CN109081267A - A kind of biomass boiler superheater installation foundation operation platform method for improving - Google Patents

A kind of biomass boiler superheater installation foundation operation platform method for improving Download PDF

Info

Publication number
CN109081267A
CN109081267A CN201811000459.6A CN201811000459A CN109081267A CN 109081267 A CN109081267 A CN 109081267A CN 201811000459 A CN201811000459 A CN 201811000459A CN 109081267 A CN109081267 A CN 109081267A
Authority
CN
China
Prior art keywords
operation platform
acting hydraulic
installation
hydraulic jack
punching
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811000459.6A
Other languages
Chinese (zh)
Inventor
韩春绿
王瑞
刘玉波
杨文华
马卫华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SEPCO Electric Power Construction Co Ltd
Original Assignee
SEPCO Electric Power Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SEPCO Electric Power Construction Co Ltd filed Critical SEPCO Electric Power Construction Co Ltd
Priority to CN201811000459.6A priority Critical patent/CN109081267A/en
Publication of CN109081267A publication Critical patent/CN109081267A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66FHOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
    • B66F7/00Lifting frames, e.g. for lifting vehicles; Platform lifts
    • B66F7/10Lifting frames, e.g. for lifting vehicles; Platform lifts with platforms supported directly by jacks
    • B66F7/16Lifting frames, e.g. for lifting vehicles; Platform lifts with platforms supported directly by jacks by one or more hydraulic or pneumatic jacks
    • B66F7/20Lifting frames, e.g. for lifting vehicles; Platform lifts with platforms supported directly by jacks by one or more hydraulic or pneumatic jacks by several jacks with means for maintaining the platforms horizontal during movement
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66FHOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
    • B66F7/00Lifting frames, e.g. for lifting vehicles; Platform lifts
    • B66F7/28Constructional details, e.g. end stops, pivoting supporting members, sliding runners adjustable to load dimensions

Abstract

A kind of biomass boiler superheater installation foundation operation platform method for improving, comprising the following steps: set up steel pipe scaffold → hanger and laying scaffold board in installation radiation beam → mounting platform outer-ring beam → mounting platform inner ring beam → installation hydraulic pressure lift drive system → installation support rod (climb steel pipe) → installation → on base concrete cushion cap and set and adhere to tower crane outside safety net → installation pylon and paving scaffold board → base concrete cushion cap.

Description

A kind of biomass boiler superheater installation foundation operation platform method for improving
Technical field
The present invention relates to boiler erection platform construction method technical field, specifically a kind of biomass boiler superheater Installation foundation operation platform method for improving.
Background technique
In order to meet requirement, boiler is frequently necessary to be mounted on high site, and the installation of high site boiler is fixed, basis Carrying platform has key effect.In the construction of existing basic platform, generally use hydraulic lifting apparatus to upper end operation platform into Row is promoted.Hydraulic lifting apparatus mostly uses hoisting frame to combine with crosshead, utilizes the load-bearing mould of lower-layer concrete basis outer wall Plate carries out the promotion of top operation platform as support, and derrick is arranged as material hoisting system mostly at Platform center.It should The material resources that kind hoisting way needs to put into are larger, set up higher cost, and there are larger security risks.
Summary of the invention
The purpose of the present invention is to provide a kind of biomass boiler superheater installation foundation operation platform method for improving, are used for Solve the technical issues of being promoted to operation platform.
The technical scheme adopted by the invention to solve the technical problem is that:
A kind of biomass boiler superheater installation foundation operation platform method for improving, comprising the following steps: in basic coagulation Steel pipe scaffold is set up on native cushion cap;
Installation radiation beam, radiation beam are uniformly arranged one week, and the outer end for radiating beam is connected by girder steel annular, to form installation Platform outer-ring beam;The middle part of radiation beam is connected by girder steel annular, to form mounting platform inner ring beam;The radiation beam, peace Assembling platform outer-ring beam and mounting platform outer-ring beam form operation platform framework;
Hydraulic pressure lift drive system is installed in mounting frame, hydraulic pressure lift drive system includes hydraulic control panel, punching Formula single-acting hydraulic jack and corresponding oil pipe, oil pressure valve;
Support rod is installed, sliding of the support rod for punching single-acting hydraulic jack is climbed, to drive integral construction Platform framework is climbed;Punching single-acting hydraulic is very heavy to be separately mounted to radiate on beam accordingly, while punching single-acting What hydraulic jack can be climbed is mounted on corresponding support rod;
Interior hanger is installed on the base concrete cushion cap of lower section, then the laying construction platform scaffold board on interior hanger, And safety net is set;Pylon is installed on the base concrete cushion cap of lower section, then in pylon upper berth facility work platform legs Palm;
The attachment installation tower crane outside base concrete cushion cap, to lift required material.
Preferably, very heavy be equipped with of punching single-acting hydraulic described in more is controlled by a hydraulic control panel, and every Independent oil pressure valve is arranged in punching single-acting hydraulic jack.
Preferably, during sliding, according to the stability of entire operation platform framework, support rod is cut using screw-thread steel Knife support carries out consolidation process.
Preferably, when each punching single-acting hydraulic jack has height difference, fixation punching single-acting liquid is answered Jack horizontal control snap ring suitable for reading is pressed, its oil pressure valve is opened repeatedly, rises to each jack at control snap ring, so as to Punching single-acting hydraulic jack is in the same horizontal position, to keep entire operation platform framework holding horizontal.
Preferably, for operation platform framework during sliding, the discovery of punching single-acting hydraulic jack climb altitude is inclined When poor, the corresponding oil pressure valve of the punching single-acting hydraulic jack for climbing too fast is closed, it will punching single-acting liquid at a slow speed The jack several strokes of continuance lifting again are pressed, until integral construction platform framework is in the same horizontal plane.
Preferably, before operation platform framework is sliding, with cruciform fastening for falsework by scaffolding steel pipe and support rod lateral connection at One, makes whole support rod be in stable state.
The effect provided in summary of the invention is only the effect of embodiment, rather than invents all whole effects, above-mentioned A technical solution in technical solution have the following advantages that or the utility model has the advantages that
The technical program vertical hydraulic promotes drive system and combines outer adhesion tower-crane, eliminates the peace of derrick and hoist engine Dress alleviates the weight of operating platform simultaneously because not having to the affiliated facilities such as installation pulley frame.
Conventional construction method, operation difficulty are larger;The technical program can realize convenient and quick construction.
Specific embodiment
In order to clearly illustrate the technical characterstic of this programme, below by specific embodiment, the present invention is carried out detailed It illustrates.Present invention omits to known assemblies and technical description to avoid being unnecessarily limiting the present invention.
A kind of biomass boiler superheater installation foundation operation platform method for improving, comprising the following steps: base concrete Steel pipe scaffold → installation radiation beam → mounting platform outer-ring beam → mounting platform inner ring beam → installation is hydraulic is set up on cushion cap to mention It rises drive system → installation support rod (climb steel pipe) → hanger and laying scaffold board in installing → and sets safety net → installation Adhere to tower crane outside pylon and paving scaffold board → base concrete cushion cap.
(upper layer construction reinforced bar cage can be set up in advance) on the base concrete cushion cap of lower section, set up steel pipe scaffold, The height of steel pipe scaffold should be greater than the specified climb altitude of jack that climbs.After steel pipe scaffold is set up, installation radiation Beam.It radiates beam and is equipped with 14, be uniformly arranged one week, radiate between beam by reinforcing attachment beam connection.The outer end of the radiation beam It is connected by girder steel annular, to form mounting platform outer-ring beam;The middle part of radiation beam is connected by girder steel annular, to form installation Platform inner ring beam.Radiation beam, mounting platform outer-ring beam and the mounting platform outer-ring beam forms operation platform framework.? Hydraulic pressure lift drive system is installed, hydraulic pressure lift drive system includes hydraulic control panel, punching single-acting liquid in mounting frame Press jack and corresponding oil pipe, oil pressure valve.It installs support rod (climb steel pipe), support rod is used for punching single-acting hydraulic The sliding of jack is climbed, to drive climbing for integral construction platform framework.Punching single-acting hydraulic is very heavy to be equipped with 14, branch It holds bar and is also accordingly arranged 14;Punching single-acting hydraulic is very heavy to be separately mounted to radiate on beam accordingly, while punching list Acting hydraulic is very heavy being mounted on corresponding support rod of climbing.Hanger in being installed on the base concrete cushion cap of lower section, Then the laying construction platform scaffold board on interior hanger, and safety net is set.It is installed on the base concrete cushion cap of lower section outer Hanger, then in pylon upper berth facility work platform scaffold board.The attachment installation tower crane outside base concrete cushion cap, to lift The material needed.Finally, reaching specified altitude assignment by the upward integral hoisting construction platform framework of hydraulic pressure lift drive system Afterwards, the work such as casting concrete on top layer operating platform, to form the basic body structure of carrying boiler.
Further, 14 punching single-acting hydraulic jack pass through a hydraulic control panel control, every punching Independent oil pressure valve is arranged in single-acting hydraulic jack.When hydraulic control panel manipulation oil pressure valve is opened simultaneously, 14 thousand Jin top is upward simultaneously sliding (every 1 stroke is 30mm, is risen 56 times repeatedly, altogether sliding 1680mm height), during sliding, Consolidation process should be carried out to support rod and (carried out using 16 screw thread steel cross strut of Φ according to the stability of entire operation platform framework It reinforces).
Further, during punching single-acting hydraulic jack is sliding, each punching single-acting hydraulic jack has When height difference, should be adjusted in time (fixation punching single-acting hydraulic jack horizontal control snap ring suitable for reading, repeatedly Its oil pressure valve is opened, rises to each jack at control snap ring, so that punching single-acting hydraulic jack is same A horizontal position, to keep entire operation platform framework holding horizontal).
Further, the necessary firm welding of the upper lower contact of support rod, and it is smooth, prevent punching single-acting liquid It presses very heavy climb to block in the process, influences the normal sliding of entire operation platform framework.
Further, during operation platform framework is sliding, the reinforcing bar in construction site is observed, to drawing screw etc. must not hook Operation platform framework is hung, to prevent causing danger.
Further, after operation platform framework is sliding in place, construction personnel can carry out reinforcement installation, mould on lower hanger Plate is removed, installation is reinforced, the work such as casting concrete in operation platform framework.
Further, it before operation platform framework is sliding, above the punching single-acting hydraulic jack at 1.80m, uses Cruciform fastening for falsework is integral by scaffolding steel pipe and support rod lateral connection, and whole support rod is made to be in stable state.It is applying in this way When work platform framework is sliding, stability is preferable.When meeting hole in support rod, using two transverse direction scaffolding steel pipes and cross buckle Part is attached reinforcing, prevent support rod tilt or bending and so on.
Further, operation platform framework is during sliding, due to punching single-acting hydraulic jack climbing speed Agree not exclusively synchronize, causes operation platform framework unhorizontal.When finding deviation, the punching nonoculture that will can climb too fast Closed with the corresponding oil pressure valve of hydraulic jack, will punching single-acting hydraulic jack several strokes of continuance lifting again at a slow speed, Until integral construction platform framework is in the same horizontal plane.
Except for the technical features described in the specification, it all is technically known to those skilled in the art.
Above-mentioned specific embodiments of the present invention have been described, but it is not intended to limit the protection scope of the present invention, On the basis of technical solution of the present invention, those skilled in the art do not need to pay for creative labor the various modifications that can be made Or deformation is still within the scope of the present invention.

Claims (6)

1. a kind of biomass boiler superheater installation foundation operation platform method for improving, characterized in that the following steps are included: in base Steel pipe scaffold is set up on plinth concrete bearing platform;
Installation radiation beam, radiation beam are uniformly arranged one week, and the outer end for radiating beam is connected by girder steel annular, to form mounting platform Outer-ring beam;The middle part of radiation beam is connected by girder steel annular, to form mounting platform inner ring beam;The radiation beam, installation are flat Platform outer-ring beam and mounting platform outer-ring beam form operation platform framework;
Hydraulic pressure lift drive system is installed in mounting frame, hydraulic pressure lift drive system includes hydraulic control panel, punching list Acting hydraulic jack and corresponding oil pipe, oil pressure valve;
Support rod is installed, sliding of the support rod for punching single-acting hydraulic jack is climbed, to drive integral construction platform Framework is climbed;Punching single-acting hydraulic is very heavy to be separately mounted to radiate on beam accordingly, while punching single-acting hydraulic It is very heavy climb be mounted on corresponding support rod;
Interior hanger is installed, then the laying construction platform scaffold board on interior hanger on the base concrete cushion cap of lower section, and sets Set safety net;Pylon is installed on the base concrete cushion cap of lower section, then in pylon upper berth facility work platform scaffold board;
The attachment installation tower crane outside base concrete cushion cap, to lift required material.
2. a kind of biomass boiler superheater installation foundation operation platform method for improving according to claim 1, feature It is that punching single-acting hydraulic described in more is very heavy to be equipped with through a hydraulic control panel control, every punching single-acting Independent oil pressure valve is arranged in hydraulic jack.
3. a kind of biomass boiler superheater installation foundation operation platform method for improving according to claim 1, feature It is during sliding, according to the stability of entire operation platform framework, to be reinforced to support rod using screw thread steel cross strut Processing.
4. a kind of biomass boiler superheater installation foundation operation platform method for improving according to claim 1, feature It is when each punching single-acting hydraulic jack has height difference, to answer fixation punching single-acting hydraulic jack suitable for reading Level control snap ring, opens its oil pressure valve repeatedly, rises to each jack at control snap ring, so as to punching single-acting Hydraulic jack withstands on the same horizontal position, to keep entire operation platform framework holding horizontal.
5. a kind of biomass boiler superheater installation foundation operation platform method for improving according to claim 1, feature It is that operation platform framework when punching single-acting hydraulic jack climb altitude finds deviation, will climb during sliding The corresponding oil pressure valve of fast punching single-acting hydraulic jack is closed, will at a slow speed punching single-acting hydraulic jack it is continuous again Several strokes are promoted, until integral construction platform framework is in the same horizontal plane.
6. a kind of biomass boiler superheater installation foundation operation platform method for improving according to claim 1, feature It is, it is with cruciform fastening for falsework that scaffolding steel pipe and support rod lateral connection is integral before operation platform framework is sliding, make whole branch It holds bar and is in stable state.
CN201811000459.6A 2018-08-29 2018-08-29 A kind of biomass boiler superheater installation foundation operation platform method for improving Pending CN109081267A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811000459.6A CN109081267A (en) 2018-08-29 2018-08-29 A kind of biomass boiler superheater installation foundation operation platform method for improving

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811000459.6A CN109081267A (en) 2018-08-29 2018-08-29 A kind of biomass boiler superheater installation foundation operation platform method for improving

Publications (1)

Publication Number Publication Date
CN109081267A true CN109081267A (en) 2018-12-25

Family

ID=64795244

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811000459.6A Pending CN109081267A (en) 2018-08-29 2018-08-29 A kind of biomass boiler superheater installation foundation operation platform method for improving

Country Status (1)

Country Link
CN (1) CN109081267A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101126279A (en) * 2007-07-31 2008-02-20 中国建筑第七工程局 Silo slipform construction technique
CN201151633Y (en) * 2007-11-27 2008-11-19 北京中建建筑科学研究院有限公司 Spiral releasing hydraulic jacks
CN201367728Y (en) * 2009-03-19 2009-12-23 二十三冶建设集团有限公司 Derrick-less hydraulic slip form device used for reinforced concrete water tower supporting tube construction
CN203613464U (en) * 2013-11-22 2014-05-28 中铁三局集团有限公司 Slip form construction cargo transportation device
CN107795122A (en) * 2017-11-21 2018-03-13 中国十九冶集团有限公司南京分公司 Concrete stack shell constructing device and construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101126279A (en) * 2007-07-31 2008-02-20 中国建筑第七工程局 Silo slipform construction technique
CN201151633Y (en) * 2007-11-27 2008-11-19 北京中建建筑科学研究院有限公司 Spiral releasing hydraulic jacks
CN201367728Y (en) * 2009-03-19 2009-12-23 二十三冶建设集团有限公司 Derrick-less hydraulic slip form device used for reinforced concrete water tower supporting tube construction
CN203613464U (en) * 2013-11-22 2014-05-28 中铁三局集团有限公司 Slip form construction cargo transportation device
CN107795122A (en) * 2017-11-21 2018-03-13 中国十九冶集团有限公司南京分公司 Concrete stack shell constructing device and construction method

Similar Documents

Publication Publication Date Title
CN108019076B (en) Construction method of large-diameter reinforced concrete silo and device for conical shell construction
CN110230393B (en) Large concrete tank dome climbing high formwork support system and installation method
CN106437130A (en) Inner roof external climbing type formwork construction platform for super high-rise building construction
CN202450774U (en) Shaft template of small-step-pitch self-climbing elevator
CN108979131B (en) Integral lifting platform device for high-rise building construction steel formwork and operation frame
CN201367728Y (en) Derrick-less hydraulic slip form device used for reinforced concrete water tower supporting tube construction
CN205134939U (en) Hydraulic pressure creeping formwork system suitable for inboard narrow and small region in space of a core section of thick bamboo
CN207294093U (en) A kind of large span steel truss integral lifting apparatus
CN205296803U (en) Elevator automatic lifting operation panel
CN106481060A (en) Operating platform for tower and hanging method
CN112458918A (en) High-pier hydraulic jacking integral steel frame platform formwork turnover construction system and construction method
CN206233541U (en) A kind of interior top external climbing mould bases operation platform for construction of super highrise building
CN102733608B (en) Construction method for spray head layer of granulation tower
CN109252656B (en) High-rise building climbing template and assembling, pouring and lifting method
CN203452375U (en) Hydraulic self-jacking oblique creeping formwork
CN113090014A (en) High-rise assembled building integral operation platform and construction method and application thereof
CN201714056U (en) Truss-type operating platform
CN109081267A (en) A kind of biomass boiler superheater installation foundation operation platform method for improving
CN217439544U (en) Building top outer vertical surface overhanging structure template supporting system
CN203684708U (en) Hydraulic multipoint synchronous lifting device
CN216840692U (en) Construction device for super high-rise building
CN216810895U (en) Elevator shaft operation platform
CN105625732A (en) Supporting-free construction method of ultrahigh overhung steel-structure truss
CN202831621U (en) Integrated slipform for silo concrete
CN204402001U (en) For the mobile operating platform system that structure for steel structure roof inner slab is installed

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181225