CN109056731B - 一种紧邻既有无砟轨道路基的岩溶注浆加固方法 - Google Patents
一种紧邻既有无砟轨道路基的岩溶注浆加固方法 Download PDFInfo
- Publication number
- CN109056731B CN109056731B CN201810741698.0A CN201810741698A CN109056731B CN 109056731 B CN109056731 B CN 109056731B CN 201810741698 A CN201810741698 A CN 201810741698A CN 109056731 B CN109056731 B CN 109056731B
- Authority
- CN
- China
- Prior art keywords
- karst
- grouting
- base
- unit
- subgrade
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C3/00—Foundations for pavings
- E01C3/04—Foundations produced by soil stabilisation
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Architecture (AREA)
- Railway Tracks (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
Description
技术领域
本发明涉及岩土工程技术领域,特别涉及一种紧邻既有无砟轨道路基的岩溶注浆加固方法。
背景技术
随着高速铁路快速发展,无砟轨道路基得到广泛应用。在工程建设中,新建建筑物或构筑物不可避免地会紧邻既有无砟轨道路基修建。在岩溶地区,新建建筑物基底岩溶大量采用注浆加固,但其紧邻的既有无砟轨道路基基底可能存在隐伏岩溶。若采用注浆加固新建建筑物基底岩溶,浆液极易通过裂隙通道进入既有无砟轨道路基基底岩溶,若注浆压力控制不当,既有无砟轨道路基基底岩溶浆液压力可能形成过大的上拱压力,引发覆盖层及其顶部路基产生上拱变形,引发轨道不平顺性加剧,威胁高速列车安全运营。由此可见,目前存在的技术不足是如何控制紧邻既有无砟轨道路基的岩溶注浆压力,迫切需要提出合理的注浆加固方法。
发明内容
本发明所要解决的技术问题是提供一种紧邻既有无砟轨道路基的岩溶注浆加固方法,以科学合理地开展紧邻既有无砟轨道路基新建建筑物基底岩溶注浆加固,有效避免无砟轨道路基产生上拱变形。
本发明解决上述技术所采用的技术方案如下:
本发明的一种紧邻既有无砟轨道路基的岩溶注浆加固方法,包括以下步骤:
①通过资料收集或高密度电法或探地雷达或地震反射法或电磁波CT,确定以下参数:
既有无砟轨道路基基底至路基基底岩溶中心的竖向距离h,单位m;
新建建筑物基底岩溶与路基基底岩溶之间的裂隙通道的宽度δ和长度L,单位m;
路基基底岩溶的分布面积Ak,单位m2;
通过以下公式确定路基基底岩溶的等效半径rk:
式中,rk,单位m;
③通过以下公式确定新建建筑物基底岩溶的注浆压力σz:
式中,σz,单位kPa;σj为既有无砟轨道路基基底应力,单位kPa;K为安全系数,取1.4~1.8;μ0为浆液的初始运动黏度,单位kpa;Q为注浆量,单位m3;δ,单位m;L,单位m;rc为注浆管半径,单位m;
④在新建建筑物基底钻孔至岩溶分布区,并按不大于步骤③确定的注浆压力σz进行注浆加固。
本发明的有益效果是,针对目前存在的技术不足,在考虑既有无砟轨道路基基底岩溶覆盖层抗剪强度、覆盖层自重、上覆路基荷载及裂隙通道压力差等因素的基础上,提出一种紧邻既有无砟轨道路基的岩溶注浆加固方法,能够解决紧邻既有无砟轨道路基新建建筑物基底岩溶注浆加固问题,可有效避免无砟轨道路基上拱变形。该方法实施便捷,流程清晰,能够适应实际工程需要。
附图说明
图1是紧邻既有无砟轨道路基新建建筑物的横断面示意图。
图中示出构件和对应的标记:既有无砟轨道路基S,新建建筑物X,路基基底岩溶1,裂隙通道2,新建建筑物基底岩溶3,路基基底至岩溶中心的竖向距离h,裂隙通道长度L。
具体实施方式
下面通过具体的实施例并结合附图进一步说明本发明。
参照图1,本发明一种紧邻既有无砟轨道路基的岩溶注浆加固方法,包括以下步骤:
①通过资料收集或高密度电法或探地雷达或地震反射法或电磁波CT,确定以下参数:
既有无砟轨道路基S基底至路基基底岩溶1中心的竖向距离h,单位m;
新建建筑物基底岩溶3与路基基底岩溶1之间的裂隙通道2的宽度δ和长度L,单位m;
路基基底岩溶1的分布面积Ak,单位m2;
通过以下公式确定路基基底岩溶1的等效半径rk:
式中,rk,单位m;
③通过以下公式确定新建建筑物基底岩溶3的注浆压力σz:
式中,σz,单位kPa;σj为既有无砟轨道路基S基底应力,单位kPa;K为安全系数,取1.4~1.8;μ0为浆液的初始运动黏度,单位kpa;Q为注浆量,单位m3;δ,单位m;L,单位m;rc为注浆管半径,单位m;
④在新建建筑物X基底钻孔至岩溶分布区,并按不大于步骤③确定的注浆压力σz进行注浆加固。
实施例:
参照图1,某一无砟轨道高速铁路路基修建于岩溶地区,路基填高1.6m,既有无砟轨道路基S基底可能存在隐伏岩溶,现紧邻该路基需新建一建筑物,且该建筑物基底探有岩溶发育区,拟采用注浆进行岩溶加固,注浆量Q为100m3,rc为注浆管半径为0.025m。浆液的初始运动黏度μ0为10-6kpa。
为避免岩溶注浆加固造成既有无砟轨道路基S产生上拱变形,采用本发明方法确定紧邻既有无砟轨道路基S新建建筑物X基底岩溶3的注浆加固方法,具体步骤如下:
1.通过探地雷达,确定既有无砟轨道路基S基底至岩溶中心的竖向距离h为3.5m;确定新建建筑物基底岩溶3与路基基底岩溶1之间的裂隙通道2宽度δ为0.025m,长度L为10.5m;确定路基基底岩溶1的分布面积Ak为6.4m2,并通过以下公式确定路基基底岩溶1的等效半径rk:
3.既有无砟轨道路基S基底应力σj取43.1kPa,安全系数K取1.4,新建建筑物基底岩溶3的注浆压力σz为:
(4)在新建建筑物X基底钻孔至岩溶分布区,并按注浆压力不大于278.5kPa进行注浆加固。
本发明的优点在于提供的一种紧邻既有无砟轨道路基的岩溶注浆加固方法,科学合理,实施简便,能满足实际工程的需要,具有广阔的推广应用前景。
以上所述只是采用图解说明本发明一种紧邻既有无砟轨道路基的岩溶注浆加固方法的一些原理,并非是要将本发明局限在所示和所述的具体方法和适用范围内,故凡是所有可能被利用的相应修改以及等同物,均属于本发明所申请的专利范围。
Claims (1)
1.一种紧邻既有无砟轨道路基的岩溶注浆加固方法,包括以下步骤:
①通过资料收集或高密度电法或探地雷达或地震反射法或电磁波CT,确定以下参数:
既有无砟轨道路基(S)基底至路基基底岩溶(1)中心的竖向距离h,单位m;
新建建筑物基底岩溶(3)与路基基底岩溶(1)之间的裂隙通道(2)的宽度δ和长度L,单位m;
路基基底岩溶(1)的分布面积Ak,单位m2;
通过以下公式确定路基基底岩溶(1)的等效半径rk:
式中,rk,单位m;
③通过以下公式确定新建建筑物基底岩溶(3)的注浆压力σz:
式中,σz,单位kPa;单位rad;σj为既有无砟轨道路基(S)基底应力,单位kPa;K为安全系数,取1.4~1.8;μ0为浆液的初始运动黏度,单位kpa;Q为注浆量,单位m3;δ,单位m;L,单位m;rc为注浆管半径,单位m;
④在新建建筑物(X)基底钻孔至岩溶分布区,并按不大于步骤③确定的注浆压力σz进行注浆加固。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810741698.0A CN109056731B (zh) | 2018-07-06 | 2018-07-06 | 一种紧邻既有无砟轨道路基的岩溶注浆加固方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810741698.0A CN109056731B (zh) | 2018-07-06 | 2018-07-06 | 一种紧邻既有无砟轨道路基的岩溶注浆加固方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109056731A CN109056731A (zh) | 2018-12-21 |
CN109056731B true CN109056731B (zh) | 2020-07-24 |
Family
ID=64819525
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810741698.0A Active CN109056731B (zh) | 2018-07-06 | 2018-07-06 | 一种紧邻既有无砟轨道路基的岩溶注浆加固方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109056731B (zh) |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
NL1030145C2 (nl) * | 2005-10-07 | 2007-04-11 | Konink Bam Groep Nv | Werkwijze voor het instorten van bielzen en daarvoor gebruikte bekisting. |
DE102006005376A1 (de) * | 2006-02-03 | 2007-08-16 | Rail.One Gmbh | Feste Fahrbahn für Schienenfahrzeuge |
CN102306225B (zh) * | 2011-09-27 | 2013-01-09 | 上海大学 | 多线叠交隧道施工过程及对隧道变形影响数值模拟方法 |
CN106499407B (zh) * | 2016-10-20 | 2019-05-24 | 上海交通大学 | 一种岩溶地区盾构隧道安全盾尾注浆压力的确定方法 |
CN106567719B (zh) * | 2016-10-20 | 2019-04-19 | 上海交通大学 | 一种砂土岩溶地层盾构隧道注浆安全溶洞距离的确定方法 |
CN108108507B (zh) * | 2017-08-26 | 2021-03-30 | 中铁二院工程集团有限责任公司 | 一种高强土工布加固铁路岩溶路基的设计方法 |
-
2018
- 2018-07-06 CN CN201810741698.0A patent/CN109056731B/zh active Active
Also Published As
Publication number | Publication date |
---|---|
CN109056731A (zh) | 2018-12-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Liu et al. | Structural responses and treatments of shield tunnel due to leakage: A case study | |
CN105239563B (zh) | 一种后注浆配套旋挖钻机干法成孔灌注桩结构及施工方法 | |
CN111058855B (zh) | 一种盾构下穿的结构物的形变控制方法及评估系统 | |
Di et al. | In situ grouting tests for differential settlement treatment of a cut-and-cover metro tunnel in soft soils | |
CN105040775B (zh) | 深层承压自流井封堵系统与方法 | |
CN106988302A (zh) | 一种大倾角坚硬岩层旋挖桩施工工法 | |
CN110108838A (zh) | 一种定向钻孔注浆浆液扩散的模拟试验方法 | |
CN109577319A (zh) | 一种干式旋挖成孔钻孔灌注桩施工方法 | |
CN103410522A (zh) | 浅埋暗挖法连续近距离下穿铁路桥的施工方法 | |
CN113010956A (zh) | 锚拉式支挡结构中预应力锚索的设计优化方法 | |
WO2019109700A1 (zh) | 基于顶板稳定性的煤巷强顶护帮锚杆支护方法 | |
CN103628508B (zh) | 模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验装置 | |
Ning et al. | Deformation characteristics observed during multi-step excavation of underground oil storage caverns based on field monitoring and numerical simulation | |
CN109056731B (zh) | 一种紧邻既有无砟轨道路基的岩溶注浆加固方法 | |
CN204040021U (zh) | 城市地下工程暗挖导洞内大直径桩施工设备系统 | |
Korff | Deformations and damage to buildings adjacent to deep excavations in soft soils | |
Niu et al. | Combined support system and calculation model for deep foundation pits in fill soil areas | |
CN109811771B (zh) | 使锚杆钢腰梁张拉时不发生弯曲的简易方法 | |
WO2024032003A1 (zh) | 一种大断面铁路隧道围岩稳定性控制方法 | |
Lougheed | Limit states testing of a buried deep-corrugated large-span box culvert | |
Thiyyakkandi | Study of grouted deep foundations in cohesionless soils | |
CN115627746A (zh) | 一种基于原位测试的承压水地层基坑抗突涌安全评估方法 | |
CN114704265A (zh) | 一种地铁盾构隧道下穿高架桥隧道施工工法 | |
CN108930265B (zh) | 一种既有无砟轨道路基基底再生隐伏岩溶的注浆修复方法 | |
CN112431217A (zh) | 一种大型撬装式冷箱无桩抗震筏板基础施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |