CN205045696U - Iron tower lower margin cable suspension device for hot -galvanize - Google Patents
Iron tower lower margin cable suspension device for hot -galvanize Download PDFInfo
- Publication number
- CN205045696U CN205045696U CN201520789760.5U CN201520789760U CN205045696U CN 205045696 U CN205045696 U CN 205045696U CN 201520789760 U CN201520789760 U CN 201520789760U CN 205045696 U CN205045696 U CN 205045696U
- Authority
- CN
- China
- Prior art keywords
- iron tower
- chain sling
- foundation
- hoist
- bracket
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- XEEYBQQBJWHFJM-UHFFFAOYSA-N iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 title claims abstract description 68
- 229910052742 iron Inorganic materials 0.000 title claims abstract description 34
- 239000000725 suspension Substances 0.000 title claims abstract description 25
- 239000000463 material Substances 0.000 claims description 6
- 229910000831 Steel Inorganic materials 0.000 claims description 4
- 239000010959 steel Substances 0.000 claims description 4
- 238000005452 bending Methods 0.000 claims description 3
- 238000004519 manufacturing process Methods 0.000 abstract 1
- 238000007747 plating Methods 0.000 abstract 1
- HCHKCACWOHOZIP-UHFFFAOYSA-N zinc Chemical compound [Zn] HCHKCACWOHOZIP-UHFFFAOYSA-N 0.000 abstract 1
- 239000011701 zinc Substances 0.000 abstract 1
- 229910052725 zinc Inorganic materials 0.000 abstract 1
- 238000000034 method Methods 0.000 description 8
- 238000005246 galvanizing Methods 0.000 description 2
- 241001391944 Commicarpus scandens Species 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
Abstract
The utility model discloses an iron tower lower margin cable suspension device for hot -galvanize belongs to iron tower assembly technical field, including gallows (2), lug (1), chain sling (3), hoist and mount support (4) and round pin axle (6), lug (1) is adorned on the upper portion of gallows (2), and the one end of chain sling (3) is linked with the lower part of gallows (2), the other end is linked with the one end of hoist and mount support (4), and the other end that hoists supports (4) is equipped with two hoist and mount piece (5) that have the lewis hole, chain sling (3) link each other by a plurality of rings and constitute, round pin axle (6) pass two hoist and mount pieces (5) from the lewis hole, chain sling (3), hoist and mount support (4) all be two at least with round pin spool (6). The zinc -plating of can the stable iron tower lower margin of hoisting being convenient for, simultaneously repetitious usage can be repeated, the manufacturing cost of enterprise is reduced.
Description
Technical field
The utility model relates to a kind of erecting by overhang, and specifically a kind of foundation of iron tower pot galvanize erecting by overhang, belongs to steel tower assembly technique field.
Background technology
Carrying out foundation of iron tower being first hang workpiece in zinc-plated process, needing in the process to face down less, reducing and dripping knurl thus the presentation quality improving zinc-plated rear lower margin.Current hanging uses a large amount of iron wires to hang up can achieve the goal.But can not use by secondary for used iron wire, and in use iron wire is easy to break, such workman just needs to supplement new iron wire in time, which not only adds productive costs, also can increase work capacity to workman simultaneously.
Summary of the invention
For above-mentioned prior art Problems existing, the utility model provides a kind of foundation of iron tower pot galvanize erecting by overhang, can be convenient to zinc-plated by stable foundation of iron tower of slinging; Repeatedly can use simultaneously, reduce enterprise's productive costs.
To achieve these goals, the technical solution adopted in the utility model is: this kind of foundation of iron tower pot galvanize erecting by overhang, comprise suspension bracket, hanger, chain sling, hoisting bracket and bearing pin, hanger is contained in the top of suspension bracket, one end of chain sling and the bottom of suspension bracket link, the other end links with one end of hoisting bracket, the other end of hoisting bracket is provided with two lifting blocks with lifting hole(eyelet), and described chain sling is interlinked by multiple suspension ring and forms, and described bearing pin lifts blocks through two from lifting hole(eyelet); Described chain sling, hoisting bracket and bearing pin are all at least two.
Further, described chain sling, hoisting bracket and bearing pin are three, and described suspension bracket material is I-beam section.
Further, one end bending of described bearing pin.
Further, described suspension ring material is round steel.
Compared with prior art, the mode that the utility model adopts suspension bracket, chain sling and hoisting bracket to combine, by bearing pin, hoisting bracket is connected with the pin hole of foundation of iron tower, then suspension bracket is lifted by crane by hanger with lifting appliance, staff can carry out zinc-plated process to foundation of iron tower, and in whole galvanizing process, this device can make foundation of iron tower keep stabilized conditions; Zinc-plated complete after foundation of iron tower can be put down, then can carry out slinging of next foundation of iron tower, this device can repeatedly use, and reduces the productive costs of enterprise.
Accompanying drawing explanation
Fig. 1 is process chart of the present utility model.
In figure: 1, hanger, 2, suspension bracket, 3, chain sling, 4, hoisting bracket, 5, lifting block, 6, bearing pin, 7, foundation of iron tower.
Detailed description of the invention
The utility model is described in further detail below.
As shown in Figure 1, the utility model comprises suspension bracket 2, hanger 1, chain sling 3, hoisting bracket 4 and bearing pin 6, hanger 1 is contained in the top of suspension bracket 2, one end and the bottom of suspension bracket 2 of chain sling 3 link, the other end links with one end of hoisting bracket 4, the other end of hoisting bracket 4 is provided with two lifting blocks 5 with lifting hole(eyelet), described chain sling 3 is interlinked by multiple suspension ring and forms, and described bearing pin 6 lifts blocks 5 through two from lifting hole(eyelet); Described chain sling 3, hoisting bracket 4 and bearing pin 6 are all at least two.
Improve as one of the present utility model, described chain sling 3, hoisting bracket 4 and bearing pin 6 are three, and described suspension bracket 2 material is I-beam section; Because foundation of iron tower 7 model is different, cause its size also different, and then make the spacing between the pin hole of each foundation of iron tower 7 different, such employing three chain slings 3, hoisting bracket 4 and bearing pin 6, according to the spacing between different foundation of iron tower 7 pin holes, select wherein two groups of chain slings adapted 3 and hoisting bracket 4 to lift by crane, the utility model can be enable like this to sling two kinds of foundation of iron towers varied in size 7, improve applicability of the present utility model.
Further, one end bending of described bearing pin 6.
Further, described suspension ring material is round steel.
During work, by bearing pin 6, lifting block 5 is connected with the pin hole of foundation of iron tower 7, and then by hoisting bracket 4 and chain sling 3, suspension bracket 2 is connected indirectly with foundation of iron tower 7, then suspension bracket 2 is lifted by crane by hanger 1 with lifting appliance, staff can carry out zinc-plated process to foundation of iron tower 7, and in whole galvanizing process, this device can make foundation of iron tower 7 keep stabilized conditions; Zinc-plated complete after foundation of iron tower 7 can be put down, then can carry out slinging of next foundation of iron tower 7.
Claims (4)
1. a foundation of iron tower pot galvanize erecting by overhang, it is characterized in that, comprise suspension bracket (2), hanger (1), chain sling (3), hoisting bracket (4) and bearing pin (6), hanger (1) is contained in the top of suspension bracket (2), one end of chain sling (3) links with the bottom of suspension bracket (2), the other end links with the one end of hoisting bracket (4), the other end of hoisting bracket (4) is provided with two lifting blocks (5) with lifting hole(eyelet), described chain sling (3) is interlinked by multiple suspension ring and forms, described bearing pin (6) lifts block (5) through two from lifting hole(eyelet), described chain sling (3), hoisting bracket (4) and bearing pin (6) are all at least two.
2. foundation of iron tower pot galvanize erecting by overhang according to claim 1, it is characterized in that, described chain sling (3), hoisting bracket (4) and bearing pin (6) are three, and described suspension bracket (2) material is I-beam section.
3. foundation of iron tower pot galvanize erecting by overhang according to claim 1 and 2, is characterized in that, one end bending of described bearing pin (6).
4. foundation of iron tower pot galvanize erecting by overhang according to claim 1 and 2, is characterized in that, described suspension ring material is round steel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520789760.5U CN205045696U (en) | 2015-10-12 | 2015-10-12 | Iron tower lower margin cable suspension device for hot -galvanize |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520789760.5U CN205045696U (en) | 2015-10-12 | 2015-10-12 | Iron tower lower margin cable suspension device for hot -galvanize |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205045696U true CN205045696U (en) | 2016-02-24 |
Family
ID=55339294
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520789760.5U Expired - Fee Related CN205045696U (en) | 2015-10-12 | 2015-10-12 | Iron tower lower margin cable suspension device for hot -galvanize |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205045696U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106088433A (en) * | 2016-08-17 | 2016-11-09 | 四川省建筑科学研究院 | A kind of novel bidirectional stress superimposed sheet and construction method thereof |
-
2015
- 2015-10-12 CN CN201520789760.5U patent/CN205045696U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106088433A (en) * | 2016-08-17 | 2016-11-09 | 四川省建筑科学研究院 | A kind of novel bidirectional stress superimposed sheet and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201864459U (en) | Buckle type hoisting and fastening device for hoisting electrode of large diameter | |
CN201990370U (en) | Complete machine hanger with adjustable center of gravity | |
CN202296842U (en) | Hanger special for universal shaft of vertical rolling mill | |
CN204342250U (en) | A kind of multi-state hoisting balance beam | |
CN202181165U (en) | Cross lifting beam for box type transformer | |
CN205045696U (en) | Iron tower lower margin cable suspension device for hot -galvanize | |
CN205132903U (en) | Steel wire slings | |
CN202785251U (en) | Crane hook fixture | |
CN202156871U (en) | Lifting appliance capable of unhooking automatically | |
CN109095343A (en) | Assembled hanger | |
CN203237922U (en) | Hanger | |
CN204569141U (en) | Steel plate overhead hoist | |
CN205953335U (en) | Shape mould of preapring for an unfavorable turn of events is hoisted in equipment of electrolysis trough bottom plate | |
CN205034964U (en) | A hoist for vertical rolling mill transmission shaft | |
CN201962679U (en) | Lifting bracket used for vertically and aswirl lifting steel reinforcement cage and lifting system | |
CN204958135U (en) | Hoist of handling modularization wall body | |
CN206955528U (en) | A kind of novel labour saving hoisting mechanism | |
CN203159036U (en) | Line-shaped lifting appliance | |
CN202864675U (en) | Shaft-type part hoisting tool | |
CN206720556U (en) | A kind of Current Collector Sleave | |
CN205241050U (en) | I -shaped wheel lifting device | |
CN205772842U (en) | Inverted arch prefabricated section suspender | |
CN201495022U (en) | Steel tube lifting appliance | |
CN205616431U (en) | Electric power angle steel for iron tower hot -galvanize hoist | |
CN104261283A (en) | Construction method of antenna hoisting device of wireless base station |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160224 Termination date: 20181012 |
|
CF01 | Termination of patent right due to non-payment of annual fee |