CN205346612U - Many hoisting points of integral component of building assembly hoist and mount automatic balance hoist - Google Patents

Many hoisting points of integral component of building assembly hoist and mount automatic balance hoist Download PDF

Info

Publication number
CN205346612U
CN205346612U CN201620032490.8U CN201620032490U CN205346612U CN 205346612 U CN205346612 U CN 205346612U CN 201620032490 U CN201620032490 U CN 201620032490U CN 205346612 U CN205346612 U CN 205346612U
Authority
CN
China
Prior art keywords
fixed pulley
wire rope
steel wire
pulley
trapeze
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620032490.8U
Other languages
Chinese (zh)
Inventor
汪丕明
萧树忠
孙兵
张玲
刘继鹏
张晓东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Qixing Residential Industry Co Ltd
Original Assignee
Shandong Qixing Residential Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Qixing Residential Industry Co Ltd filed Critical Shandong Qixing Residential Industry Co Ltd
Priority to CN201620032490.8U priority Critical patent/CN205346612U/en
Application granted granted Critical
Publication of CN205346612U publication Critical patent/CN205346612U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

This sets up connecting device in the lower part of trapeze and is connected with fixed pulley and running block. All assembly pulleys concatenate with a wire rope, and wire rope carries out the automatically regulated of length, atress distribution through the assembly pulley. Horizontal swinging can be controlled to direction at two fixed pulleys of trapeze tip. Middle fixed pulley sets up to two -way standing block to guarantee that wire rope can carry out two -way regulation length. The quantity of middle two -way standing block is generally no longer than two sets of. Whenever, set up a two -way standing block more, just can have more a movable pulley. Link to each other with the lifting hook through the wire rope of both ends fixed pulley is direct, link to each other with the movable pulley to reach the requirement that increases hoisting weight. The utility model discloses mainly be applicable to the component hoist and mount of many hoisting points.

Description

Building assembled integral lifting component many suspension centres autobalance suspender
Technical field
This utility model relates to Architectural Equipment technical field, particularly to building assembled integral lifting component many suspension centres autobalance suspender.
Background technology
According to code requirement, selecting suitable hoisting machinery according to lifting weight and safe dose, be not preferably less than 45 degree according to the angle of lifting rope Yu component during lifting, the requirement not also being preferably greater than 60 degree selects suitable suspender.The component volume of present architectural industrialization is big, size disunity, and hoisting structure is complicated.Can only changing different suspenders according to component feature in hoisting process, the component that weight is identical sometimes also also must change suspender because of shape difference.Particularly the lifting component of many suspension centres is especially prominent.Concrete embodiment is as follows: many suspension centres component to use the steel wire rope of different length to ensure every steel wire rope all uniform force, this is just just relatively strict to the length requirement of steel wire rope, and length that different size of component requires steel wire rope is also different, this has seriously constrained speed and the safety of many suspension centres lifting component, also result in the significant wastage of the suspenders such as steel wire rope, also have impact on the efficiency of construction simultaneously.
Utility model content
For overcoming problems of the prior art, this utility model provide a kind of realize the lifting of many suspension centres, without changing suspender, can automatically adjust lifting angle and ensure the suspender of steel wire rope uniform force and safety.
The technical scheme in the invention for solving the technical problem is: this kind of building assembled integral lifting component many suspension centres autobalance suspender, it is characterized in that: include the trapeze of a strip, it is interval with two in trapeze upper horizontal and is flexibly connected ring, lifting rope two ends are fixing to be connected with flexible connection ring, is provided with the link being connected with lifting machine in the middle part of lifting rope;It is connected with mounting the connecting device of component to be hung at trapeze, described connecting device includes respectively being articulated and connected in the bottom, two ends of trapeze a fixed pulley, respectively the first fixed pulley and the second fixed pulley, first fixed pulley and the second fixed pulley are wound with steel wire rope, steel wire naturally droop and its end is connected to suspension hook;In the middle of trapeze, lower section is hingedly connected with two-way fixed pulley group, fixed pulley group includes two coaxial fixed pulleys, respectively the 3rd fixed pulley and the 4th fixed pulley, 3rd fixed pulley and the 4th fixed pulley are wound with the steel wire rope being connected with the first fixed pulley and the second fixed pulley, being provided with movable pulley bottom the steel wire rope of the 3rd fixed pulley and the 4th fixed pulley, movable pulley is connected with suspension hook by connecting steel part.
Further, the end bolt of the steel wire rope below the first described fixed pulley and the second fixed pulley is solid on suspension hook.
Further, the steel wire rope below the first described fixed pulley and the second fixed pulley by movable pulley be connected between steel and be connected with suspension hook.
Further, described the first fixed pulley, the second fixed pulley and the 3rd fixed pulley are hinged with trapeze each through the bearing pin at fixture top.
Further, in the middle part of trapeze, it is provided with lower section is hingedly connected with some fixed pulley groups, fixed pulley group includes two coaxial fixed pulleys, fixed pulley is wound with the steel wire rope being connected with other each fixed pulleys, each fixed pulley is connected by a steel wire rope, being provided with movable pulley bottom the steel wire rope of middle each fixed pulley, movable pulley is connected with suspension hook by connecting steel part.
To sum up, the having the beneficial effect that of technique scheme of the present utility model:
1, realize multiple spot to lift, it is prevented that treat the inclination of lifting components simultaneously, improve the safe coefficient of lifting component.
2, without because treating that lifting components weight changes different suspenders with change of shape, being greatly saved the lifting time, improve lifting efficiency.
3, suspender varies in weight according to Components Shape, automatically adjusts steel wire rope lifting angle, it is ensured that the uniform stressed of every steel wire rope.
Accompanying drawing explanation
Fig. 1 is the structural representation of this utility model embodiment one;
Fig. 2 is the structural representation of this utility model embodiment two;
Fig. 3 is the structural representation of this utility model embodiment three;
Fig. 4 is the structural representation of lower section fixed pulley group in the middle part of this utility model trapeze.
In figure:
1 trapeze, 2 are flexibly connected ring, 3 links, 4 first fixed pulleys, 5 second fixed pulleys, 6 steel wire ropes, 7 suspension hooks, 8 the 3rd fixed pulleys, 9 the 4th fixed pulleys, 10 movable pulleys, and 11 connect steel part, 12 fixtures, 13 bearing pins.
Detailed description of the invention
Below in conjunction with accompanying drawing 1-4, feature of the present utility model and principle being described in detail, illustrated embodiment is only used for explaining this utility model, not limits protection domain of the present utility model with this.
As it is shown in figure 1, this utility model includes the trapeze 1 of a strip, for ensureing its intensity, this trapeze 1 can adopt structure steel material.It is provided with two connecting holes being connected with flexible connection ring 2 in horizontal interval, trapeze 1 upper marginal position place, is flexibly connected ring and is movably connected on this connecting hole.Lifting rope two ends are fixing to be connected with flexible connection ring 2, is provided with the link 3 being connected with lifting machine in the middle part of lifting rope.
Embodiment one, as shown in Figure 1, it is connected with mounting the connecting device of component to be hung at trapeze 1, described connecting device includes respectively being articulated and connected in the bottom, two ends of trapeze 1 fixed pulley, respectively the first fixed pulley 4 and the second fixed pulley 5, first fixed pulley and the second fixed pulley are wound with steel wire rope 6, steel wire naturally droop and its end is connected to suspension hook 7.As shown in Figure 4, in the middle of trapeze 1, lower section is hingedly connected with two-way fixed pulley group, to ensure that steel wire rope can carry out two-ways regulation length.Fixed pulley group includes two coaxial fixed pulleys, respectively the 3rd fixed pulley 8 and the 4th fixed pulley 9, being wound with the steel wire rope 6 being connected with the first fixed pulley 4 and the second fixed pulley 5 on 3rd fixed pulley 8 and the 4th fixed pulley 9, namely same steel wire rope is from left to right once through the first fixed pulley the 4, the 3rd fixed pulley the 8, the 4th fixed pulley 9 and the second fixed pulley 5.Being provided with movable pulley 10 bottom the steel wire rope of the 3rd fixed pulley and the 4th fixed pulley, movable pulley 10 is connected with suspension hook 7 by connecting steel part 11.The end bolt of the steel wire rope below the first described fixed pulley 4 and the second fixed pulley 5 is solid on suspension hook 7.
Embodiment two: as in figure 2 it is shown, further, can also the passing through movable pulley 10 and be connected steel part 11 and be connected with suspension hook 7 of the first described fixed pulley 4 and the steel wire rope below the second fixed pulley 5.
Embodiment three: as it is shown on figure 3, further, being provided with lower section and be hingedly connected with some two-way fixed pulley groups in the middle part of trapeze 1, the quantity of middle two-way fixed pulley group is usually no more than two groups.Often a two-way fixed pulley group is set, it is possible to many movable pulleys more.Directly it is connected with suspension hook by the steel wire rope of two ends fixed pulley, it is also possible to be the requirement being connected with movable pulley and reaching to increase hoisting weight.Fixed pulley group includes two coaxial fixed pulleys, and fixed pulley is wound with the steel wire rope being connected with other each fixed pulleys, and each fixed pulley is connected by steel wire rope, and namely in this design, steel wire rope only has one, and this steel wire rope is linked in sequence each fixed pulley, movable pulley.Being provided with movable pulley bottom the steel wire rope of middle each fixed pulley, movable pulley is connected with suspension hook by connecting steel part.
Further, described the first fixed pulley, the second fixed pulley and the 3rd fixed pulley are hinged with trapeze each through the bearing pin 13 at fixture 12 top, so the steel wire rope on each fixed pulley can arbitrarily swing, it is automatically adjusted according to the weight of component to be hung, shape need.
Realize multiple spot to lift, it is prevented that treat the inclination of lifting components simultaneously, improve the safe coefficient of lifting component.
Without because treating that lifting components weight changes different suspenders with change of shape, being greatly saved the lifting time, improve lifting efficiency.
Suspender varies in weight according to Components Shape, automatically adjusts steel wire rope lifting angle, it is ensured that the uniform stressed of every steel wire rope.
Above-described embodiment is only the description that preferred implementation of the present utility model is carried out; not the scope of the present invention is defined; under the premise designing spirit without departing from this utility model; relevant technical staff in the field, to various deformation of the present utility model and improvement, all should expand in the determined protection domain of this utility model claims.

Claims (5)

1. building assembled integral lifting component many suspension centres autobalance suspender, it is characterized in that: include the trapeze of a strip, being interval with two in trapeze upper horizontal and be flexibly connected ring, lifting rope two ends are fixing to be connected with flexible connection ring, is provided with the link being connected with lifting machine in the middle part of lifting rope;It is connected with mounting the connecting device of component to be hung at trapeze, described connecting device includes respectively being articulated and connected in the bottom, two ends of trapeze a fixed pulley, respectively the first fixed pulley and the second fixed pulley, first fixed pulley and the second fixed pulley are wound with steel wire rope, steel wire naturally droop and its end is connected to suspension hook;In the middle of trapeze, lower section is hingedly connected with two-way fixed pulley group, fixed pulley group includes two coaxial fixed pulleys, respectively the 3rd fixed pulley and the 4th fixed pulley, 3rd fixed pulley and the 4th fixed pulley are wound with the steel wire rope being connected with the first fixed pulley and the second fixed pulley, it is provided with movable pulley bottom the steel wire rope of the 3rd fixed pulley and the 4th fixed pulley, movable pulley is connected with suspension hook by connecting steel part, and each fixed pulley is connected by a steel wire rope.
2. building assembled integral lifting component many suspension centres autobalance suspender according to claim 1, it is characterised in that: the end bolt of the steel wire rope below the first described fixed pulley and the second fixed pulley is solid on suspension hook.
3. building assembled integral lifting component many suspension centres autobalance suspender according to claim 1, it is characterised in that: being connected with suspension hook with being connected steel part by movable pulley of the steel wire rope below the first described fixed pulley and the second fixed pulley.
4. building assembled integral lifting component many suspension centres autobalance suspender according to claim 1, it is characterised in that: described the first fixed pulley, the second fixed pulley and the 3rd fixed pulley are hinged with trapeze each through the bearing pin at fixture top.
5. building assembled integral lifting component many suspension centres autobalance suspender according to claim 1, it is characterized in that: in the middle part of trapeze, be provided with lower section be hingedly connected with some fixed pulley groups, fixed pulley group includes two coaxial fixed pulleys, fixed pulley is wound with the steel wire rope being connected with other each fixed pulleys, each fixed pulley is connected by a steel wire rope, being provided with movable pulley bottom the steel wire rope of middle each fixed pulley, movable pulley is connected with suspension hook by connecting steel part.
CN201620032490.8U 2016-01-14 2016-01-14 Many hoisting points of integral component of building assembly hoist and mount automatic balance hoist Expired - Fee Related CN205346612U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620032490.8U CN205346612U (en) 2016-01-14 2016-01-14 Many hoisting points of integral component of building assembly hoist and mount automatic balance hoist

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620032490.8U CN205346612U (en) 2016-01-14 2016-01-14 Many hoisting points of integral component of building assembly hoist and mount automatic balance hoist

Publications (1)

Publication Number Publication Date
CN205346612U true CN205346612U (en) 2016-06-29

Family

ID=56175102

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620032490.8U Expired - Fee Related CN205346612U (en) 2016-01-14 2016-01-14 Many hoisting points of integral component of building assembly hoist and mount automatic balance hoist

Country Status (1)

Country Link
CN (1) CN205346612U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107021415A (en) * 2017-04-28 2017-08-08 丁灏 A kind of Current Collector Sleave
CN107244606A (en) * 2017-07-12 2017-10-13 江苏金贸科技发展有限公司 A kind of many cabin piping lane adjustable horizontal boom hoistings
CN108178068A (en) * 2017-12-08 2018-06-19 宝鸡石油机械有限责任公司 A kind of large-diameter thread attaching/detaching apparatus and its assembly and disassembly methods
CN108792986A (en) * 2018-06-26 2018-11-13 东莞唯度电子科技服务有限公司 A kind of building assembly hanging device
CN112323648A (en) * 2020-11-09 2021-02-05 中交二公局第五工程有限公司 Segment erection lifting appliance based on bridge construction and use method thereof
CN112645209A (en) * 2020-12-28 2021-04-13 叶进银 Synchronous overhead hoist of many steel pipes for construction

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107021415A (en) * 2017-04-28 2017-08-08 丁灏 A kind of Current Collector Sleave
CN107244606A (en) * 2017-07-12 2017-10-13 江苏金贸科技发展有限公司 A kind of many cabin piping lane adjustable horizontal boom hoistings
CN108178068A (en) * 2017-12-08 2018-06-19 宝鸡石油机械有限责任公司 A kind of large-diameter thread attaching/detaching apparatus and its assembly and disassembly methods
CN108792986A (en) * 2018-06-26 2018-11-13 东莞唯度电子科技服务有限公司 A kind of building assembly hanging device
CN112323648A (en) * 2020-11-09 2021-02-05 中交二公局第五工程有限公司 Segment erection lifting appliance based on bridge construction and use method thereof
CN112645209A (en) * 2020-12-28 2021-04-13 叶进银 Synchronous overhead hoist of many steel pipes for construction
CN112645209B (en) * 2020-12-28 2023-04-28 福建华航建设集团有限公司 Synchronous overhead hoist of many steel pipes for construction

Similar Documents

Publication Publication Date Title
CN205346612U (en) Many hoisting points of integral component of building assembly hoist and mount automatic balance hoist
CN205855865U (en) A kind of hoisting machine with anti-rock
CN204490312U (en) The upending frame that a kind of suspension switch cabinet moves
CN102733310B (en) Lifting construction method for arch rib segments of steel box handle-basket arch bridge
CN201545635U (en) Holding rod with double flat arms
CN204847764U (en) Prefabricated component production is with hoist and mount frame
CN103715633A (en) Clamping device and method for replacing single-hole connecting plate strain insulator string
CN202201604U (en) Self-balance rope end composite set
CN209455933U (en) A kind of superimposed sheet lifting appliance for hoisting
CN103708360B (en) Swing arm tower crane, standard knot introduction system thereof and standard knot introduction method
CN214935394U (en) Automatic steel arch rib location hoist of adjusting
CN207346996U (en) A kind of Bridge Erector
CN205275004U (en) Automatic balanced type hanging beam
CN105329766A (en) Automatic balance type lifting beam
CN204624958U (en) The row of hanging
CN205187639U (en) Hoist device that possesses two -way leveling ability
CN203159036U (en) Line-shaped lifting appliance
CN102765664A (en) Pulley assembly and crane
CN204624959U (en) Building berth main frame installation hoisting structure
CN205045696U (en) Iron tower lower margin cable suspension device for hot -galvanize
CN209143484U (en) A kind of hanging apparatus
CN203667795U (en) Suspensory rigging adopting series connection of five groups of vertically connected pulley blocks
CN209024026U (en) A kind of reinforcing bar cage hoisting machine
CN205855779U (en) Assembled architecture construction hoisting equalizer bar
CN208532061U (en) A kind of derrick crane convenient for construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160629

Termination date: 20170114

CF01 Termination of patent right due to non-payment of annual fee