CN109025273A - A kind of concrete beam mould board fixing clamp construction method - Google Patents
A kind of concrete beam mould board fixing clamp construction method Download PDFInfo
- Publication number
- CN109025273A CN109025273A CN201810853586.4A CN201810853586A CN109025273A CN 109025273 A CN109025273 A CN 109025273A CN 201810853586 A CN201810853586 A CN 201810853586A CN 109025273 A CN109025273 A CN 109025273A
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- square steel
- length
- square
- split bolt
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G13/00—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
- E04G13/04—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for lintels, beams, or transoms to be encased separately; Special tying or clamping means therefor
Abstract
A kind of concrete beam mould board fixing clamp construction method, belongs to technical field of building construction.The component of beam clamp device is made first, then together by each component welding assembly;After being completed, construction beam steel bar colligation, formwork are complete, and beam clamp device is fixed on the outside of template, reinforce back rest casting concrete.The advantage is that it is easy to operate, greatly reduce the workload of construction personnel, improves working efficiency, it is reusable and firm reliable.
Description
Technical field
The invention patent belongs to technical field of building construction, in particular to a kind of concrete beam mould board fixing clamp construction party
Method.
Background technique
Qinhuangdao COUNTRY GARDEN provincial capital engineering, this engineering are high residential building, the building 7-1#, 7-4#, 7-5#, 7-6#, 7-7#
31 layers on the ground, 2 layers of underground, structure type is frame-shear-wall structure, and base form is raft foundation, and single building area is
13107 square metres.According to construction requirement, construction beam need to be arranged in secondary structure, reinforce, tear open according to the way formwork of conventional construction beam
Except method is cumbersome, heavy workload, efficiency bottom.
Summary of the invention
The invention patent is designed to provide a kind of concrete beam mould board fixing clamp construction method, solves secondary structure
Construct beam.It realizes easy to operate, greatly reduces the workload of construction personnel, improve working efficiency, it is reusable and firm
Reliably.
Component of the present invention involved in construction includes the first square steel pipe 1, the second square steel pipe 2, third square steel pipe
3, cubic shape steel tube 4, split bolt 5 etc..Specific process step and the parameter of control are as follows:
(1) the fixed clamp device of production concrete beam mould board, the material for making fixing frame of formworks is side length 50mm, wall thickness 4mm
And side length 45mm, the square steel pipe of wall thickness 4mm, interception side length 50mm length are the first square steel pipe of 300mm 1 and 500mm second
2 each one sections of square steel pipe, interception side length 40mm length is 500mm third square steel pipe and the cubic shape steel tube 4 each one of 500mm
Section makes length 700mm long split bolt 5;
2, the first square steel pipe 1 and the second square steel pipe 2 are welded into the first L-type component 6, by 3 He of third square steel pipe
Cubic shape steel tube 4 is welded into the second L-type component 7;Second square steel pipe 2 and 3 top same position of third square steel pipe are opened
If two holes, after the completion of device welds aperture, processing and fabricating beam forms and wood reinforcement;
3, material is ready to complete, and after the completion of beam steel bar colligation, carries out formwork erection and flitch is reinforced;
4, two L-type beam clamp devices are vertically installed on the outside of template and flitch, split bolt is passed through into beam top position
Split bolt 5 is secured with nuts the circular hole of beam clamp device;
5, template and flitch beam clamp device fixation back rest casting concrete.
It is determined by checking, it is easy to operate, greatly reduce the workload of construction personnel, improves working efficiency, it is repeatable to make
With, and it is firm reliable.
Detailed description of the invention
Fig. 1 is a kind of component of concrete beam mould board fixing clamp construction method assembled formation.Wherein, the first square steel pipe 1,
Second square steel pipe 2, third square steel pipe 3, cubic shape steel tube 4, split bolt 5.
Fig. 2 is device feature welding assembly schematic diagram.
Fig. 3 is construction beam steel bar colligation, formwork erection figure.
Fig. 4 is beam clamp device installation diagram.
Specific embodiment
Component of the present invention involved in construction includes the first square steel pipe 1, the second square steel pipe 2, third square steel pipe
3, cubic shape steel tube 4, split bolt 5 etc..Specific process step and the parameter of control are as follows:
1, concrete beam mould board fixing clamp construction method is made, the material of production fixing frame of formworks first is side length 50mm,
Wall thickness 4mm and side length 45mm, the square steel pipe of wall thickness 4mm, interception side length 50mm length are 1 He of the first square steel pipe of 300mm
Each one section of the second square steel pipe of 500mm 2, interception side length 40mm length are 500mm third square steel pipe 3 and 500mm square
Steel pipe 4;Make length 700mm long split bolt 5;
2, the first square steel pipe 1 and the second square steel pipe 2 are welded into the first L-type component 6, by 3 He of third square steel pipe
Cubic shape steel tube 4 is welded into the second L-type component 7;Second square steel pipe 2 and 3 top same position of third square steel pipe are opened
If two holes, after the completion of device welds aperture, processing and fabricating beam forms and wood reinforcement;
3, material is ready to complete, and after the completion of beam steel bar colligation, carries out formwork erection and flitch is reinforced;
4, two L-type beam clamp devices are vertically installed on the outside of template and flitch, split bolt is passed through into beam top position
Split bolt 5 is secured with nuts the circular hole of beam clamp device;
5, template and flitch beam clamp device fixation back rest casting concrete.
Claims (1)
1. a kind of concrete beam mould board fixing clamp construction method, the component involved in construction includes the first square steel pipe (1), the
Two square steel pipes (2), third square steel pipe (3), cubic shape steel tube (4) split bolt (5);It is characterized in that, concrete technology
Step and the parameter of control are as follows:
1) the fixed clamp device of production concrete beam mould board, the material for making fixing frame of formworks is side length 50mm, wall thickness 4mm and side length
45mm, the square steel pipe of wall thickness 4mm, interception side length 50mm length are the second square of the first square steel pipe of 300mm (1) and 500mm
For steel pipe (2) every one section, interception side length 40mm length is 500mm third square steel pipe (3) and the cubic shape steel tube (4) of 500mm, system
Make length 700mm long split bolt (5);
2) by the first square steel pipe (1) and the second square steel pipe (2) welding l-shaped component (6), by third square steel pipe (3) and
Cubic shape steel tube (4) welds l-shaped component (7);By the first square steel pipe (2) and third square steel pipe (3) top identical bits
It sets and opens up two holes, after the completion of device welds aperture, processing and fabricating beam forms and wood reinforcement;
3) it after the completion of beam steel bar colligation, carries out formwork erection and flitch is reinforced;
4) two L-type beam clamp devices are vertically installed on the outside of template and flitch, split bolt is pressed from both sides across Liang Dingbuweizhiliang
Split bolt (5) is secured with nuts the circular hole of device;
5) template and flitch beam clamp device fixation back rest casting concrete.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810853586.4A CN109025273A (en) | 2018-07-30 | 2018-07-30 | A kind of concrete beam mould board fixing clamp construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810853586.4A CN109025273A (en) | 2018-07-30 | 2018-07-30 | A kind of concrete beam mould board fixing clamp construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109025273A true CN109025273A (en) | 2018-12-18 |
Family
ID=64647759
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810853586.4A Pending CN109025273A (en) | 2018-07-30 | 2018-07-30 | A kind of concrete beam mould board fixing clamp construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109025273A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110056186A (en) * | 2019-06-03 | 2019-07-26 | 舜元建设(集团)有限公司 | A kind of building template Simple clamp and its construction method |
CN111173272A (en) * | 2020-01-14 | 2020-05-19 | 中国十七冶集团有限公司 | Simple lintel template reinforcing device and construction method |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE20212134U1 (en) * | 2002-08-07 | 2002-10-31 | Hummel Heinz | Ring beam formwork |
CN201202276Y (en) * | 2008-06-06 | 2009-03-04 | 中冶天工建设有限公司 | Beam side panels fixture |
CN103104093A (en) * | 2013-01-14 | 2013-05-15 | 浙江凯雄科技有限公司 | Special strengthening clamping tool for building beam bottom and beam side frameworks |
CN104074352A (en) * | 2014-06-29 | 2014-10-01 | 北京首钢建设集团有限公司 | Wall body template supporting method in position with narrow space |
CN205348768U (en) * | 2015-12-30 | 2016-06-29 | 中国建筑第八工程局有限公司 | Full adaptive type fixture device of adjustable combination formula |
CN205955193U (en) * | 2016-07-11 | 2017-02-15 | 中国建筑第八工程局有限公司 | Can have enough to meet need integral concrete beam reinforcing apparatus |
CN107083840A (en) * | 2017-04-21 | 2017-08-22 | 北京首钢建设集团有限公司 | A kind of anti-bank one-shot forming formwork erection method in toilet |
CN108035540A (en) * | 2017-12-28 | 2018-05-15 | 上海建工二建集团有限公司 | A kind of heavy in section steel reinforced concrete Cast-in-situ Beam new type formwork fixture and construction method |
-
2018
- 2018-07-30 CN CN201810853586.4A patent/CN109025273A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE20212134U1 (en) * | 2002-08-07 | 2002-10-31 | Hummel Heinz | Ring beam formwork |
CN201202276Y (en) * | 2008-06-06 | 2009-03-04 | 中冶天工建设有限公司 | Beam side panels fixture |
CN103104093A (en) * | 2013-01-14 | 2013-05-15 | 浙江凯雄科技有限公司 | Special strengthening clamping tool for building beam bottom and beam side frameworks |
CN104074352A (en) * | 2014-06-29 | 2014-10-01 | 北京首钢建设集团有限公司 | Wall body template supporting method in position with narrow space |
CN205348768U (en) * | 2015-12-30 | 2016-06-29 | 中国建筑第八工程局有限公司 | Full adaptive type fixture device of adjustable combination formula |
CN205955193U (en) * | 2016-07-11 | 2017-02-15 | 中国建筑第八工程局有限公司 | Can have enough to meet need integral concrete beam reinforcing apparatus |
CN107083840A (en) * | 2017-04-21 | 2017-08-22 | 北京首钢建设集团有限公司 | A kind of anti-bank one-shot forming formwork erection method in toilet |
CN108035540A (en) * | 2017-12-28 | 2018-05-15 | 上海建工二建集团有限公司 | A kind of heavy in section steel reinforced concrete Cast-in-situ Beam new type formwork fixture and construction method |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110056186A (en) * | 2019-06-03 | 2019-07-26 | 舜元建设(集团)有限公司 | A kind of building template Simple clamp and its construction method |
CN111173272A (en) * | 2020-01-14 | 2020-05-19 | 中国十七冶集团有限公司 | Simple lintel template reinforcing device and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204435673U (en) | Integrated frame column template structure | |
WO2016062224A1 (en) | Integrated column-equipped heat insulation wallboard, manufacturing and building processes and corollary equipment thereof | |
CN104131704A (en) | Steel pipe column concrete lateral pouring method and steel pipe column structure used in method | |
KR100731593B1 (en) | A pre-fabricating forms for concrete-structure and the construction method thereof | |
CN109025273A (en) | A kind of concrete beam mould board fixing clamp construction method | |
CN210976588U (en) | Template reinforcing system for double shear walls at deformation joint | |
CN110630011A (en) | Template reinforcing system for double shear walls at deformation joint and construction method thereof | |
CN104047422A (en) | Cylinder die manufacturing and mounting method | |
CN112302209B (en) | Steel and concrete shear wall mixed structure and manufacturing method thereof | |
CN103806538B (en) | A kind of precast reinforced concrete structure | |
CN204626961U (en) | A kind of steel form trussed construction of swallow-tail form large-sized concrete pier stud | |
CN102619286A (en) | Connecting joint of steel pipe concrete column and profile steel concrete beam | |
CN104786368A (en) | Reinforcement forming technology | |
CN210713827U (en) | Internal and external corner template reinforcing device | |
CN203834809U (en) | Steel pipe column structure for steel pipe column concrete side pouring method | |
CN204898710U (en) | Novel steel construction retaining wall | |
CN209260922U (en) | Band girder rib laminated floor slab pre-tensioning system connecting joint structure | |
CN104153463A (en) | Assembled integrated frame system and construction method thereof | |
CN203668894U (en) | Concrete prefabricated form structure allowing rapid installation | |
CN103437493A (en) | Connecting node of prefabricated reinforced concrete beam and construction method of connecting node | |
CN215055279U (en) | Thickness control device for steel plate concrete shear wall symmetrical wall body | |
CN215105454U (en) | Prefabricated and cast-in-place piled raft foundation that combines together | |
CN109594687A (en) | A kind of nodal connection device and its methods and applications for vertical shear wall piece | |
CN205330156U (en) | Cast -in -place template reinforcing apparatus at position is connected to assembly outer wall and cast -in -place interior wall T type | |
CN213115520U (en) | Concrete turn-ups reinforcement tool |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |