CN205045696U - Iron tower lower margin cable suspension device for hot -galvanize - Google Patents

Iron tower lower margin cable suspension device for hot -galvanize Download PDF

Info

Publication number
CN205045696U
CN205045696U CN201520789760.5U CN201520789760U CN205045696U CN 205045696 U CN205045696 U CN 205045696U CN 201520789760 U CN201520789760 U CN 201520789760U CN 205045696 U CN205045696 U CN 205045696U
Authority
CN
China
Prior art keywords
iron tower
chain sling
foundation
hoist
bracket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520789760.5U
Other languages
Chinese (zh)
Inventor
蒋立新
朱小明
刘芝豹
朱飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU HUADIAN STEEL TOWER MANUFACTURING Co Ltd
Original Assignee
JIANGSU HUADIAN STEEL TOWER MANUFACTURING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU HUADIAN STEEL TOWER MANUFACTURING Co Ltd filed Critical JIANGSU HUADIAN STEEL TOWER MANUFACTURING Co Ltd
Priority to CN201520789760.5U priority Critical patent/CN205045696U/en
Application granted granted Critical
Publication of CN205045696U publication Critical patent/CN205045696U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Coating With Molten Metal (AREA)

Abstract

The utility model discloses an iron tower lower margin cable suspension device for hot -galvanize belongs to iron tower assembly technical field, including gallows (2), lug (1), chain sling (3), hoist and mount support (4) and round pin axle (6), lug (1) is adorned on the upper portion of gallows (2), and the one end of chain sling (3) is linked with the lower part of gallows (2), the other end is linked with the one end of hoist and mount support (4), and the other end that hoists supports (4) is equipped with two hoist and mount piece (5) that have the lewis hole, chain sling (3) link each other by a plurality of rings and constitute, round pin axle (6) pass two hoist and mount pieces (5) from the lewis hole, chain sling (3), hoist and mount support (4) all be two at least with round pin spool (6). The zinc -plating of can the stable iron tower lower margin of hoisting being convenient for, simultaneously repetitious usage can be repeated, the manufacturing cost of enterprise is reduced.

Description

Foundation of iron tower pot galvanize erecting by overhang
Technical field
The utility model relates to a kind of erecting by overhang, and specifically a kind of foundation of iron tower pot galvanize erecting by overhang, belongs to steel tower assembly technique field.
Background technology
Carrying out foundation of iron tower being first hang workpiece in zinc-plated process, needing in the process to face down less, reducing and dripping knurl thus the presentation quality improving zinc-plated rear lower margin.Current hanging uses a large amount of iron wires to hang up can achieve the goal.But can not use by secondary for used iron wire, and in use iron wire is easy to break, such workman just needs to supplement new iron wire in time, which not only adds productive costs, also can increase work capacity to workman simultaneously.
Summary of the invention
For above-mentioned prior art Problems existing, the utility model provides a kind of foundation of iron tower pot galvanize erecting by overhang, can be convenient to zinc-plated by stable foundation of iron tower of slinging; Repeatedly can use simultaneously, reduce enterprise's productive costs.
To achieve these goals, the technical solution adopted in the utility model is: this kind of foundation of iron tower pot galvanize erecting by overhang, comprise suspension bracket, hanger, chain sling, hoisting bracket and bearing pin, hanger is contained in the top of suspension bracket, one end of chain sling and the bottom of suspension bracket link, the other end links with one end of hoisting bracket, the other end of hoisting bracket is provided with two lifting blocks with lifting hole(eyelet), and described chain sling is interlinked by multiple suspension ring and forms, and described bearing pin lifts blocks through two from lifting hole(eyelet); Described chain sling, hoisting bracket and bearing pin are all at least two.
Further, described chain sling, hoisting bracket and bearing pin are three, and described suspension bracket material is I-beam section.
Further, one end bending of described bearing pin.
Further, described suspension ring material is round steel.
Compared with prior art, the mode that the utility model adopts suspension bracket, chain sling and hoisting bracket to combine, by bearing pin, hoisting bracket is connected with the pin hole of foundation of iron tower, then suspension bracket is lifted by crane by hanger with lifting appliance, staff can carry out zinc-plated process to foundation of iron tower, and in whole galvanizing process, this device can make foundation of iron tower keep stabilized conditions; Zinc-plated complete after foundation of iron tower can be put down, then can carry out slinging of next foundation of iron tower, this device can repeatedly use, and reduces the productive costs of enterprise.
Accompanying drawing explanation
Fig. 1 is process chart of the present utility model.
In figure: 1, hanger, 2, suspension bracket, 3, chain sling, 4, hoisting bracket, 5, lifting block, 6, bearing pin, 7, foundation of iron tower.
Detailed description of the invention
The utility model is described in further detail below.
As shown in Figure 1, the utility model comprises suspension bracket 2, hanger 1, chain sling 3, hoisting bracket 4 and bearing pin 6, hanger 1 is contained in the top of suspension bracket 2, one end and the bottom of suspension bracket 2 of chain sling 3 link, the other end links with one end of hoisting bracket 4, the other end of hoisting bracket 4 is provided with two lifting blocks 5 with lifting hole(eyelet), described chain sling 3 is interlinked by multiple suspension ring and forms, and described bearing pin 6 lifts blocks 5 through two from lifting hole(eyelet); Described chain sling 3, hoisting bracket 4 and bearing pin 6 are all at least two.
Improve as one of the present utility model, described chain sling 3, hoisting bracket 4 and bearing pin 6 are three, and described suspension bracket 2 material is I-beam section; Because foundation of iron tower 7 model is different, cause its size also different, and then make the spacing between the pin hole of each foundation of iron tower 7 different, such employing three chain slings 3, hoisting bracket 4 and bearing pin 6, according to the spacing between different foundation of iron tower 7 pin holes, select wherein two groups of chain slings adapted 3 and hoisting bracket 4 to lift by crane, the utility model can be enable like this to sling two kinds of foundation of iron towers varied in size 7, improve applicability of the present utility model.
Further, one end bending of described bearing pin 6.
Further, described suspension ring material is round steel.
During work, by bearing pin 6, lifting block 5 is connected with the pin hole of foundation of iron tower 7, and then by hoisting bracket 4 and chain sling 3, suspension bracket 2 is connected indirectly with foundation of iron tower 7, then suspension bracket 2 is lifted by crane by hanger 1 with lifting appliance, staff can carry out zinc-plated process to foundation of iron tower 7, and in whole galvanizing process, this device can make foundation of iron tower 7 keep stabilized conditions; Zinc-plated complete after foundation of iron tower 7 can be put down, then can carry out slinging of next foundation of iron tower 7.

Claims (4)

1. a foundation of iron tower pot galvanize erecting by overhang, it is characterized in that, comprise suspension bracket (2), hanger (1), chain sling (3), hoisting bracket (4) and bearing pin (6), hanger (1) is contained in the top of suspension bracket (2), one end of chain sling (3) links with the bottom of suspension bracket (2), the other end links with the one end of hoisting bracket (4), the other end of hoisting bracket (4) is provided with two lifting blocks (5) with lifting hole(eyelet), described chain sling (3) is interlinked by multiple suspension ring and forms, described bearing pin (6) lifts block (5) through two from lifting hole(eyelet), described chain sling (3), hoisting bracket (4) and bearing pin (6) are all at least two.
2. foundation of iron tower pot galvanize erecting by overhang according to claim 1, it is characterized in that, described chain sling (3), hoisting bracket (4) and bearing pin (6) are three, and described suspension bracket (2) material is I-beam section.
3. foundation of iron tower pot galvanize erecting by overhang according to claim 1 and 2, is characterized in that, one end bending of described bearing pin (6).
4. foundation of iron tower pot galvanize erecting by overhang according to claim 1 and 2, is characterized in that, described suspension ring material is round steel.
CN201520789760.5U 2015-10-12 2015-10-12 Iron tower lower margin cable suspension device for hot -galvanize Expired - Fee Related CN205045696U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520789760.5U CN205045696U (en) 2015-10-12 2015-10-12 Iron tower lower margin cable suspension device for hot -galvanize

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520789760.5U CN205045696U (en) 2015-10-12 2015-10-12 Iron tower lower margin cable suspension device for hot -galvanize

Publications (1)

Publication Number Publication Date
CN205045696U true CN205045696U (en) 2016-02-24

Family

ID=55339294

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520789760.5U Expired - Fee Related CN205045696U (en) 2015-10-12 2015-10-12 Iron tower lower margin cable suspension device for hot -galvanize

Country Status (1)

Country Link
CN (1) CN205045696U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106088433A (en) * 2016-08-17 2016-11-09 四川省建筑科学研究院 A kind of novel bidirectional stress superimposed sheet and construction method thereof
CN108666916A (en) * 2018-05-31 2018-10-16 国网山西省电力公司晋城供电公司 The stretching specific purpose tool of high-voltage mutual inductor metal expander

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106088433A (en) * 2016-08-17 2016-11-09 四川省建筑科学研究院 A kind of novel bidirectional stress superimposed sheet and construction method thereof
CN108666916A (en) * 2018-05-31 2018-10-16 国网山西省电力公司晋城供电公司 The stretching specific purpose tool of high-voltage mutual inductor metal expander

Similar Documents

Publication Publication Date Title
CN201864459U (en) Buckle type hoisting and fastening device for hoisting electrode of large diameter
CN201990370U (en) Complete machine hanger with adjustable center of gravity
CN204342250U (en) A kind of multi-state hoisting balance beam
CN202296842U (en) Hanger special for universal shaft of vertical rolling mill
CN205045696U (en) Iron tower lower margin cable suspension device for hot -galvanize
CN109095343A (en) Assembled hanger
CN202181165U (en) Cross lifting beam for box type transformer
CN204369401U (en) Roll coater roll change auxiliary device
CN205132903U (en) Steel wire slings
CN202864675U (en) Shaft-type part hoisting tool
CN202156871U (en) Lifting appliance capable of unhooking automatically
CN105329766A (en) Automatic balance type lifting beam
CN204569141U (en) Steel plate overhead hoist
CN205953335U (en) Shape mould of preapring for an unfavorable turn of events is hoisted in equipment of electrolysis trough bottom plate
CN104773645A (en) Tool for lifting bearing end cover of permanent magnet directly-driven wind generator
CN201962679U (en) Lifting bracket used for vertically and aswirl lifting steel reinforcement cage and lifting system
CN205034964U (en) A hoist for vertical rolling mill transmission shaft
CN204661128U (en) Spraying suspender
CN204958135U (en) Hoist of handling modularization wall body
CN114148885A (en) Height-adjustable cab lifting appliance
CN208948679U (en) Assembled hanger
CN203159036U (en) Line-shaped lifting appliance
CN206720556U (en) A kind of Current Collector Sleave
CN205241050U (en) I -shaped wheel lifting device
CN204958138U (en) Hoist of handling modularization roof truss

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160224

Termination date: 20181012

CF01 Termination of patent right due to non-payment of annual fee