CN109052149A - PC precast floor slab pulley suspender - Google Patents

PC precast floor slab pulley suspender Download PDF

Info

Publication number
CN109052149A
CN109052149A CN201811155115.2A CN201811155115A CN109052149A CN 109052149 A CN109052149 A CN 109052149A CN 201811155115 A CN201811155115 A CN 201811155115A CN 109052149 A CN109052149 A CN 109052149A
Authority
CN
China
Prior art keywords
pulley
wirerope
bracket
floor slab
suspension hook
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811155115.2A
Other languages
Chinese (zh)
Inventor
郭飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinshaw Architecture Technology Co Ltd
Original Assignee
Jinshaw Architecture Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinshaw Architecture Technology Co Ltd filed Critical Jinshaw Architecture Technology Co Ltd
Priority to CN201811155115.2A priority Critical patent/CN109052149A/en
Publication of CN109052149A publication Critical patent/CN109052149A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/12Slings comprising chains, wires, ropes, or bands; Nets
    • B66C1/14Slings with hooks

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention discloses a kind of PC precast floor slab pulley suspender, including bracket, pulley assembly, upper wirerope, lower wirerope, shackle, pulley suspension hook;Vertical bar is fixed at bracket both ends respectively, and pedestal lower end fixes several pulley assemblies;Bracket both ends are installed by fixed block;The lower wirerope is connected between pulley assembly;Pulley suspension hook is fixed on lower wirerope;Fixed lifting lug above bracket;Shackle is installed, shackle is connected with one end of upper wirerope on lifting lug;The distance between pulley assembly is identical.The configuration of the present invention is simple, can be according to actual field situation, if the winding of multiple brackets and lower wirerope and pulley assembly, has adjusted point at any time, and uniform force when reaching floor lifting reduces the damage in lifting to floor.

Description

PC precast floor slab pulley suspender
Technical field
The present invention relates to the suspender of PC prefabricated components more particularly to the suspenders of PC precast floor slab.
Background technique
Precast concrete is referred to as PC prefabricated components in housing industry field;Briefly, it is exactly prefabricated in the factory Then concrete component, including beam, plate, column, wall etc. transport to scene and carry out lifting splicing, be finally completed a solitary building It builds.In recent years, with various regions housing industrialization project implementation, China's prefabricated concrete structure enters high speed development rank Section, this promotes its construction to ask continuous improvement to the needs of safe design.Lifting has run through each construction link of fabricated construction, wraps Demoulding lifting, overturning, transport lifting and on-site hoisting etc. are included, lifting construction and safety are component construction emphasis link, inhomogeneity The difference of type hanging method and Lift-on/Lift-off System will lead to force unbalance in hoisting process, and lifting deviation is big, or even can be to structure Part causes the damage that can not be repaired, and therefore, effect of the special hanger in construction is increasingly prominent.
Summary of the invention
Based on described above, the present invention proposes a kind of PC precast floor slab pulley suspender, since floor is all bigger, Ke Yigen According to the size of actual field floor, while several groups of pulley suspenders are mostly used, distance wants identical and is parallel to each other between suspender, so that whole Piece floor lifts by crane simultaneously, uniform force, reduce floor unbalance stress and caused by phenomena such as cracking, reduce in hoisting process Damage.
Used technical solution is: PC precast floor slab pulley suspender, including bracket, pulley assembly, upper wirerope, lower steel Cord, shackle, pulley suspension hook;Vertical bar is fixed at bracket both ends respectively, and pedestal lower end fixes several pulley assemblies;Bracket both ends peace Fill fixed block;Lower wirerope is connected between pulley assembly;Pulley suspension hook is fixed on lower wirerope;Fixed lifting lug above bracket;It hangs Shackle is installed, shackle is connected with one end of upper wirerope on ear;The distance between the pulley assembly is identical.
The triangle of two pulley assemblies and pulley suspension hook composition is equilateral triangle.
The triangle of fixed block and a pulley assembly and pulley suspension hook composition on bracket, is equilateral triangle.
Lower wirerope is an entirety;It is starting point from a fixed block, it is V-shaped, by pulley assembly, it is solid to go to another Determine block.
Lifting lug at least there are two, be separately fixed on bracket, the distance between lifting lug be entire bracket 1/2.
A upper wirerope is fixed on lifting lug respectively.
Pulley suspension hook be it is detachable, pulley is parallel sister block, on a pulley on lower wirerope, another pulley around Suspension hook.
PC precast floor slab pulley suspender of the present invention, structure is simple, according to the length and width of the practical floor in scene when use, Using the bracket and multiple brackets of appropriate length, pulley assembly is fixed on bracket, it can according to field condition, to adjust infraclass silk The winding of rope and pulley assembly, can be every a pulley assembly around lower wirerope;Suspension hook is installed on lower wirerope again, only need floor by Force is uniform, while can also according to circumstances, and adjusting the upper wirerope on lifting lug is same intersection point lifting of mutually reporting to the leadship after accomplishing a task, or respectively flat Row, therefore suspension centre can be freely combined, purposes is wide, can be suitble to the floor of various length according to the length of floor in the present invention.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of PC precast floor slab pulley suspender of the present invention.
Specific embodiment
The present invention is described in further detail with reference to the accompanying drawing and by embodiment, and following embodiment is to this hair Bright explanation and the invention is not limited to following embodiments.
It is shown in Figure 1, PC precast floor slab pulley suspender, including bracket 1, pulley assembly 2, upper wirerope 5, lower wirerope 6, shackle 4, pulley suspension hook 9;Vertical bar 7 is fixed at 1 both ends of bracket respectively, several pulley assemblies 2 are fixed in 1 lower end of bracket;Pulley blocks The distance between part is identical;1 both ends of bracket are installed by fixed block 8;Lower wirerope 6 is connected between pulley assembly 2;On lower wirerope 6 Fixed pulley suspension hook 9;Lower wirerope 6 is an entirety;It is starting point from a fixed block 8, it is V-shaped, by pulley assembly 2, walk To another fixed block.The triangle of two pulley assemblies 2 and a pulley suspension hook 9 composition is equilateral triangle.On bracket 1 Fixed block 8 and a pulley assembly 2 and a pulley suspension hook 9 composition triangle, be equilateral triangle.
Lifting lug 3 is fixed above bracket 1;Lifting lug at least there are two, be separately fixed on bracket, the distance between lifting lug be it is whole The 1/2 of a bracket.Shackle 4 is installed, shackle 4 is connected with one end of upper wirerope 5 on lifting lug 3.One is fixed on lifting lug 3 respectively Upper wirerope.
Pulley suspension hook 9 be it is detachable, pulley is parallel sister block, on a pulley on lower wirerope, another pulley Around suspension hook.

Claims (7)

1.PC precast floor slab pulley suspender, it is characterised in that: including bracket, pulley assembly, upper wirerope, lower wirerope, shackle, Pulley suspension hook;Vertical bar is fixed at the bracket both ends respectively, and pedestal lower end fixes several pulley assemblies;The installation of bracket both ends is fixed Block;The lower wirerope is connected between pulley assembly;Pulley suspension hook is fixed on the lower wirerope;Fixation is hung above the bracket Ear;Shackle is installed, shackle is connected with one end of upper wirerope on lifting lug;The distance between the pulley assembly is identical.
2. PC precast floor slab pulley suspender according to claim 1, it is characterised in that described two pulley assemblies and one The triangle of pulley suspension hook composition is equilateral triangle.
3. PC precast floor slab pulley suspender according to claim 1, it is characterised in that the fixed block on the bracket and one The triangle of a pulley assembly and pulley suspension hook composition is equilateral triangle.
4. PC precast floor slab pulley suspender according to claim 1, it is characterised in that the lower wirerope is an entirety; It is starting point from a fixed block, it is V-shaped, by pulley assembly, go to another fixed block.
5. PC precast floor slab pulley suspender according to claim 1, it is characterised in that the lifting lug at least there are two, respectively It is fixed on bracket, the distance between lifting lug is the 1/2 of entire bracket.
6. PC precast floor slab pulley suspender according to claim 1 or 5, it is characterised in that fix one respectively on the lifting lug Wirerope on root.
7. PC precast floor slab pulley suspender according to claim 1, it is characterised in that the pulley suspension hook is detachable, cunning Taking turns is parallel sister block, around suspension hook on lower wirerope, another pulley on a pulley.
CN201811155115.2A 2018-09-30 2018-09-30 PC precast floor slab pulley suspender Pending CN109052149A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811155115.2A CN109052149A (en) 2018-09-30 2018-09-30 PC precast floor slab pulley suspender

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811155115.2A CN109052149A (en) 2018-09-30 2018-09-30 PC precast floor slab pulley suspender

Publications (1)

Publication Number Publication Date
CN109052149A true CN109052149A (en) 2018-12-21

Family

ID=64766934

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811155115.2A Pending CN109052149A (en) 2018-09-30 2018-09-30 PC precast floor slab pulley suspender

Country Status (1)

Country Link
CN (1) CN109052149A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109750804A (en) * 2019-01-10 2019-05-14 杭州江润科技有限公司 Assembled stair and its construction method
CN109958219A (en) * 2019-04-11 2019-07-02 中国十七冶集团有限公司 A kind of complex environment roofing truss lower part liner plate suspension cable installation method
CN114014147A (en) * 2021-11-11 2022-02-08 广东省建工设计顾问有限公司 Multipoint hanger structure and hoisting method thereof

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011006245A (en) * 2009-06-29 2011-01-13 Mitsui Eng & Shipbuild Co Ltd Rope hooking structure for container crane
CN207390887U (en) * 2017-11-06 2018-05-22 成都城投远大建筑科技有限公司 A kind of hanging apparatus
CN209052274U (en) * 2018-09-30 2019-07-02 锦萧建筑科技有限公司 PC precast floor slab pulley suspender

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011006245A (en) * 2009-06-29 2011-01-13 Mitsui Eng & Shipbuild Co Ltd Rope hooking structure for container crane
CN207390887U (en) * 2017-11-06 2018-05-22 成都城投远大建筑科技有限公司 A kind of hanging apparatus
CN209052274U (en) * 2018-09-30 2019-07-02 锦萧建筑科技有限公司 PC precast floor slab pulley suspender

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109750804A (en) * 2019-01-10 2019-05-14 杭州江润科技有限公司 Assembled stair and its construction method
CN109958219A (en) * 2019-04-11 2019-07-02 中国十七冶集团有限公司 A kind of complex environment roofing truss lower part liner plate suspension cable installation method
CN114014147A (en) * 2021-11-11 2022-02-08 广东省建工设计顾问有限公司 Multipoint hanger structure and hoisting method thereof

Similar Documents

Publication Publication Date Title
CN109052149A (en) PC precast floor slab pulley suspender
CN105645248B (en) A kind of steel reinforcement cage lifting device and method
CN204917648U (en) Turbine rotor lifts by crane instrument
CN104060840A (en) Construction method for lifting large-span dome net rack by using bolt sphere truss lifter
CN205346612U (en) Many hoisting points of integral component of building assembly hoist and mount automatic balance hoist
CN109095343A (en) Assembled hanger
CN209052274U (en) PC precast floor slab pulley suspender
CN208948666U (en) The prefabricated beam column pulley suspender of PC
CN208964364U (en) A kind of assembled laminated floor slab Automatic hook block
CN205296844U (en) Precast box girder steel strand wires hoisting point
CN204454235U (en) A kind of novel many suspension centres equalizing bar device
CN108532963A (en) The hydraulic lifting installation method of large span high-altitude steel frame gallery structure
CN203474231U (en) Steel bar tower safety hoisting device
CN105780659A (en) Lifting appliance special for erection of large-tonnage steel box beam segment in non-stayed cable area of cable-stayed bridge
CN205527302U (en) Steel reinforcement cage hoisting accessory
CN204624958U (en) The row of hanging
CN104030176B (en) The equalizer bar of hoisting platform truss and hanging method thereof
CN105329766A (en) Automatic balance type lifting beam
CN109052146A (en) The prefabricated beam column pulley suspender of PC
CN208948679U (en) Assembled hanger
CN114835003A (en) Device and hoisting method suitable for balanced hoisting of large and medium-sized space prefabricated unit parts
CN213011542U (en) Multifunctional combined adjustable hanging frame
CN107235413A (en) A kind of component Current Collector Sleave
CN110316649A (en) A kind of suspender and hanging method suitable for irregular truss
CN110697564A (en) Hoisting device and hoisting method for precast concrete beam

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination