CN109025273A - A kind of concrete beam mould board fixing clamp construction method - Google Patents

A kind of concrete beam mould board fixing clamp construction method Download PDF

Info

Publication number
CN109025273A
CN109025273A CN201810853586.4A CN201810853586A CN109025273A CN 109025273 A CN109025273 A CN 109025273A CN 201810853586 A CN201810853586 A CN 201810853586A CN 109025273 A CN109025273 A CN 109025273A
Authority
CN
China
Prior art keywords
steel pipe
square steel
length
square
split bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810853586.4A
Other languages
Chinese (zh)
Inventor
张东
孟凡勇
秦亮
周放
张海涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Shougang Construction Group Co Ltd
Original Assignee
Beijing Shougang Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Shougang Construction Group Co Ltd filed Critical Beijing Shougang Construction Group Co Ltd
Priority to CN201810853586.4A priority Critical patent/CN109025273A/en
Publication of CN109025273A publication Critical patent/CN109025273A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/04Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for lintels, beams, or transoms to be encased separately; Special tying or clamping means therefor

Abstract

A kind of concrete beam mould board fixing clamp construction method, belongs to technical field of building construction.The component of beam clamp device is made first, then together by each component welding assembly;After being completed, construction beam steel bar colligation, formwork are complete, and beam clamp device is fixed on the outside of template, reinforce back rest casting concrete.The advantage is that it is easy to operate, greatly reduce the workload of construction personnel, improves working efficiency, it is reusable and firm reliable.

Description

A kind of concrete beam mould board fixing clamp construction method
Technical field
The invention patent belongs to technical field of building construction, in particular to a kind of concrete beam mould board fixing clamp construction party Method.
Background technique
Qinhuangdao COUNTRY GARDEN provincial capital engineering, this engineering are high residential building, the building 7-1#, 7-4#, 7-5#, 7-6#, 7-7# 31 layers on the ground, 2 layers of underground, structure type is frame-shear-wall structure, and base form is raft foundation, and single building area is 13107 square metres.According to construction requirement, construction beam need to be arranged in secondary structure, reinforce, tear open according to the way formwork of conventional construction beam Except method is cumbersome, heavy workload, efficiency bottom.
Summary of the invention
The invention patent is designed to provide a kind of concrete beam mould board fixing clamp construction method, solves secondary structure Construct beam.It realizes easy to operate, greatly reduces the workload of construction personnel, improve working efficiency, it is reusable and firm Reliably.
Component of the present invention involved in construction includes the first square steel pipe 1, the second square steel pipe 2, third square steel pipe 3, cubic shape steel tube 4, split bolt 5 etc..Specific process step and the parameter of control are as follows:
(1) the fixed clamp device of production concrete beam mould board, the material for making fixing frame of formworks is side length 50mm, wall thickness 4mm And side length 45mm, the square steel pipe of wall thickness 4mm, interception side length 50mm length are the first square steel pipe of 300mm 1 and 500mm second 2 each one sections of square steel pipe, interception side length 40mm length is 500mm third square steel pipe and the cubic shape steel tube 4 each one of 500mm Section makes length 700mm long split bolt 5;
2, the first square steel pipe 1 and the second square steel pipe 2 are welded into the first L-type component 6, by 3 He of third square steel pipe Cubic shape steel tube 4 is welded into the second L-type component 7;Second square steel pipe 2 and 3 top same position of third square steel pipe are opened If two holes, after the completion of device welds aperture, processing and fabricating beam forms and wood reinforcement;
3, material is ready to complete, and after the completion of beam steel bar colligation, carries out formwork erection and flitch is reinforced;
4, two L-type beam clamp devices are vertically installed on the outside of template and flitch, split bolt is passed through into beam top position Split bolt 5 is secured with nuts the circular hole of beam clamp device;
5, template and flitch beam clamp device fixation back rest casting concrete.
It is determined by checking, it is easy to operate, greatly reduce the workload of construction personnel, improves working efficiency, it is repeatable to make With, and it is firm reliable.
Detailed description of the invention
Fig. 1 is a kind of component of concrete beam mould board fixing clamp construction method assembled formation.Wherein, the first square steel pipe 1, Second square steel pipe 2, third square steel pipe 3, cubic shape steel tube 4, split bolt 5.
Fig. 2 is device feature welding assembly schematic diagram.
Fig. 3 is construction beam steel bar colligation, formwork erection figure.
Fig. 4 is beam clamp device installation diagram.
Specific embodiment
Component of the present invention involved in construction includes the first square steel pipe 1, the second square steel pipe 2, third square steel pipe 3, cubic shape steel tube 4, split bolt 5 etc..Specific process step and the parameter of control are as follows:
1, concrete beam mould board fixing clamp construction method is made, the material of production fixing frame of formworks first is side length 50mm, Wall thickness 4mm and side length 45mm, the square steel pipe of wall thickness 4mm, interception side length 50mm length are 1 He of the first square steel pipe of 300mm Each one section of the second square steel pipe of 500mm 2, interception side length 40mm length are 500mm third square steel pipe 3 and 500mm square Steel pipe 4;Make length 700mm long split bolt 5;
2, the first square steel pipe 1 and the second square steel pipe 2 are welded into the first L-type component 6, by 3 He of third square steel pipe Cubic shape steel tube 4 is welded into the second L-type component 7;Second square steel pipe 2 and 3 top same position of third square steel pipe are opened If two holes, after the completion of device welds aperture, processing and fabricating beam forms and wood reinforcement;
3, material is ready to complete, and after the completion of beam steel bar colligation, carries out formwork erection and flitch is reinforced;
4, two L-type beam clamp devices are vertically installed on the outside of template and flitch, split bolt is passed through into beam top position Split bolt 5 is secured with nuts the circular hole of beam clamp device;
5, template and flitch beam clamp device fixation back rest casting concrete.

Claims (1)

1. a kind of concrete beam mould board fixing clamp construction method, the component involved in construction includes the first square steel pipe (1), the Two square steel pipes (2), third square steel pipe (3), cubic shape steel tube (4) split bolt (5);It is characterized in that, concrete technology Step and the parameter of control are as follows:
1) the fixed clamp device of production concrete beam mould board, the material for making fixing frame of formworks is side length 50mm, wall thickness 4mm and side length 45mm, the square steel pipe of wall thickness 4mm, interception side length 50mm length are the second square of the first square steel pipe of 300mm (1) and 500mm For steel pipe (2) every one section, interception side length 40mm length is 500mm third square steel pipe (3) and the cubic shape steel tube (4) of 500mm, system Make length 700mm long split bolt (5);
2) by the first square steel pipe (1) and the second square steel pipe (2) welding l-shaped component (6), by third square steel pipe (3) and Cubic shape steel tube (4) welds l-shaped component (7);By the first square steel pipe (2) and third square steel pipe (3) top identical bits It sets and opens up two holes, after the completion of device welds aperture, processing and fabricating beam forms and wood reinforcement;
3) it after the completion of beam steel bar colligation, carries out formwork erection and flitch is reinforced;
4) two L-type beam clamp devices are vertically installed on the outside of template and flitch, split bolt is pressed from both sides across Liang Dingbuweizhiliang Split bolt (5) is secured with nuts the circular hole of device;
5) template and flitch beam clamp device fixation back rest casting concrete.
CN201810853586.4A 2018-07-30 2018-07-30 A kind of concrete beam mould board fixing clamp construction method Pending CN109025273A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810853586.4A CN109025273A (en) 2018-07-30 2018-07-30 A kind of concrete beam mould board fixing clamp construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810853586.4A CN109025273A (en) 2018-07-30 2018-07-30 A kind of concrete beam mould board fixing clamp construction method

Publications (1)

Publication Number Publication Date
CN109025273A true CN109025273A (en) 2018-12-18

Family

ID=64647759

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810853586.4A Pending CN109025273A (en) 2018-07-30 2018-07-30 A kind of concrete beam mould board fixing clamp construction method

Country Status (1)

Country Link
CN (1) CN109025273A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110056186A (en) * 2019-06-03 2019-07-26 舜元建设(集团)有限公司 A kind of building template Simple clamp and its construction method
CN111173272A (en) * 2020-01-14 2020-05-19 中国十七冶集团有限公司 Simple lintel template reinforcing device and construction method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE20212134U1 (en) * 2002-08-07 2002-10-31 Hummel Heinz Ring beam formwork
CN201202276Y (en) * 2008-06-06 2009-03-04 中冶天工建设有限公司 Beam side panels fixture
CN103104093A (en) * 2013-01-14 2013-05-15 浙江凯雄科技有限公司 Special strengthening clamping tool for building beam bottom and beam side frameworks
CN104074352A (en) * 2014-06-29 2014-10-01 北京首钢建设集团有限公司 Wall body template supporting method in position with narrow space
CN205348768U (en) * 2015-12-30 2016-06-29 中国建筑第八工程局有限公司 Full adaptive type fixture device of adjustable combination formula
CN205955193U (en) * 2016-07-11 2017-02-15 中国建筑第八工程局有限公司 Can have enough to meet need integral concrete beam reinforcing apparatus
CN107083840A (en) * 2017-04-21 2017-08-22 北京首钢建设集团有限公司 A kind of anti-bank one-shot forming formwork erection method in toilet
CN108035540A (en) * 2017-12-28 2018-05-15 上海建工二建集团有限公司 A kind of heavy in section steel reinforced concrete Cast-in-situ Beam new type formwork fixture and construction method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE20212134U1 (en) * 2002-08-07 2002-10-31 Hummel Heinz Ring beam formwork
CN201202276Y (en) * 2008-06-06 2009-03-04 中冶天工建设有限公司 Beam side panels fixture
CN103104093A (en) * 2013-01-14 2013-05-15 浙江凯雄科技有限公司 Special strengthening clamping tool for building beam bottom and beam side frameworks
CN104074352A (en) * 2014-06-29 2014-10-01 北京首钢建设集团有限公司 Wall body template supporting method in position with narrow space
CN205348768U (en) * 2015-12-30 2016-06-29 中国建筑第八工程局有限公司 Full adaptive type fixture device of adjustable combination formula
CN205955193U (en) * 2016-07-11 2017-02-15 中国建筑第八工程局有限公司 Can have enough to meet need integral concrete beam reinforcing apparatus
CN107083840A (en) * 2017-04-21 2017-08-22 北京首钢建设集团有限公司 A kind of anti-bank one-shot forming formwork erection method in toilet
CN108035540A (en) * 2017-12-28 2018-05-15 上海建工二建集团有限公司 A kind of heavy in section steel reinforced concrete Cast-in-situ Beam new type formwork fixture and construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110056186A (en) * 2019-06-03 2019-07-26 舜元建设(集团)有限公司 A kind of building template Simple clamp and its construction method
CN111173272A (en) * 2020-01-14 2020-05-19 中国十七冶集团有限公司 Simple lintel template reinforcing device and construction method

Similar Documents

Publication Publication Date Title
CN204435673U (en) Integrated frame column template structure
WO2016062224A1 (en) Integrated column-equipped heat insulation wallboard, manufacturing and building processes and corollary equipment thereof
CN104131704A (en) Steel pipe column concrete lateral pouring method and steel pipe column structure used in method
KR100731593B1 (en) A pre-fabricating forms for concrete-structure and the construction method thereof
CN109025273A (en) A kind of concrete beam mould board fixing clamp construction method
CN210976588U (en) Template reinforcing system for double shear walls at deformation joint
CN110630011A (en) Template reinforcing system for double shear walls at deformation joint and construction method thereof
CN104047422A (en) Cylinder die manufacturing and mounting method
CN112302209B (en) Steel and concrete shear wall mixed structure and manufacturing method thereof
CN103806538B (en) A kind of precast reinforced concrete structure
CN204626961U (en) A kind of steel form trussed construction of swallow-tail form large-sized concrete pier stud
CN102619286A (en) Connecting joint of steel pipe concrete column and profile steel concrete beam
CN104786368A (en) Reinforcement forming technology
CN210713827U (en) Internal and external corner template reinforcing device
CN203834809U (en) Steel pipe column structure for steel pipe column concrete side pouring method
CN204898710U (en) Novel steel construction retaining wall
CN209260922U (en) Band girder rib laminated floor slab pre-tensioning system connecting joint structure
CN104153463A (en) Assembled integrated frame system and construction method thereof
CN203668894U (en) Concrete prefabricated form structure allowing rapid installation
CN103437493A (en) Connecting node of prefabricated reinforced concrete beam and construction method of connecting node
CN215055279U (en) Thickness control device for steel plate concrete shear wall symmetrical wall body
CN215105454U (en) Prefabricated and cast-in-place piled raft foundation that combines together
CN109594687A (en) A kind of nodal connection device and its methods and applications for vertical shear wall piece
CN205330156U (en) Cast -in -place template reinforcing apparatus at position is connected to assembly outer wall and cast -in -place interior wall T type
CN213115520U (en) Concrete turn-ups reinforcement tool

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination