qingpei

Inventor after: Chen Gang

Inventor after: Qiang Yonglin

Inventor after: Zhou Yongkai

Inventor after: Gong Jin

Inventor before: Hu Hongjun

Inventor before: Li Qingpei

Inventor before: Chen Gang

Inventor before: Qiang Yonglin

Inventor before: Zhou Yongkai

Inventor before: Gong Jin

GR01 Patent grant
GR01 Patent grant