CN103628508B - 模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验装置 - Google Patents

模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验装置 Download PDF

Info

Publication number
CN103628508B
CN103628508B CN201210310998.6A CN201210310998A CN103628508B CN 103628508 B CN103628508 B CN 103628508B CN 201210310998 A CN201210310998 A CN 201210310998A CN 103628508 B CN103628508 B CN 103628508B
Authority
CN
China
Prior art keywords
pile
slip casting
rear flank
experimental rig
model casing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201210310998.6A
Other languages
English (en)
Other versions
CN103628508A (zh
Inventor
钱建固
黄茂松
木林隆
马霄
王永刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tongji University
Original Assignee
Tongji University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tongji University filed Critical Tongji University
Priority to CN201210310998.6A priority Critical patent/CN103628508B/zh
Publication of CN103628508A publication Critical patent/CN103628508A/zh
Application granted granted Critical
Publication of CN103628508B publication Critical patent/CN103628508B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

本发明涉及一种模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验装置,该试验装置包括气压单元、浆液存储室、模型箱及注浆管路,气压单元、浆液存储室及模型箱依次通过注浆管路连接,气压单元由气源及设在气源后面的压力表组成,浆液存储室为储藏水泥浆液的桶状结构,模型箱为由铝合金板和钢化玻璃经螺栓连接组合而成的可拆卸的箱体。与现有技术相比,本发明提出一种模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验装置,基于此可以了解桩侧后注浆抗拔桩桩土接触面的力学性质,探讨后注浆技术对增强桩侧摩阻力的机理,进而分析桩侧后注浆抗拔桩的承载变形特性,本发明具有结构简单、便于操作、实用性强等优点。

Description

模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验装置
技术领域
本发明涉及基础工程建设领域中模拟抗拔桩桩土接触面物理性质的试验装置,尤其是设计一种模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验系统。
背景技术
现代城市建设逐渐向功能化,集约化和综合化的方向发展,地下空间的开发成为新的发展趋势。但在我国沿海软土地区,由于地下水位较高,大规模地下建筑的抗浮问题已成为地下工程界的焦点问题。设置抗拔桩是目前广泛采用的抵抗上拔荷载的工程措施。桩侧后注浆抗拔桩借鉴了后注浆技术,对常规等截面抗拔桩进行改进,可有效的提高抗拔桩的承载能力,有着广阔的应用前景。
作为一种新型的抗拔桩基础,目前对于桩侧后注浆抗拔桩承载变形特性的研究较少,理论研究滞后于工程实践的发展。抗拔桩的承载能力主要取决于桩侧阻力,桩侧后注浆抗拔桩通过改善桩土接触面的摩擦特性以及桩周土体的力学性质来提高抗拔桩的极限抗拔承载力。因此,桩土接触面力学性质的研究是探索桩侧后注浆抗拔桩承载能力的关键问题。本发明提出一种模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验装置,基于此可以进行桩土接触面的剪切试验,分析桩侧后注浆抗拔桩桩土接触面的力学性质,从而更好的指导桩侧后注浆抗拔桩的工程实践。
发明内容
本发明的目的就是为了克服上述现有技术存在的缺陷而提供一种结构简单、便于操作、实用性强的模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验装置。
本发明的目的可以通过以下技术方案来实现:
一种模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验装置,该试验装置包括气压单元、浆液存储室、模型箱及注浆管路,所述的气压单元、浆液存储室及模型箱依次通过注浆管路连接。
所述的气压单元由施加注浆压力的气源及设在气源后面的度量注浆压力大小的压力表组成。
所述的浆液存储室为储藏水泥浆液的桶状结构。
所述的模型箱为由铝合金板和钢化玻璃经螺栓连接组合而成的箱体。抗拔桩模型制作完成并经养护后,拆掉模型箱四周的铝合金板便可直接进行剪切试验;通过钢化玻璃可以实时观察注浆效果。
所述的模型箱为可拆卸的模型箱。
所述的浆液存储室及模型箱之间的注浆管路上设有阀门。通过阀门可以开启和关闭注浆管路。
所述的注浆管路连接到模型箱的内部,模型箱内部的注浆管路上开设有梅花形孔洞。
与现有技术相比,本发明具有以下优点及有益效果:
桩侧后注浆抗拔桩是一种新型的抗拔桩基础形式,国内外对其承载能力的研究并不充分,本发明提出一种模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验装置,基于此可以了解桩侧后注浆抗拔桩桩土接触面的力学性质,探讨后注浆技术对增强桩侧摩阻力的机理,进而分析桩侧后注浆抗拔桩的承载变形特性,本发明通过气源及压力表构成气压单元,能够方便,准确的模拟注浆压力,本发明采用的模拟箱为可拆卸的由铝合金板和钢化玻璃经螺栓连接组合而成的箱体,操作方便,并可观察注浆效果,本发明具有结构简单、便于操作、实用性强等优点。
附图说明
图1为本发明的结构示意图。
图中:1为气源,2为压力表,3为浆液存储室,4为阀门,5为注浆管路,6为模型箱。
具体实施方式
下面结合附图和具体实施例对本发明进行详细说明。
实施例
一种模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验装置,结构如图1所示,该试验装置包括气压单元、浆液存储室3、模型箱6及注浆管路5,气压单元、浆液存储室3及模型箱6依次通过注浆管路5连接。气压单元由气源1及设在气源1后面的压力表2组成。通过气源1施加注浆压力,通过压力表2度量注浆压力的大小。浆液存储室3为储藏水泥浆液的桶状结构。模型箱6为由铝合金板和钢化玻璃经螺栓连接组合而成的箱体。抗拔桩模型制作完成并经养护后,拆掉模型箱四周的铝合金板便可直接进行剪切试验;通过钢化玻璃可以实时观察注浆效果。模型箱6为可拆卸的模型箱,通过模型箱6制作抗拔桩模型。浆液存储室3及模型箱6之间的注浆管路5上设有阀门4。通过阀门4可以开启和关闭注浆管路5。注浆管路5连接到模型箱6的内部,模型箱6内部的注浆管路5上开设有梅花形孔洞。
制作尺寸为600mm×400×200mm的模型箱6,在模型箱6的底部现浇C30的混凝土用来模拟桩侧后注浆抗拔桩桩身,厚度为100mm。待混凝土强度到达设计强度的70%后,安装注浆管路5,并在混凝土表面覆盖土层,土样采用上海②3层灰色砂质粉土。土样装备完成后,于土层表面通过承压板加压固结,压力大小根据抗拔桩的不同埋深确定。根据试验设备的要求和现场施工时的后注浆工艺确定,浆液水灰比为0.55,水泥用量为2kg。水泥浆液制备完成后放入浆液存储室,通过阀门4打开注浆管路5,通过气压单元设定注浆压力0.2MPa。注浆完成后将整个试块制作箱放入养护室进行养护。待试件养护28天后,拆开模型箱6,将试件放入多功能界面剪切仪中进行剪切试验,得到剪切应力和相对位移关系,进而分析桩侧后注浆抗拔桩的承载变形特性。由此可见,本发明提供的模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验装置具有较大的工程价值。
本发明已以较佳实施例揭示如上,然其并非用以限定本发明。本发明所属技术领域中具有通常知识者,在不脱离本发明的精神和范围内,当可作各种的更动与润饰。因此,本发明不限于上述实施例,本领域技术人员根据本发明的揭示,不脱离本发明的范畴所做出的改进和修改都应该在本发明的保护范围之内。

Claims (6)

1.一种模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验装置,其特征在于,该试验装置包括气压单元、浆液存储室、模型箱及注浆管路,所述的气压单元、浆液存储室及模型箱依次通过注浆管路连接,所述的注浆管路连接到模型箱的内部,模型箱内部的注浆管路上开设有梅花形孔洞;
该试验装置使用方法为:首先制作模型箱,在模型箱的底部现浇C30的混凝土用来模拟桩侧后注浆抗拔桩桩身,待混凝土强度到达设计强度的70%后,安装注浆管路,并在混凝土表面覆盖土层,土样装备完成后,于土层表面通过承压板加压固结,水泥浆液制备完成后放入浆液存储室,打开注浆管路,通过气压单元设定注浆压力0.2MPa,注浆完成后将整个试块制作箱放入养护室进行养护,待试件养护28天后,拆开模型箱,将试件放入多功能界面剪切仪中进行剪切试验,得到剪切应力和相对位移关系,进而分析桩侧后注浆抗拔桩的承载变形特性。
2.根据权利要求1所述的一种模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验装置,其特征在于,所述的气压单元由施加注浆压力的气源及设在气源后面的度量注浆压力大小的压力表组成。
3.根据权利要求1所述的一种模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验装置,其特征在于,所述的浆液存储室为储藏水泥浆液的桶状结构。
4.根据权利要求1所述的一种模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验装置,其特征在于,所述的模型箱为由铝合金板和钢化玻璃经螺栓连接组合而成的箱体。
5.根据权利要求4所述的一种模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验装置,其特征在于,所述的模型箱为可拆卸的模型箱。
6.根据权利要求1所述的一种模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验装置,其特征在于,所述的浆液存储室及模型箱之间的注浆管路上设有阀门。
CN201210310998.6A 2012-08-28 2012-08-28 模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验装置 Expired - Fee Related CN103628508B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210310998.6A CN103628508B (zh) 2012-08-28 2012-08-28 模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210310998.6A CN103628508B (zh) 2012-08-28 2012-08-28 模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验装置

Publications (2)

Publication Number Publication Date
CN103628508A CN103628508A (zh) 2014-03-12
CN103628508B true CN103628508B (zh) 2016-04-20

Family

ID=50209935

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210310998.6A Expired - Fee Related CN103628508B (zh) 2012-08-28 2012-08-28 模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验装置

Country Status (1)

Country Link
CN (1) CN103628508B (zh)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103499492B (zh) * 2013-10-01 2016-11-02 浙江工业职业技术学院 桩端后注浆室内载荷试验装置
CN106284443B (zh) * 2016-09-07 2018-03-02 同济大学 一种模拟注浆扩底桩抗抜承载力的试验方法
CN108828195B (zh) * 2018-03-14 2020-10-02 同济大学 一种模拟桩端后注浆浆液上返的室内试验方法
CN108613885B (zh) * 2018-03-14 2020-10-02 同济大学 一种模拟桩侧后注浆的室内试验方法
CN108374440B (zh) * 2018-05-11 2023-09-05 广州市建筑科学研究院有限公司 一种非挤土后注浆预制管桩模型试验装置及方法
CN113373989B (zh) * 2021-06-04 2022-09-27 吉林建筑大学 一种地基注浆膨胀试验仪

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20070004244A (ko) * 2005-07-04 2007-01-09 양형칠 2중 팩-앵커를 이용한 재하시험방법 및 장치
CN101451986A (zh) * 2008-11-27 2009-06-10 浙江大学 一种新型注浆模拟装置
CN102419303A (zh) * 2011-08-15 2012-04-18 山东科技大学 复杂条件下的裂隙注浆可视化试验装置

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20070004244A (ko) * 2005-07-04 2007-01-09 양형칠 2중 팩-앵커를 이용한 재하시험방법 및 장치
CN101451986A (zh) * 2008-11-27 2009-06-10 浙江大学 一种新型注浆模拟装置
CN102419303A (zh) * 2011-08-15 2012-04-18 山东科技大学 复杂条件下的裂隙注浆可视化试验装置

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
"注浆桩土接触面试验研究及后注浆抗拔桩承载特性数值分析";钱建固等;《岩土力学》;20110430;第32卷;第663页第2节 *

Also Published As

Publication number Publication date
CN103628508A (zh) 2014-03-12

Similar Documents

Publication Publication Date Title
CN103628508B (zh) 模拟桩侧后注浆抗拔桩桩土接触面物理性质的试验装置
Wu et al. Dewatering–induced building settlement around a deep excavation in soft deposit in Tianjin, China
Elbaz et al. Investigation into performance of deep excavation in sand covered karst: a case report
CN109371974A (zh) 一种适用于坚硬地质的phc管桩植入施工方法
CN103981861A (zh) 桩基理论、灰土桩承载力、灰土桩搅拌击实操作系统
Tang et al. Effect mechanism of unfrozen water on the frozen soil-structure interface during the freezing-thawing process
CN113343417A (zh) 一种基于采动地表裂缝的含隔水层及表土层再造修复方法
Wan et al. Study on the response of postside-grouted piles subjected to lateral loading in calcareous sand
CN111021440A (zh) Cpt一体化的土工封装散体桩室内模型试验装置及方法
CN110245426B (zh) 一种用于管廊结构顶管施工的有限元精细化模拟方法
CN105926626B (zh) 超长风动潜孔锤振动旋喷桩施工工艺
Sun Experimental and theoretical investigation on the stability of deep excavations against confined aquifers in Shanghai, China
Niu et al. Grouting treatment of water and mud inrush in fully weathered granite tunnel: a case study
Shu et al. A case study: observed deformation characteristics and internal force of pile-anchor retaining excavation
Miao et al. Mechanical characteristics and optimum design of SMW construction method for a comprehensive pipe gallery in a water-rich weak stratum
Tung et al. Application of pile bottom post-grouting technology to increase the bearing capacity of bored piles in Vietnam
Bai et al. Green coal mining under buildings by overburden grout injection for coalmine sustainable development of central China
CN101906779B (zh) 一种门架式锚管土钉喷网支护工艺及其所用的改性加固水泥浆
CN217298886U (zh) 一种输电线路工程注浆岩锚基础结构
Xie et al. Numerical analysis on large-section pipe jacking within close distance in soft soil
Min et al. Experimental research on the influence of stratum permeability on the time-varying properties of active grout
Ma et al. Discussion on a new technique for controlling the seepage damage to an ancient tomb
Fan et al. Analysis of the deep foundation pit precipitation based on abaqus
WANG et al. Field study on the ultimate bearing capacity of enlarged grout base of pre-bored grouted planted pile
Ding et al. Analysis of Excavation with Numerical Simulation and Monitoring Data Has Effect on Surface Subsidence

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160420

Termination date: 20180828

CF01 Termination of patent right due to non-payment of annual fee